Method for controlling the solid phase of drilling fluid during oil drilling
By employing a combined control method of filtration, sedimentation, and grouting devices in different stages of drilling fluid processing, the problem of high solid content in drilling fluid was solved, achieving a low solid state in drilling fluid, reducing costs and waste, and improving cleaning efficiency.
Patent Information
- Application Number
- CN202110524191.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-05-13
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2041-05-13
AI Technical Summary
Existing methods for controlling the solid phase of drilling fluids suffer from problems such as waste and increased costs due to high solid content, and it is difficult to maintain a low solid content state continuously.
A solid phase control device consisting of a filtration device, a sedimentation device, and a grouting device controls the solid phase of the drilling fluid in different steps of drilling, connecting single sections, and retrieving drilling equipment through different process flows. This includes using a combination of multi-terminal connecting pipes and valves to achieve a low solid phase state of the drilling fluid.
It effectively reduces the high solids content of drilling fluid, improves cleaning efficiency, reduces drilling fluid maintenance costs, avoids waste of drilling fluid and mud, maintains the low solids state of drilling fluid, and reduces bentonite content and flow conditioner usage.
Smart Images

Figure CN115341865B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the field of solid phase control of drilling fluid, and in particular to a method for controlling the solid phase of drilling fluid during oil drilling. Background Art
[0002] Drilling fluid is the blood of drilling. There are ten recognized functions of drilling fluid: cleaning the bottom of the well and carrying cuttings. Cooling and lubricating the drill bit and drill string. Balancing the side pressure of the well wall rock, forming filter cake on the well wall, sealing and stabilizing the well wall. Balancing (controlling) the formation pressure. Suspending cuttings and weighting agents. Sinking sand and cuttings on the ground. Effectively transmitting hydraulic power. Bearing part of the gravity of the drill pipe and casing. Providing a large amount of information about the drilled formation. Hydraulically breaking rocks. The high-speed jet formed by the drilling fluid through the nozzle can directly break or assist in breaking rocks.
[0003] Drilling circulation places higher requirements on drilling fluid. Drilling fluid needs to maintain low bentonite content and low solid phase for a long time. The general solid phase control process of drilling fluid is: wellhead → elevated tank → vibrating screen → conical tank → desander → desilter → centrifuge. The bottom sedimentation treatment of the conical tank is a very important link. The sedimentation at the bottom of the conical tank needs to be discharged and treated regularly by the staff. The following problems arise during the treatment process: (1) The discharge cycle is short. The sedimentation and high solid phase drilling fluid are discharged together. It is difficult for the staff to distinguish the sedimentation and drilling fluid with the naked eye. There is no unified standard for the discharge volume, which requires the staff to have certain experience. Therefore, a large amount of drilling fluid will be lost during the sand discharge process. The drilling fluid needs to be reconfigured to replenish the loss, resulting in an increase in the cost of drilling fluid maintenance. (2) The discharge treatment cycle is long, the large amount of sedimentation, and the continuous entry of cuttings into the circulation system are the main reasons for the high solid phase and high bentonite content. It poses a major threat to the safety of the drilling fluid, aggravates the irreversible pollution of the gasoline layer, and increases the cost of drilling.
[0004] Based on the above situation, there is an urgent need to provide a method that can continuously control the low solid phase of drilling fluid, so as to ensure that the drilling fluid can continuously maintain a low solid phase state in the well. Summary of the invention
[0005] The embodiment of the present invention provides a method for controlling the solid phase of drilling fluid during oil drilling, which can ensure that the drilling fluid continuously maintains a low solid phase state in the well.
[0006] On the one hand, the present invention provides a method for controlling the solid phase of drilling fluid during oil drilling, comprising the following steps: when the drilling equipment is drilling, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a first method; when the drilling equipment is connecting a single root, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a second method; when the drilling equipment is fishing out of the well, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a third method.
[0007] In some optional embodiments, the solid phase control equipment of the drilling fluid includes a filtering device, a sand settling device and a grouting device. The outlet of the filtering device is connected to the inlet of the sand settling device. The outlet of the sand settling device is installed with a first multi-terminal connecting pipe. The first pipe of the first multi-terminal connecting pipe is connected to the inlet of the grouting device. The outlet of the grouting device is installed with a second multi-terminal connecting pipe. The second pipe of the second multi-terminal connecting pipe is connected to the inlet of the filtering device.
[0008] In some optional embodiments, the first pipeline is installed with a first valve, and the second pipeline is installed with a second valve.
[0009] In some optional embodiments, it is characterized in that the first multi-end connecting pipeline also includes a third pipeline and a fourth pipeline, the third pipeline is connected to the outlet of the sand settling device, and the fourth pipeline is installed with a third valve.
[0010] In some optional embodiments, the second multi-end connecting pipeline further includes a fifth pipeline and a sixth pipeline, the fifth pipeline is connected to the outlet of the grouting device, the sixth pipeline is connected to the wellhead, and the sixth pipeline is installed with a fourth valve.
[0011] In some optional embodiments, a seventh pipeline is further included, and the grouting device is connected to the seventh pipeline of the metering device through the seventh pipeline, and the seventh pipeline is installed with a fifth valve.
[0012] In some optional embodiments, the solid phase control device for the drilling fluid further includes an elevated tank, the inlet of the elevated tank is connected to the wellhead, and the outlet of the elevated tank is connected to each of the filtering devices via a connecting channel.
[0013] In some optional embodiments, during the drilling step of the drilling equipment, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid in a first manner, including: blocking a portion of the connecting channel before starting the drilling equipment; filtering drill cuttings through a portion of the filtering device during the drilling of the cement plug by the drilling equipment; after the drilling equipment has processed the cement plug, filtering the drilling fluid returned from the wellhead through a portion of the filtering device; waiting for a preset time period, opening the remaining filtering devices, closing the fourth valve and the fifth valve, opening the first valve and the second valve, and starting the grouting device.
[0014] In some optional embodiments, during the step of connecting single roots by the drilling equipment, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a second method, including: keeping the grouting device in continuous operation.
[0015] In some optional embodiments, in the step of retrieving the drilling equipment from the well, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid in a third manner, including: closing the first valve when stopping the drilling fluid pump; waiting for the grouting device to continue running for a preset period of time and then pausing; after the grouting device is paused, opening the fourth valve and the fifth valve, and closing the second valve.
[0016] Compared with the prior art, the present invention has the following technical effects:
[0017] 1. The solid phase control equipment of the drilling fluid uses different methods to control the state of the drilling fluid in the drilling step of the drilling equipment, the step of connecting a single root by the drilling equipment, and the step of fishing the drilling equipment out of the well, so that there is no dead angle in the solid phase treatment of the drilling fluid, and the drilling fluid is continuously kept in a low solid phase state.
[0018] 2. The staff found that in the solid phase control steps of drilling fluid, the elevated tank → vibrating screen → conical tank is the key to handling the solid phase state of drilling fluid. The solid phase control equipment of drilling fluid can maintain the low solid phase state of drilling fluid by changing the process flow without replacing the original equipment, thus reducing costs and avoiding waste.
[0019] 3. The high solid phase removal efficiency of the drilling fluid is improved, the density increase of the drilling fluid during the circulation step in the well disappears, the bentonite content of the drilling fluid is reduced, and the solid phase content of the drilling fluid is reduced.
[0020] 4. It avoids the discharge of drilling fluid and sediment together, thus avoiding waste. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the invention and, together with the description, serve to explain the principles of the invention.
[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, for ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative labor.
[0023] Figure 1 It is a process flow chart of the method for controlling the solid phase of drilling fluid during oil drilling provided by the present invention;
[0024] Figure 2 It is a schematic diagram of the structure of a solid phase control device for drilling fluid provided in an embodiment of the present invention.
[0025] Figure markings: 1-filtering device; 2-sand settling device; 3-grouting device; 4-second multi-terminal connecting pipe; 41-first pipe; 411-first valve; 42-third pipe; 43-fourth pipe; 431-third valve; 5-second multi-terminal connecting pipe; 51-second pipe; 511-second valve; 52-fifth pipe; 53-sixth pipe; 531-fourth valve; 6-metering device; 61-seventh pipe; 611-fifth valve; 7-elevated trough; 71-connecting channel. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the embodiments of the present application clearer, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of this application.
[0027] The present application provides a solid phase control device for drilling fluid, the solid phase control device for drilling fluid comprises a filtering device 1, a sand settling device 2 and a grouting device 3, the outlet of the filtering device 1 is connected to the inlet of the sand settling device 2, the outlet of the sand settling device 2 is installed with a first multi-terminal connecting pipe, the first pipe 41 of the first multi-terminal connecting pipe 4 is connected to the inlet of the grouting device 3, the outlet of the grouting device 3 is installed with a second multi-terminal connecting pipe 5, and the second pipe 51 of the second multi-terminal connecting pipe 5 is connected to the inlet of the filtering device 1.
[0028] Specifically, the first multi-terminal connecting pipeline 4 is a pipeline connected in three directions, and the first multi-terminal connecting pipeline 4 includes a first pipeline 41, a third pipeline 42 and a fourth pipeline 43. The first pipeline 41 is installed with a first valve 411, the third pipeline 42 is connected to the outlet of the sand settling device 2, the fourth pipeline 43 is installed with a third valve 431, and the fourth pipeline 43 is a pipeline that does not go to the ground. The second multi-terminal connecting pipeline 5 is a pipeline connected in three directions, and the second multi-terminal connecting pipeline 5 includes a second pipeline 51, a fifth pipeline 52 and a sixth pipeline 53. The fifth pipeline 52 is connected to the outlet of the grouting device 3, and the sixth pipeline 53 is connected to the wellhead. The second pipeline 52 is installed with a second valve 511, and the sixth pipeline 53 is installed with a fourth valve 531.
[0029] In some optional embodiments, the solid phase control device of the drilling fluid further includes an elevated tank 7, the inlet of the elevated tank 7 is connected to the wellhead, and the outlet of the elevated tank 7 is connected to each filter device 1 through a connecting channel 71. Optionally, there are three connecting channels 71, which are divided into connecting channel No. 1, connecting channel No. 2 and connecting channel No. 3. Connecting channel No. 1, connecting channel No. 2 and connecting channel No. 3 are respectively connected to the inlet of the vibrating screen, the outlet of the vibrating screen is connected to the inlet of the sand settling tank, and one connecting channel 71 is connected to a sand settling tank.
[0030] Furthermore, the solid phase control equipment of the drilling fluid also includes a seventh pipeline 61 , through which the grouting device 3 is connected to the seventh pipeline of the metering device 6 , and the seventh pipeline 61 is installed with a fifth valve 611 .
[0031] Optionally, the filtering device 1 is a vibrating screen, the sand settling device 2 is a sand settling tank, and the grouting device 3 is a grouting pump.
[0032] The present invention finds that in the conventional solid phase treatment process of drilling fluid, the elevated tank→vibrating screen→conical tank is the focus of treating the solid phase state of drilling fluid. The solid phase control equipment of drilling fluid installs a three-way pipe at the bottom of the conical tank and a three-way pipe at the outlet of the grouting pump without replacing the original equipment. The solid phase control equipment of drilling fluid respectively controls different valves inside the two three-way pipes in different ways in the drilling step of the drilling equipment, the step of connecting a single root of the drilling equipment and the step of fishing the drilling equipment out of the well, so as to achieve the drilling fluid always maintaining a low solid phase state during the circulation of the drilling fluid in the well, effectively reduce the poor solid phase content of the drilling fluid, maintain the cleanliness of the drilling fluid, reduce the maintenance cost of drilling and drilling fluid, keep the drilling equipment safe and efficient during the drilling process, reduce the discharge of drilling fluid and save costs.
[0033] In some optional embodiments, during the drilling step of the drilling equipment, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid in a first manner, including: blocking part of the connecting channel 71 before starting the drilling equipment, filtering the drill cuttings through part of the filtering device 1 during the drilling of the cement plug, and filtering the drilling fluid returned from the wellhead through part of the filtering device 1 after the drilling equipment has processed the cement plug; waiting for a preset time period, opening the remaining filtering devices 1, closing the fourth valve 531 and the fifth valve 611, opening the first valve 411 and the second valve 511, and starting the grouting device 3.
[0034] Furthermore, before the drilling equipment is started, two of the connecting channels 71 in the elevated trough are blocked by a baffle, for example, the No. 2 connecting channel 71 and the No. 3 connecting channel 71 can be blocked, and the drill cuttings after the drill bit drills the cement plug need to be processed by the vibrating screens corresponding to the No. 2 connecting channel 71 and the No. 3 connecting channel. After the drill bit drills the cement plug, the vibrating screens corresponding to the No. 2 connecting channel and the No. 3 connecting channel are immediately opened to process the drilling fluid returned from the wellhead. After waiting for 5-10 minutes, the vibrating screen corresponding to the No. 1 connecting channel 71 is opened, the fourth valve 531 and the fifth valve 611 are closed, the first valve 411 and the second valve 511 are opened, and then the grouting pump is started. Before the grouting pump is turned on, it is necessary to pump for a few weeks so that the high solid phase state of the drilling fluid can be continuously removed.
[0035] Optionally, the vibrating screen corresponding to the No. 1 connecting channel 71 uses a screen cloth of 120-140 mesh, the vibrating screen corresponding to the No. 2 connecting channel 71 uses a screen cloth of 120-140 mesh, and the vibrating screen corresponding to the No. 3 connecting channel 71 uses a screen cloth of more than 200 mesh.
[0036] In some optional embodiments, during the step of single-root connection by the drilling equipment, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a second method, including: keeping the grouting device 3 in continuous operation, that is, during the process of single-root connection by the drilling equipment, the grouting pump is continuously operated to continuously remove the high solid phase state of the drilling fluid.
[0037] In some optional embodiments, during the process of retrieving the drilling equipment from the well, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid through a third method, including: closing the first valve 411 when stopping the drilling fluid pump; after waiting for the grouting device 3 to continuously operate for a preset period of time, opening the fourth valve 531 and the fifth valve 611, and closing the second valve 511.
[0038] Specifically, during the drilling process, after the drilling fluid pump stops running, the first valve 411 is immediately closed, and after the grouting device 3 continues to operate for 1 minute, the fourth valve 531 and the fifth valve 611 are opened, the second valve 511 is closed, and then the drilling equipment is retrieved from the well normally.
[0039] The present invention provides a method for controlling the solid phase of drilling fluid during oil drilling, comprising: in the step of drilling by drilling equipment, the solid phase control device of drilling fluid controls the solid phase of drilling fluid by a first method; in the step of connecting a single root by drilling equipment, the solid phase control device of drilling fluid controls the solid phase of drilling fluid by a second method; in the step of fishing out the drilling equipment from the well, the solid phase control device of drilling fluid controls the solid phase of drilling fluid by a third method. The solid phase control device of drilling fluid controls the drilling fluid by different methods in the step of drilling by drilling equipment, the step of connecting a single root by drilling equipment and the step of fishing out the drilling equipment from the well, respectively, achieving the following technical effects: (1) There is no dead angle in the high solid phase treatment of drilling fluid, and all are converted to continuous removal. (2) The high solid phase removal efficiency of drilling fluid is higher, the natural increase of drilling fluid density disappears, the bentonite content of drilling fluid is reduced from ≥120g / L to ≤80g / L, the solid phase content of drilling mud is reduced by an average of 1.6%, and the calculated solid phase removal efficiency is increased from ≤70% to ≥85%. (3) The use of flow regulator in drilling fluid is reduced by 38.6%, the average use of filtration agent and mud cake enhancer is reduced by 26.7%, and the total cost of drilling fluid maintenance and treatment is reduced by more than 30% on average. (4) Drilling fluid achieves "0" discharge, and the amount of waste liquid treated without mud falling to the ground is reduced by more than 30% on average. (5) Drilling fluid solid control equipment can allow larger fiber particles to pass through. After treatment, the anti-leakage slurry can block the 40-60 mesh sand bed, with a pressure bearing capacity of ≥3.5MPa and a closed filtration loss of ≤15mL.
[0040] Specifically, as shown in Table 1 below, Table 1 is the data comparing the natural rise density and bentonite content of the Minghua bottom drilling fluid in the field implementation well and the comparison well. The data in each implementation well is the data of the process implemented by the present invention. The data in each comparison well is the data of the state of the drilling fluid controlled by the traditional process. It can be seen from Table 1 that the method for controlling the solid phase of the drilling fluid in the oil drilling process provided by the present invention has played an obvious effect in the actual production process, so that the drilling fluid always maintains low-density drilling fluid and low bentonite content during the circulation process of the implementation well.
[0041]
[0042] Table 1
[0043] Specifically, as shown in Table 2 below, Table 2 compares the bentonite content and solid content of the drilling fluid in the on-site implementation wells and the comparison wells. The data in each implementation well is the data of the process implemented by the present invention. The data in each comparison well is the data of the state of the drilling fluid controlled by the traditional process. It can be seen from Table 2 that the method for controlling the solid phase of the drilling fluid during the oil drilling process provided by the present invention has played an obvious effect in the actual production process. It can be seen from Table 2 that the completion density of the drilling fluid in the comparison well and the implementation well has not changed, but the solid content of the drilling fluid has decreased significantly.
[0044]
[0045] Table 2
[0046] Specifically, as shown in Table 3 below, Table 3 is the comparison data of the amount of residual liquid in the mud that does not fall to the ground in the implementation well and the comparison well. The data in each implementation well is the data of the process implemented by the present invention. The data in each comparison well is the data of the state of the drilling fluid controlled by the traditional process. The method for controlling the solid phase of the drilling fluid in the oil drilling process provided by the present invention has played an obvious effect in the actual production process. It can be seen from Table 3 that the amount of residual liquid in the mud that does not fall to the ground in the implementation well is significantly reduced.
[0047]
[0048]
[0049] Table 3
[0050] Specifically, as shown in Table 4 below, Table 4 is the comparative data of the consumption of drilling fluid materials in the implementation wells and the comparison wells. The data in each implementation well is the data of the process implemented by the present invention. The data in each comparison well is the data of the state of drilling fluid controlled by the traditional process. The method for controlling the solid phase of drilling fluid in the oil drilling process provided by the present invention has played an obvious effect in the actual production process. It can be seen from Table 4 that the viscosity reducer, filtration loss reducer, and mud cake improver of the drilling fluid in the implementation well have been significantly reduced.
[0051]
[0052] Table 4
[0053] In addition, the term "and / or" in this article is only a description of the association relationship between the associated objects, indicating that there can be three relationships. For example, A and / or B can represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " in this article generally indicates that the associated objects before and after are in an "or" relationship.
[0054] It should be understood that in the embodiment of the present invention, "B corresponding to A" means that B is associated with A, and B can be determined according to A. However, it should also be understood that determining B according to A does not mean determining B only according to A, and B can also be determined according to A and / or other information.
[0055] The above is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed by the present invention, and these modifications or replacements should be included in the protection scope of the present invention. Therefore, the protection scope of the present invention shall be based on the protection scope of the claims.
Claims
1. A method for controlling the solid phase of drilling fluid during oil drilling, comprising the following steps: During the drilling step of the drilling equipment, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a first method; When the drilling equipment is performing the step of connecting a single root, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a second method; In the step of fishing out the drilling equipment from the well, the solid phase control device of the drilling fluid controls the solid phase of the drilling fluid by a third method; The solid phase control equipment of the drilling fluid includes a filtering device (1), a sand settling device (2) and a grouting device (3); The outlet of the filtering device (1) is connected to the inlet of the sand settling device (2); the outlet of the sand settling device (2) is provided with a first multi-end connecting pipe (4); the first pipe (41) of the first multi-end connecting pipe (4) is connected to the inlet of the grouting device (3); the outlet of the grouting device (3) is provided with a second multi-end connecting pipe (5); the second pipe (51) of the second multi-end connecting pipe (5) is connected to the inlet of the filtering device (1); The first pipeline (41) is installed with a first valve (411), and the second pipeline (51) is installed with a second valve (511); The first multi-end connecting pipeline (4) further comprises a third pipeline (42) and a fourth pipeline (43), wherein the third pipeline (42) is connected to the outlet of the sand settling device (2), and the fourth pipeline (43) is provided with a third valve (431); The second multi-end connecting pipeline (5) further comprises a fifth pipeline (52) and a sixth pipeline (53), wherein the fifth pipeline (52) is connected to the outlet of the grouting device (3), the sixth pipeline (53) is connected to the wellhead, and the sixth pipeline (53) is installed with a fourth valve (531); The drilling fluid solid phase control device further comprises an elevated tank (7), the inlet of the elevated tank (7) is connected to the wellhead, and each outlet of the elevated tank (7) is connected to each filtering device (1) in a one-to-one correspondence through a connecting channel (71); It also comprises a seventh pipeline (61), the grouting device (3) is connected to the metering device (6) via the seventh pipeline, and the seventh pipeline (61) is installed with a fifth valve (611); The first method is specifically: Before the drilling equipment is started, a portion of the connecting passage (71) is blocked; The drilling equipment filters drill cuttings through a partial filtering device (1) during the process of drilling the cement plug; After the drilling equipment has processed the cement plug, the drilling fluid returned from the wellhead is filtered through a partial filtering device (1); Waiting for a preset time period, opening the remaining filtering devices (1), closing the fourth valve (531) and the fifth valve (611), opening the first valve (411) and the second valve (511), and starting the grouting device (3); The second method includes: Keeping the grouting device (3) in continuous operation; The third method includes: When the drilling fluid pump is stopped, the first valve (411) is closed; after the grouting device (3) is allowed to operate continuously for a preset period of time, it is paused; after the grouting device (3) is paused, the fourth valve (531) and the fifth valve (611) are opened, and the second valve (511) is closed.