A profile base structure and construction method for reclaiming cultivated land from an abandoned quarry

By designing the structure of the gravel drainage layer, soil conservation layer and water-holding layer in the abandoned quarry, and using non-woven geotextile and calcium bentonite, the problem of lack of soil resources and rainfall infiltration after the quarry was reclaimed was solved. It improves the water storage capacity of the land and crop growth conditions, and achieves economical and applicable land reclamation effects.

CN115748649BActive Publication Date: 2024-10-01SHANDONG AGRICULTURAL UNIVERSITY +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211286643.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-20
Publication Date
2024-10-01
Estimated Expiration
2042-10-20

AI Technical Summary

Technical Problem

After the reclamation of abandoned quarries, soil resources are scarce, and rainfall water resources cannot penetrate deeply, resulting in poor water storage and retention capacity of the soil, which affects the success or failure of land use.

Method used

A base structure of reclaimed cultivated land profile is designed, including gravel drainage layer, soil conservation layer and water-holding layer from bottom to top, using non-woven geotextile and calcium-based bentonite, combined with waste gravel and stone from the quarry. Form an effective drainage and water retention system.

Benefits of technology

It significantly improves the ability to regulate and store rainfall resources, reduces the loss of fine particles, avoids water logging, is suitable for crop growth, reduces reclamation costs, and improves the quality and productivity of newly added cultivated land.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115748649B_ABST
    Figure CN115748649B_ABST
Patent Text Reader

Abstract

The present invention discloses a profile base structure and construction method of reclaimed farmland from an abandoned quarry, and belongs to the technical field of land improvement and ecological restoration. The profile base structure of reclaimed farmland from an abandoned quarry of the present invention includes, from bottom to top, a gravel drainage layer, a soil retention layer and a water holding layer; the gravel drainage layer is composed of gravel with a diameter of 10-60 mm, and the thickness of the gravel drainage layer is 20-30 cm; the soil retention layer is composed of a non-woven geotextile; the water holding layer is composed of calcite and calcium-based bentonite, and the content of calcium-based bentonite is 1-2% of the volume of calcite; the thickness of the water holding layer is 10-20 cm. The present invention improves the rainfall regulation and storage capacity of reclaimed farmland from an abandoned quarry; and the profile base structure of reclaimed farmland from an abandoned quarry is constructed by using local materials, which is convenient to construct, low in cost, and suitable for large-scale promotion and application.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of land improvement and ecological restoration, and in particular to a profile base structure for reclaiming cultivated land from an abandoned quarry and a construction method thereof. Background Art

[0002] In recent years, with the acceleration of my country's social and economic development and urbanization, especially the rapid development of railways, highways and real estate industries, the quarrying industry has developed rapidly. After the quarrying mines are finished, there are a lot of abandoned gravel and stone, and most of the quarrying surfaces have exposed base rocks. Combined with the land reclamation suitability evaluation, some damaged units can be reclaimed as arable land, which is one of the important directions for the reclamation of abandoned quarrying mines. This is of great significance for supplementing arable land resources, maintaining the balance of arable land occupation and compensation, and ensuring food security.

[0003] Land reclamation in mining areas is a hot topic in the world's mining countries. Soil reconstruction is the core of land reclamation research. As the most basic reconstruction profile optimization research in soil reconstruction research, it has been relatively less carried out in my country. At present, the focus is mainly on the profile reconstruction of the returned soil and the conventional measures of soil improvement, and few people pay attention to the treatment of the base structure. The key problem faced in reclamation on the bare rock base of abandoned quarries or abandoned gravel layers is that due to the scarcity of soil resources and the limited backfill depth, rainfall water resources cannot be retained in the soil through deep infiltration, the soil has poor water storage and retention capacity, and the soil is also prone to loss. In the limestone mining area of ​​the hilly region of North China, groundwater resources are scarce and precipitation resources are extremely precious. The full utilization of rainwater resources is crucial and is related to the success or failure of land use after reclamation. By using local materials and designing a scientific and reasonable base structure of the reclamation soil profile, it can play an important supporting role in improving the comprehensive quality and productivity of reclaimed arable land. Summary of the invention

[0004] In view of the above-mentioned prior art, the purpose of the present invention is to provide a profile base structure and construction method for reclaiming arable land from abandoned quarries, so as to solve the technical problems of low comprehensive quality of reclaimed arable land from abandoned bare rock land in quarries and poor drainage and storage capacity of rainfall resources.

[0005] To achieve the above object, the present invention adopts the following technical solution:

[0006] In a first aspect, the present invention provides a profile base structure for reclaiming farmland from an abandoned quarry, which comprises, from bottom to top, a gravel drainage layer, a soil retention layer and a water holding layer;

[0007] The gravel drainage layer is composed of gravel with a diameter of 10-60 mm, and the thickness of the gravel drainage layer is 20-30 cm;

[0008] The soil retention layer is composed of non-woven geotextile;

[0009] The water-holding layer is composed of pyrophyllite and calcium-based bentonite, wherein the content of the calcium-based bentonite is 1-2% of the volume of the pyrophyllite; and the thickness of the water-holding layer is 10-20 cm.

[0010] Preferably, the slope of the gravel drainage layer is 0.2%-0.4%, tending towards the direction of the drainage ditch inside the reclaimed field; the average elevation of the drainage ditch bottom should be 10-15 cm lower than the elevation of the gravel drainage layer, which can both accumulate some precipitation resources and facilitate drainage.

[0011] Preferably, the specification of the non-woven geotextile is 200g / m 2 The overlap width is greater than or equal to 10 cm. The nonwoven geotextile used in the present invention has the dual functions of drainage and anti-filtration, and can meet the requirements of water permeability and soil retention.

[0012] Preferably, the particle size of the lithospermum parkii is between 0.16-4.75 mm.

[0013] Preferably, the particle size of the calcium-based bentonite is 0.5-1 mm. Adding a certain volume of calcium-based bentonite with strong water absorption capacity into the stone can significantly improve the nutrient retention effect of the water-bearing layer.

[0014] A second aspect of the present invention provides a method for constructing a profile base structure for reclaiming farmland from an abandoned quarry, comprising the following steps:

[0015] (1) Level the base of the abandoned quarry site to be reclaimed as farmland, cut the high and fill the low, and then use the abandoned gravel from the quarry to backfill and construct a gravel drainage layer;

[0016] (2) Lay non-woven geotextile on the gravel drainage layer to form a soil retention layer;

[0017] (3) Lay limestone and calcium-based bentonite on the soil retention layer to construct a water-retaining layer.

[0018] Preferably, in step (1), a road roller is used for compaction and leveling, the ground height difference does not exceed 5 cm, and the compaction degree is above 90%.

[0019] Preferably, in step (2), when laying the non-woven geotextile, the overlap width is greater than or equal to 10 cm.

[0020] The third aspect of the present invention provides the application of the above-mentioned abandoned quarry reclaimed farmland profile base structure in improving the rainfall storage capacity of abandoned quarry reclaimed farmland.

[0021] Beneficial effects of the present invention:

[0022] (1) The land reclamation arable land base structure of the present invention makes full use of waste gravel slag to construct the base, significantly reducing the need for backfill soil. The base includes a gravel drainage layer, a soil retention layer and a water holding layer, which can prevent the loss of fine particles and allow the upper soil to store water during moderate rains and drain smoothly during heavy rains, avoiding waterlogging, being suitable for crop growth, improving the quality of newly added arable land, and increasing production capacity.

[0023] (2) The gravel drainage layer of the present invention is made of quarry waste gravel, the filter layer is made of ordinary geotextile, and the water-holding layer is made of quarry waste stone, mixed with locally abundant calcium-based bentonite with good water and fertilizer retention effects. The raw materials are simple and easy to obtain, cheap, economical and applicable, especially the stone is used instead of sand, which is green and environmentally friendly, and has low reclamation cost.

[0024] (3) The present invention uses a forklift and a roller, in combination with manual work, to lay the road in sequence. The process is simple, easy to operate, and convenient for promotion. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 : A schematic diagram of the profile base structure of the abandoned quarry reclaimed farmland of the present invention; in the figure, 1-gravel drainage layer, 2-soil retention layer, 3-water holding layer, 4-imported soil layer.

[0026] Figure 2 : Schematic diagram of the experimental device structure for simulating soil column leaching test. DETAILED DESCRIPTION

[0027] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0028] Terminology Note:

[0029] Shixiao: refers to particles with a size less than 5mm screened out during the mechanical processing of crushed stone in the quarry, and the particle size is mainly between 0.16-4.75mm.

[0030] Slope: refers to the height difference of the road surface or level; a slope of 0.2%-0.4% means that there is a height difference of 0.2-0.4m on a 100m long road surface.

[0031] As mentioned above, the key problem faced in reclamation on the bare rock base or abandoned gravel layer of abandoned quarries is that due to the scarcity of soil resources and the limited backfill depth, rainfall water resources cannot be retained in the soil through deep infiltration, the soil has poor water storage and retention capacity, and the soil is also prone to loss. In the limestone mining area of ​​the hilly region of North China, groundwater resources are scarce and precipitation resources are extremely precious. The full utilization of rainwater resources is crucial and is related to the success or failure of land use after reclamation.

[0032] Based on this, the present invention designs a profile base structure for reclaiming cultivated land from an abandoned quarry. The profile base structure for reclaiming cultivated land from an abandoned quarry of the present invention mainly refers to the non-important soil part of the bottom of the profile created during reclamation, that is, the gravel drainage layer, soil retention layer and stone water retention layer created by using gravels of different particle sizes and other materials abandoned from the quarry. The profile base structure and construction method for reclaiming cultivated land from an abandoned quarry of the present invention first screen the residual sand and gravel in the abandoned quarry, and then backfill gravel, mechanically compact and level the abandoned arable bare rock platform of the quarry that has passed the feasibility evaluation to form a drainage and water storage layer; lay a geotextile; on the geotextile, lay fine gravel and gravel soil, add bentonite to form a water and fertilizer retention layer; then cover it with a certain thickness of imported soil according to the land reclamation standard requirements. The method of the present invention uses local materials, is convenient to construct, has low cost, and is suitable for large-scale promotion and application; it is particularly suitable for use in the process of reclamation of abandoned limestone quarries in mountainous and hilly areas in the semi-arid North China.

[0033] In order to enable those skilled in the art to more clearly understand the technical solution of the present application, the technical solution of the present application will be described in detail below in conjunction with specific examples. If the specific experimental conditions are not specified in the examples, they are usually in accordance with conventional conditions or the conditions recommended by the reagent company; the reagents, consumables, etc. used in the following examples, unless otherwise specified, can be obtained through commercial channels.

[0034] Example 1: Construction of profile base structure for reclaiming farmland from abandoned quarry

[0035] In an abandoned quarry that is to be reclaimed as farmland in the limestone mining area of ​​the hilly region of North China, a basic structure of the abandoned quarry reclaimed farmland profile is created. The specific process is as follows:

[0036] (1) The abandoned quarry's subgrade is compacted and leveled with a roller, with the ground elevation difference not exceeding 5 cm and a compaction degree of more than 90%. Then, gravel with a diameter of 10-60 mm discarded from the quarry is used to backfill and construct a gravel drainage layer. The thickness of the gravel drainage layer is 20 cm. The slope of the gravel drainage layer is 0.3%, and it tends to the direction of the drainage ditch inside the reclaimed field. The average elevation of the drainage ditch bottom should be 10-15 cm lower than the elevation of the gravel drainage layer, which can not only store some precipitation resources but also facilitate drainage.

[0037] (2) Lay non-woven geotextile on the gravel drainage layer. The specification of non-woven geotextile is 200g / m 2 ; The overlap width is greater than or equal to 10cm, forming a soil retention layer.

[0038] (3) Laying lithospermum and calcium-based bentonite on the soil-retaining layer to construct a water-holding layer with a thickness of 10 cm; the particle size of lithospermum is 0.16-4.75 mm; the particle size of calcium-based bentonite is 0.5-1 mm; the amount of calcium-based bentonite accounts for 1.5% of the volume of lithospermum.

[0039] The above method is used to create the base structure of the abandoned quarry reclaimed farmland profile. Backfill soil is placed on the water-holding layer to form a 50cm thick soil layer. The structural diagram is shown in the figure. Figure 1 shown.

[0040] Example 2: Investigation of the effect of the profile base structure of the abandoned quarry to reclaim farmland

[0041] use Figure 2 The experimental device for simulating soil column leaching test is used to investigate the effect of the profile base structure of the abandoned quarry reclaimed farmland of the present invention, as follows:

[0042] 1. Test method:

[0043] The experimental device uses a PVC pipe with a diameter of 30 cm and a height of 90 cm, with the bottom sealed and a leaching solution collection pipe laid; the design is as follows:

[0044] Treatment 1: The PVC pipe was filled with a 30 cm gravel layer and a 50 cm imported soil layer from bottom to top.

[0045] Treatment 2: The PVC pipe was filled with a 20 cm gravel layer, a 10 cm stone layer and a 50 cm imported soil layer from bottom to top.

[0046] Treatment 3: The PVC pipe was filled with a 20 cm gravel layer, a non-woven geotextile and a 50 cm imported soil layer from bottom to top.

[0047] Treatment 4: The PVC pipe was filled with a 20 cm gravel layer, a calcium-based bentonite layer and a 50 cm guest soil layer from bottom to top. The amount of calcium-based bentonite added was 1.5% of the volume of the 10 cm gravel layer.

[0048] Treatment 5: The PVC pipe was filled with a 20 cm gravel layer, a non-woven geotextile, a 10 cm stone layer and a 50 cm imported soil layer from bottom to top.

[0049] Treatment 6: The PVC pipe was filled with a 20 cm gravel layer, a non-woven geotextile, a water-holding layer and a 50 cm imported soil layer from bottom to top; the water-holding layer consisted of a 10 cm gravel layer + calcium-based bentonite; the amount of calcium-based bentonite added was 1.0% of the volume of the 10 cm gravel layer.

[0050] Treatment 7: The PVC pipe was filled with a 20 cm gravel layer, a non-woven geotextile, a water-holding layer and a 50 cm imported soil layer from bottom to top; the water-holding layer consisted of a 10 cm gravel layer + calcium-based bentonite; the amount of calcium-based bentonite added was 1.5% of the volume of the 10 cm gravel layer.

[0051] Treatment 8: The PVC pipe was filled with a 20 cm gravel layer, a non-woven geotextile, a water-holding layer and a 50 cm soil layer from bottom to top; the water-holding layer consisted of a 10 cm gravel layer + calcium-based bentonite; the amount of calcium-based bentonite added was 2.0% of the volume of the 10 cm gravel layer.

[0052] In the above treatments, the gravel layers involved are composed of gravels with a diameter of 10-60 mm, and there is no significant difference in the average particle size of gravels treated by different methods; the average particle size of the stone layer involved is 0.16-4.75 mm, and there is no significant difference in the average particle size of the stone treated by different methods; the specifications of the non-woven geotextiles involved are all 200g / m 2 The particle size of the calcium-based bentonite involved was 0.5-1mm, and there was no significant difference in the average particle size of the calcium-based bentonite with different treatments; the imported soil all met the requirements of the land reclamation quality control standards, and the imported soil with different treatments was taken from the same location, and there was no significant difference in soil composition.

[0053] First, saturate the soil column with water until treatment 1 begins to drain. Drain the water and let it stand for 30 days to balance, so as to approach the natural situation. Then apply 3g of urea to the guest soil layer, which is about 28kg / mu of urea, and mix it evenly with the 15cm surface soil. Use tap water to simulate irrigation and rainfall tests, and the amount of water added is 8.5L (equivalent to 120mm irrigation depth). Collect all the discharged leaching solutions, count the total amount of leaching solutions for each treatment, and analyze nutrient loss (TN) and suspended solids (SS, mainly soil particles leached from the overlying soil layer).

[0054] The total nitrogen (TN) in the leaching solution was determined by the alkaline potassium persulfate digestion ultraviolet spectrophotometry method (HJ636-2012).

[0055] The suspended solids (SS) in the leaching solution were determined using the Gravimetric Method for Determination of Suspended Solids in Water Quality (GB 11901-1989).

[0056] 2. Test results:

[0057] The test results are shown in Table 1.

[0058] Table 1: Results of simulated soil column leaching test

[0059]

[0060] From the test results in Table 1, it can be seen that after the "non-woven fabric + gypsum layer + bentonite" design structural profile is adopted, the average water loss, TN loss, and soil particle loss are greatly reduced compared with the traditional construction method. The designed "non-woven fabric + gypsum layer + bentonite" base construction mode has played an obvious role in supporting water and fertilizer, with good water retention and less nutrient leaching loss. Considering the economic efficiency of bentonite dosage and the difference between the effects, it is recommended to add 1% bentonite to the gypsum layer to achieve a good effect.

[0061] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A profile base structure for reclaiming farmland from an abandoned quarry, characterized in that: From bottom to top, it includes: gravel drainage layer, soil retention layer and water holding layer; The gravel drainage layer is composed of gravels with a diameter of 10-60 mm, and the thickness of the gravel drainage layer is 20 cm; The soil retention layer is composed of non-woven geotextile; The water-holding layer is composed of pyrophyllite and calcium-based bentonite, and the content of calcium-based bentonite is 1.5% of the volume of pyrophyllite; the thickness of the water-holding layer is 10 cm; the particle size of the pyrophyllite is 0.16-4.75 mm; the particle size of the calcium-based bentonite is 0.5-1 mm; The slope of the gravel drainage layer is 0.3%, tending towards the drainage ditch inside the reclaimed field.

2. The section base structure for reclaiming farmland from an abandoned quarry according to claim 1 is characterized in that: The specification of the non-woven geotextile is 200g / m 2 ; Overlap width is greater than or equal to 10cm.

3. The method for constructing a profile base structure for reclaiming farmland from an abandoned quarry according to claim 1 or 2, characterized in that: The following steps are involved: (1) Level the base of the abandoned quarry site to be reclaimed as farmland, cut the high and fill the low, and then use the quarry waste gravel to backfill and construct a gravel drainage layer; (2) Lay non-woven geotextile on the gravel drainage layer to form a soil retention layer; (3) Lay limestone and calcium-based bentonite on the soil-retaining layer to construct a water-retaining layer; In step (1), a roller is used to compact and level the ground, the ground height difference does not exceed 5 cm, and the compaction degree is above 90%; In step (2), when laying the non-woven geotextile, the overlap width is greater than or equal to 10 cm.

4. Application of the profile base structure for reclaimed farmland from an abandoned quarry as claimed in claim 1 or 2 in improving the rainfall storage capacity of reclaimed farmland from an abandoned quarry.