Construction method of cast-in-place box beam
By using anti-fall doorway brackets, integrally adjustable full-hall brackets, linear precision control formwork and preloaded bracket rainproof systems in the construction of urban viaducts, the cast-in-place box girder formwork bracket system solves the problem of the cast-in-place box girder formwork bracket system spanning the circular cast-in-place box girder on the active highway. The safety and traffic impact issues under working conditions are eliminated, and the construction effect is achieved quickly, safely and efficiently.
Patent Information
- Application Number
- CN202210777614.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-07-04
- Publication Date
- 2024-10-22
- Estimated Expiration
- 2042-07-04
AI Technical Summary
During the construction process of urban viaducts, the design and construction of the cast-in-place box girder formwork support system has safety risks. Especially when the circular cast-in-place box girder spans an active highway, the construction nodes are complex and difficult to optimize, which affects traffic safety and Concrete pour quality.
It adopts an anti-fall doorway bracket system, an overall adjustable full-hall bracket system, a linear precision control template system and a pre-loaded bracket rain-proof system. Through precise positioning and linkage overall lifting equipment, adjustable bottom brackets and side brackets, and bagged gravel pre-storage The combination of pressure and waterproof canopies ensures the stability and safety of the support system, and traffic diversion and drainage measures are set up during construction.
It improves the construction speed and safety, reduces the traffic closure time, meets the linear requirements of the circular box girder, ensures safety when the bracket is removed, and achieves an improvement in economic and technical benefits.
Smart Images

Figure CN114991018B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of highway engineering, and in particular relates to a construction method of a cast-in-place box beam. Background Art
[0002] In order to solve the problem of urban road congestion, compared with the construction of underground expressways, the construction of urban elevated expressways has great advantages in terms of construction cost and construction difficulty. However, the biggest source of danger in the construction of urban viaducts is the cast-in-place box girder formwork support system. Once a safety accident occurs, it often causes irreparable losses to the property and lives of the people. Therefore, it is very necessary to study the design and construction of the cast-in-place box girder formwork support system.
[0003] Among the cast-in-place box girder formwork support systems, the circular cast-in-place box girder support system that crosses the existing highway is a special working condition. It is necessary to ensure that the support system construction does not hinder the traffic safety of the existing highway section, and to consider the support of the circular curve formwork, the adjustment of the longitudinal and transverse elevations, the quality assurance of concrete pouring, and other issues. It is also necessary to fully coordinate the traffic diversion issues in the complex interchange area. In addition, the safety measures for the dismantling of the support system are also a top priority. The existing cast-in-place box girder formwork support system construction is very mature, but under the above special working conditions, many construction nodes have room for optimization. Summary of the invention
[0004] The purpose of the invention is to overcome the deficiencies in the prior art and provide a construction method for a cast-in-place box beam.
[0005] The construction method of this cast-in-place box girder comprises the following steps:
[0006] Step 1: Traffic diversion;
[0007] Step 2: Basic treatment of the support system;
[0008] Step 3, construction of the overall adjustable full-floor support system: Lay out the lines on the basis of the processed support system, accurately locate the adjustable base of the buckle support, install the support poles, support cross bars and support diagonal braces in order from bottom to top, and pre-install pressure strain gauges in the overlap plates of some support poles and support cross bars; pre-weld the support panels on some cross bars of the first layer of the buckle support; evenly arrange the lifting equipment on the base surface of the support system and abut against the support panel 53; connect them through data cables to form a linkage overall lifting equipment;
[0009] Step 4, construction of anti-fall door opening support system: after traffic diversion on site, first close the lane on one side and guide the traffic to the non-motorized vehicle lane, then start to install the precast concrete foundation of the support at the cross-road door opening, and then use the automobile crane to install the steel pipe column and the column top unloading sand box, and control the column top elevation through the sand box; after the sand box height adjustment is completed, hoist the main beam of the double-jointed I-beam into the limit plate on the top surface of the sand box; then hoist the anti-fall I-beam platform, and manually remove the limit bolts, unfold the anti-fall cover plate, and place the anti-fall cover plate on the lower flange plate of the adjacent I-beam; finally, erect the upper distribution beam and the plate buckle frame;
[0010] Step 5, installation of linear precision control formwork system: After the overall adjustable full-floor support system has been accepted, the bottom formwork of the cast-in-place box girder will be installed; first, the top elevation of the bottom formwork is measured with a level, and the adjustable top support and adjustable small side support are installed. The template position line is measured and laid out according to the edge line of the cast-in-place box girder. After that, the template is hoisted into place in batches by a crane, and then the position of the adjustable top support and adjustable small side support is manually and dynamically adjusted to complete the linear control;
[0011] Step 6: Lifting of bagged gravel and preloading of brackets: After the overall adjustable full-chamber bracket system and the bottom formwork of the cast-in-place box beam are installed, bagged gravel is loaded into ton bags for preloading;
[0012] Step 7, installation of waterproof foldable canopy: in the pre-pressing construction, use the installed bracket pole as the main support pole in time before the rain, install the foldable connecting rod by sleeve-connecting the adjustable sleeve and the auxiliary support rod, and then lay the waterproof canopy;
[0013] Step 8, template axis and elevation adjustment: After pre-pressing, adjust the elevation of the bottom mold according to the set pre-camber. After the bottom mold axis and elevation meet the requirements after verification, proceed to the next step of construction;
[0014] Step 9. Construction of cast-in-place box girder reinforcement and concrete: After the above construction is completed, install the box girder inner formwork, box girder inner formwork support and other remaining side formworks, tie the box girder reinforcement, and pour the box girder concrete to complete the construction of the circular box girder section across the existing highway.
[0015] As a preferred embodiment, step 1 is specifically as follows: before construction, traffic is diverted in the complex interchange area to avoid the steel pipe column 7 and the elevated pier, the motor vehicle lane and non-motor vehicle lane are replanned, and at the same time, fences and safety warning signs are set up in the areas where the motor vehicle lane and non-motor vehicle lane are located.
[0016] Preferably, step 2 is as follows: backfill and compact thick slag in layers to form a slag layer, compact and fill it layer by layer from bottom to top to the top surface of the support system foundation, take corresponding drainage measures, and finally pour a C30 concrete foundation as the support system foundation.
[0017] As a preferred embodiment: in step 2, the thickness of the slag layer is 60 cm; when the compaction degree is greater than 95%, a 20 cm thick C30 concrete foundation is poured.
[0018] As a preferred embodiment: the preset pressure strain gauges in step 3 are used to monitor the value changes of the sensors on both sides to ensure that the bracket is erected or dismantled symmetrically and balanced; when an elevation error occurs during the erection of the disc-type full-hall bracket, the linked overall lifting device is used to adjust the elevation of the local unit, and the base is adjusted in time after the local unit is lifted, and the linked overall lifting device is unloaded synchronously.
[0019] As a preferred embodiment: in step 4, a 25T truck crane is used to install the steel pipe column and the sand box unloading box on the top of the column; the main beam specification of the double-piece I-beam is I63a; when hoisting the main beam of the double-piece I-beam into the limit plate on the top surface of the sand box, if there is a gap at the top of the main beam, the height of the sand in the sand box is readjusted, or steel plates are used for support and adjustment.
[0020] The cast-in-place box girder is obtained by the above method.
[0021] The beneficial effects of the present invention are:
[0022] (1) Aiming at the working condition of crossing the existing highway, the present invention proposes a cast-in-place box girder construction method through field test research, construction material and construction method comparison, adopts an anti-fall door opening support system, an overall adjustable full-height support system, a linear precision-controlled template system and a pre-stressed support rain protection system; and has been verified by multiple projects; the present invention is suitable for cast-in-place box girder support operations, especially for the construction of circular cast-in-place box girders crossing the existing highway; it can provide a certain technical reference for cast-in-place box girder construction, with fast construction speed, high safety, and outstanding economic and technical benefits;
[0023] (2) The present invention adopts a section-by-section road closure and anti-fall doorway support system. The doorway support is an integral structure and is provided with an anti-fall I-beam platform to ensure the traffic safety of the existing highways. The entire structural system is formed quickly, reducing the traffic closure time and maximizing the traffic flow of the existing highways.
[0024] (3) The present invention adopts a linear precision-controlled formwork system for circular cast-in-place box girders and combines it with a lower integrally adjustable full-bridge support system to achieve all-round adjustability of node coordinates, effectively ensuring the linear requirements of the circular box girders.
[0025] (4) The present invention uses bagged crushed stone to accurately preload the bracket for the hollow section of the cast-in-place box girder, and adds a rainproof covering system to ensure the stability of the hollow section bracket system, and sets a bracket removal control sensing device at the local node of the bracket to ensure the safety of bracket removal; during the preloading construction, the installed bracket uprights are used as the main support poles in time before the rain, and the foldable connecting rods are installed by sleeve-connecting adjustable sleeves and auxiliary support rods, and then a waterproof canopy is laid to prevent overload preloading caused by water accumulation on the top. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 This is a schematic diagram of traffic diversion according to the present invention;
[0027] Figure 2 It is a schematic diagram of the anti-fall door opening bracket system in the present invention;
[0028] Figure 3 It is a schematic diagram of the anti-fall door opening bracket system in the present invention;
[0029] Figure 4 It is a schematic diagram of the anti-fall I-beam platform in the present invention;
[0030] Figure 5 It is a schematic diagram of the structure of the unloading and falling sand box in the present invention;
[0031] Figure 6 It is a cross-sectional view of the unloading and falling sand box in the present invention;
[0032] Figure 7 It is a schematic diagram of the rainproof system of the pre-compression support in the present invention;
[0033] Figure 8 Schematic diagram of the overall adjustable full-chamber bracket system in the present invention;
[0034] Fig. 9 It is a construction flow chart of the present invention.
[0035] Explanation of reference numerals: edge line of cast-in-place box girder 1; motor vehicle lane 2; reverse motor vehicle lane 3; diversion motor vehicle lane 4; diversion non-motor vehicle lane 5; elevated pier 6; steel pipe column 7; non-motor vehicle lane 8; reverse non-motor vehicle lane 9; isolation and protection pier 10; separation guardrail 11; double-jointed I-beam 12; anti-fall I-beam platform 13; sand unloading box 14; limit plate 15; C30 concrete foundation 16; full-hall support construction area 17; hinge shaft 18; anti-fall cover plate 19; limit bolt 20; magnetic strip 21; concrete body 22; sand box wall 23; sand storage 24; drill rod 25; sand unloading cavity 26; reserved passage Road 27; sand box base 28; sleeve 29; partition plate 30; slag layer 31; adjustable sleeve 32; guardrail 33; adjustable small side support 34; data cable 35; linked integral lifting device 36; foldable connecting rod 37; auxiliary support rod 38; waterproof canopy 39; bagged gravel 40; bottom mold 41; adjustable top support 42; overall adjustable full-floor support system 43; adjustable bottom support 44; support cross bar 45; support diagonal support 46; support vertical rod 47; box girder inner mold support 48; box girder inner mold 49; cast-in-place box girder 50; precast concrete foundation 51; pressure strain gauge 52, support panel 53. DETAILED DESCRIPTION
[0036] The present invention is further described below in conjunction with embodiments. The description of the following embodiments is only used to help understand the present invention. It should be noted that for ordinary persons in the art, without departing from the principle of the present invention, the present invention can also be modified in some ways, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
[0037] As an example, Figures 1 to 9 As shown, a construction method of a cast-in-place box beam is characterized by comprising the following steps:
[0038] Step 1: Traffic diversion: Before construction, traffic diversion is carried out in the complex interchange area to avoid the steel pipe column 7 and the elevated pier 6, and the motor vehicle lane 2 and the non-motor vehicle lane 8 are replanned. At the same time, enclosures and safety warning signs are set up in the areas where the motor vehicle lane 2 and the non-motor vehicle lane 8 are located;
[0039] Step 2, support system foundation treatment: thick slag is backfilled and compacted in layers to form a slag layer 31, which is compacted layer by layer from bottom to top to the top surface of the support system foundation, and corresponding drainage measures are taken, and finally a C30 concrete foundation 16 is poured as the support system foundation; the thickness of the slag layer 31 is 60 cm; when the compaction degree is greater than 95%, a 20 cm thick C30 concrete foundation 16 is poured;
[0040] Step 3, construction of the overall adjustable full-hall bracket system 43: Lay out the lines on the basis of the processed bracket system, accurately locate the adjustable base of the disc-type bracket, install the bracket uprights 47, bracket crossbars 45 and bracket diagonal braces 46 in order from bottom to top, and pre-install pressure strain gauges 52 in the overlap plates of some bracket uprights 47 and bracket crossbars 45; pre-weld the support panels 53 on some crossbars of the first layer of the disc-type bracket; evenly arrange the lifting equipment on the base surface of the bracket system and abut against the support panels 53; connect them through data lines 35 to form a linkage-type overall lifting equipment 36; the preset pressure strain gauges 52 are used to monitor the value changes of the sensors on both sides to ensure that the bracket is erected or dismantled symmetrically and balanced; when an elevation error occurs during the erection of the disc-type full-hall bracket, the linkage-type overall lifting equipment 36 is used to adjust the elevation of the local unit, and the base is adjusted in time after the local unit is lifted, and the linkage-type overall lifting equipment is unloaded synchronously;
[0041] Step 4, construction of anti-fall door opening support system: after traffic diversion on site, first close the lane in one direction and guide the traffic to the non-motorized vehicle lane 8, then start to install the precast concrete foundation 51 of the support at the cross-road door opening, and then use the automobile crane to install the steel pipe column 7 and the column top unloading sand box, and control the column top elevation through the sand box; after the height adjustment of the sand box is completed, hoist the main beam of the double-piece I-beam 12 to the limit plate 15 on the top surface of the sand box; then hoist the anti-fall I-beam platform 13, and pass the personnel to install the anti-fall I-beam platform 13. The workers disassemble the limit bolts 20, unfold the anti-fall cover plate 19, and place the anti-fall cover plate 19 on the lower flange plate of the adjacent I-beam 12; finally, the upper distribution beam and the buckle frame are erected; a 25T truck crane is used to install the steel pipe column 7 and the column top unloading sand box; the main beam specification of the double-jointed I-beam 12 is I63a; when the main beam of the double-jointed I-beam 12 is hoisted to the limit plate 15 on the top surface of the sand box, if there is a gap at the top of the main beam, the height of the sand in the sand box is readjusted, or a steel plate is used for support and adjustment;
[0042] Step 5, installation of linear precision control formwork system: after the overall adjustable full-floor support system 43 has been accepted, the bottom formwork 41 of the cast-in-place box beam 50 is installed; first, the top elevation of the bottom formwork 41 is measured with a level, and the adjustable top support 42 and the adjustable small side support 34 are installed. The template position line is measured and laid out according to the edge line 1 of the cast-in-place box beam, and then the template is hoisted into place in batches by a crane, and then the position of the adjustable top support 42 and the adjustable small side support 34 are manually and dynamically adjusted to complete the linear control;
[0043] Step 6, lifting and preloading of bagged gravel and brackets: After the overall adjustable full-chamber bracket system 43 and the bottom formwork 41 of the cast-in-place box beam 50 are installed, bagged gravel 40 is loaded into ton bags for preloading;
[0044] Step 7, installation of waterproof foldable canopy: In the pre-pressing construction, the installed bracket pole 48 is used as the main pole in time before the rain, and the foldable connecting rod 37 is installed by sleeve-connecting the adjustable sleeve 32 and the auxiliary support rod 38, and then the waterproof canopy 39 is laid;
[0045] Step 8, template axis and elevation adjustment: After pre-pressing, adjust the elevation of the bottom mold 41 according to the set pre-camber. After the bottom mold axis and elevation meet the requirements after verification, proceed to the next step of construction;
[0046] Step 9, construction of cast-in-place box girder reinforcement and concrete: After the above construction is completed, the box girder inner formwork 49, the box girder inner formwork support 48 and other remaining side formworks are installed, the box girder reinforcement is tied, and the box girder concrete is poured to complete the construction of the circular box girder section across the existing highway.
[0047] According to the cast-in-place box girder obtained by the above method, the edge line 1 of the cast-in-place box girder is circular, the motor vehicle lane 2 and the reverse motor vehicle lane 3 pass through the edge line 1 of the cast-in-place box girder in parallel; the part of the diversion motor vehicle lane 4 located outside the diversion motor vehicle lane overlaps with the reverse motor vehicle lane 3; the part of the diversion motor vehicle lane 4 located inside the diversion motor vehicle lane is located on the side of the reverse motor vehicle lane 3 that is not adjacent to the motor vehicle lane 2; the diversion non-motor vehicle lane 5 is similar in shape to the diversion motor vehicle lane 4, and the diversion non-motor vehicle lane 5 is located on the side of the diversion motor vehicle lane 4 that is not adjacent to the reverse motor vehicle lane 3; it is characterized by comprising: an anti-falling door opening bracket system, an overall adjustable full-hall bracket system 43, a linear precision-controlled template system and a pre-stressed bracket rainproof system;
[0048] The anti-falling door opening support system is arranged at the road closure of the existing line section above; in the anti-falling door opening support system, the precast concrete foundation 51 is arranged on both sides of the motor vehicle lane 2 and the non-motor vehicle lane 8 along the direction of the cast-in-place box girder edge line 1 on the cast-in-place box girder 50; an isolation protection pier 10 is arranged between the precast concrete foundation 51 and the motor vehicle lane 2, and a separation guardrail 11 is arranged between the precast concrete foundation 51 and the non-motor vehicle lane 8; a separation guardrail 11 is arranged between the precast concrete foundation 51 and the reverse non-motor vehicle lane 9, and the precast concrete An isolation protection pier 10 is provided between the foundation 51 and the reverse motor vehicle lane 3; a steel pipe column 7, a sand unloading box 14, a double-jointed I-beam 12 and an anti-falling I-beam platform 13 are sequentially installed on the top surface of the precast concrete foundation 51 from bottom to top, and an elevated pier column 6 is provided between the plurality of anti-falling I-beam platforms 13; the top of the steel pipe column 7 is a sand unloading box 14, and a double-jointed I-beam 12 is installed in the sand unloading box 14; a box beam inner mold 49 is provided in the cast-in-place box beam 50, and a box beam inner mold support 48 is provided in the box beam inner mold 49;
[0049] The overall adjustable full-span support system is located in the fan-shaped full-span support construction area 17. The overall adjustable full-span support system consists of an adjustable bottom support 44, a support cross bar 45, a support diagonal support 46, a support vertical bar 47, a pressure strain gauge 52 and a linkage overall lifting device 36; the linear precision control formwork system includes an adjustable top support 42, an adjustable small side support 34 and a bottom formwork 41; the pre-compression support rainproof system consists of an adjustable sleeve 32, a foldable connecting rod 37, an auxiliary support rod 38 and a waterproof canopy 39.
[0050] The anti-falling I-beam platform 13 is composed of a double-jointed I-beam 12, an anti-falling cover plate 19 and a magnetic strip 21. The bottom of the web of the double-jointed I-beam 12 is connected to the anti-falling cover plate 19 through a hinge shaft 18; the anti-falling cover plate 19 is a hinge structure, and the outer edge of the anti-falling cover plate 19 is provided with a magnetic strip 21. The anti-falling cover plate 19 is adsorbed and connected with the lower flange plate of the adjacent double-jointed I-beam 12 through the magnetic strip 21, and the anti-falling cover plate 19 and the lower flange plate of the double-jointed I-beam 12 are fixed by limiting bolts 20.
[0051] The sand unloading box 14 includes a limit plate 15, a concrete body 22, a sand storage 24, a partition plate 30 and a drill rod 25; the limit plate 15 is pre-buried in the top surface of the concrete body 22, the concrete body 22 is arranged in the sand box wall 23 and abuts against the sand storage 24, the sand unloading cavity 26 is located below the sand storage 24 and is separated from the sand unloading cavity 26 by the partition plate 30; a reserved channel 27 is provided on the drill rod 25 located at the center of the partition plate 30, and the reserved channel 27 connects the sand storage 24 and the sand unloading cavity 26; a sand box base 28 is provided at the bottom of the sand unloading cavity 26; a sleeve 29 is provided between the drill rod 25 and the sand box wall 23.
[0052] In the overall adjustable full-hall bracket system: a pressure strain gauge 52 is preset in the overlapping section between the disc of the bracket upright 47 and the bracket cross bar 45, and the unoverlapping section of the bracket upright 47 and the bracket cross bar 45 is connected and fixed by the bracket diagonal brace 46; the linked overall lifting device 36 is in contact with the support panel 53 of the first layer of the bracket cross bar 47 located below the adjustable base 44; all the linked overall lifting devices 36 are connected to the host through the data cable 35.
[0053] A C30 concrete foundation 16 is provided below the linkage type integral lifting device 36 , and a slag layer 31 is provided at the bottom of the C30 concrete foundation 16 .
[0054] In the linear precision control template system: the adjustable top support 42 and the adjustable small side support 34 are both arranged on the top of the bracket upright 47; the adjustable top support 42 and the adjustable small side support 34 both support and connect the bottom mold 41, and the adjustable top support 42 abuts against the bottom surface of the bottom mold 41, and the adjustable small side support 34 abuts against the side of the bottom mold 41.
[0055] In the rainproof system of the pre-stressed support: the foldable connecting rod 37 is installed on the top of the guardrails 33 on both sides through the adjustable sleeve 32, and the top surface of the foldable connecting rod 37 is paved with a waterproof canopy 39, and an auxiliary support rod 38 is arranged in the middle of the waterproof canopy 39.
[0056] The support panel 53 is partially welded to the crossbar of the first layer of the buckle bracket.
Claims
1. A construction method for a cast-in-place box girder, characterized in that: The following steps are involved: Step 1: Traffic diversion; Step 2: Basic treatment of the support system; Step 3, construction of the overall adjustable full-height support system (43): Lay out the lines on the basis of the processed support system, accurately locate the adjustable base of the buckle support, install the support uprights (47), the support cross bars (45) and the support diagonal braces (46) in order from bottom to top, and pre-install pressure strain gauges (52) in the overlap plates of some support uprights (47) and support cross bars (45); pre-weld the support panels (53) on some cross bars of the first layer of the buckle support; evenly arrange the lifting equipment on the base surface of the support system and abut against the support panels (53); connect them through data cables (35) to form a linkage-type overall lifting equipment (36); Step 4, construction of anti-fall door opening support system: after traffic diversion on site, first close the lane in one direction and guide the traffic to the non-motorized vehicle lane (8), then start installing the precast concrete foundation (51) of the support at the cross-road door opening, then use a car crane to install the steel pipe column (7) and the column top unloading sand box, and control the column top elevation through the sand box; after the sand box height adjustment is completed, hoist the main beam of the double-jointed I-beam (12) into the limit plate (15) on the top surface of the sand box; then hoist the anti-fall I-beam platform (13), and manually remove the limit bolts (20), unfold the anti-fall cover plate (19), and place the anti-fall cover plate (19) on the lower flange plate of the adjacent I-beam (12); finally, erect the upper distribution beam and the plate buckle frame; Step 5, installation of linear precision control formwork system: after the overall adjustable full-height support system (43) has been inspected and accepted, the bottom formwork (41) of the cast-in-place box beam (50) is installed; first, the top elevation of the bottom formwork (41) is measured with a level, and the adjustable top support (42) and the adjustable small side support (34) are installed. The template position line is measured and laid out according to the edge line (1) of the cast-in-place box beam, and then the template is hoisted into place in batches by a crane, and then the position of the adjustable top support (42) and the adjustable small side support (34) are manually and dynamically adjusted to complete the linear control; Step 6, lifting and transporting bagged gravel and preloading the support: after the overall adjustable full-span support system (43) and the bottom formwork (41) of the cast-in-place box beam (50) are installed, bagged gravel (40) is loaded into ton bags for preloading; Step 7, installation of waterproof foldable canopy: in the pre-pressing construction, before the rain, the installed support pole (47) is used as the main support pole in time, and the foldable connecting rod (37) is installed by sleeve-connecting the adjustable sleeve (32) and the auxiliary support rod (38), and then the waterproof canopy (39) is laid; Step 8, template axis and elevation adjustment: after pre-pressing, the elevation of the bottom mold (41) is adjusted according to the set pre-camber. After the bottom mold axis and elevation are checked to meet the requirements, the next step of construction is carried out; Step 9, construction of cast-in-place box girder reinforcement and concrete: After the above construction is completed, the box girder inner formwork (49), the box girder inner formwork support (48) and other remaining side formworks are installed, the box girder reinforcement is tied, and the box girder concrete is poured to complete the construction of the circular box girder section that crosses the existing highway.
2. The construction method of the cast-in-place box girder according to claim 1, characterized in that: Step 1 specifically includes: before construction, traffic is redirected in the complex interchange area to avoid the steel pipe column (7) and the elevated pier (6), the motor vehicle lane (2) and the non-motor vehicle lane (8) are replanned, and at the same time, fences and safety warning signs are set up in the areas where the motor vehicle lane (2) and the non-motor vehicle lane (8) are located.
3. The construction method of the cast-in-place box girder according to claim 2 is characterized in that: Step 2 specifically includes: using thick slag to backfill and compact in layers to form a slag layer (31), compacting and filling from bottom to top layer by layer to the top surface of the support system foundation, and taking corresponding drainage measures, and finally pouring a C30 concrete foundation (16) as the support system foundation.
4. The construction method of the cast-in-place box beam according to claim 3 is characterized in that: In step 2, the thickness of the slag layer (31) is 60 cm; when the compaction degree is greater than 95%, a 20 cm thick C30 concrete foundation (16) is poured.
5. The construction method of the cast-in-place box beam according to claim 1 is characterized in that: In step 3, the preset pressure strain gauge (52) is used to monitor the value change of the sensors on both sides to ensure that the support is erected or dismantled symmetrically and balanced; when an elevation error occurs during the erection of the disc-type full-hall support, the linkage-type overall lifting device (36) is used to adjust the elevation of the local unit, and the base is adjusted in time after the local unit is lifted, and the linkage-type overall lifting device is unloaded synchronously.
6. The construction method of the cast-in-place box beam according to claim 1 is characterized in that: Step 4: Use a 25T truck crane to install the steel pipe column (7) and the sand box on the top of the column; the main beam specification of the double-jointed I-beam (12) is I63a; when hoisting the main beam of the double-jointed I-beam (12) to the limit plate (15) on the top surface of the sand box, if there is a gap at the top of the main beam, readjust the height of the sand in the sand box, or use steel plates for support and adjustment.
7. Cast-in-place box beam, characterized in that: Obtained according to any one of claims 1 to 6.