A method for rapid tunnel straightening construction in hard rock tunnels with a single roof-lifting operation
By employing methods such as auxiliary passage elevation, permanent arched gantry, and temporary pilot tunnel construction in hard rock tunnel construction, the problem of interrupted arch wall support in hard rock tunnel construction was solved, achieving rapid, safe, and efficient construction results, expanding the construction scope, and reducing environmental impact.
Patent Information
- Application Number
- CN202310418635.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-04-18
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-04-18
AI Technical Summary
In existing hard rock tunnel construction, the construction of the cantilever section at the intersection of the main tunnel and the auxiliary passage is hampered by the interruption of the initial support of the arch wall, which prevents the formation of a closed structure. The excavation span is large, the exposure time is long, the construction progress is slow and complicated, it cannot be completed in one go, and it is not conducive to construction organization and the use of large machinery.
The method of auxiliary passage elevation construction, permanent arched gantry construction, temporary guide tunnel construction, cross-section main tunnel upper step construction and main tunnel construction was adopted. By raising each section one by one, strengthening the anchor pipe and shotcrete, the continuity of the arch structure was ensured. When the integrity of the surrounding rock was poor, temporary guide tunnel steel was installed to control the excavation depth. The five-inch platform method was used for layout and connection to form a stable support structure.
It has enabled convenient and stable construction of hard rock tunnels, improved construction efficiency, reduced costs, reduced secondary damage to the surrounding rock, protected rock mass stability, shortened exposure time at intersections, and improved construction safety and environmental protection.
Smart Images

Figure CN116464453B_ABST
Abstract
Description
Technical Field
[0001] This invention belongs to the field of building engineering technology, specifically a method for rapid tunnel straightening construction in hard rock tunnels with a single roof tilting. Background Technology
[0002] With the rapid development of high-speed rail, tunnel projects are becoming increasingly common. To alleviate construction schedule pressures, auxiliary passages such as parallel pilot tunnels and inclined shafts are increasingly used in construction. Hard surrounding rock is a frequent challenge in our work. Currently, the common method is to construct the auxiliary passage at the intersection of the auxiliary passage and the main tunnel in hard rock tunnels using a cantilevered section construction. However, conventional cantilever methods suffer from several drawbacks. The initial support of the main tunnel arch wall is interrupted at the intersection, preventing the formation of a closed structure that becomes a load-bearing system. This results in large excavation spans, long exposure times, numerous procedures, extensive removal of temporary steel sections, high risks of expanded excavation, and slow construction progress. Furthermore, these methods cannot achieve a single-stage completion and do not utilize efficient construction organization or large machinery. Summary of the Invention
[0003] The purpose of this invention is to provide a method for rapid tunnel straightening construction in hard rock tunnels by a single roof-lifting operation, thereby solving the above-mentioned problems.
[0004] To achieve the above objectives, this invention discloses a method for rapid conversion of a hard rock tunnel to the main tunnel in a single-stage top-lifting operation, comprising the following steps: S1, auxiliary passage elevation construction; S2, permanent arc-shaped gantry construction; S3, temporary pilot tunnel construction; S4, cross-section main tunnel upper step construction; S5, main tunnel construction.
[0005] Furthermore, in step S1, before carrying out the construction at the junction, the auxiliary passage is raised 4-6 meters away from the junction of the main tunnel. Each section is raised in turn, while the arched steel arch frame remains unchanged. The steel columns of the side walls are gradually lengthened until the height of the permanent arched portal frame of the main tunnel is reached.
[0006] Furthermore, in step S1, the end of the auxiliary channel is made of steel, anchor pipes are installed at the arch feet on both sides of the auxiliary channel, and shotcrete is used at the arch frame feet at the end of the auxiliary channel, and the shotcrete is applied simultaneously with the shotcrete of the arch wall.
[0007] Furthermore, step S2 includes the following steps: S21, excavating the intersection of the auxiliary passage and the main tunnel; S22, installing the double-panel gantry; S23, installing the reinforced anchor pipe; S24, installing the reinforced anchor rod of the crossbeam; S25, installing the reinforced steel mesh; S26, spraying shotcrete.
[0008] Furthermore, in step S3, when the surrounding rock integrity is poor, temporary guide tunnel steel is installed at intervals of 1-1.4 meters, and initial support is carried out. The clearance reserved by the guide tunnel steel can ensure that there is no under-excavation after the main tunnel steel is installed. When the surrounding rock is relatively intact, temporary guide tunnel steel is not required.
[0009] Furthermore, in step S4, the five-inch platform method is used for construction layout. When drilling, the angle needs to be controlled according to the height difference to be raised. The steel arch frame or grid arch frame of the main tunnel is installed at intervals of 1-1.4 meters. It is connected to the connecting plate on one side of the crossbeam with bolts. Other nodes are connected by welding connecting plates or by bolts.
[0010] Furthermore, in step S4, adjacent steel arch frames or grid arch frames are connected by staggered internal and external threaded steel bars, and the steel mesh overlaps each other by at least one mesh. Locking anchor pipes are installed at the arch feet and are securely welded with steel bars.
[0011] Furthermore, in step S5, the initial support for the upper step of the main tunnel in the cantilever section is completed, and the temporary auxiliary guide tunnel steel legs are removed. A section of the main tunnel is constructed along the smaller mileage, and the working face is sealed; the temporary steel legs are removed. A section of the main tunnel is constructed along the larger mileage, and the working face is sealed. The lower step and invert arch are constructed at the bottom to form the normal working face.
[0012] Compared with the prior art, the advantages of the present invention are as follows:
[0013] The construction method of this invention is convenient, has a stable progress, and strong guarantee of the construction period. Compared with the traditional method of widening the tunnel after turning to the main tunnel, it increases efficiency and reduces costs. Furthermore, this invention expands the application scope of rapid roof-lifting technology in hard rock tunnels. By adopting a reasonable structural design and construction organization design, it simplifies the originally complex roof-lifting process, shortens the exposure time at intersections, and makes roof-lifting construction safer and more efficient. This method has broad prospects for promotion and application value, and can provide reference and guidance for the construction of similar projects. At the same time, the timely closure of the initial support of the main tunnel in this invention reduces secondary damage to the surrounding rock caused by widening excavation and protects the relative stability of the rock mass. It also reduces the use of explosives, lowers the impact on the ecology and environment, and achieves good social benefits.
[0014] The present invention will now be described in further detail with reference to the accompanying drawings. Attached Figure Description
[0015] The accompanying drawings, which form part of this application, are used to provide a further understanding of the invention. The illustrative embodiments of the invention and their descriptions are used to explain the invention and do not constitute an undue limitation of the invention. In the drawings:
[0016] Figure 1 This is a flowchart of the construction process for a hard rock tunnel with a single-stage roof-lifting and rapid tunnel-to-center conversion, as disclosed in a preferred embodiment of the present invention.
[0017] Figure 2 This is a schematic diagram of the elevation of the auxiliary passage disclosed in a preferred embodiment of the present invention;
[0018] Figure 3 This is a schematic diagram of the cantilever roof construction elevation disclosed in a preferred embodiment of the present invention;
[0019] Figure 4 This is a schematic diagram of the auxiliary channel being raised section by section according to a preferred embodiment of the present invention;
[0020] Figure 5 This is a schematic diagram of the installation of a permanent arc-shaped gantry disclosed in a preferred embodiment of the present invention;
[0021] Figure 6 This is a schematic diagram of the temporary guide tunnel steel structure disclosed in a preferred embodiment of the present invention;
[0022] Figure 7 This is a schematic diagram of the initial support arch frame of the main tunnel disclosed in a preferred embodiment of the present invention. Detailed Implementation
[0023] The embodiments of the present invention will be described in detail below with reference to the accompanying drawings, but the present invention can be implemented in many different ways as defined and covered by the claims.
[0024] like Figure 1-7 As shown, this invention discloses a method for rapid tunnel straightening construction in hard rock tunnels using a single-stage roof-jacking technique, comprising the following steps (see...). Figure 1 S1: Construction of auxiliary passageway elevation; S2: Construction of permanent curved gantry; S3: Construction of temporary guide tunnel; S4: Construction of steps leading up to the main tunnel at the intersection; S5: Construction of the main tunnel.
[0025] In step S1, see Appendix Figure 2 Before commencing construction at the junction, the auxiliary passage will be raised approximately 5 meters from the junction with the main tunnel. This will be done segment by segment, with the arched steel frame of the main tunnel remaining unchanged, while the steel columns of the side walls will be gradually lengthened, until the height reaches the level of the permanent arched portal frame of the main tunnel. (See attached document.) Figure 2 The three auxiliary passageways at the end are constructed of double-section 18-type steel, with four supports installed at the arched bases on both sides. Anchor pipes for locking feet, L=3.5m; at the end of the auxiliary passage, 0.5m thick C30 shotcrete is used at the foot of the three arch frames, applied simultaneously with the shotcrete application to the arch walls. See attached document. Figure 3 .
[0026] Step S2 includes the following steps: S21, excavating the intersection of the auxiliary passage and the main tunnel; S22, installing the double-panel gantry; S23, reinforcing the anchor pipes; S24, reinforcing the crossbeams with anchor bolts; S25, installing the reinforcing steel mesh; S26, spraying shotcrete. For details, please refer to the appendix. Figure 4After completing the elevation construction of the auxiliary passage, construction is required at the intersection of the auxiliary passage and the main tunnel. Before construction, Φ42mm small guide pipes (3.5-4m long, 30cm circumferential spacing) are used for pre-support. Excavation is carried out according to the blasting design. After excavation, Φ6 steel reinforcement mesh with a 20*20 spacing is installed on the arch, and mortar anchors are installed at a density of 3-3.5m, along with four double-row locking anchors (L=4.0m). Permanent support beams and columns are installed at the junction of the auxiliary passage, using double-section I22a / I25a steel, connected by bolts and welding. The permanent arch frame and the arch frame at the end of the auxiliary passage are connected by Φ20 longitudinal connecting bars at 1-meter intervals on each side, staggered internally and externally. The arch feet of the portal frame and the three arches at the end of the auxiliary passage are connected by I18 crossbeams. The permanent arch frame is made of 0.5m thick C30 shotcrete, which is applied at the same time as the shotcrete application on the arch wall.
[0027] In step S3, see Appendix Figure 5 Following the step method, a temporary auxiliary pilot tunnel is constructed. Considering construction safety, quality, progress, and cost, and taking into account the existing conditions, the pilot tunnel cross-section is constructed at 8.6m*7.3m (width*height). The main tunnel section is excavated step by step. When the surrounding rock integrity is poor, temporary pilot tunnel steel is installed at a spacing of 1.2m, and initial support is then carried out. The clearance reserved for the pilot tunnel steel can ensure that there is no under-excavation after the main tunnel steel is installed. When the surrounding rock is relatively intact, temporary pilot tunnel steel is not required.
[0028] The support parameters for the pilot tunnel are shown in the table below:
[0029] Initial support parameters for the pilot tunnel (for tunnels with poor surrounding rock integrity)
[0030]
[0031] Initial support parameter table for pilot tunnel (surrounding rock integrity is relatively good)
[0032]
[0033]
[0034] In step S4, see Appendix Figure 6The construction layout is carried out using the 5-inch platform method. During drilling, the angle must be controlled according to the required elevation difference. 7-8 steel arch frames or grid arch frames are installed at 1.2m intervals as designed. These are connected to the crossbeams using M24 bolts. Other nodes are connected by welded plates using bolts. Adjacent steel arch frames or grid arch frames are connected using Φ20 threaded steel at 1-meter intervals on each side, with alternating inner and outer sections. The steel mesh overlaps by at least one grid. Two anchor pipes, each with four sections, are installed at the arch foot and securely welded using Φ18 U-shaped steel bars.
[0035] In step S4, see Appendix Figure 7 After completing the initial support of the upper bench of the main tunnel in the cantilever section, the temporary auxiliary guide tunnel steel legs were removed. Along the smaller mileage, a section of the main tunnel was constructed, and the working face was sealed; the temporary steel legs were removed. Along the larger mileage, a section of the main tunnel was constructed, the working face was sealed, and the lower bench and invert arch were constructed at the bottom to form the working face.
[0036] The above are merely preferred embodiments of the present invention and are not intended to limit the present invention. Various modifications and variations can be made to the present invention by those skilled in the art. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the scope of protection of the present invention.
Claims
1. A method for rapid tunnel straightening construction in hard rock tunnels using a single-stage roof-lifting technique, characterized in that... The process includes the following steps: S1, construction of the auxiliary passageway elevation; S2, construction of the permanent curved gantry; S3, construction of the temporary pilot tunnel; S4, construction of the steps leading up to the main tunnel at the intersection; S5, construction of the main tunnel. In step S1, before the construction at the junction, the auxiliary passage is raised 4-6 meters away from the junction of the main tunnel. The raising is carried out frame by frame, while the arched steel arch frame of the arch remains unchanged. The steel columns of the side walls are gradually lengthened and raised to the height of the permanent arched portal frame of the main tunnel. Step S2 includes the following steps: S21, excavating the intersection of the auxiliary passage and the main tunnel; S22, installing the double-panel gantry; S23, installing the reinforced anchor pipes; S24, installing the reinforced anchor bolts on the crossbeam; S25, installing the reinforced steel mesh; S26, spraying concrete. In step S3, when the surrounding rock integrity is poor, temporary guide tunnel steel sections are installed at intervals of 1-1.4 meters, and initial support is carried out. The clearance reserved by the temporary guide tunnel steel sections can ensure that there is no under-excavation after the main tunnel steel sections are installed. When the surrounding rock is relatively intact, temporary guide tunnel steel sections are not required. In step S4, the five-inch platform method is used for construction layout. When drilling, the angle needs to be controlled according to the height difference to be raised. The steel arch frame or grid arch frame of the main tunnel arch is installed at a spacing of 1-1.4 meters. It is connected to the connecting plate on one side of the crossbeam with bolts. Other nodes are connected by welding connecting plates or by bolts. In step S5, the initial support of the upper step of the main tunnel is completed, and the support legs of the temporary guide tunnel steel are removed; a section of the main tunnel is constructed along the small mileage, and the working face is closed; the support legs of the temporary guide tunnel steel are removed; a section of the main tunnel is constructed along the large mileage, and the working face is closed; the lower step and invert arch are constructed at the bottom to form the normal working face.
2. The method for rapid tunnel straightening in hard rock tunnels with a single-stage roof-lifting operation according to claim 1, characterized in that, In step S1, the end of the auxiliary channel is made of steel, the two sides of the arch foot of the auxiliary channel are fitted with anchor pipes, and the arch foot of the end of the auxiliary channel is made of shotcrete, which is carried out at the same time as the shotcrete of the arch wall.
3. The method for rapid tunnel straightening construction in hard rock tunnels with a single-stage roof-lifting operation according to claim 1, characterized in that, In step S4, adjacent steel arch frames or grid arch frames are connected by staggered internal and external threaded steel bars, and the steel mesh overlaps each other by at least one mesh. Locking anchor pipes are installed at the arch feet and are securely welded with steel bars.