Coastline landscape restoration method and system

By setting up a transverse wave-removing zone structure on the coastline, using stone slopes and oyster shells to slow down the impact of waves, combined with anti-corrosion wooden piles and geotextiles, the stability of plant planting in harsh coastline environments is solved, and the coastline ecology is realized Repair and environmental protection goals.

CN115119680BActive Publication Date: 2024-12-06BEIJING ZHENGHE HENGJI INT URBAN PLANNING & DESIGN CO LTD
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202210829270.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-15
Publication Date
2024-12-06
Estimated Expiration
2042-07-15

AI Technical Summary

Technical Problem

The existing coastline restoration methods are difficult to ensure stable planting and survival of plants in the harsh environment of the coastline. They are high in construction costs and serious material pollution. They are not suitable for the bottom of rocky beaches, which pose safety hazards and environmental pollution problems.

Method used

Adopt a transverse wave-removing belt structure, including stone slopes and wave-removing grooves, to reduce the impact of waves through the oyster shell, combine anti-corrosion wooden piles and geotextiles to form a stable planting bed, providing a stable growth environment for plants, and Reduce construction costs and pollution.

Benefits of technology

Effectively slow down the impact of waves, improve plant survival rate, enhance coastline ecological diversity, reduce construction costs and environmental pollution risks, and is suitable for a variety of coastline geological conditions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115119680B_ABST
    Figure CN115119680B_ABST
Patent Text Reader

Abstract

The present invention relates to a method and system for repairing coastline landscape. The method comprises setting a wave-breaking belt on the seaward side of a planting bed of landscape plants, and using the wave-breaking belt to mitigate the impact of waves on the planting bed and landscape plants. The system comprises a planting bed and a stone slope arranged transversely on the beach. The stone slope is located on the seaward side of the planting bed, and a gap is left between the two to form a wave-breaking groove. The stone slope is laid from top to bottom in an inclined manner toward the ocean, and the height of the top of the slope is lower than the height of the top surface or the bottom of the slope of the planting bed. The wave-breaking groove is filled with oyster shells, and the top surface of the oyster shell layer in the wave-breaking groove is lower than the height of the top of the stone slope. Landscape plants are planted on the planting bed. The present invention can weaken the impact of waves layer by layer through the stone slope, the wave-breaking groove, and the oyster shell layer on the top of the planting bed, thereby providing a stable growth environment for landscape plants and facilitating the rapid recovery of the landscape ecosystem.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a coastline landscape restoration method and system, belonging to the technical field of environmental protection. Background Art

[0002] For damaged coastal zones, restoration is usually carried out by transplanting landscape plants on the coastline. However, the coastline itself has poor site conditions, with strong sea breezes, fast seawater flow and strong seawater impact. For newly planted seedlings, stable planting bed conditions and their own stability after transplantation are the biggest challenges to their survival. The conventional way to solve this problem is to enclose steel sheet piles around the low tide level of the coastline, drain the seawater in the enclosed area, backfill the enclosed area with planting soil and then plant seedlings. However, this method has the following defects: (1) The roots of newly planted plants are not fully integrated with the soil. Under the scouring of seawater and the blowing of sea breeze, they are particularly prone to lodging and floating, making the plants unable to survive; (2) Steel sheet piles are heavy and require large pile drivers or pile beds for construction. The high material and machinery costs make the construction cost high; (3) Steel sheet piles are only suitable for In silt and sandy areas, construction cannot be carried out if there are a large number of boulders on the bottom of the water or the beach; (4) The steel sheet pile cofferdam needs to withstand the pressure of seawater and prevent seawater from flowing in. Therefore, very high requirements are placed on the airtightness, strength and rigidity of the cofferdam. Once the steel sheet piles tilt or collapse during construction, it will cause very serious consequences and pose a safety hazard; (5) During the construction of the steel sheet pile cofferdam, the exhaust gas emitted by large machinery and equipment, the leaked engine oil, and the dirt attached to the surface of the steel sheet piles will pollute the surrounding environment, especially the water environment (marine environment). Summary of the invention

[0003] In order to overcome the above-mentioned defects of the prior art, the present invention provides a coastline landscape restoration method and system, which can effectively mitigate the impact of waves on planting beds and planted plants, avoid or reduce soil loss, provide a stable growth environment for newly planted plants, and facilitate the rapid recovery of the landscape ecosystem.

[0004] The technical solution for achieving the above-mentioned purpose of the present invention is: a coastline landscape restoration method, laying a planting bed on the beach, planting landscape plants on the planting bed, and setting a horizontal (referring to a direction parallel to or approximately parallel to the coastline) wave-breaking belt on the beach on the sea side of the planting bed, so that the impact of waves on the planting bed and the landscape plants is mitigated by the wave-breaking belt. The wave-breaking belt includes a stone slope and a wave-breaking groove. The stone slope is inclined from top to bottom toward the ocean direction to weaken the impact force of the waves once. A gap is left between the stone slope and the planting bed to form the wave-breaking groove to weaken the impact force of the waves twice. The wave-breaking groove is filled with oyster shells, and the top surface of the oyster shell layer in the wave-breaking groove is lower than the top surface of the planting bed and the top of the stone slope.

[0005] Preferably, the height of the top of the rock slope is higher than the average low tide level of the ocean.

[0006] Preferably, the top surface of the planting bed is a plane or a slope sloping downward toward the ocean, the top of the stone slope is lower than the top or bottom of the planting bed, and the top or top of the planting bed is lower than the average high tide level of the ocean.

[0007] Furthermore, the top surface of the planting bed is a slope that slopes downward from top to bottom toward the ocean, the height of the top of the block stone slope is lower than the height of the bottom of the planting bed, and the height of the top of the planting bed is lower than the average high tide level of the ocean.

[0008] Furthermore, the slope of the planting bed is not greater than 1:5.

[0009] Preferably, the slope of the block stone slope is not less than 1:2.5.

[0010] Preferably, two rows of anti-corrosion wooden piles are arranged closely transversely and inserted into the beach between the planting bed and the block stone slope, the two rows of anti-corrosion wooden piles constitute the groove wall of the wave-breaking groove, the height of the front row of anti-corrosion wooden piles (the anti-corrosion wooden piles on the block stone slope side) is lower than the height of the rear row of anti-corrosion wooden piles (the anti-corrosion wooden piles on the planting bed side) and is the same as the height of the top of the block stone slope, the height of the rear row of anti-corrosion wooden piles is not lower than the top surface of the planting bed (when the top surface of the planting bed is a plane) or the height of the bottom of the slope (when the top surface of the planting bed is an inclined surface), the two rows of anti-corrosion wooden piles are covered with geotextiles, and the bottom of the wave-breaking groove is paved with geotextiles.

[0011] Preferably, a geotextile is laid on the beach below the planting bed, or a geotextile is laid on the beach below the planting bed in an area close to the rear row of antiseptic wooden piles.

[0012] Preferably, the planting bed includes a silt layer, a planting layer and an oyster shell layer from bottom to top, the planting layer includes plant material bundles arranged in a grid pattern and planting soil in which the grid-shaped plant material bundles are buried, the landscape plants are planted in the planting soil of the planting layer and tied to the plant material bundles by geotextiles.

[0013] Preferably, the beach is a beach with a flat surface.

[0014] A coastline landscape restoration system is applicable to the coastline landscape restoration method, comprising a planting bed and a stone slope arranged transversely (referring to a direction parallel to or approximately parallel to the coastline) on the beach, the stone slope being located on the seaward side of the planting bed, with a gap between the two forming a wave-breaking groove, the top surface of the planting bed being a plane or a slope sloping from top to bottom toward the ocean, the stone slope being paved from top to bottom toward the ocean, the height of the top of the slope being lower than the height of the top surface or bottom of the planting bed, the wave-breaking groove being filled with oyster shells, the top surface of the oyster shell layer in the wave-breaking groove being lower than the height of the top of the stone slope, and landscape plants being planted on the planting bed.

[0015] Preferably, the height of the top of the rock slope is higher than the average low tide level of the ocean.

[0016] Preferably, the height of the top surface of the planting bed (when the top surface of the planting bed is a plane) or the top of the slope (when the top surface of the planting bed is an inclined surface) is lower than the average high tide level of the ocean.

[0017] Furthermore, the top surface of the planting bed is a slope that slopes downward from top to bottom toward the ocean, and the slope of the planting bed is not greater than 1:5.

[0018] Preferably, the slope of the block stone slope is not less than 1:2.5.

[0019] Preferably, two rows of anticorrosive wooden piles are arranged closely transversely and inserted into the beach between the planting bed and the stone slope, the two rows of anticorrosive wooden piles constitute the groove wall of the wave-breaking groove, the height of the front row of anticorrosive wooden piles (the anticorrosive wooden piles on the stone slope side) is lower than the height of the rear row of anticorrosive wooden piles (the anticorrosive wooden piles on the planting bed side) and is the same as the height of the top of the stone slope, and the height of the rear row of anticorrosive wooden piles is not lower than the height of the top surface or bottom of the planting bed.

[0020] When the top surface of the planting bed is a slope, the height of the rear row of antiseptic wood piles is preferably higher than the height of the bottom of the slope of the planting bed and lower than the height of the top of the slope of the planting bed.

[0021] Preferably, the two rows of anticorrosive wooden piles are covered with geotextiles, and the bottom of the wave-breaking groove is paved with geotextiles.

[0022] Preferably, a geotextile is laid on the beach below the planting bed, or a geotextile is laid on the beach below the planting bed in an area close to the rear row of antiseptic wooden piles.

[0023] Preferably, the mass per unit area of ​​the geotextile is 150-300 g / m 2 .

[0024] Preferably, the planting bed comprises a silt layer, a planting layer and an oyster shell layer in order from bottom to top, and the planting layer comprises a planting layer skeleton in a grid shape formed by crisscrossing plant material bundles and planting soil in which the planting layer skeleton is buried.

[0025] Preferably, the landscape plants are planted at the vertical and horizontal intersections of the plant material bundles.

[0026] Preferably, the landscape plants are close to the plant material bundles and are tied to the plant material bundles by geotextile ropes.

[0027] Preferably, the grid of the planting layer skeleton is a square grid.

[0028] Preferably, the landscape plants are planted at the intersections of the transversely and longitudinally arranged plant material bundles, and are tied to the intersections of the transversely and longitudinally arranged plant material bundles by the geotextile ropes.

[0029] The plant material bundle may be a branch bundle, which is formed by bundling plant branches, and the plant branches may be branches pruned from seedlings, willow branches or bamboos.

[0030] The landscape plants are preferably mangrove plants.

[0031] The beneficial effects of the present invention are:

[0032] (1) The present invention weakens the impact of waves layer by layer through the stone slope, wave-breaking grooves and oyster shell layer on the top of the planting bed, which can effectively reduce the impact of waves on the planting bed and landscape plants, avoid or reduce soil (planting soil) loss, provide a stable growth environment for newly planted plants, and facilitate the rapid recovery of the landscape ecosystem;

[0033] (2) The present invention effectively transforms the inland area from the low tide level of the ocean into an ecological green space, lengthens the extension depth from the inland to the ocean, increases the richness of the transition zone between land and ocean, provides more living environments for animals and plants, and effectively improves the water ecological space, creating an ecological landscape along the coast;

[0034] (3) During the application process, as the oyster shells grow, the overall structure of the restoration system (mainly the wave-breaking grooves and planting beds) can be made more stable, while also promoting the implantation, habitat and reproduction of marine organisms, effectively improving the landscape diversity and biodiversity of the coastline;

[0035] (4) The present invention ties the newly planted plants to the plant material bundle, which can effectively ensure that the newly planted plants are stable and take root and sprout, thereby improving the survival rate of the newly planted plants. As time goes by, the plant material bundle gradually degrades, which can provide necessary nutrients for the growth of the newly planted plants, further ensuring the healthy growth of the newly planted plants;

[0036] (5) The materials used in the present invention are all eco-friendly materials, which can effectively ensure that they will not cause pollution and damage to the water environment and the surrounding environment during and after the ecological restoration process;

[0037] (6) The implementation of the present invention does not require a cofferdam and the construction can be arranged according to the tide level. No large-scale piling machinery is required during the construction process, and the construction period is short, the cost is low, and the safety hazard is low. BRIEF DESCRIPTION OF THE DRAWINGS

[0038] Figure 1 is a schematic diagram of the cross-sectional structure of the repair system of the present invention;

[0039] Figure 2 It is a partial schematic diagram of the planting layer of the present invention and the plants planted thereon. DETAILED DESCRIPTION

[0040] The present invention discloses a method for restoring coastline landscape, which comprises laying planting beds on a beach, planting landscape plants on the planting beds to form a coastline landscape belt, and arranging a transverse (referring to a direction parallel to or approximately parallel to the coastline) wave-breaking belt on the beach on the sea side of the planting beds, so that the impact of sea waves on the planting beds and landscape plants is mitigated by the wave-breaking belt, thereby avoiding or reducing the loss of soil (mainly referring to planting soil) of the planting beds, and providing a stable growth environment for landscape plants. The wave-breaking belt includes a stone slope and a wave-breaking groove, wherein the stone slope is inclined from top to bottom toward the ocean. When the tide is high, the slope of the stone slope toward the ocean is used to weaken the impact force of the waves once. A gap is left between the stone slope and the planting bed to form the wave-breaking groove, which is used to weaken the impact force of the waves passing over the stone slope for a second time. The wave-breaking groove is filled with oyster shells, and the height of the top surface of the oyster shell layer in the wave-breaking groove is lower than the top surface of the planting bed and the height of the top of the stone slope, so as to maintain the groove structure between the planting bed and the stone slope, and ensure the secondary weakening effect of the impact force of the waves. As the oyster shells grow, they are gradually squeezed toward the planting bed and the stone slope, so that the overall structure of the landscape restoration system composed of the planting bed, the wave-breaking groove and the stone slope can be made more stable, and at the same time, it can also drive the implantation, habitat and reproduction of marine organisms, effectively improving the landscape diversity and biodiversity of the coastline.

[0041] The height of the top of the stone slope is preferably higher than the average low tide level of the ocean. Preferably, at least 3 / 4 of the stone slope from top to bottom is located above the average low tide level of the ocean. This allows all or most of the landscape restoration system to leak out of the sea surface at low tide, thereby beautifying the coastline landscape. At high tide, the stone slope can have sufficient height and slope to weaken the impact of waves.

[0042] The top surface of the planting bed can be a plane or a slope that slopes downward from top to bottom toward the ocean. When the top surface of the planting bed is a plane, the height of the top of the stone slope is lower than the height of the top surface of the planting bed. When the top surface of the planting bed is a slope, the height of the top of the stone slope is lower than the height of the bottom of the planting bed, which can further reduce the impact of the waves that cross the wave-breaking grooves at high tide on the planting bed and landscape plants. The height of the top surface or top of the planting bed is lower than the average high tide level of the ocean, so that the landscape plants can leak out above the sea surface even at high tide. The top surface of the planting bed is preferably a slope that slopes downward from top to bottom toward the ocean, which can not only allow the seawater to retreat smoothly from the planting bed at low tide and reduce the amount of seawater on the planting bed, but also enable the plants in the landscape belt to form a stepped visual effect with a height difference, making the landscape belt more beautiful.

[0043] The slope of the planting bed is preferably no greater than 1:5, for example, 1:5, 1:6 or 1:7.

[0044] The slope of the block rock slope is preferably not less than 1:2.5, for example, 1:2.5, 1:2 or 1:1.5.

[0045] Preferably, two rows of anticorrosive wood piles are arranged closely transversely and inserted into the beach between the planting bed and the stone slope. The two rows of anticorrosive wood piles constitute the groove wall of the wave-breaking groove. The height of the front row of anticorrosive wood piles (the anticorrosive wood piles on the stone slope side) is lower than the height of the back row of anticorrosive wood piles (the anticorrosive wood piles on the planting bed side) and is the same as the height of the top of the stone slope. When the top surface of the planting bed is a plane, the height of the back row of anticorrosive wood piles is not lower than the height of the top surface of the planting bed and lower than the average high tide level of the ocean. When the top surface of the planting bed is an inclined surface, the height of the back row of anticorrosive wood piles is not lower than the height of the bottom of the planting bed, usually higher than the height of the bottom of the planting bed and lower than the height of the average high tide level of the ocean. The provision of two rows of anticorrosive wood piles can not only make the structure of the wave-breaking groove more stable and less prone to collapse, but also effectively block and weaken the waves during high tide. The back row of anticorrosive wood piles can also prevent the waves from directly impacting the planting bed, causing damage to the planting bed or soil loss.

[0046] The two rows of anticorrosive wood piles are preferably covered with geotextiles, and the bottom of the wave-breaking groove is preferably paved with geotextiles. The beach below the planting bed is paved with geotextiles, or the area of ​​the beach below the planting bed near the rear row of anticorrosive wood piles is paved with geotextiles, which is both water-permeable and can effectively prevent soil loss.

[0047] The planting bed adopts a multi-layer structure, preferably including a silt layer, a planting layer and an oyster shell layer from bottom to top. The silt layer can be paved on site using beach silt. The planting layer includes plant material bundles that are crisscrossed in a grid shape and planting soil filled in the grid. The landscape plants are planted in the planting soil of the planting layer and tied to the plant material bundles by geotextile ropes, which can effectively ensure that the landscape plants are stable and take root and sprout, improve the survival rate of plants, and avoid the landscape plants from falling down due to the impact of waves and the sweep of sea breeze in the early stage of planting, causing large-scale death. As time goes by, the plant material bundles gradually degrade, which can provide necessary nutrients for the growth of the planted landscape plants, and further ensure the healthy growth of the plants. The laying height of the oyster shell layer is preferably 100-150mm, which does not affect the growth of plants, prevents the silt and planting soil from being washed away by sea water, and can also improve the biodiversity of the coastline.

[0048] The beach is preferably a beach with a flat surface. If the beach is a rocky beach, the rocky beach surface can be compacted and leveled by using silt caulking.

[0049] The landscape plants are preferably mangrove plants, forming the main body of the mangrove landscape on the beach. The landscape plants may also be other evergreen trees or shrubs, forming a wetland woody plant community on the beach.

[0050] By applying the method of the present invention, when the sea water is high tide, the impact force of the waves can be weakened layer by layer through the block stone slope, the wave-breaking groove (including the groove structure and two rows of antiseptic wooden piles) and the oyster shell layer on the top of the planting bed, thereby effectively mitigating the impact of the waves on the planting bed and landscape plants, avoiding or reducing the loss of soil and silt, preventing the plants from lodging and dying, providing a stable growth environment for the planted plants, and promoting the rapid recovery of the landscape ecosystem.

[0051] See also Figure 1 The present invention also discloses a coastline landscape restoration system, which is applicable to the coastline landscape restoration method, including a planting bed 1 and a stone slope 2 arranged horizontally (referring to a direction parallel to or approximately parallel to the coastline) on a beach 12, the stone slope is located on the seaward side of the planting bed, and a gap is left between the two to form a wave-breaking groove 3, the top surface of the planting bed is a plane or an inclined surface inclined from top to bottom toward the ocean, the stone slope is laid inclined from top to bottom toward the ocean, and the height of the top of the slope is lower than the height of the top surface of the planting bed (when the top surface of the planting bed is a plane) or the bottom of the slope (when the top surface of the planting bed is an inclined surface), the wave-breaking groove is filled with oyster shells, the top surface of the oyster shell layer 4 in the wave-breaking groove is lower than the height of the top of the stone slope, and landscape plants 5 are planted on the planting bed.

[0052] The height of the top of the rock slope is preferably higher than the average low tide level of the ocean. Preferably, at least 3 / 4 of the rock slope from top to bottom is located above the average low tide level of the ocean.

[0053] The top surface of the planting bed (when the top surface of the planting bed is a plane) or the top of the slope (when the top surface of the planting bed is an inclined surface) is preferably lower than the average high tide level of the ocean. The top surface of the planting bed is preferably an inclined surface that slopes downward from top to bottom toward the ocean, and the slope of the planting bed is preferably not greater than 1:5, for example, 1:5, 1:6 or 1:7.

[0054] Preferably, the slope of the block stone slope is not less than 1:2.5, for example, 1:2.5, 1:2 or 1:1.5.

[0055] Two rows of anticorrosive wooden piles are preferably arranged closely transversely and inserted into the beach between the planting bed and the stone slope. The two rows of anticorrosive wooden piles constitute the groove wall of the wave-breaking groove. The height of the front row of anticorrosive wooden piles (the anticorrosive wooden piles on the stone slope side) 6 is lower than the height of the rear row of anticorrosive wooden piles (the anticorrosive wooden piles on the planting bed side) 7 and is the same as the height of the top of the stone slope. When the top surface of the planting bed is a plane, the height of the rear row of anticorrosive wooden piles is not lower than the height of the top surface of the planting bed and is lower than the average high tide level of the ocean. When the top surface of the planting bed is a slope, the height of the rear row of anticorrosive wooden piles is not lower than the height of the bottom of the slope of the planting bed, and is usually higher than the height of the bottom of the slope of the planting bed and lower than the height of the average high tide level of the ocean.

[0056] The anticorrosive wood pile can be made of pine wood pile or other wood materials coated with anticorrosive coating. To facilitate the insertion of the anticorrosive wood pile into the beach, the bottom end of the anticorrosive wood pile can be sharpened so that the bottom end of the anticorrosive wood pile is pointed or close to a pointed end.

[0057] The two rows of anticorrosive wood piles are preferably covered with geotextiles, and the bottom of the wave-breaking groove is preferably paved with geotextiles. The beach below the planting bed is paved with geotextiles, or the area of ​​the beach below the planting bed near the rear row of anticorrosive wood piles is paved with geotextiles, which is both water-permeable and can effectively prevent soil loss.

[0058] The unit area mass of the geotextile is preferably 150-300 g / m 2 , for example 150g / m 2 , 200g / m 2 or 300g / m 2 .

[0059] See also Figure 1 and Figure 2The planting bed adopts a multi-layer structure, preferably including a silt layer 8, a planting layer 9 and an oyster shell layer 10 from bottom to top. The silt layer can be paved on site using beach silt. The planting layer is provided with a planting layer skeleton 11 in the form of a grid formed by crisscrossing plant material bundles. The grid of the planting layer skeleton is buried in the planting soil of the planting layer, and the landscape plants are planted on the planting layer provided with the planting layer skeleton.

[0060] The landscape plants are preferably planted close to the plant material bundles and tied to the plant material bundles by geotextile ropes, which can effectively ensure that the landscape plants are stable and take root and sprout, improve the survival rate of plants, and avoid the landscape plants from falling over due to the impact of waves and sea breeze in the early stage of planting, causing large-scale death.

[0061] The grid of the planting layer skeleton is preferably a square grid, which is regular and beautiful. The landscape plants are preferably planted at the intersection (intersection area) of the transversely and longitudinally arranged plant material bundles, and are tied to the intersection of the transversely and longitudinally arranged plant material bundles by the geotextile ropes (not shown in the figure).

[0062] The plant material bundle may be a branch bundle, which is formed by bundling plant branches. The plant branches may be branches pruned from seedlings, willow branches or bamboos, so that garden waste can be reused and costs can be greatly saved. In order to ensure the stability of the plant material bundle and prevent it from spreading, ropes can be used to bundle the plant material bundles at a certain interval (for example, 200 mm).

[0063] During construction, part of the planting soil can be laid on the surface of the simply leveled silt layer first, and corresponding grooves can be dug on the surface of the laid planting soil according to the vertical and horizontal distribution of the plant material bundles required by the grid. A simple planting hole can be dug (expanded) at one side corner of the intersection of the vertical and horizontal grooves. The size and shape of the simple planting hole can be adjusted according to actual conditions. The plant material bundle is placed on the groove, with the lower part of the plant material bundle located in the groove and the upper part exposed above the groove. If necessary, a proper amount of planting soil is filled into the groove to facilitate the initial fixation of the plant material bundle. The roots / soil balls of the plants (trees) are placed in the corresponding simple planting holes. Since it is necessary to continue laying planting soil, the upper part of the tree roots / soil balls is exposed above the simple planting holes. If necessary, a proper amount of planting soil should also be filled into the gaps in the simple planting holes to facilitate the initial fixation of the plants. , bundle the vertical and horizontal intersections of the plant bundles and the connecting parts in any direction (if any) to form an overall structure. When bundling the vertical and horizontal intersections, bundle the plants located at the intersections together with the plant bundles from the thicker part of the area where their roots and trunks are connected, and then lay the planting soil again to cover or roughly cover the top of the plant bundles. When laying the planting soil this time, you should pay attention to filling the gaps in the simple planting holes and the gaps in the grooves first. The thickness of the planting soil after two layings should meet the corresponding thickness requirements of the planting layer. The main purpose of the first laying of planting soil is to facilitate the stability of the plant bundles and plants. The appropriate laying thickness can be set according to actual operation needs. The thickness and distribution of the plant bundles should be conducive to ensuring the stability of the planting layer and the fixation of the plants, which can be set according to actual conditions.

[0064] According to actual needs, after both planting soils are laid, plants can be planted after a certain period of stabilization (e.g., one month) or not. If necessary, the planting layer can be trimmed once or more during and / or at the end of the stabilization process.

[0065] The laying height of the oyster shell layer is preferably 100-150 mm, which does not affect plant growth, prevents silt and planting soil from being washed away by sea water, and improves the biodiversity of the coastline.

[0066] The beach is preferably a flat beach. The landscape plants are preferably mangrove plants, forming a main body of mangrove landscape on the beach. The landscape plants can also be other evergreen trees or shrubs, forming a wetland woody plant community on the beach.

[0067] A preferred construction method of the coastline landscape restoration system is:

[0068] (1) The beach surface is flat. If the beach is a rocky beach, the rocky beach surface is compacted and leveled by silt caulking. The height of the rock layer is 50-100 mm.

[0069] (2) Install the rear row of anticorrosive wood piles. The length of the rear row of anticorrosive wood piles is 4m, the diameter is 150mm, and one end is sharpened. The diameter of the sharpened end is 80mm. The depth of the rear row of anticorrosive wood piles inserted into the beach is 2.6m, and the length of the beach surface exposed is 1.4m (this length can be adjusted, and after completion, the top of the rear row of anticorrosive wood piles is 5-10cm below the average high tide level);

[0070] (3) The front row of anticorrosive wood piles are installed 500mm away from the seaward side of the rear row of anticorrosive wood piles. The length of the front row of anticorrosive wood piles is 4m, the diameter is 150mm, and one end is sharpened. The diameter of the sharpened end is 80mm. The depth of the front row of anticorrosive wood piles inserted into the beach is 3.1m, and the length of the beach surface exposed is 0.9m (the exposed length can be adjusted to ensure that the slope is consistent with the stone slope after construction);

[0071] (4) Specification: 150g / m 2 Geotextiles are used to cover the beach surface between two rows of anticorrosive wood piles, the beach surface behind the rear row of anticorrosive wood piles, and two rows of anticorrosive wood piles to control the leakage and loss of silt;

[0072] (5) Backfill silt to the rear side of the rear row of antiseptic wood piles to form a silt layer with a height of 950 mm;

[0073] (6) Lay bundles of branches (or other plant material bundles, the same below) with a diameter of 150 mm on top of the silt layer. Tie the bundles with ropes every 200 mm. Arrange and tie the bundles crosswise to form a 1000 mm × 1000 mm square. Fill the squares with planting soil to form a planting layer. Before laying out the bundles, lay a layer of planting soil of appropriate thickness to facilitate the stability of the bundles during the subsequent construction process.

[0074] (7) Planting landscape plants in the grid and tying the plant seedlings to the branch bundles at intervals of 1000 mm using geotextile ropes, usually at the intersection of the vertical and horizontal branch bundles;

[0075] (8) Lay oyster shells with a particle size of 50-80 mm on top of the planting layer to form an oyster shell layer to prevent silt from being washed away and lost by water flow. The laying height of the oyster shell layer is about 100 mm;

[0076] (9) Stack oyster shells with a particle size of 50-80 mm between two rows of antiseptic wooden piles, with a stacking height of 500 mm;

[0077] (10) Backfill the front side of the front row of antiseptic wood with boulders and stack them neatly to form a boulders slope. The top height of the boulders slope is 900 mm and the slope is 1:2.5.

[0078] Unless otherwise specified or one preferred or optional technical means is a further limitation of another technical means, all preferred and optional technical means disclosed in the present invention can be arbitrarily combined to form several different technical solutions.

Claims

1. A method for restoring a coastline landscape, characterized in that A planting bed is laid on the beach, and landscape plants are planted on the planting bed. A wave-breaking belt is set on the beach on the sea side of the planting bed, and the wave-breaking belt is used to mitigate the impact of waves on the planting bed and the landscape plants. The wave-breaking belt includes a stone slope and a wave-breaking groove. The stone slope is inclined from top to bottom toward the ocean and is used to weaken the impact force of waves once. A spacing is left between the stone slope and the planting bed to form the wave-breaking groove, which is used to weaken the impact force of waves twice. The wave-breaking groove is filled with oyster shells, and the top surface of the oyster shell layer in the wave-breaking groove is lower than the top surface of the planting bed and the top of the stone slope. Two rows of antiseptic wood piles are arranged closely horizontally and inserted into the beach between the planting bed and the stone slope. The two rows of antiseptic wood piles constitute the groove wall of the wave-breaking groove. The height of the antiseptic wood piles on the stone slope side is lower than the height of the antiseptic wood piles on the planting bed side and is the same as the height of the antiseptic wood piles on the stone slope side. The top heights of the block stone slopes are the same. The planting beds include a silt layer, a planting layer and an oyster shell layer from bottom to top. The planting layer includes plant material bundles that are crisscrossed in a grid shape and planting soil in which the grid-shaped plant material bundles are buried. The landscape plants are planted in the planting soil of the planting layer and tied to the plant material bundles by geotextile ropes. The plant material bundles are branch bundles formed by binding plant branches. During construction, part of the planting soil is first laid on the surface of the silt layer that has been simply leveled. Corresponding grooves are dug on the surface of the laid planting soil according to the vertical and horizontal distribution of the plant material bundles required by the grid. The plant material bundles are placed on the grooves, with the lower part of the plant material bundles located in the grooves and the upper part exposed above the grooves. Then the planting soil is laid again to cover or roughly cover the top of the plant material bundles. When laying the planting soil this time, attention should be paid to filling the gaps in the grooves first. The thickness of the planting soil after two layings should meet the corresponding thickness requirements of the planting layer.

2. The coastline landscape restoration method according to claim 1, characterized in that The top of the rock slope is higher than the average low tide level of the ocean.

3. The coastline landscape restoration method according to claim 2, characterized in that The top surface of the planting bed is a plane or a slope sloping downward toward the ocean, the top of the stone slope is lower than the top or bottom of the planting bed, and the top or top of the planting bed is lower than the average high tide level of the ocean.

4. The coastline landscape restoration method according to claim 3, characterized in that The height of the anticorrosive wood piles on the side of the planting bed is not lower than the height of the top surface or the bottom of the slope of the planting bed, and the two rows of the anticorrosive wood piles are covered with geotextiles.

5. The method for restoring the coastline landscape according to claim 4, characterized in that The bottom of the wave-breaking ditch is paved with geotextile.

6. Coastline landscape restoration system, characterized by The invention comprises a planting bed and a stone slope which are arranged transversely on the beach, the stone slope is located on the seaward side of the planting bed, a gap is left between the two to form a wave-breaking groove, the top surface of the planting bed is a plane or a slope which slopes downward from top to bottom toward the ocean, the stone slope is laid inclined downward from top to bottom toward the ocean, the height of the top of the slope is lower than the height of the top surface or the bottom of the planting bed, the wave-breaking groove is filled with oyster shells, the top surface of the oyster shell layer in the wave-breaking groove is lower than the height of the top of the stone slope, landscape plants are planted on the planting bed, two rows of antiseptic wooden piles which are closely arranged transversely and inserted into the beach are arranged between the planting bed and the stone slope, the two rows of antiseptic wooden piles constitute the groove wall of the wave-breaking groove, the height of the antiseptic wooden piles on the stone slope side is lower than the height of the antiseptic wooden piles on the planting bed side and is the same as the height of the top of the stone slope, and the planting bed is self-supporting. From bottom to top, it includes a silt layer, a planting layer and an oyster shell layer in sequence. The planting layer includes plant material bundles that are cross-shaped in a grid and planting soil in which the grid-shaped plant material bundles are buried. The landscape plants are planted in the planting soil of the planting layer and tied to the plant material bundles by geotextile ropes. The plant material bundles are branch bundles, which are formed by bundling plant branches. During construction, part of the planting soil is first laid on the surface of the silt layer that has been simply leveled. Corresponding grooves are dug on the surface of the laid planting soil according to the vertical and horizontal distribution of the plant material bundles required by the grid. The plant material bundles are placed on the grooves, with the lower part of the plant material bundles located in the grooves and the upper part exposed above the grooves. Then the planting soil is laid again to cover or roughly cover the top of the plant material bundles. When laying the planting soil this time, attention should be paid to filling the gaps in the grooves first. The thickness of the planting soil after two layings should meet the corresponding thickness requirements of the planting layer.

7. The coastline landscape restoration system according to claim 6, characterized in that The height of the antiseptic wood piles on the side of the planting bed is not lower than the height of the top surface or the bottom of the slope of the planting bed.

8. The coastline landscape restoration system according to claim 7, characterized in that The two rows of anticorrosive wooden piles are both covered with geotextiles.

9. The coastline landscape restoration system according to claim 8, characterized in that The bottom of the wave-breaking ditch is paved with geotextile.

10. The coastline landscape restoration system according to claim 9, characterized in that The landscape plants are planted at the vertical and horizontal intersections of the plant material bundles, close to the plant material bundles and tied to the horizontal and vertical intersections of the plant material bundles through geotextile ropes.

Citation Information

Patent Citations

  • Stepped water drop energy dissipation type mangrove forest ecological breakwater and working method thereof

    CN112681220A

  • Method for constructing suitable forest land of mangrove forest based on oyster reefs

    CN113179847A

  • Wood stake ecological revetment

    CN202298560U

  • Coastline landscape restoration system

    CN217694666U