A stepped core soil auxiliary reinforcement device for a dark tunnel and a construction method thereof

By using oblique support rods and baffle structures to fix the soil in the underground excavation tunnel, the problem of the stepped core soil slipping or collapsing due to not being excavated for a long time is solved, and the stability of the soil is improved and construction safety is achieved. Sexual security.

CN115288702BActive Publication Date: 2024-09-27CHINA FIRST METALLURGICAL GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210848697.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-07-19
Publication Date
2024-09-27
Estimated Expiration
2042-07-19

AI Technical Summary

Technical Problem

In underground excavation tunnel projects, the stepped core soil is easily affected by the groundwater level and upper load because it has not been excavated for a long time, resulting in soil slippage or collapse.

Method used

Design a stepped core soil auxiliary reinforcement device for underground excavation tunnels, which adopts diagonally supported reinforced support rods and baffle structures. It is fixed in the soil through a combined locking mechanism of steel nails and sliding grooves, and is connected using bolts and wire ropes. and fixed to ensure the firmness and integrity of the support rod.

Benefits of technology

It effectively improves the stability of the soil, prevents slippage and collapse, enhances the support performance, ensures safety and convenience during the construction process, and the installation and disassembly process is simple and does not cause strong disturbance.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115288702B
    Figure CN115288702B
Patent Text Reader

Abstract

The present invention provides an auxiliary reinforcement device for stepped core soil of a dark-excavated tunnel and a construction method thereof. The reinforcement device is obliquely supported and fixed around the stepped core soil. The reinforcement device includes a plurality of reinforcement support rods for oblique support and a plurality of baffles arranged between adjacent reinforcement support rods. The reinforcement support rod includes a middle reinforcement support rod body, steel nails at both ends of the reinforcement support rod body, and a fixed joint vertically fixed in the middle of the reinforcement support rod body. Connection holes are provided at both ends of the fixed joint. The baffle is connected and fixed to the connection holes on the reinforcement support rod by bolts. The present invention is improved on the basis of the traditional underground dark-excavated stepped core soil, and solves the problem that the traditional stepped core soil is easily affected by the groundwater level and upper related loads during a long period of non-continuation of excavation, and the soil body is easily slipped or collapsed, and the supporting performance is also greatly improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of engineering construction stepped core soil reinforcement, and in particular relates to a stepped core soil auxiliary reinforcement device for a dark-excavated tunnel and a construction method thereof. Background Art

[0002] At present, the method of reserving core soil is very common in underground tunnel projects. During the excavation of the pilot tunnel, construction operators usually use a scraper, excavator + manual excavation method to excavate. After a certain distance, the soil is excavated into a stepped core soil shape, and then the support system in the pilot tunnel is constructed. Since the soil in the pilot tunnel is not excavated for a long time, it will be affected by the groundwater level and related upper loads during the process, and it is easy to slip or collapse. Therefore, it is necessary to take further reinforcement measures for the core soil to ensure its stability during the construction process.

[0003] In order to solve the above problems, the present invention proposes to design a stepped core soil auxiliary reinforcement device for a dark-excavated tunnel and a construction method thereof, by which the problems and difficulties of stepped core soil reinforcement can be fully solved. Summary of the invention

[0004] In view of the problem in the prior art that the soil body is easily slipped or collapsed due to the influence of the groundwater level and the upper related load when the soil body is not excavated for a long time, the technical solution adopted by the present invention to solve the problems existing in the prior art is as follows:

[0005] A device for auxiliary reinforcement of stepped core soil in a dark-excavated tunnel, wherein the reinforcement device is obliquely supported and fixed around the stepped core soil, the reinforcement device comprises a plurality of reinforcement support rods 1 for oblique support, and a plurality of baffles 2 arranged between adjacent reinforcement support rods, the reinforcement support rod 1 comprises a middle reinforcement support rod body 7, steel nails 8 located at both ends of the reinforcement support rod body 7, a fixing joint 9 vertically fixed to the middle of the reinforcement support rod body, connection holes are provided at both ends of the fixing joint 9, and the baffle 2 is connected and fixed to the connection holes on the reinforcement support rod 1 by bolts.

[0006] The end of the steel nail 8 is provided with a steel nail connector 5 which is perpendicular to the steel nail, and both ends of the reinforcement support rod body 7 are provided with sliding grooves 6, and the steel nail 8 and the reinforcement support rod body 7 are slidably connected through the sliding grooves 6.

[0007] The steel nail connector 5 is in the shape of a long strip, and the outer end of the sliding groove 6 is provided with a snap-in slot that is consistent with the thickness of the steel nail connector 5. When the steel nail extends to both ends of the reinforcement support rod and is inserted into the soil, the steel nail connector 5 is rotated and the steel nail connector is snapped into the snap-in slot at the end of the sliding groove to fix the steel nail.

[0008] The steel nail connecting head is provided with connecting holes at both ends, and the edge of the baffle 2 is provided with a plurality of connecting holes. The spacing between the connecting holes at the edge of the baffle is consistent with the spacing between the connecting holes on the steel nail connecting head 5 and the connecting holes on the middle fixed joint 9. The baffle 2 is connected and fixed to the reinforcement support rod by bolts passing through the aligned connecting holes.

[0009] The baffle 2 is made of steel.

[0010] The construction method of the stepped core soil auxiliary reinforcement device for a dark excavated tunnel comprises the following steps:

[0011] Step 1: Position the reinforcement support rod: After the excavation of the stepped core soil of the pilot tunnel is completed, the reinforcement support rod is placed obliquely around the stepped core soil to position the reinforcement support rod;

[0012] Step 2: Drive in steel nails: After the reinforcement support rod is positioned, use a hammer to hit the steel nail connector, and drive the upper and lower steel nails into the soil after grouting reinforcement along the direction of the sliding groove. After they are fully driven in, rotate the steel nail connector to embed it into the bayonet position of the sliding groove to lock it;

[0013] Step 3, fix the baffle: after the steel nails are driven into the reinforcement support rod and locked, place the baffles on the upper side of the support rod in turn, align them with the connection holes, and lock them in turn with bolts;

[0014] Step 4: Bind the steel wire rope: After the last baffle is installed and locked, bind the unused connectors on the edge of the reinforcement support rod with steel wire rope.

[0015] Step 5: Overall adjustment: After completing the above steps, check the device by pressing or vertically tapping it, and reinforce any loose positions in time to ensure the stability of the device during use.

[0016] The present invention is an improvement on the traditional underground stepped core soil, which solves the problem that the traditional stepped core soil is easily affected by the groundwater level and the upper related load during the long period of non-excavation, and the soil body slides or collapses easily, and the supporting performance is also greatly improved. The specific advantages are as follows:

[0017] 1. The present invention adopts the form of reinforced support rods for support. By erecting them at the core soil position of the dark excavated tunnel, the upper and lower parts of the soil body after grouting reinforcement can be supported, ensuring that the soil body has an additional vertical support under normal conditions, and the stability of the soil body is effectively improved during the construction of the working surface;

[0018] 2. The reinforcement support rod adopts a structure in which a sliding groove is combined with a steel nail connector. After the reinforcement support rod body is positioned, the steel nails are hammered into the upper and lower parts of the soil to lock them. This structure can ensure the firmness of the reinforcement support rod and provide more effective support and reinforcement for the loosening of the soil in the later stage.

[0019] 3. Add connection holes on the steel nail connection head of the reinforcement support rod body. After the reinforcement support rod is fixed, it is connected to the baffle by bolts, and the edge reinforcement support rod is locked and connected with a steel wire rope, which can enhance the integrity of the device and ensure that the device can resist the pressure caused by the loosening of the soil when it is impacted by the soil, and is not prone to falling off or instability.

[0020] 4. During the installation and disassembly process, the combination of reinforced support rods and baffles is adopted. Through simple manual installation, the construction process is not only convenient, but also can ensure that no strong disturbance occurs in the dark excavation channel during the construction process, thereby ensuring the overall safety of the support process. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a front view of the device of the present invention;

[0022] Figure 2 To reinforce the large-scale drawing of the support rod;

[0023] Figure 3 Detailed construction of the steel nail connection head Figure I ;

[0024] Figure 4 Detailed construction of the steel nail connection head Figure II ;

[0025] Figure 5 This is a large-scale drawing of the baffle;

[0026] Figure 6 A three-dimensional diagram of the device of the present invention in use;

[0027] Figure 7 This is a side view of the device of the present invention in use.

[0028] Among them: 1-reinforcement support rod, 2-baffle, 3-connection hole, 4-steel wire rope, 5-steel nail connector, 6-sliding groove, 7-reinforcement support rod body, 8-steel nail, 9-fixed joint, 10-plate body, 11-reinforcement device, 12-soil after grouting reinforcement, 13-working surface, 14-core soil. DETAILED DESCRIPTION

[0029] The technical solution of the present invention is further described in detail below through embodiments and in conjunction with the accompanying drawings. Figure 1-7As shown, a stepped core soil auxiliary reinforcement device for a dark excavated tunnel is provided. The reinforcement device is obliquely supported and fixed around the stepped core soil. The reinforcement device includes a plurality of reinforcement support rods 1 for oblique support, and a plurality of steel baffles 2 arranged between adjacent reinforcement support rods. The reinforcement support rod 1 includes a middle reinforcement support rod body 7, steel nails 8 located at both ends of the reinforcement support rod body 7, and steel nail connectors 5 perpendicular to the steel nails are provided at the ends of the steel nails 8. Sliding grooves 6 are provided at both ends of the reinforcement support rod body 7. The steel nails 8 are slidably connected to the reinforcement support rod body 7 through the sliding grooves 6. The steel nail connector 5 is in the shape of an elongated strip, and the outer end of the sliding groove 6 is provided with a steel nail connector 5 that is perpendicular to the steel nails. The steel nail connecting head 5 has a bayonet with consistent thickness. When the steel nail extends to both ends of the reinforcement support rod and is inserted into the soil, the steel nail connecting head 5 is rotated and the steel nail connecting head 5 is snapped into the bayonet at the end of the sliding groove 6 to fix the steel nail 8; a fixing joint 9 is vertically fixed in the middle of the reinforcement support rod 7, and connecting holes are provided at both ends of the fixing joint 9. Connecting holes are also provided at both ends of the steel nail connecting head 5. A plurality of connecting holes are provided at the edge of the baffle 2. The spacing between the connecting holes at the edge of the baffle is consistent with the spacing between the connecting holes on the steel nail connecting head 5 to the connecting holes on the middle fixing joint 9. The baffle 2 is connected and fixed to the reinforcement support rod by bolts passing through the aligned connecting holes.

[0030] A construction method for a stepped core soil auxiliary reinforcement device for a dark excavated tunnel comprises the following steps:

[0031] Step 1: Position the reinforcement support rod: After the excavation of the stepped core soil of the pilot tunnel is completed, the reinforcement support rod is placed obliquely around the stepped core soil to position the reinforcement support rod;

[0032] Step 2: Drive in steel nails: After the reinforcement support rod is positioned, use a hammer to hit the steel nail connector, and drive the upper and lower steel nails into the soil after grouting reinforcement along the direction of the sliding groove. After they are fully driven in, rotate the steel nail connector to embed it into the bayonet position of the sliding groove to lock it;

[0033] Step 3, fix the baffle: after the steel nails are driven into the reinforcement support rod and locked, place the baffles on the upper side of the support rod in turn, align them with the connection holes, and lock them in turn with bolts;

[0034] Step 4: Bind the steel wire rope: After the last baffle is installed and locked, bind the unused connectors on the edge of the reinforcement support rod with steel wire rope.

[0035] Step 5: Overall adjustment: After completing the above steps, check the device by pressing or vertically tapping it, and reinforce any loose positions in time to ensure the stability of the device during use.

[0036] The protection scope of the present invention is not limited to the above-mentioned embodiments. Obviously, those skilled in the art can make various changes and modifications to the present invention without departing from the scope and spirit of the present invention. If these changes and modifications fall within the scope of the claims of the present invention and their equivalents, the present invention is intended to include these changes and modifications.

Claims

1. A stepped core soil auxiliary reinforcement device for a dark excavated tunnel, characterized in that: The reinforcement device is obliquely supported and fixed around the stepped core soil, and the reinforcement device includes a plurality of reinforcement support rods for oblique support, and a plurality of baffles arranged between adjacent reinforcement support rods, the reinforcement support rod includes a middle reinforcement support rod body, steel nails located at both ends of the reinforcement support rod body, and a fixing joint vertically fixed to the middle of the reinforcement support rod body, and connection holes are provided at both ends of the fixing joint, and the baffle is connected and fixed to the connection holes on the reinforcement support rod by bolts; The end of the steel nail is provided with a steel nail connector perpendicular to the steel nail, and both ends of the reinforcement support rod body are provided with sliding grooves, and the steel nail and the reinforcement support rod body are slidably connected through the sliding grooves; The steel nail connector is in the shape of a long strip, and a snap-on socket having the same thickness as the steel nail connector is provided at the outer end of the sliding groove. When the steel nail extends to both ends of the reinforcement support rod and is inserted into the soil, the steel nail connector is fixed by rotating the steel nail connector and snapping it into the snap-on socket at the end of the sliding groove.

2. The stepped core soil auxiliary reinforcement device for a dark excavated tunnel according to claim 1, characterized in that: The steel nail connecting head is provided with connecting holes at both ends, and the edge of the baffle is provided with a plurality of connecting holes. The spacing between the connecting holes at the edge of the baffle is consistent with the spacing between the connecting holes on the steel nail connecting head and the connecting holes on the middle fixed joint. The baffle is connected and fixed to the reinforcement support rod by bolts passing through the aligned connecting holes.

3. The stepped core soil auxiliary reinforcement device for a dark excavated tunnel according to claim 1, characterized in that: The baffle is made of steel.

4. A construction method for a stepped core soil auxiliary reinforcement device for a dark excavated tunnel as claimed in any one of claims 1 to 3, characterized in that: The steps include: Step 1: Position the reinforcement support rod: After the excavation of the stepped core soil of the pilot tunnel is completed, the reinforcement support rod is placed obliquely around the stepped core soil to position the reinforcement support rod; Step 2: Drive in steel nails: After the reinforcement support rod is positioned, use a hammer to hit the steel nail connector, and drive the upper and lower steel nails into the soil after grouting reinforcement along the direction of the sliding groove. After they are fully driven in, rotate the steel nail connector to embed it into the bayonet position of the sliding groove to lock it; Step 3, fix the baffle: after the steel nails are driven into the reinforcement support rod and locked, place the baffles on the upper side of the support rod in turn, align them with the connection holes, and lock them in turn with bolts; Step 4: Bind the steel wire rope: After the last baffle is installed and locked, bind the unused connectors on the edge of the reinforcement support rod with steel wire rope; Step 5: Overall adjustment: After completing the above steps, check the device by pressing or vertically tapping it, and reinforce any loose positions in time to ensure the stability of the device during use.