Counterweight bearing platform and counterweight bridge pier

By introducing the design of stacked ballast modules and steel cover beams into the piers, the problem that conventional auxiliary piers cannot cope with the asymmetric double-cantilever tension conditions of the main beam is solved, and stable support under compression and tension conditions is achieved. and force transmission to ensure construction safety and balance.

CN116464093BActive Publication Date: 2024-10-15ROAD & BRIDGE SOUTH CHINA ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310514145.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-31
Publication Date
2024-10-15
Estimated Expiration
2040-12-31

AI Technical Summary

Technical Problem

Conventional auxiliary piers can only solve the balance problem under compression conditions during the asymmetric double cantilever construction of the main beam, but cannot effectively solve the balance problem under tension conditions, which limits its application scope.

Method used

A counterweighted bridge pier is designed, including pile foundation, cap platform, stacked ballast module and steel cover beam. The stacked ballast module has the same size as the cap platform. By setting steel pipe columns and concrete filling on the pier body, the number of piles is increased. The weight of the foundation is used to resist the tensile force, and the force balance is ensured by the anchoring device of the steel cap beam.

Benefits of technology

This design provides support when the pier is under pressure to prevent settlement; it adds weight when under tension to prevent the pile foundation from being stretched, ensuring the stability of the bridge pier, and transmits tension through the anchoring device of the steel cap beam to ensure the stability of the main beam and the bridge pier. connection to achieve balance and construction safety in asymmetric double cantilever construction.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116464093B_ABST
    Figure CN116464093B_ABST
Patent Text Reader

Abstract

The present application relates to a counterweighted pedestal, comprising a pedestal body, a stacked ballast module arranged on the pedestal body, and a connecting structure penetrating the pedestal body and a first steel pipe column penetrating the stacked ballast module; the connecting structure is coaxially connected to the first steel pipe column; the first steel pipe column is filled with concrete. The counterweighted pedestal of the present application is arranged between the pile foundation and the pier body. When the pier body is under pressure, the counterweighted pedestal itself can provide a certain supporting force. When the pier body is under tension, the added weight of the counterweighted pedestal enhances the tensile resistance of the pile foundation.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] This application is a divisional application of the patent application "Counterweight Bridge Pier". The application date of the original application is 2020-12-31, the application number is 2020116296769, and the publication number is CN 112695622A. Technical Field

[0002] The present invention relates to the technical field of bridges, and in particular to a counterweight type bearing platform and a counterweight type bridge pier. Background Art

[0003] At present, in the construction process of the main beam of a large bridge, auxiliary piers are usually required to support the main beam segments installed first. The conventional auxiliary pier structure includes pile foundation, pedestal, pier body and cap beam from bottom to top. The structure is relatively simple and can only use the pile foundation to resist compression, which makes the conventional auxiliary piers have a single function and foundation. However, during the construction of the asymmetric double cantilever of the main beam, depending on different working conditions, the side span will be under tension or compression. The conventional auxiliary piers can only solve the balance of the asymmetric double cantilever of the main beam under compression conditions, but cannot solve the tension condition of the side span, which limits the application of the auxiliary piers. More structures need to be deployed on the construction site to solve the problem of the balance of the asymmetric double cantilever of the main beam under tension conditions. Summary of the invention

[0004] In order to overcome the above technical problems, especially the conventional auxiliary pier can only solve the problem of the balance of the asymmetric double cantilever of the main beam under compression conditions, the following technical solutions are proposed:

[0005] The counterweight-type bridge pier provided in the embodiment of the present application includes: a pile foundation, a pedestal arranged on the pile foundation, a load-bearing and ballast module arranged on the pedestal, a pier body arranged on the load-bearing and ballast module, and a steel cap beam anchored on the pier body, wherein the load-bearing and ballast module is consistent in size with the pedestal.

[0006] Optionally, the pier body is composed of four first steel pipe columns.

[0007] Optionally, the anchoring connection device in the cap is provided with a through hole through which the first steel pipe column passes on the load-bearing weight module, the first steel pipe column passes through the through hole and is connected to one end of the connection device, and the other end of the connection device is connected to the steel casing.

[0008] Optionally, the first steel pipe column is filled with concrete.

[0009] Optionally, a second steel pipe column is further provided between the pier body and the steel cap beam, and the second steel pipe column is connected to the first steel pipe column.

[0010] Optionally, the second steel tube column is sleeved in the first steel tube column, and the ratio of the length of the second steel tube column sleeved in the first steel tube column to the length of the second steel tube column exposed between the steel cap beam and the first steel tube column is 1:5-2:5.

[0011] Optionally, diagonal braces are respectively provided between the first steel tube column and the second steel tube column.

[0012] Optionally, an anchoring device for anchoring the main beam of the bridge is provided on the steel cap beam.

[0013] Optionally, an annular stiffening rib is provided on the first steel pipe column.

[0014] Optionally, the pile foundation includes a cast-in-place pile and a steel casing sleeved on the cast-in-place pile.

[0015] Optionally, the ratio of the length of the steel casing sleeved on the cast-in-place pile to the total length of the steel casing is 23:63-5:7.

[0016] Compared with the prior art, the present invention has the following beneficial effects:

[0017] The counterweight bridge pier provided in the embodiment of the present application includes: a pile foundation, a cap disposed on the pile foundation, a heap load and ballast module disposed on the cap, a pier body disposed on the heap load and ballast module, and a steel cap beam anchored on the pier body, wherein the heap load and ballast module has the same size as the cap. The heap load and ballast module is disposed between the cap and the pier body. When the counterweight bridge pier is under pressure, the pile foundation can provide support for the bridge main beam, and the pile foundation will not sink. When the counterweight bridge pier is under tension, the heap load and ballast module increases the weight of the pile foundation, thereby preventing the pile foundation from being under tension under the action of the pier superstructure. The entire pier can withstand the tension generated by the unbalanced force on the pier, and can further ensure the stability of the pile foundation. The steel cap beam is anchored on the pier to ensure that when the pier is under tension, the tension can be continuously and stably transmitted to the pier and the pile foundation is not affected by the tension.

[0018] The counterweight bridge pier provided in the embodiment of the present application has a pier body installed on the said pile load and weight anchor block, and a steel cap beam hoisted on the said pier body, wherein after the said pier body is anchored and connected with the steel cap beam, it includes: installing an anchor device for anchoring the bridge main beam on the said steel cap beam. It is ensured that the forces on both sides of the main pier can be balanced during the main beam construction process, and the bridge main beam is firmly connected with the counterweight bridge pier, effectively ensuring the asymmetric double cantilever construction of the main beam, so that the force on the main beam can be continuously and stably transmitted to the counterweight bridge pier, thereby ensuring the safety of construction.

[0019] Additional aspects and advantages of the present invention will be given in part in the following description, which will become obvious from the following description, or may be learned through practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] The above and / or additional aspects and advantages of the present invention will become apparent and easily understood from the following description of the embodiments in conjunction with the accompanying drawings, in which:

[0021] Figure 1 It is a schematic structural diagram of the counterweight type bridge pier of the present invention. DETAILED DESCRIPTION

[0022] Embodiments of the present invention are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present invention, and cannot be interpreted as limiting the present invention.

[0023] Those skilled in the art will appreciate that, unless otherwise stated, the singular forms "a", "an", "said" and "the" used herein may also include plural forms. It should be further understood that the term "comprising" used in the specification of the present invention refers to the presence of features, integers, steps, operations, but does not exclude the presence or addition of one or more other features, integers, steps, operations.

[0024] It will be understood by those skilled in the art that, unless otherwise defined, all terms (including technical and scientific terms) used herein have the same meaning as generally understood by those skilled in the art in the art to which the present invention belongs. It should also be understood that terms such as those defined in general dictionaries should be understood to have meanings consistent with the meanings in the context of the prior art, and will not be interpreted with idealized or overly formal meanings unless specifically defined as herein.

[0025] The counterweight bridge pier provided in the embodiment of the present application is mainly used in the construction of asymmetric double cantilever bridges, to meet the situation that the side span main beam will apply tension or pressure to the bridge pier during the construction of the asymmetric double cantilever bridge, and balance the unbalanced force on both sides of the main pier during the construction of the asymmetric double cantilever bridge. Figure 1As shown, the counterweight bridge pier includes a pile foundation, a cap 3 arranged on the pile foundation, a ballast module 4 arranged on the cap 3, a pier body 7 arranged on the ballast module 4, and a steel cap beam 10 anchored on the pier body 7. The ballast module 4 has the same size as the cap 3. According to the construction sequence of the bridge pier, a pile hole of a preset length is first drilled at a set position so that a sufficient amount of concrete can be poured in the pile hole, and the solidified concrete can ensure the stability of the entire bridge pier. Furthermore, since the ground matrix above the pile hole is relatively soft and collapsible, the pile hole wall is prone to collapse during the concrete pouring process, and the silt is also mixed into the concrete, so that the pile foundation is prone to form a sandwich layer, and the strength is not high. Therefore, the steel casing 2 is lowered along the inner wall of the pile hole to the designed position, and then concrete is poured into the pile hole along the steel casing 2. After the concrete solidifies, a bored pile 1 is formed. The bored pile 1 and the steel casing 2 together form a pile foundation, wherein the length of the steel casing 2 sleeved on the bored pile 1 and the total length of the steel casing 2 are in the ratio of 23:63-5:7. Preferably, the length of the steel casing 2 sleeved on the bored pile 1 and the total length of the steel casing 2 are in the ratio of 3:10. The steel casing 2 isolates the silt from the concrete of the cast bored pile 1, and the silt will not sink into the bored pile 1, thereby ensuring the integrity of the pile hole, so that the formed pile foundation has just the right stability and high strength, while protecting the pile hole, and the silt will not collapse. After the pile foundation is formed, the cap 3, the stacked load and weight module 4, the pier body 7, and the steel cap beam 10 are installed in sequence.

[0026] In this application, if Figure 1 As shown, the pile load and ballast module 4 is arranged between the pier 3 and the pier body 7. When the counterweight pier is under pressure, the pile foundation can provide support for the bridge main beam, and the pile foundation will not sink; when the counterweight pier is under tension, the pile load and ballast module 4 increases the weight of the pile foundation, so that the pile foundation will not be under tension under the action of the pier superstructure, and the entire pier can withstand the tension generated by the unbalanced force applied to the pier, and can further ensure the stability of the pile foundation. Accordingly, in order to ensure that when the pier is under tension, the tension can be continuously and stably transmitted to the pier and the pile foundation is not affected by the tension, in the embodiment provided in the present application, the steel cap beam 10 is anchored on the pier body 7. In order to ensure that the pile load and ballast module 4 can be stably located on the pier 3, the size of the pile load and ballast module 4 is consistent with the size of the pier. For example, when the size of the pier is 7×7×3.5m, the size of the pile load and ballast module 4 is also 7×7×3.5m.

[0027] In order to ensure that the forces on both sides of the main pier can be balanced during the main beam construction, it is necessary to ensure that the main beam and the pier are firmly connected so that the forces on the main beam can be continuously and stably transmitted to the counterweight pier. Figure 1As shown, an anchoring device 11 for anchoring the main beam of the bridge is installed on the steel cap beam 10. Among them, the anchoring device 11 includes, from the steel cap beam upward, a steel pad, a concrete leveling block, and a polytetrafluoroethylene slide plate. Furthermore, in order to ensure the stability of the connection, a steel strand connecting the main beam and the steel cap beam is also included. The steel pad, the concrete leveling block, and the polytetrafluoroethylene slide plate enable both sides of the main beam to contact with the counterweight piers to ensure the linear shape of the main beam of the bridge. After the main beams on both sides of the main piers of the bridge are constructed to the preset section, a construction consolidation is formed between the main beam on one side and the counterweight pier to balance the pressure or tension on the main beam on the side where the counterweight pier is located, thereby ensuring the normal construction of the main beam.

[0028] In the embodiments provided in this application, Figure 1 As shown, the counterweight bridge pier is used in the construction of asymmetric cantilever beams. On the side where the counterweight bridge pier is located, a hanging basket is used to install the bridge main beam, because the hanging basket has a certain size. If the steel cap beam 10 is installed on the pier body 7 during the construction of the counterweight bridge pier, or the pier body 7 is built too high, it will affect the movement of the hanging basket. Therefore, in the embodiment provided in the present application, the pier body 7 is composed of four first steel pipe columns, which ensures the convenience of installing the pier body 7 while ensuring the strength of the pier body. In order to ensure that the steel cap beam 10 can be firmly connected to the pier body 7, a second steel pipe column 9 is set between the steel cap beam 10 and the pier body 7 to ensure that the height of the pier is consistent with the design height, so that it can be connected to the bridge main beam through the anchoring device and the linear shape of the bridge can be ensured. The second steel pipe column 9 and the steel cap beam 10 are pre-assembled before hoisting. After the hanging basket moves forward to the position above the counterweight pier, the pre-assembled second steel tube column 9 is hoisted together with the steel cap beam 10 above the first steel tube column, and the two are lowered together so that the second steel tube column 9 can be inserted into the first steel tube column, and the second steel tube column 9 and the first steel tube column are connected. When the counterweight pier is subjected to tension, the tension can be stably transmitted to the pier body 7 (first steel tube column) through the second steel tube column 9. The ratio of the length of the second steel tube column sleeved in the first steel tube column and the length of the second steel tube column exposed between the steel cap beam and the first steel tube column is 1:5-2:5. Preferably, the ratio of the length of the second steel tube column sleeved in the first steel tube column and the length of the second steel tube column exposed between the steel cap beam and the first steel tube column is 3:10. While meeting the height requirement of the entire pier body, the second steel tube column and the first steel tube column have a larger contact area, thereby increasing the stability of the second steel tube column 9 and the steel cap beam 10.

[0029] In the embodiments provided in this application, Figure 1As shown, in order to ensure the stability and integrity between the steel tube columns and increase the stability of the entire counterweight pier, a diagonal brace 8 and a parallel joint are respectively installed between the first steel tube column and the second steel tube column 9, and the diagonal brace 8 is made of a φ0.4m steel tube. Furthermore, a stiffening plate is also arranged between the second steel tube column 9 and the steel cap beam 10 to increase the stability and rigidity of the second steel tube column 9.

[0030] In the embodiment provided in the present application, after the first steel tube column is installed, in order to ensure the stability of the first steel tube column, concrete 5 (such as C30 concrete) is filled in the first steel tube column. In order to ensure the strength of the first steel tube column after being filled with concrete 5, the first steel tube column is not easily deformed. Before the first steel tube column is filled with concrete 5, an annular stiffening rib 6 is installed on the first steel tube column, and the thickness of the stiffening rib is 1.2 mm. The setting position of the annular stiffening rib 6 is the top position of the concrete filling. After the annular stiffening rib 6 is installed, concrete 5 is filled until the top of the concrete reaches the position of the annular stiffening rib 6 on the first steel tube column.

[0031] As before, after the pile foundation construction is completed, the cap is installed on it. The cap is prefabricated with concrete. During the construction of the counterweight bridge pier, the cap can be directly installed on the pile foundation. Figure 1 As shown, in order to ensure that the pier body 7 has good stability, the pier body 7 is directly connected to the pedestal 3. Accordingly, the loading and ballast module 4 is provided with a through hole through which the first steel pipe column can pass, wherein the loading and ballast module 4 can be a prefabricated concrete structure, steel structure, etc. During the prefabrication process of the loading and ballast module 4, the through hole is reserved on the loading and ballast module 4 according to the size of the first steel pipe column and the installation position on the pedestal, so that after the loading and ballast module 4 is installed on the pedestal 3, the first steel pipe column can pass through the through hole and be directly connected to the pedestal 3. In other embodiments, the loading and ballast module 4 can also be installed on the pedestal after the first steel pipe column is connected to the pedestal, so that the loading and ballast module 4 can better fit with the pedestal 3, and the loading and ballast module 4 can also generate a certain pulling force on the pier body 7, thereby ensuring the tensile strength and stability of the pier body 7.

[0032] like Figure 1 As shown, in order to ensure the stability of the connection between the pier body 7 and the cap 3, and the pile foundation can provide continuous and stable support to the cap 3. When the cap is prefabricated, the connection structure 11 is anchored in the cap 3, one end of the connection structure 11 is connected to the first steel pipe column, and the other end is connected to the steel casing 2, wherein the end of the connection structure 11 connected to the steel casing 2 is provided with a stiffening plate, and the end of the steel casing 2 connected to the connection structure 11 is also provided with a stiffening plate, and the stiffening plate increases the pressure-bearing stiffness and stability of the steel casing 2 and the connection structure 11, so that the steel casing 2 and the connection structure 11 are not easily deformed.

[0033] In summary, the counterweight bridge pier provided by the present application has the following beneficial effects:

[0034] The counterweight bridge pier provided in the embodiment of the present application comprises: a pile foundation, a cap disposed on the pile foundation, a heap load and ballast module disposed on the cap, a pier body disposed on the heap load and ballast module, and a steel cap beam anchored on the pier body, wherein the heap load and ballast module has the same size as the cap. The heap load and ballast module is disposed between the cap and the pier body, and when the counterweight bridge pier is under pressure, the pile foundation can provide support for the bridge main beam, and the pile foundation will not sink; when the counterweight bridge pier is under tension, the heap load and ballast module increases the weight of the pile foundation, thereby preventing the pile foundation from being under tension under the action of the pier superstructure, and the entire pier can withstand the tension generated by the unbalanced force on the pier, and can further ensure the stability of the pile foundation. The steel cap beam is anchored on the pier to ensure that when the pier is under tension, the tension can be continuously and stably transmitted to the pier, and the pile foundation will not be under tension, thereby ensuring the stability of the pile foundation.

[0035] The counterweight pier provided in the embodiment of the present application has an anchoring device for anchoring the main beam of the bridge arranged on the steel cap beam, so as to ensure that during the construction of the main beam, the forces on both sides of the main pier can be balanced, and the main beam of the bridge is firmly connected to the counterweight pier, thereby effectively ensuring the asymmetric double cantilever construction of the main beam, so that the force exerted on the main beam can be continuously and stably transmitted to the counterweight pier, thereby ensuring construction safety.

[0036] The above are only some embodiments of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.

Claims

1. A counterweight bridge pier, characterized in that: include: A pile foundation, a counterweight cap arranged on the pile foundation, a pier body arranged on the counterweight cap and a steel cap beam anchored on the pier body; the counterweight cap comprises a cap body, a stacked ballast module arranged on the cap body, and also comprises a connecting structure penetrating the cap body and a first steel pipe column penetrating the stacked ballast module; one end of the connecting structure is coaxially connected to the first steel pipe column, and the other end is coaxially connected to the steel casing under the counterweight cap; the first steel pipe column is filled with concrete, and the top of the first steel pipe column is A second steel pipe column is sleeved, the length ratio of the second steel pipe column exposed between the steel cap beam and the first steel pipe column is 1:5-2:5, and the filling height of the concrete in the first steel pipe column does not exceed the length of the second steel pipe column sleeved on the first steel pipe column; the steel cap beam is connected to the second steel pipe column and is anchored to the bridge main beam through an anchoring device; the anchoring device includes a steel pad, a concrete leveling block, a PTFE slide plate, and a steel strand connecting the bridge main beam and the steel cap beam in sequence from the steel cap beam upwards; The pile foundation, the counterweight-type pedestal and the first steel pipe column are connected and installed, and the second steel pipe column and the steel cap beam are pre-assembled. After the hanging basket used in the asymmetric cantilever beam construction moves forward to the position above the counterweight-type pier, the pre-assembled second steel pipe column and the steel cap beam are hoisted above the first steel pipe column, and the pre-assembled second steel pipe column and the steel cap beam are lowered together, so that the second steel pipe column can be inserted into the first steel pipe column, and the second steel pipe column and the first steel pipe column are connected to form the pier body, and then the anchor device is installed on the steel cap beam and the bridge main beam.

2. The counterweight bridge pier according to claim 1, characterized in that: The size of the stack load ballast module is consistent with the size of the support platform body.

3. The counterweight bridge pier according to claim 1, characterized in that: The stack load ballast module is a prefabricated concrete structure or a steel structure.

4. The counterweight bridge pier according to claim 1, characterized in that: The first steel pipe column is provided with an annular stiffening rib, which is arranged at the top of the filled concrete.

5. The counterweight bridge pier according to claim 1, characterized in that: The number of the first steel pipe columns is set to four.

6. The counterweight bridge pier according to claim 5, characterized in that: Diagonal braces are provided between the first steel pipe columns.

7. The counterweight bridge pier according to claim 1, characterized in that: The lower end of the connection structure is provided with an anchor piece for docking with the steel casing.