Geological exploration methods, devices and equipment for deep buried long tunnels
Through horizontal drilling equipment and well logging equipment, geological information around the deep buried long tunnel is obtained, and a three-dimensional geological model is generated, which solves the problems of insufficient geological exploration accuracy and construction interference in the existing technology, and improves the safety and construction period management of tunnel construction.
Patent Information
- Application Number
- CN202210946064.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-08
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2042-08-08
AI Technical Summary
In the prior art, the geological exploration accuracy of the deep buried long tunnel is insufficient in the early stage of construction, resulting in serious construction interference during the advance forecast process and the inability to provide accurate geological data, which in turn affects the safety and construction period of the tunnel construction.
The horizontal drilling equipment is used to drill the core along the preset direction of the large displacement well to obtain the geological information of the core, and combine the well logging equipment to obtain the geological information around the drilling hole to generate a three-dimensional geological model to guide the deep buried long tunnels. construction.
Through precise geological information acquisition and three-dimensional model generation, we avoid construction interference, improve the utilization rate of geological information, ensure the safety and construction period of tunnel construction, and provide scientific construction guidance.
Smart Images

Figure CN115343782B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of geological exploration, and in particular to a geological exploration method, device and equipment applied to deep buried long tunnels. Background Art
[0002] Deep buried long tunnels have to pass through complex geological structures along the way, and there may be geological disaster risks such as rock bursts, water inrush, and tunnel boring machine jams during construction. Geological exploration methods are used to obtain geological structure information of tunnels, thereby guiding the construction of tunnel projects.
[0003] In the prior art, vertical drilling is performed on the ground in the early stage, and geological prediction work for the tunnel project is performed through advanced prediction methods during the construction period.
[0004] However, in the above method, since the accuracy of the previous geological exploration cannot meet the construction requirements of deep and long tunnels, there is significant construction interference in the advance prediction process, resulting in a low utilization rate of tunnel geological information, and unable to provide accurate geological data, and thus unable to accurately guide tunnel construction operations. Summary of the invention
[0005] The present application provides a geological exploration method, device and equipment for deep buried long tunnels, which are used to solve the problem that accurate construction advice cannot be made due to construction interference in the advance prediction process.
[0006] In a first aspect, the present application provides a geological exploration method for a deep buried long tunnel, comprising:
[0007] Acquire first geological information of a core obtained by drilling and coring with a horizontal drilling device, wherein the core is collected by drilling and coring with the horizontal drilling device along a preset direction of a deep-buried long tunnel in an extended-reach well; the first geological information represents geological information of the core; the extended-reach well is arranged above the central axis of the deep-buried long tunnel;
[0008] Acquire second geological information of the borehole generated by the logging equipment after coring the drilling, wherein the second geological information represents geological information around the borehole;
[0009] Generate a three-dimensional geological model based on the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel;
[0010] According to the three-dimensional geological model, the construction equipment is controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel.
[0011] In a feasible implementation mode, during the geological exploration of a deep-buried long tunnel to be excavated, first, a large displacement well is set above the central axis of the deep-buried long tunnel, and a horizontal drilling device is used to drill and coring along a preset direction of the deep-buried long tunnel in the large displacement well, and the core is analyzed and the geological structure information of the core is obtained; then, based on the borehole generated after drilling and coring, the geological information around the borehole is obtained from the logging equipment; and then, according to the geological structure information of the core and the geological information around the borehole, a three-dimensional geological model can be generated; thus, according to the three-dimensional geological model, the geological information around the deep-buried long tunnel to be excavated can be obtained, and then the construction equipment can be controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel, which is beneficial to the construction of the deep-buried long tunnel.
[0012] In a second aspect, the present application provides a geological exploration device for a deep buried long tunnel, comprising:
[0013] A first acquisition unit is used to acquire first geological information of a core obtained by a horizontal drilling device through drilling and coring, wherein the core is collected by the horizontal drilling device through drilling and coring along a preset direction of a deep-buried long tunnel in an extended displacement well; the first geological information represents the geological information of the core; the extended displacement well is arranged above the central axis of the deep-buried long tunnel;
[0014] A second acquisition unit is used to acquire second geological information of the borehole generated by the logging equipment after the drilling and coring, wherein the second geological information represents geological information around the borehole;
[0015] A generating unit, configured to generate a three-dimensional geological model according to the first geological information and the second geological information; wherein the three-dimensional geological model represents geological information around the deep-buried long tunnel;
[0016] A control unit is used to control the construction equipment to perform tunnel excavation and tunnel construction on the deep buried long tunnel according to the three-dimensional geological model.
[0017] In a feasible implementation, during the geological exploration of a deep-buried long tunnel to be excavated, first, a first acquisition unit uses a horizontal drilling device to drill and coring along a preset direction of the deep-buried long tunnel in a large displacement well, analyzes the core and obtains the geological structure information of the core; then, based on the borehole generated after the drilling and coring, a second acquisition unit obtains the geological information around the borehole from the logging equipment; then, based on the geological structure information of the core and the geological information around the borehole, the generation unit can generate a three-dimensional geological model; thus, based on the three-dimensional geological model, the control unit can obtain the geological information around the deep-buried long tunnel to be excavated, and then control the construction equipment to perform tunnel excavation and tunnel construction on the deep-buried long tunnel, which is facilitating the construction of the deep-buried long tunnel.
[0018] In a third aspect, an embodiment of the present application provides an electronic device, including: a memory, a processor;
[0019] Memory; Memory for storing instructions executable by the processor;
[0020] The processor is configured to execute the method described in the first aspect.
[0021] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium, wherein the computer-readable storage medium stores computer-executable instructions, and when the computer-executable instructions are executed by a processor, they are used to implement the method described in the first aspect.
[0022] In a fifth aspect, an embodiment of the present application provides a computer program product, comprising: a computer program, wherein the computer program is stored in a readable storage medium, at least one processor of an electronic device can read the computer program from the readable storage medium, and the at least one processor executes the computer program so that the electronic device executes the method described in the first aspect.
[0023] The present application provides a geological exploration method, device and equipment for deep-buried long tunnels, which obtain first geological information of cores obtained by horizontal drilling equipment for coring, wherein the cores are collected by the horizontal drilling equipment for coring along a preset direction of a deep-buried long tunnel in a large displacement well; obtain second geological information of the borehole generated by the logging equipment after drilling and coring, wherein the second geological information represents geological information around the borehole; generate a three-dimensional geological model based on the first geological information and the second geological information; wherein the three-dimensional geological model represents geological information around the deep-buried long tunnel; and control construction equipment to perform tunnel excavation and tunnel construction on the deep-buried long tunnel based on the three-dimensional geological model. Before the construction of a deep-buried long tunnel, a horizontal drilling device is used to drill and coring along a preset direction of the deep-buried long tunnel in a large-displacement well, and the core is analyzed and the geological structure information of the core is obtained; then, based on the borehole generated after the drilling and coring, the geological information around the borehole is obtained from the logging equipment, so that the geological exploration process is not disturbed by the construction; and then a three-dimensional geological model can be generated based on the geological structure information of the core and the geological information around the borehole; based on the three-dimensional geological model, the geological information around the deep-buried long tunnel to be excavated can be obtained, and then the construction equipment can be controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel; continuous large-scale geological conditions can be obtained, the utilization rate of geological information is improved, and it is beneficial to the construction of the deep-buried long tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] The accompanying drawings, which are incorporated in and constitute a part of this specification, illustrate embodiments consistent with the present application and, together with the description, serve to explain the principles of the present application.
[0025] Figure 1 A schematic diagram of a flow chart of a geological exploration method for a deep buried long tunnel provided in an embodiment of the present application;
[0026] Figure 2 A schematic flow chart of another geological exploration method for a deep buried long tunnel provided in an embodiment of the present application;
[0027] Figure 3 is a schematic diagram of an extended reach well according to an exemplary embodiment;
[0028] Figure 4 is a schematic cross-sectional view of a three-dimensional geological model according to an exemplary embodiment;
[0029] Figure 5 A schematic diagram of the structure of a geological exploration device for a deep-buried long tunnel provided in an embodiment of the present application;
[0030] Figure 6 A schematic structural diagram of another geological exploration device for deep-buried long tunnels provided in an embodiment of the present application;
[0031] Figure 7 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application;
[0032] Figure 8 The figure is a block diagram of an electronic device according to an exemplary embodiment.
[0033] The above drawings have shown clear embodiments of the present application, which will be described in more detail later. These drawings and text descriptions are not intended to limit the scope of the present application in any way, but to illustrate the concept of the present application to those skilled in the art by referring to specific embodiments. DETAILED DESCRIPTION
[0034] Exemplary embodiments will be described in detail herein, examples of which are shown in the accompanying drawings. When the following description refers to the drawings, the same numbers in different drawings represent the same or similar elements unless otherwise indicated. The implementations described in the following exemplary embodiments do not represent all implementations consistent with the present application. Instead, they are merely examples of devices and methods consistent with some aspects of the present application as detailed in the appended claims.
[0035] During the geological exploration and excavation of deep long tunnels, the deep long tunnels have to pass through complex geological structures along the way. There may be geological disasters such as rock bursts, water inrush, and tunnel boring machine jams during construction, resulting in high uncertainty and high risk in construction safety and construction period. The geological structure information of deep long tunnels can be obtained through geological exploration methods to guide the construction of deep long tunnel projects.
[0036] In the geological exploration process of deep buried long tunnel projects, vertical drilling is carried out on the ground where the deep buried long tunnel is to be excavated in the early stage. During the construction period, geological prediction work of the tunnel project is carried out through geological radar method, infrared water detection method, horizontal drilling method and other advanced prediction geological exploration methods to guide the construction process of the deep buried long tunnel project.
[0037] In one example, before the excavation of a deep long tunnel, vertical drilling is performed on the ground of the deep long tunnel to obtain some geological information around the deep long tunnel to be excavated, and the excavation of the deep long tunnel project is carried out based on the obtained geological information; during the excavation of the deep long tunnel, the horizontal drilling method is used to obtain other geological information around the deep long tunnel, and then the geological structure of the deep long tunnel is supplemented, thereby guiding the construction work of the deep long tunnel workers.
[0038] However, in the above method, the initial vertical drilling on the ground is costly, inefficient, and has great limitations, and may miss or misjudge some important geological structures. In addition, the advance prediction process is significantly disturbed by construction, resulting in a relatively low utilization rate of tunnel geological information, making it difficult to accurately infer the three-dimensional geological structure of deep buried long tunnels, which is not conducive to the excavation and construction of deep buried long tunnels.
[0039] The present application provides a geological exploration method, device and equipment for deep buried long tunnels, aiming to solve the above technical problems of the prior art.
[0040] The technical solution of the present application and how the technical solution of the present application solves the above-mentioned technical problems are described in detail below with specific embodiments. The following specific embodiments can be combined with each other, and the same or similar concepts or processes may not be repeated in some embodiments. The embodiments of the present application will be described below in conjunction with the accompanying drawings.
[0041] Figure 1 A schematic diagram of a process flow of a geological exploration method for a deep buried long tunnel provided in an embodiment of the present application is shown as follows: Figure 1 As shown, the method includes:
[0042] S101. Acquire first geological information of a core obtained by a horizontal drilling device during coring, wherein the core is collected by the horizontal drilling device during coring along a preset direction of a deep-buried long tunnel in an extended displacement well; the first geological information represents geological information of the core; and the extended displacement well is disposed above the central axis of the deep-buried long tunnel.
[0043] Exemplarily, the execution subject of this embodiment may be an electronic device, or a server, or a terminal device, or other devices or equipment that can execute this embodiment. This embodiment is described by taking the execution subject as an electronic device as an example.
[0044] Before the excavation of a deep-buried long tunnel, a large-displacement well is set above the central axis of the deep-buried long tunnel. Horizontal drilling equipment drills and samples cores along the preset direction of the deep-buried long tunnel in the large-displacement well to obtain cores and boreholes. The obtained cores are structurally analyzed to obtain geological information of the obtained cores.
[0045] Among them, the preset direction of the deep buried long tunnel is the excavation direction of the deep buried long tunnel.
[0046] In one example, before the excavation of a deep and long tunnel, based on the preset locations of large-displacement wells around the deep and long tunnel, the horizontal drilling equipment can accurately perform directionally drilling on the mountain along the preset direction using drilling guidance system measurement technology or horizontal drilling coring technology, and obtain rock cores and generate boreholes. The geological information of the rock cores can be obtained by performing structural analysis on the rock cores.
[0047] S102, obtaining second geological information of the borehole generated by the logging equipment after coring, wherein the second geological information represents geological information around the borehole.
[0048] For example, based on the borehole generated after coring in step S101, a logging device is placed in the borehole, the borehole is logged using the logging device, and then geological information around the borehole is obtained from the logging device.
[0049] In one example, based on the borehole generated after drilling and coring, logging equipment and data transmission cables are placed in the borehole to log the borehole and transmit and save relevant logging data. A variety of logging methods can be used, such as conventional logging methods, sonic logging methods, imaging logging methods, or element logging methods, to obtain geological information around the borehole from the logging equipment.
[0050] S103. Generate a three-dimensional geological model based on the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel.
[0051] For example, based on the acquired core geological information and the geological information around the borehole, a three-dimensional geological model including the geological information around the deep-buried long tunnel can be generated through three-dimensional modeling software.
[0052] In one example, based on the acquired core geological information and the geological information around the borehole, the core geological information and the geological information around the borehole are input into a three-dimensional modeling software, and the three-dimensional modeling software can generate a three-dimensional geological model including the geological information around the deep-buried long tunnel.
[0053] S104. According to the three-dimensional geological model, control the construction equipment to perform tunnel excavation and tunnel construction on the deep-buried long tunnel.
[0054] For example, based on the three-dimensional geological model of the geological information around the deep-buried long tunnel, the geological information required for the design of the deep-buried long tunnel can be directly read or obtained through calculation, providing scientific guidance for tunnel line selection, reinforcement, lining and other work, thereby controlling the construction equipment to carry out tunnel excavation and tunnel construction of the deep-buried long tunnel.
[0055] In one example, based on the three-dimensional geological model of the geological information around the deep-buried long tunnel, the geological information required for the design of the deep-buried long tunnel can be directly read. The information obtained can be the geological structure information around the axis of the deep-buried long tunnel, or the geological faults and broken zones passed through in the route selection path of the deep-buried long tunnel, or the geostress conditions within the high geostress area in the deep-buried long initial geostress field. Based on the geological information obtained, the construction equipment is controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel.
[0056] In another example, based on the three-dimensional geological model of the geological information around the deep buried long tunnel, the three-dimensional geological model can be simulated and calculated through modeling software to obtain the stress and strain of the rock during the excavation of the deep buried long tunnel. According to the geological information obtained, the position, excavation method, support method, and tunnel slope of the deep buried long tunnel in the initial deep buried long tunnel design plan are corrected to provide scientific and reasonable guidance for the deep buried long tunnel excavation plan, thereby controlling the construction equipment to carry out tunnel excavation and tunnel construction on the deep buried long tunnel.
[0057] In this embodiment, first geological information of the core obtained by the horizontal drilling equipment through drilling and coring is obtained, wherein the core is collected by the horizontal drilling equipment through drilling and coring along a preset direction of a deep-buried long tunnel in a large-displacement well; the first geological information represents the geological information of the core; the large-displacement well is arranged above the central axis of the deep-buried long tunnel; second geological information of the borehole generated by the logging equipment after drilling and coring is obtained, wherein the second geological information represents the geological information around the borehole; a three-dimensional geological model is generated based on the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel; based on the three-dimensional geological model, the construction equipment is controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel. Before the construction of a deep-buried long tunnel, the horizontal drilling equipment is used to drill and sample cores along the preset direction of the deep-buried long tunnel in the extended-displacement well, and the cores are analyzed and the geological structure information of the cores is obtained; then, the geological information around the borehole is obtained from the logging equipment, so that the geological exploration process is not disturbed by the construction; and then, a three-dimensional geological model is generated based on the geological structure information of the core and the geological information around the borehole, and further continuous large-scale geological conditions can be obtained, thereby controlling the construction equipment to excavate and construct the deep-buried long tunnel, which is beneficial to the construction of the deep-buried long tunnel.
[0058] Figure 2 A schematic diagram of a process flow of another geological exploration method for a deep buried long tunnel provided in an embodiment of the present application is shown in FIG. Figure 2 As shown, the method includes:
[0059] S201. Determine the location of the large displacement well around the deep buried long tunnel.
[0060] In one example, the horizontal axis of the extended displacement well is 0.5 to 2 times the diameter of the deep-buried long tunnel from the top of the deep-buried long tunnel, and the horizontal section length of the extended displacement well is equal to or greater than the length of the deep-buried long tunnel.
[0061] In one example, the burial depth of a deep buried long tunnel ranges from 1.5 km to 2.5 km, the length of the deep buried long tunnel ranges from 4.5 km to 15 km, and the diameter of the deep buried long tunnel ranges from 2 meters to 15 meters.
[0062] In one example, a ratio of a length of the extended reach well in a horizontal direction to a length of the extended reach well in a vertical direction is greater than or equal to 2.
[0063] For example, based on previous geological exploration data, large-displacement wells are measured and laid out above the axis of the deep-buried long tunnel to be excavated. The horizontal direction of the large-displacement well is parallel to the axis of the deep-buried long tunnel. The axis of the large-displacement well in the horizontal direction is 0.5 to 2 times the diameter of the deep-buried long tunnel from the top of the deep-buried long tunnel. The horizontal section length of the large-displacement well is equal to or greater than the length of the deep-buried long tunnel.
[0064] Among them, the burial depth of the deep buried long tunnel ranges from 1.5 kilometers to 2.5 kilometers, the length of the deep buried long tunnel ranges from 4.5 kilometers to 15 kilometers, and the diameter of the deep buried long tunnel ranges from 2 meters to 15 meters.
[0065] Furthermore, a ratio of a length of the extended reach well in a horizontal direction to a length in a vertical direction is greater than or equal to 2.
[0066] In one example, Figure 3 FIG. 1 is a schematic diagram of an extended reach well according to an exemplary embodiment. Figure 3 As shown, for the deep-buried long tunnel to be excavated, before the construction of the deep-buried long tunnel to be excavated, a directional drilling platform and a ground drilling rig are arranged, and then the large-displacement well is measured and laid out, so that the horizontal section of the large-displacement well is located at a position twice the tunnel diameter above the deep-buried long tunnel, and the length of the horizontal section of the large-displacement well is equal to the length of the deep-buried long tunnel.
[0067] S202: Perform structural analysis on the core and generate a borehole column chart, where the borehole column chart represents the first geological information.
[0068] In one example, the first geological information includes one or more of the following information: rock mechanics parameters of the core, fault information, structural surface information, and weak zone geological structure information.
[0069] In one example, the diameter of the drilled hole is greater than 80 mm.
[0070] Exemplarily, after the location of the extended displacement well is determined, the mountain is drilled and cored by horizontal drilling equipment along the preset direction of the deep-buried long tunnel in the extended displacement well to obtain rock cores and boreholes. The obtained rock cores are structurally analyzed to obtain geological information of the obtained rock cores, including rock mechanical parameters, fault information, structural surface information, and geological structure information of weak zones. Based on the geological information of the rock cores, a drilling column chart is generated.
[0071] Among them, the diameter of the borehole obtained after drilling and coring is greater than 80 mm.
[0072] In one example, based on the preset locations of large-displacement wells around a deep-buried long tunnel, horizontal drilling coring technology can be used to drill and coring the mountain using horizontal drilling equipment to obtain rock cores and boreholes. The obtained rock cores can then be structurally analyzed to analyze the core integrity, mechanical parameters, structural characteristics and other properties, obtain geological structure information such as the rock mechanical parameters, faults, structural surfaces, weak zones, and form a borehole column chart.
[0073] S203, obtaining second geological information of the borehole generated by the logging equipment after coring, wherein the second geological information represents geological information around the borehole.
[0074] In one example, the second geological information includes one or more of the following: formation density, porosity, lithology, ground stress, water pressure, porosity, formation dip, and fault weak zone distribution information of the borehole.
[0075] For example, a logging device is placed in the borehole, and the borehole is logged using the logging device. Then, geological information such as formation density, porosity, lithology, ground stress, water pressure, porosity, formation dip, and distribution of fault weak zones around the borehole is obtained from the logging device.
[0076] S204, generating an initial numerical model based on the first geological information and the second geological information; the initial numerical model represents the geological information around the deep-buried long tunnel.
[0077] Exemplarily, according to the acquired core geological information and the geological information around the borehole, after the core geological information and the geological information around the borehole are processed by three-dimensional modeling software, an initial numerical model can be generated based on the modeling function of the three-dimensional modeling software.
[0078] In one example, after obtaining the core geological information and the geological information around the borehole, a numerical model was preliminarily established in three-dimensional numerical software based on the rock formation trend, lithology, joints and fissures, and rock mechanical properties obtained from the core geological information, the geological structure shape and formation dip around the borehole determined by the logging information were integrated, and reference was made to previous geological exploration data.
[0079] S205. Invert the initial numerical model to generate a three-dimensional geological model.
[0080] In one example, step S205 includes: inverting the initial numerical model according to the geostress information in the second geological information to generate a three-dimensional geological model.
[0081] For example, after the initial numerical model is formed, in order to generate a three-dimensional geological model of a deep-buried long tunnel, it is necessary to invert the initial numerical model using the acquired geological information.
[0082] According to the geostress information in the geological information around the borehole, the initial numerical model is inverted based on inversion technology and 3D modeling software to form a 3D geological model of the surrounding area of the deep-buried long tunnel with geostress conditions.
[0083] In one example, Figure 4 FIG. 1 is a schematic cross-sectional view of a three-dimensional geological model according to an exemplary embodiment. Figure 4 As shown, after the model is initially formed, based on the ground stress conditions in the geological information obtained by the logging equipment, the initial numerical model can be inverted by using the stress function trend analysis method, the linear regression analysis method, the boundary load method, or the lateral stress coefficient method, and finally a three-dimensional geological model of the surrounding area of the deep-buried long tunnel with ground stress conditions is formed, for example, a three-dimensional geological model profile, which includes the geological information of the profile around the deep-buried long tunnel.
[0084] S206. According to the three-dimensional geological model, control the construction equipment to perform tunnel excavation and tunnel construction on the deep-buried long tunnel.
[0085] Exemplarily, this step may refer to step S104 and will not be described in detail.
[0086] In this embodiment, based on the above embodiment, the position of the large displacement well is determined around the deep buried long tunnel; the core is structurally analyzed to generate a borehole column chart, which represents the first geological information; the second geological information of the borehole generated by the logging equipment after drilling and coring is obtained, wherein the second geological information represents the geological information around the borehole; based on the first geological information and the second geological information, an initial numerical model is generated; the initial numerical model represents the geological information around the deep buried long tunnel; the initial numerical model is inverted to generate a three-dimensional geological model; based on the three-dimensional geological model, the construction equipment is controlled to perform tunnel excavation and tunnel construction on the deep buried long tunnel. By determining the location of the extended-reach wells around the deep-buried long tunnel, based on the extended-reach well technology, horizontal drilling can be carried out once to reduce construction costs; after coring, the geological information of the core and the borehole can be obtained respectively, so that the continuous large-scale geological conditions around the deep-buried long tunnel can be obtained in advance before construction; based on the three-dimensional model, more required geological information can be obtained to provide scientific guidance for tunnel line selection, reinforcement, lining and other work, which is conducive to the construction of deep-buried long tunnels.
[0087] Figure 5 A schematic diagram of a geological exploration device for a deep buried long tunnel provided in an embodiment of the present application is shown in FIG. Figure 5 The device comprises:
[0088] The first acquisition unit 31 is used to acquire first geological information of the core obtained by the horizontal drilling equipment during drilling and coring, wherein the core is collected by the horizontal drilling equipment during drilling and coring along a preset direction of a deep-buried long tunnel in the large-displacement well; the first geological information represents the geological information of the core; the large-displacement well is arranged above the central axis of the deep-buried long tunnel.
[0089] The second acquisition unit 32 is used to acquire second geological information of the borehole generated by the logging equipment after coring, wherein the second geological information represents geological information around the borehole.
[0090] The generating unit 33 is used to generate a three-dimensional geological model according to the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel.
[0091] The control unit 34 is used to control the construction equipment to perform tunnel excavation and tunnel construction on the deep buried long tunnel according to the three-dimensional geological model.
[0092] The device of this embodiment can execute the technical solution in the above method. Its specific implementation process and technical principles are the same and will not be repeated here.
[0093] Figure 6 A schematic diagram of the structure of another geological exploration device for deep buried long tunnels provided in an embodiment of the present application is shown in FIG. Figure 6 The device comprises:
[0094] The first acquisition unit 41 is used to acquire first geological information of the core obtained by the horizontal drilling equipment during coring, wherein the core is collected by the horizontal drilling equipment during coring along a preset direction of a deep-buried long tunnel in the extended displacement well; the first geological information represents the geological information of the core; the extended displacement well is arranged above the central axis of the deep-buried long tunnel.
[0095] The second acquisition unit 42 is used to acquire second geological information of the borehole generated by the logging equipment after coring the borehole, wherein the second geological information represents geological information around the borehole.
[0096] The generating unit 43 is used to generate a three-dimensional geological model according to the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel.
[0097] The control unit 44 is used to control the construction equipment to perform tunnel excavation and tunnel construction on the deep buried long tunnel according to the three-dimensional geological model.
[0098] In one example, the first acquisition unit 41 includes:
[0099] The first generating module 411 is used to perform structural analysis on the core and generate a borehole column chart, wherein the borehole column chart represents the first geological information.
[0100] In one example, the first geological information includes one or more of the following information: rock mechanics parameters of the core, fault information, structural surface information, and weak zone geological structure information.
[0101] In one example, the diameter of the drilled hole is greater than 80 mm.
[0102] In one example, the second geological information includes one or more of the following: formation density, porosity, lithology, ground stress, water pressure, porosity, formation dip, and fault weak zone distribution information of the borehole.
[0103] In one example, the generating unit 43 includes:
[0104] The second generating module 431 is used to generate an initial numerical model according to the first geological information and the second geological information; the initial numerical model represents the geological information around the deep-buried long tunnel.
[0105] The third generating module 432 is used to invert the initial numerical model to generate a three-dimensional geological model.
[0106] In one example, the third generation module 432 includes:
[0107] The generation submodule is used to invert the initial numerical model according to the geostress information in the second geological information to generate a three-dimensional geological model.
[0108] In one example, the device provided by this embodiment further includes:
[0109] The determination unit 45 is used to determine the position of the extended displacement well around the deep buried long tunnel.
[0110] The device of this embodiment can execute the technical solution in the above method. Its specific implementation process and technical principles are the same and will not be repeated here.
[0111] Figure 7 A schematic diagram of the structure of an electronic device provided in an embodiment of the present application is shown in FIG. Figure 7 As shown, the electronic device includes: a memory 51 and a processor 52; the memory 51; and a memory for storing instructions executable by the processor 52.
[0112] The processor 52 is configured to execute the method provided in the above embodiment.
[0113] The terminal device further includes a receiver 53 and a transmitter 54. The receiver 53 is used to receive instructions and data sent by other devices, and the transmitter 54 is used to send instructions and data to external devices.
[0114] Figure 8 It is a block diagram of an electronic device according to an exemplary embodiment, which device may be a mobile phone, a computer, a digital broadcast terminal, a messaging device, a game console, a tablet device, a medical device, a fitness device, a personal digital assistant, etc.
[0115] The device 800 may include one or more of the following components: a processing component 802 , a memory 804 , a power component 806 , a multimedia component 808 , an audio component 810 , an input / output (I / O) interface 812 , a sensor component 814 , and a communication component 816 .
[0116] The processing component 802 generally controls the overall operation of the device 800, such as operations associated with display, phone calls, data communications, camera operations, and recording operations. The processing component 802 may include one or more processors 820 to execute instructions to complete all or part of the steps of the above-mentioned method. In addition, the processing component 802 may include one or more modules to facilitate the interaction between the processing component 802 and other components. For example, the processing component 802 may include a multimedia module to facilitate the interaction between the multimedia component 808 and the processing component 802.
[0117] The memory 804 is configured to store various types of data to support operations on the device 800. Examples of such data include instructions for any application or method operating on the device 800, contact data, phone book data, messages, pictures, videos, etc. The memory 804 can be implemented by any type of volatile or non-volatile storage device or a combination thereof, such as static random access memory (SRAM), electrically erasable programmable read-only memory (EEPROM), erasable programmable read-only memory (EPROM), programmable read-only memory (PROM), read-only memory (ROM), magnetic memory, flash memory, magnetic disk or optical disk.
[0118] The power supply component 806 provides power to the various components of the device 800. The power supply component 806 may include a power management system, one or more power supplies, and other components associated with generating, managing, and distributing power for the device 800.
[0119] The multimedia component 808 includes a screen that provides an output interface between the device 800 and the user. In some embodiments, the screen may include a liquid crystal display (LCD) and a touch panel (TP). If the screen includes a touch panel, the screen may be implemented as a touch screen to receive input signals from the user. The touch panel includes one or more touch sensors to sense touch, slide, and gestures on the touch panel. The touch sensor may not only sense the boundaries of the touch or slide action, but also detect the duration and pressure associated with the touch or slide operation. In some embodiments, the multimedia component 808 includes a front camera and / or a rear camera. When the device 800 is in an operating mode, such as a shooting mode or a video mode, the front camera and / or the rear camera may receive external multimedia data. Each front camera and rear camera may be a fixed optical lens system or have a focal length and optical zoom capability.
[0120] The audio component 810 is configured to output and / or input audio signals. For example, the audio component 810 includes a microphone (MIC), and when the device 800 is in an operating mode, such as a call mode, a recording mode, and a speech recognition mode, the microphone is configured to receive an external audio signal. The received audio signal can be further stored in the memory 804 or sent via the communication component 816. In some embodiments, the audio component 810 also includes a speaker for outputting audio signals.
[0121] I / O interface 812 provides an interface between processing component 802 and peripheral interface modules, such as keyboards, click wheels, buttons, etc. These buttons may include but are not limited to: a home button, a volume button, a start button, and a lock button.
[0122] The sensor assembly 814 includes one or more sensors for providing various aspects of status assessment for the device 800. For example, the sensor assembly 814 can detect the open / closed state of the device 800, the relative positioning of components, such as the display and keypad of the device 800, the sensor assembly 814 can also detect the position change of the device 800 or a component of the device 800, the presence or absence of user contact with the device 800, the orientation or acceleration / deceleration of the device 800 and the temperature change of the device 800. The sensor assembly 814 can include a proximity sensor configured to detect the presence of nearby objects without any physical contact. The sensor assembly 814 can also include an optical sensor, such as a CMOS or CCD image sensor, for use in imaging applications. In some embodiments, the sensor assembly 814 can also include an accelerometer, a gyroscope sensor, a magnetic sensor, a pressure sensor or a temperature sensor.
[0123] The communication component 816 is configured to facilitate wired or wireless communication between the device 800 and other devices. The device 800 can access a wireless network based on a communication standard, such as WiFi, 2G or 3G, or a combination thereof. In an exemplary embodiment, the communication component 816 receives a broadcast signal or broadcast-related information from an external broadcast management system via a broadcast channel. In an exemplary embodiment, the communication component 816 also includes a near field communication (NFC) module to facilitate short-range communication. For example, the NFC module can be implemented based on radio frequency identification (RFID) technology, infrared data association (IrDA) technology, ultra-wideband (UWB) technology, Bluetooth (BT) technology and other technologies.
[0124] In an exemplary embodiment, the apparatus 800 may be implemented by one or more application specific integrated circuits (ASICs), digital signal processors (DSPs), digital signal processing devices (DSPDs), programmable logic devices (PLDs), field programmable gate arrays (FPGAs), controllers, microcontrollers, microprocessors or other electronic components to perform the above method.
[0125] In an exemplary embodiment, a non-transitory computer-readable storage medium including instructions is also provided, such as a memory 804 including instructions, and the instructions can be executed by the processor 820 of the device 800 to perform the above method. For example, the non-transitory computer-readable storage medium can be a ROM, a random access memory (RAM), a CD-ROM, a magnetic tape, a floppy disk, an optical data storage device, etc.
[0126] An embodiment of the present application also provides a non-temporary computer-readable storage medium, which, when instructions in the storage medium are executed by a processor of an electronic device, enables the electronic device to perform the above method.
[0127] According to an embodiment of the present application, the present application also provides a computer program product, which includes: a computer program, the computer program is stored in a readable storage medium, at least one processor of an electronic device can read the computer program from the readable storage medium, and at least one processor executes the computer program so that the electronic device executes the solution provided by any of the above embodiments.
[0128] Those skilled in the art will readily appreciate other embodiments of the present application after considering the specification and practicing the invention disclosed herein. The present application is intended to cover any modification, use or adaptation of the present application, which follows the general principles of the present application and includes common knowledge or customary techniques in the art that are not disclosed in the present application. The specification and examples are intended to be exemplary only, and the true scope and spirit of the present application are indicated by the following claims.
[0129] It should be understood that the present application is not limited to the precise structures that have been described above and shown in the drawings, and that various modifications and changes may be made without departing from the scope thereof. The scope of the present application is limited only by the appended claims.
Claims
1. A geological exploration method for a deep buried long tunnel, characterized in that: The method comprises: Acquire first geological information of a core obtained by drilling and coring with a horizontal drilling device, wherein the core is collected by drilling and coring with the horizontal drilling device along a preset direction of a deep-buried long tunnel in an extended-reach well; the first geological information represents geological information of the core; the extended-reach well is arranged above the central axis of the deep-buried long tunnel; Acquire second geological information of the borehole generated by the logging equipment after coring the drilling, wherein the second geological information represents geological information around the borehole; Generate a three-dimensional geological model based on the first geological information and the second geological information; wherein the three-dimensional geological model represents the geological information around the deep-buried long tunnel; According to the three-dimensional geological model, the construction equipment is controlled to perform tunnel excavation and tunnel construction on the deep-buried long tunnel.
2. The method according to claim 1, characterized in that The first geological information of the core obtained by drilling and coring with horizontal drilling equipment is obtained, including: A structural analysis is performed on the core to generate a borehole columnar graph, wherein the borehole columnar graph represents first geological information.
3. The method according to claim 2, characterized in that The first geological information includes one or more of the following information: rock mechanics parameters of the core, fault information, structural surface information, and weak zone geological structure information.
4. The method according to claim 1, characterized in that: Generating a three-dimensional geological model according to the first geological information and the second geological information includes: Generate an initial numerical model based on the first geological information and the second geological information; the initial numerical model represents the geological information around the deep buried long tunnel; The initial numerical model is inverted to generate the three-dimensional geological model.
5. The method according to claim 4, characterized in that Inverting the initial numerical model to generate the three-dimensional geological model includes: The initial numerical model is inverted according to the geostress information in the second geological information to generate the three-dimensional geological model.
6. The method according to claim 1, characterized in that Before obtaining the first geological information of the core obtained by drilling and coring with a horizontal drilling device, the method further includes: The location of the extended reach well is determined around the deep buried long tunnel.
7. The method according to any one of claims 1 to 6, characterized in that The diameter of the borehole is greater than 80 mm.
8. The method according to any one of claims 1 to 6, characterized in that The second geological information includes one or more of the following: formation density, porosity, lithology, ground stress, water pressure, porosity, formation dip, and fault weak zone distribution information of the borehole.
9. A geological exploration device for deep buried long tunnels, characterized in that: The device comprises: A first acquisition unit is used to acquire first geological information of a core obtained by a horizontal drilling device through drilling and coring, wherein the core is collected by the horizontal drilling device through drilling and coring along a preset direction of a deep-buried long tunnel in a large-displacement well; the first geological information represents the geological information of the core; A second acquisition unit is used to acquire second geological information of the borehole generated by the logging equipment after the drilling and coring, wherein the second geological information represents geological information around the borehole; A generating unit, configured to generate a three-dimensional geological model according to the first geological information and the second geological information; wherein the three-dimensional geological model represents geological information around the deep-buried long tunnel; A control unit is used to control the construction equipment to perform tunnel excavation and tunnel construction on the deep buried long tunnel according to the three-dimensional geological model.
10. An electronic device, characterized in that: include: A processor, and a memory communicatively connected to the processor; The memory stores computer-executable instructions; The processor executes the computer-executable instructions stored in the memory to implement the method according to any one of claims 1 to 8.