A prestressed tensioning jack

By integrating anchors into the prestressed tensioning jack and adopting a threaded connection and telescopic rod structure, the problem of cumbersome prestressed tensioning work processes in the existing technology is solved, and the operation time is shortened and the work efficiency is improved.

CN116255013BActive Publication Date: 2024-10-29CHINA CONSTR SECOND ENG BUREAU LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202211515820.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-25
Publication Date
2024-10-29
Estimated Expiration
2042-11-25

AI Technical Summary

Technical Problem

The workflow of existing prestressed tensioning jacks is cumbersome and the operation takes a long time, resulting in low efficiency of prestressed tensioning work.

Method used

A prestressed tensioning jack is designed, including a sleeve cylinder and a sleeve piston. The first anchor and the second anchor are integrated on the sleeve cylinder. The steel strand passes through the channel through the through hole of the first anchor. The through-hole export of the second anchor simplifies the installation and disassembly process, and adopts threaded connection and telescopic rod structure to improve efficiency.

Benefits of technology

The prestressed tensioning operation process is simplified, the operation time is shortened, work efficiency is improved, and the overall time of prestressed tensioning construction is reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116255013B_ABST
    Figure CN116255013B_ABST
Patent Text Reader

Abstract

The present invention discloses a prestressed tensioning jack, comprising a sleeve cylinder, a sleeve piston, a first anchor and a second anchor. The sleeve cylinder and the sleeve piston are hollow, and the sleeve cylinder is provided with an annular inner cavity, whose opening is located at the rear end surface of the sleeve cylinder; the front end of the sleeve piston is movably sleeved in the annular inner cavity, and the rear end can extend out of the opening, and the sleeve cylinder is connected with the sleeve piston to form a through passage; the first anchor is provided with a plurality of first through holes, and is fixedly installed at the front end of the sleeve cylinder, and the second anchor is provided with a plurality of second through holes, and is movably installed at the rear end of the sleeve piston along the axial direction of the sleeve cylinder; the steel strand passes through the first through hole and is led out from the second through hole via the through passage. The present invention integrates the first anchor and the second anchor on the sleeve cylinder, and when installing or disassembling the prestressed jack, there is no need to install or disassemble the first anchor, the sleeve cylinder and the second anchor one by one, which simplifies the work process of prestressed tensioning, shortens the operation time, and improves work efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering machinery, in particular to a prestressed tensioning jack. Background Art

[0002] Nuclear power plants, natural gas receiving stations, airport terminals, roads and bridges, large-span factory buildings and other construction projects all use prestressed tensioning construction technology, and generally use prestressed tensioning jacks and other devices to carry out prestressing work.

[0003] The workflow of using the existing prestressed tensioning jack is generally to first set an anchor on multiple steel strands, then make the steel strands pass through the prestressed tensioning jack and extend out of the rear end of the prestressed tensioning jack, then set another anchor, insert a conical wedge into the through hole of the anchor, and then start the cylinder to drive the prestressed tensioning jack for tensioning. The preparatory work and the disassembly and assembly process after the prestressing tensioning are cumbersome, the operation is time-consuming, and the prestressing tensioning work efficiency is low. Summary of the invention

[0004] The main purpose of the present invention is to provide a prestressed tensioning jack, which aims to provide a prestressed tensioning jack that simplifies the prestressed tensioning operation process, shortens the operation time, and improves the prestressed tensioning work efficiency.

[0005] To achieve the above object, the present invention provides a prestressed tensioning jack, comprising:

[0006] The sleeve oil cylinder is hollow, an annular inner cavity is provided between the inner wall and the outer wall of the sleeve oil cylinder, the annular inner cavity is provided with an opening, and the opening is located at the rear end surface of the sleeve oil cylinder;

[0007] The sleeve piston is hollow, with its front end movably sleeved in the annular inner cavity along the axial direction of the sleeve oil cylinder, and its rear end extending out of the opening, wherein the sleeve oil cylinder is connected to the sleeve piston to form a through passage;

[0008] A first anchor is provided with a plurality of first through holes, and the first anchor is fixedly installed at the front end of the sleeve cylinder; and

[0009] A second anchor having a plurality of second through holes extending therethrough, wherein the second anchor is movably mounted on the rear end of the sleeve piston along the axial direction of the sleeve cylinder;

[0010] The steel strand passes through the first through hole and is led out from the second through hole via the through channel.

[0011] Preferably, a first matching portion is provided on the first anchor, and a second matching portion is provided on the sleeve cylinder, and the first matching portion matches with the second matching portion to fix the first anchor to the front end of the sleeve cylinder.

[0012] Preferably, the first anchor is provided with an external threaded portion, the front end of the sleeve oil cylinder is provided with an internal threaded portion, and the external threaded portion is threadably matched with the internal threaded portion;

[0013] Wherein, the first matching portion includes an external thread portion, and the second matching portion includes an internal thread portion.

[0014] Preferably, an outer end of the first anchor close to the sleeve cylinder is provided with an external thread;

[0015] A limiting step is partially recessed on the front end surface of the sleeve oil cylinder, and an inner side wall of the limiting step is provided with an internal thread, and the internal thread cooperates with the external thread to fixedly connect the first anchor and the sleeve oil cylinder;

[0016] Wherein, the external threaded portion includes the external thread, and the internal threaded portion includes the internal thread.

[0017] Preferably, the prestressed tensioning jack also includes a movable connection structure, which is formed with two connecting parts, and the distance between the two connecting parts is adjustable, one of the connecting parts is connected to the rear end of the sleeve piston, and the other connecting part is connected to the second anchor, so that the second anchor can be movably installed at the rear end of the sleeve piston along the axial direction of the sleeve cylinder.

[0018] Preferably, the movable connection structure includes a plurality of telescopic rods, each of which has two ends to form two connecting parts, wherein one of the ends is connected to the rear end of the sleeve piston, and the other end is connected to the second anchor.

[0019] Preferably, the prestressed tensioning jack further comprises a guide structure, wherein the guide structure is arranged in the inner hole of the sleeve cylinder, and the guide structure limits the steel strand from moving along the axial direction of the sleeve cylinder.

[0020] Preferably, the guide structure comprises a plurality of guide tubes, and the plurality of guide tubes are arranged in the inner hole of the sleeve cylinder and along the axial direction of the sleeve cylinder;

[0021] Among them, the plurality of first through holes, the plurality of guide tubes and the plurality of second through holes correspond one to one.

[0022] Preferably, at least two groups of support columns are provided at the bottom of the outer side wall of the sleeve cylinder along the axial direction of the sleeve cylinder, and each column of the support column group includes at least two support columns.

[0023] Preferably, the outer side wall of the sleeve cylinder is provided with a plurality of lifting ears.

[0024] The technical solution of the present invention provides a prestressed tensioning jack, including a sleeve oil cylinder and a sleeve piston, the sleeve oil cylinder and the sleeve piston are hollow, the sleeve oil cylinder defines an annular inner cavity, the annular inner cavity is provided with an opening, and is located at the rear end surface of the sleeve oil cylinder, the front end of the sleeve piston is movably sleeved in the annular inner cavity along the axial direction of the sleeve oil cylinder, and the rear end can extend out of the opening, wherein the sleeve oil cylinder is connected with the sleeve piston to form a through channel, a first anchor is provided at the front end of the sleeve oil cylinder, and a second anchor is provided at the rear end of the sleeve piston, and the second anchor can move along the axial direction of the sleeve oil cylinder, and a plurality of through holes are penetrated on the first anchor and the second anchor, and the steel strand first passes through the first through hole of the first anchor, and is led out from the second through hole of the second anchor via the through channel. The present invention integrates the first anchor and the second anchor on the sleeve oil cylinder, and when installing or disassembling the prestressed jack, it is not necessary to install or disassemble the first anchor, the sleeve oil cylinder and the second anchor one by one, thereby simplifying the workflow of prestressed tensioning, shortening the operation time, and improving the work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on the structures shown in these drawings without paying creative work.

[0026] Figure 1 This is a schematic diagram of the overall structure of an embodiment of the prestressed tensioning jack provided by the present invention;

[0027] Figure 2 for Figure 1 Schematic diagram of the cross-sectional structure of the middle sleeve oil cylinder;

[0028] Figure 3 for Figure 1 Schematic diagram of the cross-sectional structure of the first anchor.

[0029] Description of Figure Numbers:

[0030] Label name Label name 1000 Prestressed tension jack 31 First through hole 1 Sleeve Cylinder 4 Second anchor 11 Lifting lugs 5 Telescopic rod 12 Support column 6 Steel strand 2 Sleeve piston 7 Guide tube 3 First anchor

[0031] The realization of the purpose, functional features and advantages of the present invention will be further explained in conjunction with embodiments and with reference to the accompanying drawings. DETAILED DESCRIPTION

[0032] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0033] It should be noted that all directional indications in the embodiments of the present invention (such as up, down, left, right, front, back, etc.) are only used to explain the relative position relationship, movement status, etc. between the components under a certain specific posture (as shown in the accompanying drawings). If the specific posture changes, the directional indication will also change accordingly.

[0034] In addition, the descriptions of "first", "second", etc. in the present invention are only used for descriptive purposes and cannot be understood as indicating or implying their relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include at least one of the features. In addition, the technical solutions between the various embodiments can be combined with each other, but they must be based on the ability of ordinary technicians in the field to implement them. When the combination of technical solutions is contradictory or cannot be implemented, it should be deemed that such a combination of technical solutions does not exist and is not within the scope of protection required by the present invention.

[0035] Nuclear power plants, natural gas receiving stations, airport terminals, roads and bridges, large-span factory buildings and other construction projects all use prestressed tensioning construction technology, and generally use prestressed tensioning jacks and other devices to carry out prestressing work.

[0036] The workflow of using the existing prestressed tensioning jack is generally to first set an anchor on multiple steel strands, then make the steel strands pass through the prestressed tensioning jack and extend out of the rear end of the prestressed tensioning jack, then set another anchor, insert a conical wedge into the through hole of the anchor, and then start the cylinder to drive the prestressed tensioning jack for tensioning. The preparatory work and the disassembly and assembly process after the prestressing tensioning are cumbersome, the operation is time-consuming, and the prestressing tensioning work efficiency is low.

[0037] In order to solve the above problems, the present invention proposes a prestressed tensioning jack, which aims to provide a prestressed tensioning jack that simplifies the prestressed tensioning operation process, shortens the operation time, and improves the prestressed tensioning work efficiency, wherein: Figures 1 to 3 The present invention is a schematic structural diagram of an embodiment of a prestressed jack provided by the present invention.

[0038] Please refer to Figures 1 to 3The present invention proposes a prestressed tensioning jack 1000, comprising a sleeve cylinder 1, a sleeve piston 2, a first anchor 3 and a second anchor 4, wherein the sleeve cylinder 1 is hollow, an annular inner cavity is provided between the inner wall and the outer wall of the sleeve cylinder 1, the annular inner cavity is provided with an opening, and the opening is located at the rear end face of the sleeve cylinder 1; the sleeve piston 2 is hollow, the front end is movably sleeved in the annular inner cavity along the axial direction of the sleeve cylinder 1, and the rear end can extend out of the opening, wherein the sleeve cylinder 1 is connected with the sleeve piston 2 to form a through passage; the first anchor 3 is penetrated by a plurality of first through holes 31, the first anchor 3 is fixedly installed at the front end of the sleeve cylinder 1, the second anchor 4 is penetrated by a plurality of second through holes, the second anchor 4 is movably installed at the rear end of the sleeve piston 2 along the axial direction of the sleeve cylinder 1; wherein the steel strand 6 passes through the first through hole 31 and is led out from the second through hole via the through passage.

[0039] The technical solution of the present invention provides a prestressed tensioning jack 1000, including the sleeve cylinder 1 and the sleeve piston 2, the sleeve cylinder 1 is hollow, and the annular inner cavity is defined between its inner wall and outer wall, the annular inner cavity is provided with an opening, and is located at the rear end surface of the sleeve cylinder 1, the sleeve piston 2 is hollow, and its front end is movably sleeved in the annular inner cavity along the axial direction of the sleeve cylinder 1, and the rear end can extend out of the opening, wherein the sleeve cylinder 1 is communicated with the sleeve piston 2 to form the through channel, the first anchor 3 is provided at the front end of the sleeve cylinder 1, and the second anchor 4 is provided at the rear end of the sleeve piston 2, the second anchor 4 can move along the axial direction of the sleeve cylinder 1, and a plurality of through holes are penetrated on the first anchor 3 and the second anchor 4, the steel strand 6 first passes through the first through hole 31 of the first anchor 3, and is led out from the second through hole of the second anchor 4 via the through channel. The present invention integrates the first anchor 3 and the second anchor 4 on the sleeve cylinder 1. When installing or disassembling the prestressed tensioning jack 1000, there is no need to install or disassemble the first anchor 3, the sleeve cylinder 1 and the second anchor 4 one by one, thereby simplifying the prestressed tensioning workflow, shortening the operation time and improving work efficiency.

[0040] It should be noted that the method of connecting the first anchor 3 and the front end of the sleeve cylinder 1 can be any connection method that can fix the two, which can be welding, or a fixed connection can be achieved through two matching parts, and the present invention does not impose specific restrictions on this. Compared with welding, the method of connecting the first anchor 3 and the sleeve cylinder 1 through two matching parts allows various types of the first anchor 3 and various types of the sleeve cylinder 1 to be freely combined, and the scope of application is wider. Therefore, in the present invention, it is preferred to use a method of connecting the two with two matching parts to achieve a fixed connection between the first anchor 3 and the front end of the sleeve cylinder 1.

[0041] Specifically, in order to achieve a fixed connection between the first anchor 3 and the front end of the sleeve cylinder 1, a first matching portion is provided on the first anchor 3, and a second matching portion is provided on the sleeve cylinder 1. The first matching portion cooperates with the second matching portion to fix the first anchor 3 to the front end of the sleeve cylinder 1.

[0042] It should be noted that the first matching part and the second matching part can be any two connection structures that can achieve a fixed connection relationship, and can be a threaded connection structure, a slot, or a buckle structure, and the present invention does not impose specific restrictions on this. Compared with the slot and buckle connection structure, the fixed connection relationship formed by the threaded connection structure has higher stability, and the processing of the first anchor 3 and the front end of the sleeve cylinder 1 is also simpler. Therefore, in the present invention, a threaded connection structure is preferably used as the first matching part and the second matching part.

[0043] Specifically, the first matching portion includes an external threaded portion, which is arranged on the first anchor 3, and the second matching portion includes an internal threaded portion, which is arranged at the front end of the sleeve cylinder 1, and the external threaded portion is threadedly matched with the internal threaded portion so that the first anchor 3 is fixedly installed on the front end of the sleeve cylinder 1.

[0044] It should be noted that the positional relationship between the first anchor 3 and the front end of the sleeve cylinder 1 can be any positional relationship that enables the steel strand 6 to pass through the first through hole 31 and enter the through channel. The first anchor 3 can be embedded in the front end of the sleeve cylinder 1, or can be arranged on the front end surface of the sleeve cylinder 1. The present invention does not impose specific restrictions on this. Compared with the latter, the positional relationship of the former makes the connection between the first anchor 3 and the sleeve cylinder 1 less susceptible to external interference, and the force-bearing structure is more stable. Therefore. In the present invention, it is preferred to embed the first anchor 3 into the front end of the sleeve cylinder 1.

[0045] Specifically, Figure 1As shown, an outer end of the first anchor 3 near the sleeve cylinder 1 is provided with an external thread as the external thread portion, and a limiting step is partially recessed on the front end surface of the sleeve cylinder 1. An internal thread is provided on the inner side wall of the limiting step as the internal thread portion. The internal thread cooperates with the external thread, so that the first anchor 3 is embedded in the front end of the sleeve cylinder 1 to fix the first anchor 3 and the sleeve cylinder 1. The threaded structure after installation is located in the limiting step, which is not easily affected by impact to cause deformation of the internal thread and the external thread, thereby preventing the difficulty of installing or removing the first anchor 3 and improving the stability of the force-bearing structure.

[0046] In order to movably install the second anchor 4 on the end of the sleeve piston 2, in one embodiment of the present invention, the prestressed tensioning jack 1000 also includes a movable connection structure, which is formed with two connecting parts, and the distance between the two connecting parts is adjustable, one of the connecting parts is connected to the rear end of the sleeve piston 2, and the other connecting part is connected to the second anchor 4, so as to movably install the second anchor 4 on the rear end of the sleeve piston 2 along the axial direction of the sleeve cylinder 1.

[0047] It should be noted that the movable connection structure can be any structure that enables the second anchor 4 to move relative to the rear end of the sleeve piston 2, and can be a hydraulic rod or a telescopic rod, and the present invention does not impose specific restrictions on this. Compared with the hydraulic rod, the telescopic rod does not need to be connected to the oil pressure pipeline or the air pressure pipeline, has a simpler structure, does not consume energy, and has a lower cost. Therefore, in the present invention, the telescopic rod is preferably used as the movable connection structure.

[0048] Specifically, Figure 1As shown, the movable connection structure includes a plurality of telescopic rods 5, each of which has two ends to form two connecting parts, one of which is connected to the rear end of the sleeve piston 2, and the other is connected to the second anchor 4. After the prestressed tensioning jack 1000 is combined with the steel strand 6, the second anchor 4 is pressed against the rear end of the sleeve piston 2, and then the prestressed tensioning jack 1000 starts to work, the sleeve piston 2 moves outward and pushes the second anchor 4 away from the sleeve cylinder 1, during this process, the telescopic rod 5 does not extend or retract; when the prestressed tensioning construction is completed, the sleeve piston 2 contracts toward the sleeve cylinder 1, and the second anchor 4 remains in position due to the tight connection between the conical wedge block and the steel strand 6, during this process, the telescopic rod 5 extends; after the sleeve piston 2 returns to its original position, it pushes the second anchor 4 in the direction toward the sleeve cylinder 1 to separate the second anchor 4 from the conical wedge block, so that the prestressed tensioning jack 1000 and the steel strand 6 are out of coordination and do not interact with each other, and then the prestressed tensioning jack 1000 is removed to complete the prestressed tensioning construction operation. The first anchor 3 and the second anchor 4 are integrated on the sleeve cylinder 1. After the construction is completed, there is no need to remove the second anchor 4, the sleeve cylinder 1 and the first anchor 3 in sequence, which simplifies the disassembly process. Generally, there are many places in a project that require prestressing. The prestressing tensioning jack 1000 in the present invention shortens the construction time of prestressing and improves the work efficiency of the entire project.

[0049] It can be understood that in order to prevent the multiple steel strands 6 from being entangled in the through channel, in one embodiment of the present invention, the prestressed tensioning jack 1000 also includes a guide structure, and the guide structure is arranged in the inner hole of the sleeve cylinder 1. The guide structure limits the movement of the steel strands 6 along the axial direction of the sleeve cylinder 1 to avoid the multiple steel strands 6 from being entangled, so that each of the steel strands 6 can extend out from the corresponding second through hole after entering the through channel from the first through hole 31, without the need for manual guidance, which is convenient and fast, and improves efficiency.

[0050] It should be noted that the guide structure can be any structure that enables the steel strand 6 to move along the axial direction of the sleeve cylinder 1, and can be a guide rail or a pipe, and the present invention does not impose any specific restrictions on this. Compared with the guide rail, the pipe is more consistent with the shape of the steel strand and is less likely to be blocked, so the pipe is preferably used as the guide structure in the present invention.

[0051] Specifically, Figure 2As shown, the guide structure includes a plurality of guide tubes 7, and the plurality of guide tubes 7 are arranged in the inner hole of the sleeve cylinder 1 and along the axial direction of the sleeve cylinder 1; wherein, the plurality of first through holes 31, the plurality of guide tubes 7 and the plurality of second through holes correspond one to one, so that after each of the steel strands 6 enters the guide tube 7 from the first through hole 31, it can extend out from the corresponding second through hole, without manual guidance, which is convenient and fast, and improves efficiency.

[0052] like Figure 2 As shown, in order to facilitate the prestressing of the steel strands 6 at a lower position, in one embodiment of the present invention, at least two groups of support column groups are provided at the bottom of the outer wall of the sleeve cylinder 1 along the axial direction of the sleeve cylinder 1, and each column of the support column group includes at least two support columns 12. When the steel strands 6 at a lower position are prestressed, there is no need for workers to support them, so that the prestressing tensioning jack 1000 can be stably placed on a plane, thereby reducing the labor of workers and reducing staffing.

[0053] like Figure 2 As shown, it can be understood that in order to facilitate the lifting of the prestressed tensioning jack 1000, in one embodiment of the present invention, the outer wall of the sleeve cylinder 1 is provided with a plurality of lifting ears 11. In order to adapt to the lifting steel cable, the inner hole diameter of the lifting ear 11 is enlarged to more than four centimeters to facilitate the passage of the lifting steel cable.

[0054] The above description is only a preferred embodiment of the present invention, and does not limit the patent scope of the present invention. All equivalent structural changes made by using the contents of the present invention specification and drawings under the inventive concept of the present invention, or directly / indirectly applied in other related technical fields are included in the patent protection scope of the present invention.

Claims

1. A prestressed tensioning jack, characterized in that: include: The sleeve oil cylinder is hollow, an annular inner cavity is provided between the inner wall and the outer wall of the sleeve oil cylinder, the annular inner cavity is provided with an opening, and the opening is located at the rear end surface of the sleeve oil cylinder; The sleeve piston is hollow, with its front end movably sleeved in the annular inner cavity along the axial direction of the sleeve oil cylinder, and its rear end extending out of the opening, wherein the sleeve oil cylinder is connected to the sleeve piston to form a through passage; A first anchor is provided with a plurality of first through holes, and the first anchor is fixedly installed at the front end of the sleeve cylinder; and A second anchor having a plurality of second through holes extending therethrough, wherein the second anchor is movably mounted on the rear end of the sleeve piston along the axial direction of the sleeve cylinder; Wherein, the steel strand passes through the first through hole and is led out from the second through hole via the through passage; The first anchor is provided with a first matching portion, and the sleeve oil cylinder is provided with a second matching portion, and the first matching portion matches with the second matching portion to fix the first anchor to the front end of the sleeve oil cylinder; The first anchor is provided with an external threaded portion, the front end of the sleeve oil cylinder is provided with an internal threaded portion, and the external threaded portion is threadably matched with the internal threaded portion; Wherein, the first matching portion includes an external thread portion, and the second matching portion includes an internal thread portion; An outer end of the first anchor close to the sleeve cylinder is provided with an external thread; A limiting step is partially recessed on the front end surface of the sleeve oil cylinder, and an inner side wall of the limiting step is provided with an internal thread, and the internal thread cooperates with the external thread to fixedly connect the first anchor and the sleeve oil cylinder; Wherein, the external threaded portion includes the external thread, and the internal threaded portion includes the internal thread; The prestressed tensioning jack also includes a movable connection structure, which is formed with two connection parts, and the distance between the two connection parts is adjustable, one of the connection parts is connected to the rear end of the sleeve piston, and the other connection part is connected to the second anchor, so that the second anchor is movably installed on the rear end of the sleeve piston along the axial direction of the sleeve cylinder; The movable connection structure includes a plurality of telescopic rods, each of which has two ends to form two connecting parts, one of which is connected to the rear end of the sleeve piston, and the other is connected to the second anchor; When the prestressing construction is completed, the sleeve piston contracts toward the sleeve cylinder, and the second anchor maintains its position unchanged due to the tight connection between the conical wedge block and the steel strand, and the telescopic rod is extended; the sleeve piston is reset and pushes the second anchor in the direction toward the sleeve cylinder to separate the second anchor from the conical wedge block.

2. The prestressed tensioning jack according to claim 1, characterized in that: The prestressed tensioning jack also includes a guide structure, which is arranged in the inner hole of the sleeve cylinder. The guide structure limits the steel strand from moving along the axial direction of the sleeve cylinder.

3. The prestressed tensioning jack according to claim 2, characterized in that: The guide structure includes a plurality of guide tubes, which are arranged in the inner hole of the sleeve cylinder and along the axial direction of the sleeve cylinder; Among them, the plurality of first through holes, the plurality of guide tubes and the plurality of second through holes correspond one to one.

4. The prestressed tensioning jack according to claim 1, characterized in that: At least two groups of support columns are provided at the bottom of the outer side wall of the sleeve cylinder along the axial direction of the sleeve cylinder, and each column of the support column group includes at least two support columns.

5. The prestressed tensioning jack according to claim 1, characterized in that: The outer side wall of the sleeve oil cylinder is provided with a plurality of lifting ears.

Citation Information

Patent Citations

  • Internal clamping type tension jack and construction method thereof

    CN104649180A