A blind shaft safety passage for soft and broken rock mining areas in underground mines
By adopting a blind vertical shaft design with a multi-cylindrical spiral step structure in underground mines, the problems of complexity and high cost of traditional blind vertical shafts are solved, low-cost and high-efficiency construction and safe passage construction are achieved, and workers are improved Pedestrian safety.
Patent Information
- Application Number
- CN202210762041.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-06-30
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2042-06-30
AI Technical Summary
In underground mines under weak and broken rock conditions, traditional blind shafts are complex and costly, making it difficult to ensure construction safety and efficiency, especially support difficulties, resulting in increased construction time and cost.
The spiral step structure consisting of multiple cylinders is composed of steel plate coiled pipes, and the handrails and steps are installed. It is reinforced by positioning rings, load-bearing rings and connecting ribs. Concrete is poured to enhance stability, and it is reduced by using a reverse well drilling rig. Blind vertical shaft section, simplifying the support process.
It realizes low-cost and high-efficiency construction and installation, provides a smooth ladder, improves pedestrian safety, and reduces construction complexity and support difficulty.
Smart Images

Figure CN115355043B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a blind shaft safety passage in a soft and broken rock mining area of an underground mine. Background Art
[0002] The second safety exit of the mining area of an underground mine is an escape safety passage after a safety accident such as roof fall, rock spalling, or fire occurs in the mining area. It is an important passage that can ensure the life safety of the workers in the mining area. In each mining area, plate area, or ore block of an underground mine, there should be two safety exits that are convenient for pedestrians. At present, the second safety passage in the mining area of a general underground mine is basically formed by setting up a ladder room in a blind shaft or laying steps in a blind inclined shaft. The laying of steps in the blind inclined shaft can ensure the safety of construction, but compared with the blind shaft, the blind inclined shaft is relatively long and the amount of waste rock is relatively large. The cost of the blind inclined shaft is not only much higher than that of the blind shaft, but also the construction time is long. Although the amount of blind shaft engineering is relatively small, the construction of traditional blind shafts is relatively complicated and the support is relatively cumbersome. Especially in underground mines with relatively weak and broken surrounding rock conditions, the construction technology of the positive excavation blind shaft requires a relatively large cross-section of the blind shaft, which will also increase the construction cost and construction time. If reverse drilling is used for construction, the size of the cross-section of the blind shaft can be effectively reduced, but the support of the blind shaft is extremely difficult, and it is difficult to effectively ensure the safety of the support construction personnel. Therefore, it is necessary to have a method with low construction cost, short construction period and easy support to construct a safe passage in the mining area. Summary of the invention
[0003] In order to solve the above technical problems, the present invention provides a blind shaft safety passage in a soft and broken rock mining area of an underground mine.
[0004] The present invention is achieved through the following technical solutions.
[0005] The present invention provides a blind shaft safety passage in a soft and broken rock mining area of an underground mine, comprising a safety passage and a blind shaft; the blind shaft connects the mining tunnel and the upper tunnel in the mine, and the safety passage is fixed in the upper tunnel;
[0006] The safety passage comprises a plurality of cylinders, in which escalators are installed, and the plurality of cylinders are vertically stacked in sequence so that the escalators inside are connected in sequence to form a continuous spiral staircase.
[0007] The cylinder body comprises a steel plate coiled tube, and spiral handrails and steps are installed on the side walls of the steel plate coiled tube.
[0008] The steps include a plurality of mesh plates, the edges of which are wrapped by a frame, the frame is approximately a right-angled triangle, one end of the short right-angled side of the frame is processed into an arc with the same diameter as the steel plate coil, and a vertical frame is fixed to its lower end, the hypotenuse and the long right-angled side of the frame are respectively connected to the vertical frame by a diagonal support rod, and a plurality of mesh plates are fixed on the steel plate coil at equal intervals through the vertical frame.
[0009] The vertical frame is an isosceles triangle, the bottom side of which is fixed on the frame, and the top side of which is connected to the diagonal support rod.
[0010] A plurality of positioning rings and load-bearing rings are also fixed on the outer wall of the steel plate coil. The load-bearing rings are evenly fixed on the upper end of the steel plate coil. The positioning rings are divided into two vertical rows and are respectively fixed on the opposite surfaces of the steel plate coil.
[0011] A plurality of connecting ribs are evenly fixedly connected to the outer wall of the steel plate coil, and concrete is poured between the steel plate coil and the blind shaft.
[0012] The top end of the steel plate coil is evenly fixed with a plurality of slots.
[0013] The slots are symmetrically fixed on the inner wall and the outer wall of the steel plate coil respectively, and the two symmetrical slots are combined into a Y-shaped
[0014] The beneficial effects of the present invention are as follows: the multiple cylinders are combined to enable efficient and low-cost construction and installation underground; the spiral steps formed by the multiple cylinders can provide workers with smooth steps and improve pedestrian safety. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] Figure 1 It is a schematic diagram of the safety passage structure of the present invention;
[0016] Figure 2 It is a schematic diagram of the structure of the safety passage of the present invention from a top view;
[0017] Figure 3 It is a schematic diagram of the steel coil structure of the present invention;
[0018] Figure 4 It is a schematic diagram of the card slot structure of the present invention;
[0019] Figure 5 is a schematic diagram of a step support structure of the present invention;
[0020] Figure 6 It is a schematic diagram of the safety passage position structure of the present invention;
[0021] Figure 7 It is a schematic diagram of the construction process structure of the present invention;
[0022] Figure 8 This is a schematic diagram of the steel plate coil lifting structure;
[0023] In the figure: 1-safety passage, 11-steel plate coil, 12-handrail, 13-step, 131-mesh plate, 132-frame, 133-vertical frame, 134-diagonal support rod, 14-entrance and exit, 15-slot, 16-connecting rib, 17-positioning ring, 18-load-bearing ring, 2-upper connecting lane, 3-blind shaft, 4-taking connecting lane, 5-sling, 6-lifting hoist, 7-positioning rope. DETAILED DESCRIPTION
[0024] The technical solution of the present invention is further described below, but the scope of protection claimed is not limited to the description.
[0025] A blind shaft safety passage in a soft and broken rock mining area of an underground mine, comprising a safety passage 1 and a blind shaft 3; the blind shaft 3 connects a mining tunnel 4 and an upper tunnel 2 in the mine, and the safety passage 1 is fixed in the upper tunnel 2;
[0026] The safety passage 1 includes a plurality of cylinders, in which escalators are installed, and the plurality of cylinders are vertically stacked in sequence so that the escalators inside are connected in sequence to form a continuous spiral staircase.
[0027] The cylinder body comprises a steel plate coiled tube 11 , on the side walls of which spiral handrails 12 and steps 13 are installed.
[0028] The step 13 includes a plurality of mesh plates 131, the edges of which are wrapped by a frame 132. The frame 132 is approximately a right-angled triangle. One end of the short right-angled side of the frame 132 is processed into an arc with the same diameter as the steel plate coil 11, and a vertical frame 133 is fixed to its lower end. The hypotenuse and the long right-angled side of the frame 132 are respectively connected to the vertical frame 133 by a diagonal support rod 134. A plurality of mesh plates 131 are fixed on the steel plate coil 11 at equal intervals through the vertical frame 133.
[0029] The vertical frame 133 is an isosceles triangle, the bottom side of which is fixed on the frame 132 , and the top side of which is connected to the diagonal support rod 134 .
[0030] A plurality of positioning rings 17 and load-bearing rings 18 are fixed on the outer wall of the steel plate coil 11 . The load-bearing rings 18 are evenly fixed on the upper end of the steel plate coil 11 . The positioning rings 17 are divided into two vertical rows and are respectively fixed on opposite surfaces of the steel plate coil 11 .
[0031] A plurality of connecting ribs 16 are evenly fixed to the outer wall of the steel plate coil 11 , and concrete is poured between the steel plate coil 11 and the blind shaft 3 .
[0032] A plurality of slots 15 are evenly fixed to the top of the steel plate coil tube 11 .
[0033] The clamping grooves 15 are symmetrically fixed on the inner wall and the outer wall of the steel plate coil tube 11 in pairs, and the two symmetrical clamping grooves 15 are combined into a Y shape.
[0034] Example:
[0035] The steel plate with a thickness of 15mm and a material of Q235 is used to process the steel pipe coil with an inner diameter of 1800mm, an outer diameter of 1830mm and a height of 5000mm. Three layers of short steel bars are welded on the outer wall of the steel plate coil as connecting bars to improve the strength of the concrete. Three load-bearing rings are welded on the outer wall of each steel plate coil for hoisting points during installation. Two layers of positioning rings are welded on the outer wall of each steel plate coil, with 3 positioning rings on each layer, and the corresponding positioning rings on each layer are vertical in direction; steps are welded inside the steel plate coil, and the steps just reach the top of the steel plate coil after spirally rising inside the steel plate coil for one week. The outer frame and bracket of the steps are made of welded steel plates, and the surface of the steps is made of lightweight plastic plates. According to the slope of the steps, handrails are welded inside the steel plate coil 1.2m higher than the steps; except for the first layer of steel plate coil, 8 slots are evenly welded on the bottom wall of each layer of steel plate coil.
[0036] Construction of blind shaft, the diameter of the blind shaft is D, the length of the connecting bar is 150mm-200mm, the thickness of the poured concrete is h, h is determined by the pressure of the surrounding rock of the mining area on the shaft, the length of the short steel bar is a<h, D>1830+2a,
[0037] The height of the connecting tunnel of the safe passage in the mining area is H, and the bottom layer of steel plate coils has an entrance and exit with a size of 1600×H.
[0038] On the roof of the upper safety passage connecting alley, in the center of the shaft of the blind shaft, a lifting hoist is installed. The lifting hoist is equipped with three load-bearing ropes with equal lengths and load-bearing hooks at the ends of the load-bearing ropes.
[0039] Construction steps:
[0040] ① First weld the steps and handrails inside the steel plate coil on the surface, and weld the load-bearing ring, positioning ring, short steel bars and slots outside the steel plate coil.
[0041] ② Use a reverse drilling rig to construct a blind vertical shaft from the upper safety passage connecting tunnel to the mining area safety passage connecting tunnel, and use a scraper to clean up the waste rock in the mining area safety passage connecting tunnel to make the bottom plate flat.
[0042] ③ Lift the first layer of steel plate coil, and then fix three positioning ropes on the positioning ring on the outer wall of the first layer of steel plate coil.
[0043] ④ After lowering the first layer of steel plate coils to the bottom plate of the mining area safety passage connecting tunnel, use the underground mine soft and broken rock mining area blind shaft safety passage to seal the steel plate coils and the side walls and top plate of the mining area safety passage connecting tunnel, and then use pipes to pour concrete between the steel plate coils and the surrounding rock from the upper safety passage connecting tunnel to allow the concrete to solidify initially to fix the first layer of steel plate coils.
[0044] ⑤ Continue to lower the load-bearing rope so that the load-bearing hook and the load-bearing ring on the first layer of steel plate reel will automatically fall off.
[0045] ⑥ Then hoist the second layer of steel plate coils, pass the positioning rope through the positioning ring of the second layer of steel plate coils, lower the second layer of steel plate coils, and make the 8 slots at the bottom of the second layer of steel plate coils clamped on the top of the first layer of steel plate coils.
[0046] ⑦ Repeat steps ⑤ and ⑥ until the last layer of steel plate coil is poured.
Claims
1. A blind shaft safety passage for a soft and broken rock mining area in an underground mine, comprising a safety passage (1) and a blind shaft (3), Features: The blind shaft (3) connects the mining tunnel (4) and the upper tunnel (2) in the mine, and the safety passage (1) is fixed in the upper tunnel (2); The safety passage (1) comprises a plurality of cylinders, each of which has a staircase installed therein, and the plurality of cylinders are stacked vertically in sequence so that the staircases therein are connected in sequence to form a continuous spiral staircase; The cylinder comprises a steel plate coil (11), and a spiral handrail (12) and a step (13) are installed on the side wall of the steel plate coil (11); The step (13) comprises a plurality of mesh plates (131), the edges of the mesh plates (131) are wrapped by a frame (132), the frame (132) is approximately a right-angled triangle, one end of the short right-angled side of the frame (132) is processed into an arc with the same diameter as the steel plate coil (11), and a vertical frame (133) is fixed at its lower end, the hypotenuse and the long right-angled side of the frame (132) are respectively connected to the vertical frame (133) by a diagonal brace (134), and the plurality of mesh plates (131) are fixed to the steel plate coil (11) at equal intervals through the vertical frame (133); The vertical frame (133) is an isosceles triangle, the bottom side of which is fixed to the frame (132), and the top side of which is connected to the diagonal support rod (134); A plurality of positioning rings (17) and load-bearing rings (18) are also fixed on the outer wall of the steel plate coil (11); the plurality of load-bearing rings (18) are evenly fixed on the upper end of the steel plate coil (11); and the plurality of positioning rings (17) are divided into two vertical rows and are respectively fixed on opposite surfaces of the steel plate coil (11); A plurality of connecting ribs (16) are evenly fixed to the outer wall of the steel plate coil (11), and concrete is poured between the steel plate coil (11) and the blind shaft (3); The top end of the steel plate coil (11) is evenly fixed with a plurality of slots (15); The clamping grooves (15) are symmetrically fixed in pairs on the inner wall and the outer wall of the steel plate coil tube (11), and the two symmetrical clamping grooves (15) are combined into a Y shape.
2. A construction method for a blind shaft safety passage in a soft and broken rock mining area of an underground mine is used to construct the blind shaft safety passage in a soft and broken rock mining area of an underground mine as claimed in claim 1, and the steps are as follows: ① Design the safety passage (1) as multiple cylinders connected in sequence, and complete the processing of each cylinder on the surface; ② Use a raise borer to construct a blind shaft from the upper safety passageway to the mining area safety passageway, and use a scraper to clean up the waste rock in the mining area safety passageway to make the floor flat; ③Install a hook on the top of the safety passage, lift the first layer of the cylinder, and then fix three positioning ropes on the positioning ring on the outer wall of the first layer of the cylinder; ④ After the first layer of cylinder is lowered to the bottom plate of the blind shaft in the mining area, the side walls and top plate of the first layer of cylinder and the safe passageway in the mining area are sealed with soft and broken rocks from the underground mine, and then concrete is poured between the first layer of cylinder and the surrounding rock through pipes from the upper safe passageway, so that the concrete is initially solidified and the cylinder is fixed; ⑤ Then hoist the second layer cylinder, let the positioning rope pass through the positioning ring of the second layer cylinder, lower the second layer cylinder, make the 8 slots at the bottom of the second layer cylinder stuck on the top of the first layer cylinder, and then pour concrete between the cylinder and the surrounding rock; ⑥Continue to install the cylinder according to step ⑤ until the last layer of cylinder is poured.
Citation Information
Patent Citations
Coal mine downhole safe passageway system
CN101302938A
Standard assembly type ladder cage for vertical shaft up-down travelling and construction method thereof
CN108457488A
Flow logging structure
CN112049643A
Supporting screw type ladder compartment
CN202347754U
Spiral type ladder compartment
CN202467913U