Automatic assembly workstation and assembly method thereof

Through the automatic loading, gluing and robotic assembly methods of the automatic assembly workstation, the low efficiency and precision problems of double-ended stud installation are solved, and efficient and precise automated assembly is achieved.

CN115365786BActive Publication Date: 2024-10-15BEIJING CSR TIMES LOCOMOTIVE & ROLLING STOCK MECHANICS
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211197057.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-28
Publication Date
2024-10-15
Estimated Expiration
2042-09-28

AI Technical Summary

Technical Problem

The installation efficiency of the double-headed studs of the existing truck air brake valve is low, the amount of manual labor is large, and the installation accuracy cannot be guaranteed.

Method used

An automatic assembly workstation is designed, including automatic feeding and gluing equipment, a valve body feeding and assembly workbench and robot equipment, which automatically completes the loading and gluing of double-headed studs through a feeding mechanism, a gluing mechanism and a retrieval mechanism. , and use robotic equipment to automatically tighten the studs into the stud holes of the valve body.

Benefits of technology

The automated assembly of double-ended studs is realized, significantly reducing the amount of manual labor, and ensuring assembly accuracy by precisely controlling the rotation angle of the tightening shaft.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115365786B_ABST
    Figure CN115365786B_ABST
Patent Text Reader

Abstract

The present invention discloses an automatic assembly workstation and an assembly method thereof, including: automatic feeding and gluing equipment, the automatic feeding and gluing equipment includes a feeding mechanism, a gluing mechanism and a material taking mechanism, the gluing mechanism is used to obtain materials and gluing the materials, the material taking mechanism is used to obtain materials, and can make the materials be located at the material taking position with the gluing head facing downward; a valve body feeding and assembly workbench, the valve body feeding and assembly workbench includes a slide and a valve body tooling, the valve body tooling is arranged on the slide, and the valve body tooling can go back and forth between the upper and lower material positions and the assembly position of the valve body; a robot device, the robot device includes a robot and a tightening shaft, the tightening shaft is arranged at the end of the robot, and the robot can drive the tightening shaft to go back and forth between the material taking position and the assembly position. The automatic assembly workstation in the present invention can automatically complete the feeding and gluing of studs, and can also automatically screw the studs into the stud holes of the valve body, thereby greatly reducing the amount of manual labor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of automation equipment, and more specifically, to an automatic assembly workstation and an assembly method thereof. Background Art

[0002] The studs of existing truck air brake valves are all installed manually using hand-held tightening tools. The valve body is manually placed, and the thread lock glue is applied to the long thread head or short thread head of the stud to form the glued head of the stud, and then the glued head of the stud is pre-screwed into the threaded hole of the valve body. After that, the worker holds a hand-held pneumatic tool with a sleeve, tightens it forward, and withdraws it in the reverse direction. However, this process is inefficient, the manual workload is heavy, and the installation accuracy cannot be guaranteed.

[0003] Therefore, how to realize the automatic assembly of studs, reduce the manual labor, and improve the installation accuracy is a key problem that needs to be solved urgently by technical personnel in this field. Summary of the invention

[0004] The purpose of the present invention is to realize the automatic assembly of studs, reduce the manual labor, and improve the installation accuracy. To achieve the above purpose, the present invention provides the following technical solutions:

[0005] An automatic assembly workstation, comprising:

[0006] Automatic feeding and gluing equipment, the automatic feeding and gluing equipment comprises a feeding mechanism, a gluing mechanism and a taking mechanism, the feeding mechanism is used to transport materials to the feeding position, the gluing mechanism is used to obtain materials from the feeding position and gluing the materials, the taking mechanism is used to obtain materials on the gluing mechanism, and can place the materials at the taking position with the gluing head facing downward;

[0007] A valve body loading and assembly workbench, the valve body loading and assembly workbench comprising a slide and a valve body tooling, the valve body tooling is used to clamp the valve body, the valve body tooling is arranged on the slide, and the valve body tooling can move back and forth between the upper and lower material positions and the assembly position of the valve body under the drive of the slide;

[0008] A robot device, comprising a robot and a tightening shaft, wherein the tightening shaft is arranged at the end of the robot, and a sleeve head is arranged on the tightening shaft, and the sleeve head is threadably adapted to the non-glue-coated head of the material. The robot can drive the tightening shaft to and from the material picking position and the assembly position, and the tightening shaft can drive the sleeve head to rotate forward and reverse.

[0009] Preferably, the glue coating mechanism comprises a truss, a glue coating device, a clamping arm, a first clamping jaw device and a first rotation driving device;

[0010] The glue coating device is arranged on the truss, and the glue coating device and the feeding position are arranged along the telescopic direction of the clamping arm; the clamping arm includes a fixed part and a telescopic part, and the fixed part of the clamping arm is arranged on the truss, and the first rotary drive device is fixed on the telescopic part of the clamping arm, and the first clamping jaw device is rotatably arranged on the telescopic part of the clamping arm, and the first clamping jaw device is used to clamp or release materials, and the first rotary drive device is used to drive the first clamping jaw device to rotate.

[0011] Preferably, the feeding mechanism comprises a storage bin, a conveyor belt is provided on one side of the storage bin, the storage bin can convey materials to the conveyor belt, and the conveyor belt is used to convey materials to the feeding position.

[0012] Preferably, the storage bin is located on one side of the conveyor belt in the width direction;

[0013] The bottom plate of the storage bin gradually slopes downward in a direction close to the conveyor belt;

[0014] A plate hole is formed between the bottom plate and the side plate of the storage bin close to the conveyor belt, and a lifting plate is arranged in the plate hole. The inclination of the plate surface of the lifting plate is consistent with the inclination of the plate surface of the bottom plate. The lifting plate cooperates with the side plate of the storage bin close to the conveyor belt to receive and lift the material. The lifting plate can be raised to form a side docking with the conveyor belt.

[0015] Preferably, a return trough is provided on the downstream side of the storage bin along the conveying direction of the conveyor belt, the feed port of the return trough is connected to the side of the conveyor belt, and the discharge port of the return trough is connected to the storage bin; a feed plate is fixedly provided at the feeding position, and the feed plate is directly connected to the output end of the conveyor belt.

[0016] Preferably, a through hole is provided on the feeding plate, a feeding column is fitted in the through hole, the top of the feeding column has a groove portion that matches the lower circumference of the material, and a lifting cylinder is provided below the feeding column, and the lifting cylinder drives the feeding column to rise and fall.

[0017] Preferably, the lower end of the feeding column is connected to a second rotation driving device, and the second rotation driving device drives the feeding column to rotate. The second rotation driving device is connected to the piston of the lifting cylinder through a connecting plate.

[0018] Preferably, the feeding mechanism includes a plurality of the storage bins arranged side by side, each of the storage bins corresponds to a feeding position, and the plurality of feeding positions are arranged side by side; the truss extends along the arrangement direction of the plurality of feeding positions, and the clamping arm and the glue coating device can be synchronously slidably arranged on the truss.

[0019] Preferably, the material taking mechanism comprises a second clamping jaw device and a third rotation driving device, wherein the second clamping jaw device is used to clamp the material on the first clamping jaw device, and the rotation shaft of the third rotation driving device is connected to the side of the second clamping jaw device, and the third rotation driving device is used to drive the second clamping jaw device to rotate to a vertical state or a horizontal state;

[0020] A translation arm is arranged on the truss, and the translation arm includes a fixed part and a movable part. The fixed part of the translation arm is arranged on the truss, the fixed part of the clamping arm and the glue coating device are arranged on the movable part of the translation arm, and the movable part can be away from or close to the second clamping jaw device.

[0021] Preferably, the valve body tooling comprises:

[0022] A seat plate, the seat plate being arranged on the slide;

[0023] A support seat, wherein the support seats are two oppositely arranged, and the two support seats are arranged on the seat plate;

[0024] A valve body fixing seat, the valve body fixing seat is arranged on the two support seats, and the valve body is placed on the valve body fixing seat;

[0025] A pneumatic clamp is located between the two support seats. There are two pneumatic clamps, which are arranged on both sides of the valve body fixing seat. The pneumatic clamp is used to press the valve body onto the valve body fixing seat.

[0026] Preferably, the pneumatic clamp includes a cylinder and a pressure head component, the pressure head component includes a pressure head and a pressure head frame, the pressure head is hinged on the pressure head frame, the piston of the cylinder is connected to one end of the pressure head, and the other end of the pressure head is used to press the valve body.

[0027] Preferably, the pneumatic clamp is arranged on a clamp seat, the clamp seat is located between the two support seats, the corresponding sides of the two support seats are provided with slide rails, the clamp seat is adapted to the two slide rails, and the clamp seat driving device can drive the clamp seat to slide along the slide rails.

[0028] Preferably, a positioning pin is provided on the valve body fixing seat, and a pin hole adapted to the positioning pin is provided on the valve body.

[0029] Preferably, the end of the robot is connected to an end flange, the end flange is connected to a tightening shaft mounting seat, and the tightening shaft is mounted on the tightening shaft mounting seat.

[0030] The present invention also provides an assembly method of an automatic assembly workstation, comprising:

[0031] Automatic feeding and gluing method:

[0032] The corresponding storage bin transports the material to the conveyor belt. During the conveying process, the conveyor belt detects whether the material is a problem material. If so, the conveyor belt transports the material to the return trough; if not, the conveyor belt transports the material to the feeding position;

[0033] The feeding column in the feeding position rises with the material to detect whether the two ends of the material are upside down. If so, the feeding column rotates a preset angle, and then continues to detect whether the two ends of the material are upside down; if not, the clamping arm carries the first clamping jaw device and extends downward, the first clamping jaw device clamps the material on the feeding column, and then the clamping arm is reset, the first clamping jaw device rotates, and the glue coating device sprays thread locking glue. At the same time, the clamping arm and the glue coating device move synchronously along the truss to align with the material picking mechanism, and then the clamping arm and the glue coating device move synchronously to above the material picking mechanism, the second clamping jaw device of the material picking mechanism clamps the glue coating head of the material, the first clamping jaw device releases the material, and the second clamping jaw device carries the material to flip, so that the material is placed in the material picking position with the glue coating head facing downward;

[0034] Loading method of valve body loading assembly workbench:

[0035] Manually load the valve body onto the valve body fixture of the slide at the upper and lower material positions of the valve body, press the start button, and after receiving the start signal, the control system controls the pneumatic clamp to press the valve body onto the valve body fixture. The pneumatic clamp sends a clamping signal to the control system, and the control system outputs a clamping completion signal. The slide is manually started, and the slide drives the valve body fixture and the valve body to move to the assembly position;

[0036] Robot equipment assembly method:

[0037] After the robot receives the material arrival signal sent by the second gripper device, the robot moves to the material taking position. After arriving at the position, the robot sends a start signal to the tightening shaft, tightens the shaft sleeve to take the non-glue-coated head of the material, and then the tightening shaft sends an opening signal to the second gripper device through the control system. The second gripper device opens, the robot takes the material, and moves to the assembly position with the material.

[0038] After the robot detects that the valve body has moved to the assembly position, the robot inserts the material into the material hole through the tightening shaft. After it is in place, the robot sends a start signal to the tightening shaft, and the tightening shaft screws the material into the valve body, then reverses and exits. The tightening shaft sends a completion signal to the robot, and the robot carries the tightening shaft to take the next material.

[0039] It can be seen from the above technical solution that the automatic assembly workstation in the present invention can automatically complete the loading and gluing of the studs, and can also automatically screw the studs into the stud holes of the valve body, thereby greatly reducing the amount of manual labor. In addition, since the screwing degree of the studs is controlled by the rotation angle of the tightening shaft, the assembly accuracy of the studs can be ensured. BRIEF DESCRIPTION OF THE DRAWINGS

[0040] In order to more clearly illustrate the scheme in the embodiment of the present invention, the following is a brief introduction to the drawings required for describing the embodiments. Obviously, the drawings in the following description are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without paying creative work.

[0041] Figure 1 A schematic diagram of the structure of an automatic assembly workstation provided by a specific embodiment of the present invention;

[0042] Figure 2 A structural schematic diagram of a glue coating mechanism provided in a specific embodiment of the present invention;

[0043] Figure 3 A schematic diagram of the structure of a feeding mechanism provided in a specific embodiment of the present invention;

[0044] Figure 4 A schematic diagram of the overall structure of an automatic feeding and gluing device provided in a specific embodiment of the present invention;

[0045] Figure 5 A schematic diagram of the structure of a material taking mechanism provided in a specific embodiment of the present invention;

[0046] Figure 6 A schematic diagram of the structure of a material taking mechanism provided in a specific embodiment of the present invention;

[0047] Figure 7 A schematic diagram of the structure of a valve body loading and assembly workbench provided in a specific embodiment of the present invention;

[0048] Figure 8 A schematic diagram of the structure of a valve body tooling provided in a specific embodiment of the present invention;

[0049] Fig. 9 A schematic structural diagram of a tightening shaft provided in a specific embodiment of the present invention.

[0050] Among them, 10 is automatic feeding and gluing equipment, 20 is valve body feeding and assembly workbench, and 30 is robot equipment;

[0051] 101 is a glue coating device, 102 is a clamping arm, 121 is a first arm plate, 122 is a second arm plate, 103 is a first clamping device, 104 is a first rotating drive device, 105 is a truss, 106 is a transition plate, 107 is a slide plate, 108 is a translation arm, 109 is a storage bin, 110 is a bottom plate, 111 is a return trough, 112 is a feeding plate, 113 is a lifting cylinder, 114 is a second rotating drive device, 115 is a feeding column, 116 is a lifting cylinder, 117 is a material taking position, 118 is a second clamping device, 119 is a third rotating drive device, 120 is a conveyor belt, and 123 is a lifting plate;

[0052] 201 is a slide, 202 is a valve body tooling, 203 is a valve body upper and lower material position, 204 is an assembly position, 205 is a seat plate, 206 is a support seat, 207 is a valve body fixing seat, 208 is a valve body, 209 is a cylinder, 210 is a pressure plate, 211 is a fixture seat, and 212 is a slide rail;

[0053] 301 is a robot, 302 is an end flange, 303 is a tightening shaft, 304 is a sleeve head, and 305 is a tightening shaft mounting seat. DETAILED DESCRIPTION

[0054] The invention discloses an automatic assembly workstation, which can realize automatic assembly of studs, reduce manual labor, and improve installation accuracy. The invention also discloses an assembly method of the automatic assembly workstation.

[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0056] The present invention discloses an automatic assembly workstation, please refer to the attached Figure 1 The automatic assembly workstation includes: an automatic feeding and gluing device 10, a valve body feeding and assembly workbench 20 and a robot device 30. The automatic feeding and gluing device 10 includes a feeding mechanism, a gluing mechanism and a picking mechanism. The feeding mechanism is used to transport the studs (materials) to the feeding position. The coating mechanism is used to clamp the studs from the feeding position and spray glue on the studs. The picking mechanism is used to clamp the material on the gluing mechanism and enable the material to be located at the picking position 117 with the gluing head facing downward.

[0057] The valve body loading and assembly workbench 20 comprises a slide 201 and a valve body tool 202, and the valve body tool 202 is used to clamp the valve body 208. The valve body tool 202 is arranged on the slide 201, and the slide 201 can drive the valve body tool 202 to and fro between the valve body upper and lower material positions 203 and the assembly position 204.

[0058] The robot device 30 includes a robot 301 and a tightening shaft 303. The tightening shaft 303 is arranged at the end of the robot 301. The tightening shaft 303 is provided with a sleeve head 304, and the sleeve head 304 is threadably adapted to the non-glue-coated head of the material. The non-glue-coated head of the material is opposite to the glue-coated head. The robot 301 can drive the tightening shaft 303 to and fro between the material taking position 117 and the assembly position 204. The tightening shaft 303 can drive the sleeve head 304 to rotate forward and reverse.

[0059] In the present invention, after the feeding mechanism delivers the stud to the feeding position, the gluing mechanism operates to clamp the stud on the feeding position, and then glue is applied to the stud. After the gluing is completed, the picking mechanism clamps the stud on the gluing mechanism, and then the picking mechanism flips the stud so that the glued head of the stud faces downward.

[0060] While the automatic feeding and gluing device 10 is feeding and gluing, the valve body 208 is loaded onto the valve body tooling 202 at the valve body loading and unloading positions 203 , and then the valve body 208 moves to the assembly position 204 along with the slide 201 .

[0061] After the robot 301 learns that the stud is located at the material taking position 117, the robot 301 moves to the material taking position 117 with the tightening shaft 303, and then the tightening shaft 303 rotates with the sleeve head 304 to screw the non-glue-coated head of the stud into the sleeve head 304. The material taking mechanism releases the stud, and the robot 301 moves to the assembly position 204 with the stud. After the robot 301 detects that the valve body 208 is located at the assembly position 204, the robot 301 drives the glue-coated head of the stud to be inserted into the stud hole of the valve body 208 through the tightening shaft 303, and the tightening shaft 303 rotates forward to tighten the stud, and then reverses to exit.

[0062] The automatic assembly workstation of the present invention can automatically complete the loading and gluing of the studs, and can also automatically screw the studs into the stud holes of the valve body 208, thereby greatly reducing the amount of manual labor. In addition, since the screwing degree of the studs is controlled by the rotation angle of the tightening shaft 303, the assembly accuracy of the studs can be ensured.

[0063] The following is a detailed description of the gluing mechanism, please refer to the attached Figure 2The gluing mechanism includes a truss 105, a gluing device 101, a clamping arm 102, a first clamping device 103 and a first rotating driving device 104. The gluing device 101 is arranged on the truss 105. The clamping arm 102 includes a fixed portion and a telescopic portion, and the telescopic portion is telescopically arranged on the fixed portion. The fixed portion of the clamping arm 102 is arranged on the truss 105. The gluing device 101 and the feeding position are arranged along the telescopic direction of the telescopic portion of the clamping arm 102.

[0064] The first rotation drive device 104 is fixed on the telescopic part of the clamping arm 102. The first clamping jaw device 103 is rotatably arranged on the telescopic part of the clamping arm 102. The first clamping jaw device 103 is used to clamp or release the stud. The first rotation drive device 104 is used to drive the first clamping jaw device 3 to rotate.

[0065] In this embodiment, the feeding mechanism conveys the stud to the feeding position. The initial position of the telescopic portion of the clamping arm 102 is located at the spraying position of the glue coating device 101. The telescopic portion of the clamping arm 102 is telescoped to carry the first clamping jaw device 103 close to the feeding position. The first clamping jaw device 103 clamps the stud on the feeding position, and then the telescopic portion of the clamping arm 102 is reset, and the stud is at the spraying position. The first rotary drive device 104 drives the stud to rotate by driving the first clamping jaw device 103, and at the same time, the needle of the glue coating device 101 sprays the thread locking glue. The stud receives the spraying of the glue coating device 101 while rotating, and the stud can receive the spraying in the circumferential direction. Since the rotation angle and rotation speed of the first rotary drive device 104 can be pre-set, the rotation angle and rotation speed of the stud can be controlled, so that it can be ensured that the stud receives the spraying uniformly in the circumferential direction, thereby improving the uniformity of the glue coating.

[0066] The glue coating device 101 specifically includes a glue storage barrel, a feed pipe, a glue dispensing valve and a needle. The glue dispensing valve is arranged on the feed pipe, and the needle is arranged at the head of the feed pipe. Compressed air enters the glue storage barrel to press the thread locking glue into the feed pipe, the glue dispensing valve is turned on, and the glue is pressed out from the needle for gluing. The glue output of the needle is adjusted by controlling the working time of the glue dispensing valve and the pressure of the glue storage barrel.

[0067] During the gluing process of the gluing mechanism, it is necessary to detect whether the stud is glued. If it is detected that no glue is applied, the gluing is repeated. If the thread lock glue is not applied twice in a row, the equipment alarms and manual processing is performed. Specifically, a detector can be used to detect whether the stud is glued.

[0068] In a specific embodiment of the present invention, the telescopic portion of the clamping arm 102 is configured to include a first arm plate 121 and a second arm plate 122. The first arm plate 121 and the second arm plate 122 are arranged opposite to each other and spaced apart. The glue coating device 101 is located on the side of the second arm plate 122 facing away from the first arm plate 121.

[0069] The first clamping device 103 is arranged horizontally. The first clamping device 103 includes a first seat body and a first clamping jaw. The first seat body passes through the first arm plate 121, the first clamping jaw passes through the second arm plate 122, and the first clamping jaw extends out on the side of the second arm plate 122 facing away from the first arm plate 121. The glue coating device 101 is arranged on the side of the second arm plate 122 facing away from the first arm plate 121, and the first seat body is located on the side of the second arm plate 122 facing away from the glue coating device 101. In this arrangement, the second arm plate 122 and the first arm plate 121 form a barrier to the first seat body, preventing excessive thread locking glue from being sprayed onto the first seat body, thereby ensuring stable operation of the first clamping device 103.

[0070] The first rotary drive device 104 is fixed on the first arm plate 121, and the rotary shaft of the first rotary drive device 104 is located between the first arm plate 121 and the second arm plate 122. The rotary shaft is connected to the portion of the first seat body located between the first arm plate 121 and the second arm plate 122 through a chain transmission assembly. The chain transmission assembly specifically includes a driving gear, a transmission chain and a driven gear. The driving gear is arranged on the rotary shaft of the first rotary drive device 104, the driven gear is arranged on the first seat body, and the transmission chain is wound around the driving gear and the driven gear. When the first clamping device 103 is located at the spraying position, the first rotary drive device 104 drives the first clamping device 103 to rotate through the chain transmission assembly, thereby driving the stud to rotate and receive spraying.

[0071] Since the first rotary drive device 104 and the chain transmission assembly are arranged on the side of the second arm plate 122 facing away from the glue coating device 101, the first arm plate 121 and the second arm plate 122 form a barrier to the first rotary drive device 104 to prevent the thread locking glue from being sprayed onto the first rotary drive device 104 as much as possible.

[0072] In a specific embodiment of the present invention, the first clamping jaw device 103 is preferably a first pneumatic clamping jaw device, and the first rotary drive device 104 is preferably a rotary motor device.

[0073] Please refer to the attached Figure 3 The feeding mechanism specifically includes a storage bin 109, and a conveyor belt 120 is provided on one side of the storage bin 109. The storage bin 109 is used to store studs and can convey the stored studs to the conveyor belt 120, and the conveyor belt 120 is used to convey the studs to the feeding position.

[0074] Specifically, the studs in the storage bin 109 can be transported to the conveyor belt 120 by a robot, and then the conveyor belt 120 transports the studs to the feeding position.

[0075] In the specific embodiment of the present invention, the studs in the storage bin 109 are lifted to the conveyor belt 120 by lifting. The specific design principle is as follows: the storage bin 109 is located on one side of the width direction of the conveyor belt 120. The surface of the bottom plate 110 of the storage bin 109 gradually tilts downward in the direction close to the conveyor belt 120.

[0076] The storage bin 109 is located on one side of the bandwidth direction of the conveyor belt 120, so one of the side plates of the storage bin 109 is closest to the conveyor belt 120. A plate hole is formed between the bottom plate 110 of the storage bin 109 and the side plate of the storage bin 109 close to the conveyor belt 120, and a lifting plate 123 is arranged in the plate hole. The inclination of the plate surface of the lifting plate 123 is consistent with the inclination of the plate surface of the bottom plate 110. In other words, when the lifting plate 123 is located in the plate hole, the lifting plate 123 is located in the extension area of ​​the plate surface of the bottom plate 110, and the lifting plate 123 and the bottom plate 110 jointly form the overall inclined bottom surface of the storage bin 109. After the operator puts the stud into the storage bin 109, the stud will slide down to the lifting plate 123 along the plate surface of the bottom plate 110 of the storage bin 109, and the side plate of the storage bin 109 close to the conveyor belt 120 forms a block for the stud. When the lifting plate 123 rises, the studs on the lifting plate 123 will rise accordingly. When the lifting plate 123 rises to form a side connection with the conveyor belt 120, the studs on the lifting plate 123 will roll onto the conveyor belt 120 along the inclined plate surface of the lifting plate 123, so that the storage bin 109 delivers the studs to the conveyor belt 120. The lifting plate 123 can be driven by the lifting cylinder 116.

[0077] When the lifting plate 123 and the conveyor belt 120 are in lateral connection, the inclined plate surface of the lifting plate 123 also forms a blocking effect on the studs, preventing the studs from moving out of the conveyor belt 120. After all the studs pass through the lifting plate 123 as conveyed by the conveyor belt 120, the lifting plate 123 is lowered into the plate hole of the storage bin 109 to receive the next batch of studs.

[0078] Along the conveying direction of the conveyor belt 120, a return trough 111 is provided at the downstream side of the storage bin 109. The feed port of the return trough 111 is connected to the conveyor belt 120. The discharge port of the return trough 111 is connected to the storage bin 109. A feed plate 112 is fixedly provided at the feeding position, and the feed plate 112 is directly connected to the output end of the conveyor belt 120. The studs on the conveyor belt 120 leave the output end of the conveyor belt 120 and then move onto the feed plate 112. The feed plate 112 is located downstream of the conveyor belt 120 relative to the feed port of the return trough 11.

[0079] During the process of conveying studs on the conveyor belt 120, if a problem is detected with the studs on the conveyor belt 120, then the studs are problematic studs. Then the studs upstream of the problematic studs will be controlled not to be taken away by the first clamping jaw device 103 temporarily, and temporarily stay on the feeding plate 112. The edge of the feeding plate 112 is provided with a fence to prevent the studs from sliding off the feeding plate 112.

[0080] Since the stud in front of the problematic stud is stranded on the feeding plate 112, the problematic stud will be blocked by the stud in front, and at the same time, the problematic stud will be pushed by the conveyor belt 120, so the problematic stud will be forced to enter the return trough 111 through the feed port of the return trough 111, and enter the storage bin 109 along the return trough 111. In this way, the problematic stud is screened out, avoiding the problematic stud being used in the equipment and causing safety hazards.

[0081] The problematic studs can also be screened out in the following manner: a retractable blocking plate is provided upstream of the feed plate 112. If the stud is detected to be a problematic stud, the blocking plate is extended to block the stud from entering the feed plate 112, and the stud is forced to enter the return chute 111.

[0082] In order to facilitate the stud to slide into the storage bin 109 along the return trough 111, the return trough 111 is configured as a spiral descending structure in the direction from the feed inlet of the return trough 111 to the discharge outlet of the return trough 111.

[0083] In order to facilitate the first clamping jaw device 103 to clamp the stud from the feeding plate 112, the present invention also makes the following design: a through hole is set on the feeding plate 112, and a feeding column 115 is matched in the through hole. The top of the feeding column 115 has a groove part, and the groove part matches the lower half of the circumference of the stud. That is, the stud can be just stuck in the groove part of the feeding column 115. A lifting cylinder 113 is set below the feeding column 115, and the lifting cylinder 113 can drive the feeding column 115 to rise and fall.

[0084] When the feeding plate 112 receives the studs conveyed by the conveyor belt 120, the feeding post 115 is matched in the through hole on the feeding plate 112, and the top of the feeding post 115 is flush with the plate surface of the feeding plate 112. When the studs are moved onto the feeding plate 112, the studs are just located above the groove. As the lifting cylinder 113 is lifted, the feeding post 115 gradually extends upward, and at the same time, the studs gradually fall into the groove at the top of the feeding post 115 and rise with the feeding post 115. The two sides of the groove at the top of the feeding post 115 form a block for the studs to prevent the studs from coming out of the groove of the feeding post 115. Since the studs are lifted by the feeding post 115, there is a certain distance between the studs and the feeding plate 112, which is convenient for the first clamping jaw device 103 to clamp the studs. After the stud is clamped by the first clamping jaw device 103 , the feeding column 115 will be driven by the lifting cylinder 113 to return to the through hole on the feeding plate 112 to prepare for receiving the next stud.

[0085] In actual applications, the stud bolts used in railway freight car brake valves have long thread heads and short thread heads. In the process of manual glue coating, the long thread heads and short thread heads of the stud bolts are often reversed. In order to solve the problem of reversing the long thread heads and short thread heads, the present invention has made the following design: the lower end of the feeding column 115 is connected to the second rotary drive device 114. The second rotary drive device 114 is used to drive the feeding column 115 to rotate. The second rotary drive device 114 is connected to the piston of the lifting cylinder 113 through a connecting plate. The lifting cylinder 113 drives the feeding column 115 to move up and down through the connecting plate and the second rotary drive device 114.

[0086] The present invention is provided with a detector around the feeding plate 112, and the detector is used to detect whether the long thread head and the short thread head of the stud on the feeding plate 112 are reversed. If reversed, then after the jacking cylinder 113 drives the feeding column 115 to rise, the second rotary drive device 114 drives the feeding column 115 to rotate 180 degrees, thereby exchanging the positions of the long thread head and the short thread head on the stud. If it is detected that the long thread head and the short thread head of the stud are not reversed, then after the jacking cylinder 113 drives the feeding column 115 to rise, the second rotary drive device 114 does not act, and waits for the first clamping jaw device 103 to clamp the stud on the feeding column 115.

[0087] The stud is in a horizontal state on the conveyor belt 120. After the first clamping device 103 descends, it will clamp the non-glue-coated head of the stud. After the first clamping device 103 is reset, the glue-coated head of the stud will be aligned with the needle of the glue-coating device 101. If the long thread head needs to be glued, the long thread head is the glue-coated head and the short thread head is the non-glue-coated head. If the short thread head needs to be glued, the short thread head is the glue-coated head and the long thread head is the non-glue-coated head.

[0088] In a specific embodiment of the present invention, the second rotation driving device 114 is preferably a rotation motor.

[0089] The driving accuracy required when driving the feeding column 115 to rotate 180° is relatively high, so this embodiment chooses to directly connect the second rotation driving device 114 to the feeding column 115 to improve the driving accuracy of the second rotation driving device 114 on the feeding column 115 .

[0090] When the feeding column 115 moves up and down, it will be guided by the through holes on the feeding plate 112. Therefore, even if a connecting plate and a second rotating drive device 114 are set between the lifting cylinder 113 and the feeding column 115, the lifting cylinder 113 indirectly drives the feeding column 115 through the connecting plate and the second rotating drive device 114, and the feeding column 115 can still move up and down smoothly.

[0091] Different types of railway freight car brake valves use different types of studs. To meet this demand, the present invention sets the storage bins 109 in the feeding mechanism to be multiple and arranged side by side, and different storage bins 109 are used to store different types of studs. Each storage bin 109 corresponds to a feeding position. Each storage bin 109 will transport the stored studs to the feeding position. Multiple feeding positions are arranged side by side. The truss 105 of the gluing mechanism extends along the multiple feeding positions. The clamping arm 102 and the gluing device 101 can be synchronously slidably arranged on the truss 105.

[0092] In a specific operation, the corresponding storage bin 109 is obtained according to the model of the railway freight car brake valve, and then the lifting plate 123 in the storage bin 109 rises to transport the studs to the conveyor belt 120, and the conveyor belt 120 transports the studs to the feeding position. At the same time, the clamping arm 102 and the glue coating device 101 synchronously slide to the vicinity of the feeding position to clamp the studs on the feeding position.

[0093] The sliding principle of the clamping arm 102 and the glue coating device 101 sliding synchronously along the truss 105 is as follows, please refer to the attached Figure 2 The fixing part of the clamping arm 102 and the glue coating device 101 are arranged on a transition plate 106, and the transition plate 106 is connected to a slide plate 107, and the slide plate 107 is slidably matched with the truss 105. The slide plate 107 is driven by a slide plate driving device. Therefore, when the clamping arm 102 and the glue coating device 101 need to slide synchronously along the truss 105, the slide plate 107 driving device can be started.

[0094] Since the clamping arm 102 and the gluing device 101 slide synchronously along the truss 105, the relative position between the clamping arm 102 and the gluing device 101 remains unchanged. Therefore, after the first clamping jaw device 103 on the clamping arm 102 clamps the stud, it only needs to be reset to the gluing position.

[0095] Please refer to the attached Figure 4 , 5 6. The material taking mechanism includes a second clamping jaw device 118 and a third rotation driving device 119. The second clamping jaw device 118 is used to clamp the stud on the first clamping jaw device 103. The rotation axis of the third rotation driving device 119 is connected to the side of the second clamping jaw device 118. The third rotation driving device 119 is used to drive the second clamping jaw device 118 to rotate to a vertical state or a horizontal state.

[0096] When the second clamping jaw device 118 is to clamp the stud on the first clamping jaw device 103, the second clamping jaw device 118 rotates to a vertical state with the third rotating drive device 119, and the jaw opening of the second clamping jaw device 118 faces upward. After the jaws of the second clamping jaw device 118 clamp the stud, the jaws of the first clamping jaw device 103 release the stud. Afterwards, the second clamping jaw device 118 is reversed to a horizontal state under the drive of the third rotating drive device 119, so that the stud is in a vertical state, and the gluing head of the stud is located at the bottom, so that it is convenient for the robot 301 to grab the stud and insert the gluing head of the stud into the brake valve to ensure the correctness of the installation.

[0097] The material taking mechanism needs to have a certain distance from the glue coating mechanism to avoid interference between the glue coating mechanism and the material taking mechanism. The present invention sets the material taking mechanism on the side of the truss 105 away from the material storage bin 109. After the spraying is completed, the glue coating device 101 and the clamping arm 102 are synchronously translated to the top of the material taking mechanism so that the material taking mechanism completes the material taking.

[0098] In order to achieve synchronous translation of the clamping arm 2 and the glue coating device 101, the present invention sets a translation arm 108 on the truss 105. Figure 2 , Attachment Figure 4 The translation arm 108 includes a fixed portion and a movable portion. The fixed portion of the translation arm 108 is arranged on the truss 105, and the fixed portion of the clamping arm 102 and the glue coating device 101 are arranged on the movable portion of the translation arm 108. The movable portion of the translation arm 108 can drive the clamping arm 102 and the glue coating device 101 to approach or move away from the material taking mechanism.

[0099] Please refer to the attached Figure 2 , the translation direction of the translation arm 108 is perpendicular to the truss 105. When the moving part of the translation arm 108 is extended, the clamping arm 102 and the glue coating device 101 will move to the top of the material taking mechanism along with the moving part.

[0100] It can be seen from the above that the truss 105 extends along the arrangement direction of the feeding position, and the clamping arm 102 and the glue coating device 101 are connected to the transition plate 106, and the transition plate 106 is connected to the slide plate 107. In this embodiment, the transition plate 106 is connected to the moving part of the translation arm 108, and the fixed part of the translation arm 108 is connected to the slide plate 107, that is, the transition plate 106 is connected to the slide plate 107 through the translation arm 108.

[0101] After the first clamping jaw device 103 on the clamping arm 102 clamps the stud, the stud rotates under the drive of the first rotary drive device 104, and the gluing device 101 starts to spray glue on the stud. At the same time, the clamping arm 102, the gluing device 101 and the translation arm 108 are driven by the slide 107 to move along the truss 105 to a position aligned with the material picking mechanism. The stud receives the glue while moving along the truss 105 with the clamping arm 102, thereby improving the glue spraying efficiency. Afterwards, under the drive of the moving part of the translation arm 108, the clamping arm 102 carries the first clamping jaw device 103 and moves to the top of the material picking mechanism in a direction perpendicular to the truss 105, so that the second clamping jaw device 118 can take away the stud on the first clamping jaw device 103.

[0102] The working process of the automatic feeding and gluing device 10 of the present invention is as follows: first determine the model of the stud, then obtain the corresponding storage bin 109, the lifting plate 123 in the storage bin 109 carries the stud to rise to dock with the side of the conveyor belt 120, and the stud slides into the conveyor belt 120. If the stud is detected to be a problem stud, then the problem stud is controlled to enter the return trough 111 and re-enter the storage bin 109 along the return trough 111. If the quality of the stud is qualified, the conveyor belt 120 conveys the stud to the feeding column 115 in the feeding plate 112. The feeding column 115 rises under the drive of the lifting cylinder 113. If the long thread head and the short thread head of the stud are reversed, the second rotary drive device 114 drives the feeding column 115 to rotate 180°. If the long thread head and the short thread head of the stud are not reversed, the second rotary drive device 114 does not act.

[0103] The slide plate 107 drives the clamping arm 102, the gluing device 101 and the translation arm 108 to move synchronously along the truss 105 to the top of the corresponding feeding column 115. The telescopic part of the clamping arm 102 extends downward, and the first clamping device 103 clamps the stud in the groove at the top of the feeding column 115, and then the clamping arm 102 carries the first clamping device 103 to reset. Under the drive of the first rotary drive device 104, the first clamping device 103 rotates with the stud. The gluing device 101 is started to spray glue on the stud. While receiving the glue, the stud moves along the truss 105 with the clamping arm 102 and the slide plate 107 to a position aligned with the material picking mechanism. After the glue spraying is completed, the translation arm 108 drives the clamping arm 102 and the first clamping device 103 to move to the top of the material picking mechanism. The second clamping device 118 in the material picking mechanism rotates to a vertical state under the drive of the third rotary drive device 119. The second clamping device 118 clamps the stud, and the first clamping device 103 releases the clamp. Then the second clamping device 118 is reversed to a horizontal state under the drive of the third rotary drive device 119 to place the stud with the glued head facing down on the material taking position 117, waiting for the robot 301 to take it away.

[0104] Next, the valve body tooling 202 is described in detail. Please refer to the attached Figure 7 and attached Figure 8 :The valve body tooling 202 includes a seat plate 205, a support seat 206, a valve body fixing seat 207 and a pneumatic clamp. Among them, the seat plate 205 is fixed on the slide 201. There are two support seats 206, the two support seats 206 are arranged opposite to each other, and the two support seats 206 are arranged on the seat plate 205. The valve body fixing seat 207 is placed along the two support seats 206, and the valve body fixing seat 207 is arranged on the two support seats 206. The valve body fixing seat 207 is used to place the valve body 208. The pneumatic clamp is located between the two support seats 206. There are two pneumatic clamps, and the two pneumatic clamps are arranged on both sides of the valve body fixing seat 207. The pneumatic clamp is used to press the valve body 208 onto the valve body fixing seat 207.

[0105] At the valve body loading and unloading position 203, the valve body fixing seat 207 is installed on the support seat 206, and then the valve body 208 is placed on the valve body fixing seat 207, and then the pneumatic clamp is started to press the valve body 208 on the valve body fixing seat 207. Then the slide 201 is started, and the slide 201 drives the valve body tooling 202 and the valve body 208 to move to the assembly position 204 through the seat plate 205.

[0106] In a specific embodiment of the present invention, the pneumatic clamp specifically includes a cylinder 209 and a pressure plate 210, and the pressure plate 210 specifically includes a pressure plate and a pressure plate frame. The pressure plate is hinged on the pressure plate frame. The cylinder 209 is located on the side of the pressure plate 210 facing away from the valve body 208. The piston of the cylinder 209 is connected to one end of the pressure plate. When the piston of the cylinder 209 extends, the pressure plate rotates toward one side of the valve body 208, and the end of the pressure plate away from the cylinder 209 will press the valve body 208 against the valve body fixing seat 207.

[0107] The pneumatic clamp in this embodiment can adapt to valve bodies 208 of different thicknesses. When the pressing force of the pressure plate of the pneumatic clamp on the valve body 208 reaches a preset value, the magnetic switch on the pneumatic clamp will send a clamping signal to the control system.

[0108] In order to further expand the scope of application of the pneumatic clamp, the specific embodiment of the present invention sets the pneumatic clamp on the clamp seat 211, and the clamp seat 211 is located between the two support seats 206. The corresponding sides of the two support seats 206 are provided with slide rails 212. The two sides of the clamp seat 211 are provided with adapter grooves, and the two adapter grooves are respectively adapted to the two slide rails 212. The clamp seat driving device can drive the clamp seat 211 to slide along the slide rails 212. In this way, different types of valve bodies 208 and valve body fixing seats 207 can be installed on the support seat 206, and the clamp seat 211 can be adjusted according to the size of the installed valve body 208 and valve body fixing seat 207 to ensure that the cylinder clamp on the clamp seat 211 can press the valve body 208 on the valve body fixing seat 207. In addition, the pneumatic clamp is detachably connected to the clamp seat 211, so different types of cylinder 209 clamps can be installed on the clamp seat 211 according to specific needs.

[0109] Different types of valve bodies 208 correspond to different types of valve body fixing seats 207. In order to ensure the stability of the valve body 208, a positioning pin is provided on the valve body fixing seat 207 in the specific embodiment of the present invention, and a pin hole adapted to the positioning pin is provided on the valve body 208. The cooperation between the positioning pin and the pin hole can position the valve body 208. In addition, the positions of the pin holes on different types of valve bodies 208 are different, so it is possible to avoid the valve body 208 from being installed incorrectly.

[0110] In the specific embodiment of the present invention, two slides 201 are provided, and each slide 201 is provided with a valve body tooling 202. Thus, when the valve body 208 on one slide 201 is receiving the stud bolt for assembly, the valve body 208 can be loaded on the other slide 201, thus improving the operation efficiency.

[0111] As can be seen from the above description, the robot device 30 specifically includes a robot 301 and a tightening shaft 303. In a specific embodiment of the present invention, please refer to the attached Fig. 9A terminal flange 302 is provided at the end of the robot 301, and the terminal flange 302 is connected to the end of the robot 301 by bolts. A tightening shaft mounting seat 305 is vertically provided at the bottom of the terminal flange 302. The tightening shaft mounting seat 305 can be welded to the terminal flange 302. The tightening shaft 303 is mounted on the tightening shaft mounting seat 305.

[0112] Since there are at most two types of stud bolts on each valve body 208, two tightening shafts 303 are provided in the specific embodiment of the present invention, and the two tightening shafts 303 are respectively provided with a sleeve head 304. Thus, which tightening shaft 303 to use is determined according to the specific type of the stud bolt.

[0113] The present invention also discloses an assembly method of an automatic assembly workstation, which includes an automatic feeding and gluing method, a feeding method of a valve body feeding and assembly workbench 20, and an assembly method of a robot device 30.

[0114] Automatic feeding and gluing method:

[0115] Different types of studs are stored in different storage bins 109 in advance, and the corresponding storage bin 109 is obtained according to the type of studs required by the valve body 208. The corresponding storage bin 109 conveys the studs to the conveyor belt 120, and during the conveying process of the conveyor belt 120, it is detected whether the studs are problematic studs. If so, the conveyor belt 120 conveys the problematic studs to the return trough 111; if not, the conveyor belt 120 conveys the studs to the feeding position.

[0116] The feeding column 115 in the feeding position is driven by the lifting cylinder 113 to rise to a preset height against the stud, and then the detector is used to detect whether the two ends of the stud are upside down. If so, the feeding column 115 rotates 180°, and then continues to detect whether the two ends of the stud are upside down. If not, the clamping arm 102 carries the first clamping device 103 and the glue coating device 101 to extend downward, and the first clamping device 103 clamps the stud on the feeding column 115, and then the clamping arm 102 carries the first clamping device 103 and the glue coating device 101 to reset. The first clamping device 103 rotates, and the glue coating device 101 sprays thread locking glue. At the same time, the clamping arm 102 and the glue coating device 101 move synchronously along the truss 105 to align with the material picking mechanism, and then the clamping arm 102 and the glue coating device 101 move synchronously to the top of the material picking mechanism under the drive of the translation arm 108. The second clamping device 118 of the picking mechanism clamps the gluing head of the stud, then the first clamping device 103 releases the stud, and the second clamping device 118 carries the stud to flip over, so that the stud is placed in the picking position with the gluing head facing down, and then the picking mechanism sends a stud in place signal to the robot 301.

[0117] Loading method of valve body loading assembly workbench 20:

[0118] Manually load the valve body 208 onto the valve body fixture 202 of the slide 201 at the valve body loading and unloading position 203, press the start button, and after receiving the start signal, the control system controls the pneumatic clamp to press the valve body 208 onto the valve body fixture 202. The pneumatic clamp sends a clamping signal to the control system, and the control system outputs a clamping completion signal. The slide 201 is manually started, and the slide 201 drives the valve body fixture 202 and the valve body 208 to move to the assembly position 204. After the valve body 208 moves to the assembly position 204, the valve body loading and assembly workbench 20 will send a valve body arrival signal to the robot 301.

[0119] Robotic device 30 assembly method:

[0120] After the robot 301 receives the stud in place signal sent by the second clamping jaw device 118, the robot 301 moves to the material picking position. After reaching the position, the robot 301 sends a start signal to the tightening shaft 303, and the tightening shaft 303 takes the non-glue-coated head of the stud. Then, the tightening shaft 303 sends an opening signal to the second clamping jaw device 118 through the control system, the second clamping jaw opens, and the robot 301 takes the stud and moves to the assembly position 204 with the stud.

[0121] After the robot 301 detects that the valve body 208 has moved to the assembly position 204, the robot 301 inserts the stud into the stud hole on the valve body 208 through the tightening shaft 303. After it is in place, the robot 301 sends a start signal to the tightening shaft 303, and the tightening shaft 303 screws the stud into the valve body 208, then reverses and exits. The tightening shaft 303 sends a completion signal to the robot 301, and the robot 301 carries the tightening shaft 303 to remove the next stud. This cycle continues until all the studs on the valve body 208 are assembled. The robot 301 sends a completion signal to the valve body loading and assembly workbench 20, the slide 201 moves to the valve body loading and unloading position 203, the valve body 208 is manually removed, and another slide 201 is manually started. The other slide 201 moves to the assembly position 204 and continues to automatically assemble the studs. While the other slide 201 is being assembled, the valve body 208 is manually loaded to the previous slide 201, and the cycle continues.

[0122] Finally, it should be noted that the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, an element defined by the phrase "comprises a ..." does not exclude the presence of other identical elements in the process, method, article or device that includes the element.

[0123] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0124] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. An automatic assembly workstation, characterized in that: include: Automatic feeding and gluing equipment (10), the automatic feeding and gluing equipment (10) comprising a feeding mechanism, a gluing mechanism and a material taking mechanism, the feeding mechanism being used to transport materials to a feeding position, the gluing mechanism being used to obtain materials from the feeding position and to apply glue to the materials, the material taking mechanism being used to obtain materials on the gluing mechanism and being able to place the materials at the material taking position with the gluing head facing downwards; A valve body loading and assembly workbench (20), the valve body loading and assembly workbench (200) comprising a slide (201) and a valve body tooling (202), the valve body tooling (202) being used to clamp the valve body (208), the valve body tooling (202) being arranged on the slide (201), and the valve body tooling (202) being able to move back and forth between valve body upper and lower material positions (203) and an assembly position (204) driven by the slide (201); A robot device (30), the robot device (30) comprising a robot (301) and a tightening shaft (303), the tightening shaft (303) being arranged at the end of the robot (301), the tightening shaft (303) being provided with a sleeve head (304), the sleeve head (304) being threadably adapted to a non-glue-coated head of the material, the robot (301) being capable of driving the tightening shaft (303) to move back and forth between the material taking position and the assembly position (204), and the tightening shaft (303) being capable of driving the sleeve head (304) to rotate forward and reverse; The glue coating mechanism comprises a truss (105), a glue coating device (101), a clamping arm (102), a first clamping claw device (103) and a first rotation driving device (104); The glue coating device (101) is arranged on the truss (105), and the glue coating device (101) and the feeding position are arranged along the telescopic direction of the clamping arm (102); the clamping arm (102) comprises a fixed portion and a telescopic portion, the fixed portion of the clamping arm (102) is arranged on the truss (105), the first rotary drive device (104) is fixedly arranged on the telescopic portion of the clamping arm (102), the first clamping jaw device (103) is rotatably arranged on the telescopic portion of the clamping arm (102), the first clamping jaw device (103) is used to clamp or release materials, and the first rotary drive device (104) is used to drive the first clamping jaw device (103) to rotate; The feeding mechanism comprises a material storage bin (109), a conveyor belt (120) is provided on one side of the material storage bin (109), the material storage bin (109) is capable of conveying materials to the conveyor belt (120), and the conveyor belt (120) is used to convey the materials to the feeding position; The feeding mechanism comprises a plurality of storage bins (109) arranged side by side, each storage bin (109) corresponds to a feeding position, and the plurality of feeding positions are arranged side by side; the truss (105) extends along the arrangement direction of the plurality of feeding positions, and the clamping arm (102) and the glue coating device (101) are synchronously slidably arranged on the truss (105); The material picking mechanism comprises a second clamping jaw device (118) and a third rotation driving device (119), wherein the second clamping jaw device (118) is used to clamp the material on the first clamping jaw device (103), and the rotation axis of the third rotation driving device (119) is connected to the side of the second clamping jaw device (118), and the third rotation driving device (119) is used to drive the second clamping jaw device (118) to rotate to a vertical state or a horizontal state; A translation arm (108) is arranged on the truss (105), and the translation arm (108) comprises a fixed portion and a movable portion, the fixed portion of the translation arm (108) is arranged on the truss (105), the fixed portion of the clamping arm (102) and the glue coating device (101) are arranged on the movable portion of the translation arm (108), and the movable portion can be moved away from or close to the second clamping jaw device (118).

2. The automatic assembly workstation according to claim 1, characterized in that: The material storage bin (109) is located on one side in the bandwidth direction of the conveyor belt (120); The surface of the bottom plate (110) of the storage bin (109) gradually slopes downward in a direction close to the conveyor belt (120); A plate hole is formed between the bottom plate (110) and the side plate of the storage bin (109) close to the conveyor belt (120), and a lifting plate (123) is arranged in the plate hole. The inclination of the plate surface of the lifting plate (123) is consistent with the inclination of the plate surface of the bottom plate (110). The lifting plate (123) cooperates with the side plate of the storage bin (109) close to the conveyor belt (120) to receive and lift the material. The lifting plate (123) can be raised to form a side connection with the conveyor belt (120).

3. The automatic assembly workstation according to claim 2, characterized in that: Along the conveying direction of the conveyor belt (120), a return trough (111) is provided on the downstream side of the storage bin (109), the feed port of the return trough (111) is connected to the side of the conveyor belt (120), and the discharge port of the return trough (111) is connected to the storage bin (109); a feed plate (112) is fixedly provided at the feed position, and the feed plate (112) is directly connected to the output end of the conveyor belt (120).

4. The automatic assembly workstation according to claim 3, characterized in that: The feeding plate (112) is provided with a through hole, in which a feeding column (115) is fitted, the top end of the feeding column (115) having a groove portion fitted with the lower circumferential surface of the material, and a lifting cylinder (113) is provided below the feeding column (115), and the lifting cylinder (113) drives the feeding column (115) to rise and fall.

5. The automatic assembly workstation according to claim 4, characterized in that: The lower end of the feeding column (115) is connected to a second rotary drive device (114), and the second rotary drive device (114) drives the feeding column (115) to rotate. The second rotary drive device (114) is connected to the piston of the lifting cylinder (113) via a connecting plate.

6. The automatic assembly workstation according to claim 1, characterized in that: The valve body tooling (202) comprises: A seat plate (205), the seat plate (205) being arranged on the slide platform (201); A support seat (206), wherein the support seats (206) are two and arranged opposite to each other, and the two support seats (206) are arranged on the seat plate (205); a valve body fixing seat (207), the valve body fixing seat (207) being arranged on the two support seats (206), and the valve body (208) being placed on the valve body fixing seat (207); A pneumatic clamp, the pneumatic clamp is located between the two support seats (206), there are two pneumatic clamps, the two pneumatic clamps are arranged on both sides of the valve body fixing seat (207), and the pneumatic clamp is used to press the valve body (208) onto the valve body fixing seat (207).

7. The automatic assembly workstation according to claim 6, characterized in that: The pneumatic clamp comprises a cylinder (209) and a pressure plate component (210), wherein the pressure plate component comprises a pressure plate and a pressure plate frame, wherein the pressure plate is hinged on the pressure plate frame, the piston of the cylinder (209) is connected to one end of the pressure plate, and the other end of the pressure plate is used to press the valve body (208).

8. The automatic assembly workstation according to claim 7, characterized in that: The pneumatic clamp is arranged on a clamp seat (211), and the clamp seat (211) is located between the two support seats (206). The corresponding sides of the two support seats (206) are provided with slide rails (212). The clamp seat (211) is adapted to the two slide rails (212), and the clamp seat driving device can drive the clamp seat (211) to slide along the slide rails (212).

9. The automatic assembly workstation according to claim 6, characterized in that: A positioning pin is provided on the valve body fixing seat (207), and a pin hole adapted to the positioning pin is provided on the valve body (208).

10. The automatic assembly workstation according to claim 1, characterized in that: The end of the robot (301) is connected to an end flange (302), the end flange (302) is connected to a tightening shaft mounting seat (305), and the tightening shaft (303) is mounted on the tightening shaft mounting seat (305).

11. An assembly method of an automatic assembly workstation, based on the automatic assembly workstation according to claim 3, characterized in that: include: Automatic feeding and gluing method: The corresponding storage bin (109) conveys the material to the conveyor belt (120). During the conveying process of the conveyor belt (120), it is detected whether the material is a problematic material. If so, the conveyor belt (120) conveys the material to the return trough (111); if not, the conveyor belt (120) conveys the material to the feeding position; The feeding column (115) in the feeding position is raised against the material to detect whether the two ends of the material are upside down. If so, the feeding column (115) is rotated by a preset angle, and then the two ends of the material are continuously detected to be upside down. If not, the clamping arm (102) carries the first clamping jaw device (103) and extends downward, and the first clamping jaw device (103) clamps the material on the feeding column (115). Then, the clamping arm (102) is reset, the first clamping jaw device (103) is rotated, and the glue coating device (101) sprays The thread locking glue is injected, and at the same time, the clamping arm (102) and the glue coating device (101) are synchronously moved along the truss (105) to be aligned with the material picking mechanism, and then the clamping arm (102) and the glue coating device (101) are synchronously moved to above the material picking mechanism, the second clamping jaw device (118) of the material picking mechanism clamps the glue coating head of the material, the first clamping jaw device (103) releases the material, and the second clamping jaw device (118) carries the material to turn over, so that the material is placed at the material picking position with the glue coating head facing downward; Loading method of valve body loading assembly workbench: The valve body (208) is manually loaded onto the valve body fixture (202) of the slide (201) at the valve body upper and lower material positions (203), and a start button is pressed. After receiving the start signal, the control system controls the pneumatic clamp to press the valve body (208) onto the valve body fixture (202). The pneumatic clamp sends a clamping signal to the control system, and the control system outputs a clamping completion signal. The slide (201) is manually started, and the slide (201) drives the valve body fixture (202) and the valve body (208) to move to the assembly position (204). Robot equipment assembly method: After the robot (301) receives a material arrival signal sent by the second clamping device (118), the robot (301) moves to the material taking position. After arriving at the position, the robot (301) sends a start signal to the tightening shaft (303), and the tightening shaft (303) takes the non-glue-coated head of the material. Then, the tightening shaft (303) sends an opening signal to the second clamping device (118) through the control system, and the second clamping device (118) opens. The robot (301) takes the material and moves to the assembly position (204) with the material. After the robot (301) detects that the valve body (208) has moved to the assembly position (204), the robot (301) inserts the material into the material hole through the tightening shaft (303). After reaching the position, the robot (301) sends a start signal to the tightening shaft (303), and the tightening shaft (303) screws the material into the valve body (208), then reverses and exits. The tightening shaft (303) sends a completion signal to the robot (301), and the robot (301) carries the tightening shaft (303) to take the next material.