A method for top-pushing construction of super-long curved steel box composite beams

By employing a separate jacking method and computer-controlled synchronous jacking technology, the problems of limited space and poor stability in the construction of ultra-long curved steel box girders were solved, achieving efficient and safe construction results.

CN115217040BActive Publication Date: 2024-11-01CCCC FOURTH HIGHWAY ENG CO LTD +2
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210581524.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-05-26
Publication Date
2024-11-01
Estimated Expiration
2042-05-26

AI Technical Summary

Technical Problem

Traditional construction methods for launching ultra-long curved steel box girders suffer from problems such as limited construction space, frequent girder displacement, poor construction stability, high equipment requirements, and low construction efficiency, making it difficult to meet the requirements for high-efficiency and safe and stable construction.

Method used

The separate launching method is adopted. First, launching platforms are erected on the supports of the left and right piers. The first steel box girder is launched first. Then, the second launching platform is erected based on the first steel box girder. The launching is carried out synchronously by computer control, and deviations are monitored and corrected in real time to reduce the impact of beam intersection and improve construction space and stability.

Benefits of technology

It increased construction space, reduced mutual interference between beams, improved construction safety and stability, saved on equipment investment, increased construction efficiency, and simplified construction procedures.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115217040B_ABST
    Figure CN115217040B_ABST
Patent Text Reader

Abstract

The present invention discloses a super-long curved steel box composite beam jacking construction method, comprising the following steps: 1) constructing a tire frame at the jacking starting point of the roadbed; 2) assembling the steel box beam and the guide beam on the tire frame; 3) setting up a right-span jacking support platform on the left and right bridge pier cap beams, and setting up jacking equipment on the right-span jacking support platform; carrying out the jacking construction of the right-span steel box beam, and after the jacking is in place, removing the right-span jacking support platform and the beam drop; 4) taking the right-span steel box beam as the foundation, setting up a left-span jacking support platform and jacking equipment above the left and right bridge pier cap beams, and the jacking process is the same as the right-span jacking. The present invention first sets up a first jacking platform, performs the first jacking, and then sets up a second jacking platform based on the first steel box beam, and performs the jacking of the second steel box beam, thereby increasing the construction space of the super-long curved steel box beam, avoiding the spatial intersection of the two beam bodies during jacking, reducing the adverse effects between the beam bodies, and improving the safety of the construction process.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge construction, and in particular to a top-pushing construction method for an ultra-long curved steel box composite beam. Background Art

[0002] Since the entire steel box girder bridge is heavy, the method of prefabricating the sections and then assembling and welding them into bridges is often used during on-site construction. For steel-concrete composite beam bridges, steel boxes are used as beams, and the panels are cast-in-place reinforced concrete structures. They are suitable for bridges with large spans and complex linear shapes; they have the advantages of light weight and short construction period. If a steel box girder bridge is built across an important trunk road, in order to avoid the construction of temporary auxiliary structures affecting the traffic on the trunk road, it is necessary to carry out steel box girder jacking construction. Extra-long means that the span between piers is longer and the span is higher, which is generally accompanied by the characteristics of higher piers; curve means that the bridge line is not in a straight line segment, and the line has complex curvature changes, which is generally accompanied by a longitudinal slope. Traditional walking-type jacking construction uses a multi-point three-phase jacking machine to jack the beam from a position convenient for hoisting construction to the designed position, and cooperates with deviation correction and beam dropping operations to carry out bridge construction.

[0003] Conventional steel box girder jacking usually involves only a single beam. If a separated bridge is jacked, the left and right spans will still be constructed in parallel and separately. However, if this method is used for the jacking construction of double-width curved steel box girders, a series of problems will arise:

[0004] 1. Due to the existence of curvature, the pushing beam will be offset during the walking-type pushing process, and the parallel construction of the left and right sections will interfere with each other. If the first section is pushed first and then the second section is pushed, the second section will be affected by the first section during the pushing process, and the construction space will be severely compressed.

[0005] 2. The parallel construction of the left and right sections requires two sets of systematic pushing equipment for both sections. Although the method of pushing the first section first and then the second section may only require one set of systematic pushing equipment for a single section (generally, two sets of systems will be used due to construction period requirements to avoid disassembly and movement time), the pushing cradle of the second section needs to be rearranged and will be moved during the construction process due to the influence of the first section.

[0006] 3. The process of bridge jacking construction generally includes three processes: jacking, deviation correction, and beam drop. Jacking is to push the beam along the bridge direction. Deviation correction is to correct the linear deviation of the beam during the process of pushing along the bridge. Beam drop is the operation of dropping the high-position beam to the designed height after jacking. In the three processes, jacking and deviation correction are intertwined. The deviation correction process is complicated. Frequent deviation correction will affect the stability of the entire jacking system. Therefore, the deviation correction process should be minimized during construction. No matter which method is used for jacking of the separated curved steel box girder, frequent deviation correction operations will occur during the construction process due to the small construction space.

[0007] 4. The columns on the pier are less connected and the system stability is poor.

[0008] 5. During the jacking and correction construction process, the judgment of the jacking step distance and the correction amount is often made by on-site personnel, which is highly subjective.

[0009] Therefore, the traditional construction method has the above-mentioned problems and cannot meet the needs of the jacking construction of ultra-long curved steel box girders. It is urgent to propose a jacking construction method that meets the requirements of high efficiency, safety and stability. Summary of the invention

[0010] In view of the problems existing in the background technology, the present invention proposes a method for jacking construction of an ultra-long curved steel box composite beam, which adopts a separate jacking method. First, a jacking platform is set up on the left and right pier supports to carry out the first jacking. Then, the form of the support arrangement is changed, and a second jacking platform is set up based on the first steel box beam to carry out jacking of the second steel box beam. This increases the construction space of the ultra-long curved steel box beam, avoids the spatial intersection of the two beams during jacking, reduces the adverse effects of the two beams on each other during the curved jacking process, and improves the safety of the construction process.

[0011] To achieve the above object, the present invention adopts the following technical solution: the super-long curved steel box composite beam top-pushing construction method comprises the following steps:

[0012] 1) A tire frame is constructed at the starting point of the jacking of the roadbed. The tire frame includes a tire frame support structure and jacking equipment;

[0013] 2) Assemble the guide beam on the tire frame, and then assemble the steel box beam after the guide beam is assembled;

[0014] 3) Set up a right-span jacking support platform on the left and right pier cap beams, and set up jacking equipment on the right-span jacking support platform; carry out jacking construction of the right-span steel box girder, push forward and splice the right-span steel box girder to the bridge position, and after the last segment is pushed into place, remove the right-span jacking support platform, and drop the right-span steel box girder as a whole onto the permanent support through the beam dropping equipment;

[0015] 4) With the right steel box girder as the foundation, set up a left-span jacking support platform above the left and right pier cap beams, and install jacking equipment on the left-span jacking support platform; push and splice the left steel box girder forward to the bridge position, and after the last segment is pushed into place, remove the left-span jacking support platform, and use the beam dropping equipment to drop the left steel box girder as a whole onto the permanent support.

[0016] Preferably, during the jacking process, observe the synchronous displacement sensor to monitor the jacking synchronization; observe the working status of the jacking equipment and measure the synchronization of each jacking equipment; use a computer to control the synchronous jacking, detect the movement deviation in real time, and correct it in time; monitor the horizontal displacement of the temporary pier in real time, combined with the jacking pressure observation.

[0017] Preferably, during the jacking process, the steel box girder is laterally moved and corrected by jacking equipment on the tire frame and the jacking support platform.

[0018] Preferably, the tire frame support structure includes a cushion beam, a first cushion block, a tire frame foundation, a support column a and a support beam, the pushing equipment is a walking jack, the cushion beam and the support beam are arranged in parallel at the same height, the cushion beam is installed on the front side above the tire frame foundation through the walking jack, the support beam is installed on the rear side of the tire frame foundation through the support column a, the steel box beam is placed on the cushion beam and the support beam, and the first cushion block is arranged on the right side of the top of the cushion beam and the support beam.

[0019] Preferably, the right-width pushing support platform comprises a support column b, a support column c, a first crossbeam and a second crossbeam, the first crossbeam being installed above the front side of the pier through the support column b, the second crossbeam being installed above the rear side of the pier through the support column c, the support columns b and c being connected by a first cross-connection, the first crossbeam being installed on the top of the support column b, the second crossbeam being installed on the top of the support column c, the first crossbeam and the second crossbeam being connected by a second cross-connection, a pushing device being installed on the top of the first crossbeam and the second beam, the pushing device being a walking jack, a pad beam being installed on the top of the walking jack, a support beam having the same height as the pad beam being installed on the top of the second beam through the support column a, and the right-width steel box girder being placed on the pad beam and the support beam.

[0020] Preferably, the bottoms of support columns b and support columns c are fixed to the piers by embedded parts, the first cross beam and support column b, the second cross beam and support column c are connected and reinforced by setting diagonal braces, and the first pad block is arranged on the right side of the top of the pad beam and the support beam.

[0021] Preferably, the left-width pushing support platform comprises a support column b, a support column c, a first crossbeam and a second crossbeam. The left side of the first crossbeam is installed above the front side of the left-width pier through the support column b, and the left side of the second crossbeam is installed above the rear side of the left-width pier through the support column c. The support column b and the support column c are connected by a first cross-connection. The left side of the first crossbeam is installed on the top of the support column b, and the left side of the second crossbeam is installed on the top of the support column c. The right sides of the first crossbeam and the second crossbeam are respectively installed on the top of the right-width steel box girder through second pads. The first crossbeam and the second crossbeam are connected by a second cross-connection. A pushing device is installed on the top of the first crossbeam and the second beam. The pushing device is a walking jack, and a pad beam is installed on the top of the walking jack. A support beam of the same height as the pad beam is installed on the top of the second crossbeam through the support column a, and the left-width steel box girder is placed on the pad beam and the support beam.

[0022] Preferably, the first cross beam and the support column b, the second cross beam and the support column c, and the left steel box beam and the first cross beam and the second cross beam are connected and reinforced by setting diagonal braces.

[0023] Preferably, a first column foot is arranged on the outer side of the bottom of support column a, a first column cap is arranged on the outer side of the top of support column a, and a second column foot and a second column cap are arranged on the bottom and top ends of support columns b and support columns c respectively.

[0024] Preferably, a pump station is provided in the middle of the pier, a safety construction platform is provided around the top of the pier, safety passages are provided on the outer sides of the first beam and the second beam respectively, and safety guardrails are provided on the outer sides of the safety passages.

[0025] Beneficial effects of the present invention:

[0026] 1. The present invention first sets up a first jacking platform on the left and right pier supports to jack-push the first steel box girder, and then sets up a second jacking platform based on the first steel box girder to jack-push the second steel box girder, thereby increasing the construction space of the super-long curved steel box girder, avoiding the spatial intersection of the two beams during jacking, reducing the adverse effects of the two beams on each other during the curved jacking process, and improving the safety of the construction process.

[0027] 2. The jacking platform support of the present invention connects the left and right pier supports, and the stability of the structural system of the first jacking is enhanced. The jacking platform set up during the second jacking is built with the help of the box girder of the first jacking, and the stability is further enhanced.

[0028] 3. The layout of the tire frame and the pushing platform during the second pushing process of the present invention are similar to those of the first pushing process, and the pushing process is similar to the first pushing process. The entire construction procedure does not require major changes, which improves construction efficiency. In addition, only one set of pushing equipment is required for the entire construction period, saving equipment investment. BRIEF DESCRIPTION OF THE DRAWINGS

[0029] Figure 1 It is a plan view of the top-pushing construction arrangement of the right steel box girder of the present invention;

[0030] Figure 2 for Figure 1 Elevation drawing of

[0031] Figure 3 It is a plan view of the top-pushing construction arrangement of the left steel box girder of the present invention;

[0032] Figure 4 for Figure 3 Elevation drawing of

[0033] Figure 5 It is a schematic diagram of the arrangement of the pushing equipment on the tire frame of the present invention;

[0034] Figure 6 for Figure 5 Side view of;

[0035] Figure 7 It is a schematic diagram of the arrangement of the support structure on the tire frame of the present invention;

[0036] Figure 8 for Figure 7 Side view of;

[0037] Fig. 9 It is a schematic diagram of the jacking support platform and jacking equipment of the right steel box girder of the present invention;

[0038] Fig.10 for Fig. 9 Side view of;

[0039] Fig.11 It is a schematic diagram of the arrangement of the jacking support platform and support columns of the right steel box girder of the present invention;

[0040] Fig.12 for Fig.11 Side view of;

[0041] Fig.13 It is a schematic diagram of the jacking support platform and jacking equipment of the left steel box girder of the present invention;

[0042] Fig.14 for Fig.13 Side view of;

[0043] Fig.15 It is a schematic diagram of the arrangement of the jacking support platform and support columns of the left steel box girder of the present invention;

[0044] Fig.16 for Fig.15 Side view of;

[0045] Fig.17 It is a schematic diagram of the structure of the support column b and the support column c of the present invention;

[0046] Fig.18 It is a structural schematic diagram of a support column a of the present invention;

[0047] Fig.19 It is a plan view of the pump station and the safe construction platform of the present invention;

[0048] Fig. 20 It is a side view of the pump station and the safe construction platform of the present invention;

[0049] Fig.21 It is the AA cross-sectional view of the present invention;

[0050] Fig. 22 It is a schematic diagram of the safety passage structure of the present invention;

[0051] The numbers in the figure are: left pier 1; right pier 2; right steel box girder 3; left steel box girder 4; permanent support 5; support column b6; support column c7; embedded parts 8; diagonal brace 9; walking jack 10; cushion beam 11; first cushion block 12; second column foot 13; second column cap 14; first cross link 15; first cross beam 16; second cross beam 17; second cross link 18; tire frame foundation 19; safe construction platform 20; second cushion block 21; support column a22; support beam 23; guide beam 24; first column foot 25; first column cap 26; pump station 27; safety passage 28; safety guardrail 29. DETAILED DESCRIPTION

[0052] In order to make the objectives, technical solutions and beneficial effects of the present invention more clear, the preferred embodiments of the present invention will be described in detail below with reference to the accompanying drawings to facilitate understanding by technicians.

[0053] Please refer to Figures 1 to 16 The super-long curved steel box composite beam top-pushing construction method comprises the following steps:

[0054] 1) The tire frame is constructed at the starting point of the top push of the roadbed. The tire frame includes the tire frame support structure and the top push equipment. The tire frame production sequence is: first install the foundation steel bars and embedded parts, then make the tire frame foundation. After the tire frame foundation meets the requirements, install the tire frame support column, crossbeam, top push equipment, and finally inspect and accept.

[0055] 2) Assemble the steel box girder on the tire frame. After the steel box girder is processed in sections in the factory, it is transported to the construction site by trailer. On the roadbed, a truck crane is used to lift the guide beam 24 and the first part of the steel box girder in sections to the tire frame for assembly and welding. CO2 shielded welding is used for welding. After welding, the top-pushing equipment is installed in place to ensure the overall anti-overturning property of the structure and the maximum cantilever steel box girder downwinding. The guide beam 24 uses a truss structure, which consists of two welded H-shaped beams. The two guide beams are supported and connected by tie rods, and holes are opened in the web of the guide beam to reduce its own weight. The guide beam 24 is welded at the sections, and the welds are required to be fully penetrated. The web of the main limb of the guide beam 24 and the web of the steel box beam are butt-jointed by full-penetration single-side groove welding, and the top and bottom plates of the guide beam 24 and the top and bottom plates of the steel box beam are butt-jointed by full-penetration single-side groove welding. .

[0056] 3) First, a right span jacking support platform is set up on the cap beams of the left span pier 1 and the right span pier 2, and a jacking device is set up on the right span jacking support platform. Because the bridge is located on a circular curve, a gentle curve and a straight section, in order to make the jacking conform to the linear shape and reduce the number of lateral deviation corrections, it is necessary to assemble the steel box girder and the guide beam 24 on the left span roadbed in the assembly area. Then the right span steel box girder 3 is jacked. When the jacking steel box girder moves forward 20 meters, the two subsequent segment steel box girders are assembled (and so on). After the last segment is assembled, the rear guide beam is set at the tail, and the steel box girder is continued to be jacked to the designed bridge position, and the guide beam is removed. The simply supported end of the steel box girder falls to the permanent support 5, and a temporary support is set at the continuous end to ensure the pre-throw height at the steel box girder support. The beam dropping equipment is removed, and the temporary support is removed after the concrete pouring is completed. The steel box girder falls to the permanent support 5, and the installation of the bridge steel box girder is completed.

[0057] 4) Secondly, with the right steel box girder 3 as the foundation, a left-span jacking support platform is set up above the left-span bridge pier 1 cap beam and the right-span steel box girder 3, and a jacking device is set up on the left-span jacking support platform. The jacking sequence of the left-span steel box girder is the same as that of the right-span steel box girder. The left-span steel box girder is continuously pushed forward and spliced ​​to the bridge position. After the last segment is pushed into place, the left-span jacking support platform is removed, and the left-span steel box girder is dropped as a whole onto the permanent support through the beam dropping device.

[0058] Through the above-mentioned jacking construction method, the left and right steel box girders are separated for jacking construction, which increases the construction space of the super-long curved steel box girder, avoids the spatial intersection of the two beams during jacking, reduces the adverse effects of the two beams on each other during the curved jacking process, and improves the safety of the construction process. At the same time, the jacking platform bracket connects the left and right pier brackets, and the stability of the structural system of the first jacking is enhanced. The jacking platform set up during the second jacking is built with the help of the box girder of the first jacking, and the stability is further enhanced. Among them, the tire frame layout and jacking platform during the jacking process of the second jacking are similar to those of the first jacking, and the jacking process is similar to the jacking process of the first jacking. The entire construction procedure does not need to be significantly changed, which improves the construction efficiency, and only one set of jacking equipment is required for the entire construction period, saving equipment investment.

[0059] Furthermore, during the jacking process, the synchronous displacement sensor is observed to monitor the jacking synchronization. During jacking, the working status of the jacking equipment is observed and the synchronization of each jacking equipment is measured. The synchronous jacking is controlled by a computer, and the movement deviation is detected in real time, and the deviation is corrected in time to avoid the single jacking cylinder from being overloaded. The horizontal displacement of the temporary pier is monitored in real time, combined with the observation of the jacking pressure, to prevent the temporary pier from being damaged.

[0060] Furthermore, according to the linear shape of the left and right axes of the steel box girder, and with the reasonable arrangement of the tire frame position on the roadbed as the premise, the steel box girder is moved and corrected laterally by the tire frame and the jacking equipment on the jacking support platform during the jacking process. During the jacking process, always ensure that the support column and the walking jack are within the 2m width of the bottom of the two box chambers of the single steel box girder, otherwise it is necessary to temporarily adjust the support column and the position of the jacking equipment.

[0061] Furthermore, the tire frame support structure includes a cushion beam 11, a first cushion block 12, a tire frame foundation 19, a support column a22 and a support beam 23. The jacking device is a walking jack 10. The cushion beam 11 and the support beam 23 are arranged in parallel and at the same height. The cushion beam 11 is installed on the front side above the tire frame foundation 19 through the walking jack 10, and the support beam 23 is installed on the rear side of the tire frame foundation 19 through the support column a22. The steel box girder is placed on the cushion beam 11 and the support beam 23. By matching the tire frame with the jacking device and the support structure, the support stability of the steel box girder assembly process is guaranteed. At the same time, after the steel box girder is assembled, it can be used as the starting position for the jacking construction. The first cushion block 12 is arranged on the right side of the top of the cushion beam 11 and the support beam 23 to support the steel box girder installed above, ensuring that the center of gravity of the steel box girder remains stable.

[0062] Further, the right-width jacking support platform comprises a support column b6, a support column c7, a first crossbeam 16 and a second crossbeam 17, wherein the first crossbeam 16 is installed above the front side of the pier through the support column b6, and the second crossbeam 17 is installed above the rear side of the pier through the support column c7, the support columns b6 and c7 are connected by a first cross link 15, the first crossbeam 16 is installed on the top of the support column b6, the second crossbeam 17 is installed on the top of the support column c7, the first crossbeam 16 and the second crossbeam 17 are connected by a second cross link 18, and a jacking device is installed on the top of the first crossbeam 16 and the second crossbeam 17, the jacking device is a walking jack 10, a cushion beam 11 is installed on the top of the walking jack 10, a support beam 23 with the same height as the cushion beam 11 is installed on the top of the second crossbeam 17 through the support column a22, and the right-width steel box girder 3 is placed on the cushion beam 11 and the support beam 23. The right-width jacking support platform uses the left-width pier 1 and the right-width pier 2 as the installation foundation at the same time to ensure the stability of the supporting structure. In addition, the bottoms of the support columns b6 and c7 are fixed to the piers through embedded parts 8, and the first cross beam 16 and the support column b6, and the second cross beam 17 and the support column c7 are connected and reinforced by diagonal braces 9, which ensures the structural strength of the jacking platform. The first cushion block 12 is arranged on the right side of the top of the cushion beam 11 and the support beam 23 to support the steel box beam and maintain the stability of the center of gravity.

[0063] Furthermore, the left-width jacking support platform comprises a support column b6, a support column c7, a first crossbeam 16 and a second crossbeam 17. The left side of the first crossbeam 16 is installed above the front side of the left-width pier column 1 through the support column b6, and the left side of the second crossbeam 17 is installed above the rear side of the left-width pier column 1 through the support column c7. The support columns b6 and c7 are connected by a first cross link 15. The left side of the first crossbeam 16 is installed on the top of the support column b6, and the left side of the second crossbeam 17 is installed on the top of the support column c7. The right sides of the beam 16 and the second beam 17 are respectively installed on the top of the right steel box beam 3 through the second pad 21, the first beam 16 and the second beam 17 are connected by the second cross link 18, and the top of the first beam 16 and the second beam 17 is installed with a jacking device, which is a walking jack 10, and the top of the walking jack 10 is installed with a pad beam 11, and the top of the second beam 17 is installed with a support beam 23 of the same height as the pad beam 11 through a support column a22, and the left steel box beam 4 is placed on the pad beam 11 and the support beam 23. Among them, the second pad 21 is installed on the web of the right steel box beam 3 to ensure the safety of the right steel box beam 3. The left jacking support platform is installed on the left pier 1 and the right steel box beam 3, and the structure is stable. At the same time, the height of the left-span jacking support platform is basically the same as that of the right-span jacking support platform. There is no need to adjust the front tire frame position and jacking equipment, and basically only the same set of support components and jacking equipment as the right-span jacking platform are needed, saving equipment investment. In addition, at this time, the left-span jacking platform is located above the right-span steel box girder 3, and the jacking operation space reserved is consistent with the right-span jacking process, so that the left-span steel box girder 4 is basically not affected by the right-span steel box girder 3 during jacking, which greatly improves the convenience and efficiency of the jacking construction of the left-span steel box girder 4. Similarly, the first crossbeam 16 and the support column b6, the second crossbeam 17 and the support column c7, and the left-span steel box girder 4 and the first crossbeam 16 and the second crossbeam 17 are connected and reinforced by setting diagonal braces 9 to ensure the stability of the supporting structure.

[0064] Furthermore, if Fig.17 and Fig.18 As shown, a first column foot 25 is arranged on the outer side of the bottom of the support column a22, a first column cap 26 is arranged on the outer side of the top of the support column a22, and a second column foot 13 and a second column cap 14 are arranged on the bottom and top ends of the support columns b6 and c7 respectively, thereby ensuring the structural strength of the support columns a22, b6 and c7.

[0065] Furthermore, if Figures 19 to 22 As shown, a pump station 27 is arranged in the middle of the pier, and a safety construction platform 20 is arranged around the top of the pier. Safety passages 28 are respectively arranged on the outside of the first cross beam 16 and the second cross beam 17, and safety guardrails 29 are arranged on the outside of the safety passages 28 to provide a platform and space for the workers to operate during the jacking work, thereby providing convenience for the construction.

[0066] In summary, compared with the traditional parallel separation construction method of the left and right steel box girders, the left and right jacking support platforms use the left and right piers as the interconnected support foundation, which not only expands the operating space of the jacking platform, but also increases the stability of the jacking platform. It can especially adapt to the situation where the center of gravity of the ultra-long curved steel box girder is constantly shifted during the jacking process, and the jacking process is stable. At the same time, the height of the left and right jacking support platforms arranged successively and the reserved operating space are basically the same, and there is no need to make too many adjustments to the layout of the construction site and the equipment used, which reduces the number of corrections and greatly improves the construction efficiency. At the same time, the jacking process of the left and right steel box girders does not interfere with each other, which improves the safety and efficiency of the construction process.

[0067] Finally, it should be noted that the above preferred embodiments are only used to illustrate the technical solutions of the present invention rather than to limit it. Although the present invention has been described in detail through the above preferred embodiments, those skilled in the art should understand that various changes can be made in form and details without departing from the scope defined by the claims of the present invention.

Claims

1. A method for pushing construction of super-long curved steel box composite beams. It is characterized in that The following steps are involved: 1) A tire frame is constructed at the starting point of the jacking of the roadbed, and the tire frame includes a tire frame support structure and jacking equipment; 2) Assemble the steel box beam on the tire frame, and assemble the guide beam after the steel box beam is assembled; 3) Set up a right-span jacking support platform on the left and right pier cap beams, and set up jacking equipment on the right-span jacking support platform; carry out jacking construction of the right-span steel box girder, splice and jack-push the right-span steel box girder forward to the bridge position, and after the last segment is jack-pushed into place, remove the right-span jacking support platform, and drop the right-span steel box girder as a whole onto the permanent support through the beam-dropping equipment; 4) With the right steel box girder as the foundation, set up a left-span jacking support platform above the left and right pier cap beams, and set up jacking equipment on the left-span jacking support platform; splice and jack-push the left steel box girder forward to the bridge position, and after the last segment is jack-pushed into place, remove the left-span jacking support platform, and drop the left steel box girder as a whole onto the permanent support through the beam-dropping equipment; The tire frame support structure comprises a cushion beam (11), a first cushion block (12), a tire frame foundation (19), a support column a (22) and a support beam (23); the pushing device is a walking jack (10); the cushion beam (11) and the support beam (23) are arranged in parallel and at the same height; the cushion beam (11) is installed on the front side above the tire frame foundation (19) through the walking jack (10); the support beam (23) is installed on the rear side of the tire frame foundation (19) through the support column a (22); the steel box beam is placed on the cushion beam (11) and the support beam (23); and the first cushion block (12) is arranged on the right side of the top of the cushion beam (11) and the support beam (23); The right-width pushing support platform comprises a support column b (6), a support column c (7), a first crossbeam (16) and a second crossbeam (17). The first crossbeam (16) is installed on the front upper side of the left-width pier column (1) and the right-width pier column (2) through the support column b (6). The second crossbeam (17) is installed on the rear upper side of the left-width pier column (1) and the right-width pier column (2) through the support column c (7). The support column b (6) and the support column c (7) are connected by a first cross link (15). The first crossbeam (16) is installed on the top of the support column b (6). A second crossbeam (17) is installed on the top of the support column c (7), the first crossbeam (16) and the second crossbeam (17) are connected via a second cross link (18), a jacking device is installed on the top of the first crossbeam (16) and the second crossbeam (17), the jacking device is a walking jack (10), a cushion beam (11) is installed on the top of the walking jack (10), a support beam (23) of the same height as the cushion beam (11) is installed on the top of the second crossbeam (17) via a support column a (22), and the right steel box beam (3) is placed on the cushion beam (11) and the support beam (23); The left-width pushing support platform comprises a support column b (6), a support column c (7), a first cross beam (16) and a second cross beam (17). The left side of the first cross beam (16) is installed above the front side of the left-width pier column (1) through the support column b (6). The left side of the second cross beam (17) is installed above the rear side of the left-width pier column (1) through the support column c (7). The support columns b (6) and the support columns c (7) are connected by a first cross link (15). The left side of the first cross beam (16) is installed on the top of the support column b (6). The left side of the second cross beam (17) is installed on the top of the support column c (7). The first cross beam (16) The first cross beam (16) and the second cross beam (17) are respectively installed on the top of the right steel box beam (3) through the second cushion block (21), the first cross beam (16) and the second cross beam (17) are connected by the second cross link (18), and a jacking device is installed on the top of the first cross beam (16) and the second cross beam (17), and the jacking device is a walking jack (10). A cushion beam (11) is installed on the top of the walking jack (10), and a support beam (23) with the same height as the cushion beam (11) is installed on the top of the second cross beam (17) through a support column a (22), and the left steel box beam (4) is placed on the cushion beam (11) and the support beam (23).

2. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: During the jacking process, observe the synchronous displacement sensors to monitor the jacking synchronization; observe the working status of the jacking equipment and measure the synchronization of each jacking equipment; use the computer to control the synchronous jacking, detect the movement deviation in real time, and correct it in time; monitor the horizontal displacement of the temporary pier in real time, combined with the jacking pressure observation.

3. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: During the jacking process, the jacking equipment on the tire frame and the jacking support platform is used to move the steel box girder laterally and correct its deviation.

4. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: The bottoms of the support columns b (6) and c (7) are fixed to the pier column via embedded parts (8); the first cross beam (16) and the support column b (6), and the second cross beam (17) and the support column c (7) are connected and reinforced by arranging diagonal braces (9); and a first cushion block (12) is arranged on the right side of the top of the cushion beam (11) and the support beam (23).

5. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: The first cross beam (16) and the support column b (6), the second cross beam (17) and the support column c (7), and the left steel box beam (4) and the first cross beam (16) and the second cross beam (17) are all connected and reinforced by arranging diagonal braces (9).

6. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: A first column foot (25) is arranged on the outer side of the bottom of the support column a (22), a first column cap (26) is arranged on the outer side of the top of the support column a (22), and a second column foot (13) and a second column cap (14) are arranged on the bottom and top ends of the support column b (6) and the support column c (7), respectively.

7. The method for pushing construction of super-long curved steel box composite beam according to claim 1, Features: A pump station (27) is arranged in the middle of the pier column, a safety construction platform (20) is arranged around the top of the pier column, and safety passages (28) are arranged outside the first cross beam (16) and the second cross beam (17), respectively, and safety guardrails (29) are arranged outside the safety passages (28).