A method and device for automatically managing safety inventory of workshop spare parts warehouse

Through the combination of equipment tree and expert database, the convolutional neural network model is used to solve the problem of predicting spare parts demand for workshop automation production line equipment, and the precise management and early warning prompts of spare parts inventory are realized, reducing production losses and resource waste.

CN116579724BActive Publication Date: 2024-11-19QINGDAO CHENGGUANGFENG AUTOMATION ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310408662.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-04-17
Publication Date
2024-11-19
Estimated Expiration
2043-04-17

AI Technical Summary

Technical Problem

The existing technology cannot effectively and accurately predict and manage the spare parts demand for workshop automation production line equipment, resulting in direct and indirect economic losses in production and waste of resources caused by abnormal shutdowns.

Method used

By obtaining the list of components of the equipment to be predicted based on the device tree, combining the alarm data information and health index in the expert database, calculate the failure rate and maintenance information of spare parts, use the convolutional neural network model to determine whether spare parts are safe inventory, and generate spare parts Requirements list to realize dynamic management and early warning prompts of spare parts inventory.

Benefits of technology

It realizes accurate and systematic prediction of spare parts requirements for workshop automated production line equipment, reduces spare parts inventory costs, improves the reliability of production equipment, and provides intelligent decision-making support to reasonably arrange spare parts purchase and storage plans.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116579724B_ABST
    Figure CN116579724B_ABST
Patent Text Reader

Abstract

The present application relates to a method and device for automatically managing the safety inventory of a workshop spare parts warehouse, including obtaining a list of components of the equipment to be predicted in the workshop based on the equipment tree; obtaining a spare parts safety inventory list of the equipment to be predicted based on an established expert database, the alarm data information, health index and component list of the equipment to be predicted received; obtaining a spare parts requirement list of the spare parts safety inventory list based on the equipment failure rate, the component parts and spare parts list, the maintenance information of the equipment to be predicted and the spare parts safety inventory list. The present application establishes a spare parts list based on the on-site equipment list; automatically generates a spare parts safety inventory list and quantity recommendations, as well as safety inventory early warning prompts based on the system expert database, mechanism model, equipment risk diagnosis and statistics; the system associates equipment maintenance and preventive maintenance activities with the expert database, automatically generates a spare parts requirement list, and associates it with the spare parts warehouse management system, thereby realizing dynamic association and management of spare parts inventory management.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the field of data processing technology, and more particularly to a method and device for automatically managing the safety inventory of a workshop spare parts warehouse. Background Art

[0002] An industrial robot is a multi-joint manipulator or multi-degree-of-freedom machine device for the industrial field. It can perform work automatically and relies on its own power and control capabilities to achieve various functions.

[0003] In the modern manufacturing industry, professional technicians can connect robots, automated production equipment, transmission lines, control systems, etc. in series according to the requirements of production processes through overall planning and design, and build automated production lines based on robot applications. Automated production lines can run according to pre-programmed programs to achieve automated production and unmanned production.

[0004] Automated production lines based on robot applications can replace humans in industrial production to do certain monotonous, frequent and repetitive long-term operations, or operations in dangerous and harsh environments. For example, in production process links such as stamping, welding, painting, machining, casting, heat treatment, and automated assembly, they can replace humans and realize automated production.

[0005] As the degree of automation of automated production lines based on robot applications increases and the number of robots and automated equipment increases, the "focus" of production management shifts from "managing people" to "managing equipment."

[0006] How to shorten the repair and recovery time of abnormal fault downtime, reduce the indirect production losses caused by long-term abnormal downtime, how to reasonably and adequately plan spare parts reserves, how to reduce spare parts costs and avoid cost waste, etc., have become the most troublesome issues for the production and equipment management departments of manufacturing companies. Scientific, rational and precise spare parts management has become the most important and difficult technical and management work in equipment management.

[0007] At present, due to the lack of mature and complete technology, it is impossible to accurately calculate and manage the daily demand for spare parts for the workshop's automated production line equipment, and it is impossible to ensure the rapid recovery of abnormal shutdowns of production lines, resulting in huge direct and indirect production economic losses and waste of resources.

[0008] How to accurately predict and calculate the spare parts demand for workshop automation equipment is a technical problem that urgently needs to be solved. Summary of the invention

[0009] The technical problem to be solved by the present application is to provide a method and device for automatically managing the safety inventory of a workshop spare parts warehouse in view of the deficiencies in the prior art.

[0010] The technical solution of this application to solve the above technical problems is as follows:

[0011] In a first aspect, the present application provides a method for automatically managing safety inventory of a workshop spare parts warehouse, the method comprising:

[0012] Obtain a list of components of the equipment to be predicted in the workshop based on the equipment tree;

[0013] Obtain a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information and health index of the equipment to be predicted and the component list;

[0014] Based on the failure rate and health index of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety stock list, a spare parts requirement list of the spare parts safety stock list is obtained, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list.

[0015] Furthermore, the obtaining of a component list of the equipment to be predicted in the workshop based on the equipment tree specifically includes:

[0016] According to the device tree of the device to be predicted, all leaf nodes in the device tree are counted to obtain a component list of the device to be predicted.

[0017] Furthermore, the spare parts safety inventory list of the equipment to be predicted is obtained based on the established expert database, the received alarm data information of the equipment to be predicted, the health index and the component list, which specifically includes:

[0018] Acquire the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted based on an established expert database;

[0019] Determine the spare parts cycle of the component of the device to be predicted according to the life cycle of the device to be predicted and the life cycle of the component of the device to be predicted, and determine whether the spare parts of the component are safety stocks according to the spare parts cycle, the alarm data information of the device to be predicted, the health index, the inventory model and the list of component parts;

[0020] If the spare parts of the component are in safety stock, the spare parts information of the component is stored in a first spare parts safety stock list; otherwise, the spare parts information of the component is stored in a second spare parts safety stock list.

[0021] Further, determining the spare parts cycle of the component of the equipment to be predicted according to the life cycle of the equipment to be predicted and the life cycle of the component of the equipment to be predicted specifically includes:

[0022] Obtaining a critical period of the device to be predicted based on the life cycle of the component of the device to be predicted and the critical coefficient of the component of the device to be predicted;

[0023] After dividing the life cycle of the equipment to be predicted by using the critical cycle of the equipment to be predicted, the spare parts cycle of the components of the equipment to be predicted is obtained.

[0024] Further, determining whether the spare parts of the component are safety stocks according to the spare parts cycle, the alarm data information of the equipment to be predicted, the health index, the inventory model and the component list specifically includes:

[0025] Taking the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted as a first parameter set;

[0026] Using the alarm data information and health index of the device to be predicted as a second parameter set;

[0027] The first parameter set and the second parameter set are input into an established inventory model to obtain whether the spare parts of the component are safety stocks, wherein the inventory model is established based on a convolutional neural network.

[0028] Further, the spare parts requirement list of the spare parts safety stock list is obtained according to the failure rate of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety stock list, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list, specifically including:

[0029] Calculating the variance value of the actual failure rate of all the spare parts and the preset failure rate, if the variance value is greater than the preset variance value, setting the spare parts rate of all the spare parts to be the first preset value, otherwise the spare parts rate of all the spare parts is the preset value of the spare parts;

[0030] Determine the key time points and spare parts maintenance list of the spare parts according to the maintenance information of the equipment to be predicted;

[0031] The spare parts requirement list is obtained according to the spare parts rate of the spare parts, the component list, the spare parts time point of the equipment to be predicted, and the spare parts maintenance list.

[0032] In a second aspect, the present application provides a device for automatically managing the safety inventory of a workshop spare parts warehouse, the device comprising:

[0033] The first processing module is used to obtain a list of components of the equipment to be predicted in the workshop based on the equipment tree;

[0034] The second processing module is used to obtain a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information and health index of the equipment to be predicted and the component list;

[0035] The third processing module is used to obtain the spare parts requirement list of the spare parts safety stock list based on the failure rate and health index of the spare parts, the list of component parts, the maintenance information of the equipment to be predicted and the spare parts safety stock list, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list.

[0036] The beneficial effects of the present application are as follows: a method for automatically managing the safety inventory of a workshop spare parts warehouse is proposed, the method comprising obtaining a list of components of the equipment to be predicted in the workshop based on the equipment tree; obtaining a spare parts safety inventory list of the equipment to be predicted based on an established expert database, the alarm data information of the equipment to be predicted, the health index and the list of components; obtaining a spare parts requirement list of the spare parts safety inventory list based on the failure rate of the spare parts, the health index, the list of components, the maintenance information of the equipment to be predicted and the spare parts safety inventory list, wherein the spare parts requirement list includes the number of spare parts in the spare parts safety inventory list. The present application establishes a spare parts list based on the on-site equipment list; automatically generates a spare parts safety inventory list and quantity recommendations, as well as safety inventory early warning prompts based on the system expert database, mechanism model, equipment risk diagnosis and statistics; the system associates equipment maintenance and preventive maintenance activities with the expert database, automatically generates a spare parts requirement list, and associates it with the spare parts warehouse management system, thereby realizing dynamic association and management of spare parts inventory management. Through this kind of automatic safety inventory management method and algorithm of the workshop spare parts warehouse, the spare parts demand of the workshop automated production line equipment can be effectively and accurately predicted, and the production and equipment management departments of the manufacturing enterprise can reasonably arrange spare parts purchase and storage plans, providing intelligent decision-making and data support. And it can achieve the following revolutionary technical effects:

[0037] 1. Accurately and systematically establish equipment spare parts records; 2. Accurately locate and evaluate equipment failure points and risk points, and store corresponding spare parts; 3. Realize the small-scale, comprehensive and systematic demand forecast of equipment spare parts and components; 4. Realize early warning and prompts of the safety line of equipment inventory. 5. According to the equipment maintenance and repair plan, real-time data updates and prompts are carried out.

[0038] Advantages of additional aspects of the present application will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present application. BRIEF DESCRIPTION OF THE DRAWINGS

[0039] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments of the present application or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0040] Figure 1 A schematic diagram of a flow chart of a method for automatically managing safety inventory of a workshop spare parts warehouse according to an embodiment of the present application;

[0041] Figure 2 This is a module diagram of a device for automatically managing the safety inventory of a workshop spare parts warehouse according to another embodiment of the present application. DETAILED DESCRIPTION

[0042] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of this application.

[0043] At present, enterprises need to complete the spare parts list of the equipment in the fastest time, which makes the correct and timely prediction and the resulting reliable decision-making the key elements of the success of modern enterprises. Accurate prediction of production spare parts demand is the key to reliable production. It can improve the reliability of production equipment, make more scientific procurement plans, and reduce inventory costs as much as possible.

[0044] However, the current prediction system cannot meet the increasingly high prediction requirements. In this case, the emergence of data mining (DM) has attracted widespread attention from academia and industry. Current data mining models are widely used in sales inventory, supply chain inventory and other fields, but spare parts have management requirements for the entire product life cycle. There are great differences between spare parts prediction models and business fields such as sales and supply chain. Data mining models for sales inventory, supply chain inventory, etc. are not suitable for spare parts prediction and cannot achieve spare parts prediction.

[0045] like Figure 1 The embodiment of the present application describes a method for automatically managing the safety inventory of a workshop spare parts warehouse, the method comprising:

[0046] 110. Obtain the component list of the equipment to be predicted in the workshop based on the equipment tree;

[0047] 120. Obtain a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information of the equipment to be predicted, the health index and the component list;

[0048] 130. According to the failure rate and health index of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety stock list, obtain the spare parts requirement list of the spare parts safety stock list, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list.

[0049] Based on the above embodiment, further, obtaining a list of components of the equipment to be predicted in the workshop based on the equipment tree specifically includes:

[0050] According to the device tree of the device to be predicted, all leaf nodes in the device tree are counted to obtain a component list of the device to be predicted.

[0051] Based on the above embodiment, the spare parts safety inventory list of the equipment to be predicted is obtained according to the established expert database, the received alarm data information of the equipment to be predicted, the health index and the component list, which specifically includes:

[0052] Acquire the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted based on an established expert database;

[0053] Determine the spare parts life cycle of the components of the equipment to be predicted based on the life cycle analysis of the equipment to be predicted and the life cycle analysis of the components of the equipment to be predicted, and determine whether the spare parts of the components are safety stocks based on the spare parts life cycle, the alarm data information and health index of the equipment to be predicted, the inventory model and the component list;

[0054] If the spare parts of the component are in safety stock, the spare parts information of the component is stored in a first spare parts safety stock list; otherwise, the spare parts information of the component is stored in a second spare parts safety stock list.

[0055] Based on the above embodiment, determining the spare parts cycle of the component of the device to be predicted according to the life cycle of the device to be predicted and the life cycle of the component of the device to be predicted specifically includes:

[0056] Obtaining a critical period of the device to be predicted based on the life cycle of the component of the device to be predicted and the critical coefficient of the component of the device to be predicted;

[0057] After dividing the life cycle of the equipment to be predicted by using the critical cycle of the equipment to be predicted, the spare parts cycle of the components of the equipment to be predicted is obtained.

[0058] Based on the above embodiment, determining whether the spare parts of the component are safety stocks according to the spare parts cycle, the alarm data information and health index of the device to be predicted, the inventory model and the component list specifically includes:

[0059] Taking the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted as a first parameter set;

[0060] Using the alarm data information and health index of the device to be predicted as a second parameter set;

[0061] The first parameter set and the second parameter set are input into an established inventory model to obtain whether the spare parts of the component are safety stocks, wherein the inventory model is established based on a convolutional neural network.

[0062] Based on the above embodiment, the spare parts requirement list of the spare parts safety stock list is obtained according to the failure rate of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety stock list, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list, specifically including:

[0063] Calculating the variance value of the actual failure rate of all the spare parts and the preset failure rate, if the variance value is greater than the preset variance value, setting the spare parts rate of all the spare parts to be the first preset value, otherwise the spare parts rate of all the spare parts is the preset value of the spare parts;

[0064] Determine the key time points and spare parts maintenance list of the spare parts according to the maintenance information of the equipment to be predicted;

[0065] The spare parts requirement list is obtained according to the spare parts rate of the spare parts, the component list, the spare parts time point of the equipment to be predicted, and the spare parts maintenance list.

[0066] Based on the above-mentioned embodiment, a method for automatically managing the safety inventory of a workshop spare parts warehouse is proposed. The method includes obtaining a list of components of the equipment to be predicted in the workshop based on the equipment tree; obtaining a spare parts safety inventory list of the equipment to be predicted based on an established expert library, the alarm data information of the equipment to be predicted, the health index and the list of components; obtaining a spare parts requirement list of the spare parts safety inventory list based on the failure rate of the spare parts, the health index, the list of components, the maintenance information of the equipment to be predicted and the spare parts safety inventory list, wherein the spare parts requirement list includes the number of spare parts in the spare parts safety inventory list. The present application establishes a spare parts list based on the on-site equipment list; automatically generates a spare parts safety inventory list and quantity recommendations, as well as a safety inventory early warning prompt based on the system expert library, mechanism model, equipment risk diagnosis and statistics; the system associates equipment maintenance and preventive maintenance activities with the expert library, automatically generates a spare parts requirement list, and associates it with the spare parts warehouse management system, thereby realizing dynamic association and management of spare parts inventory management. Through the automatic safety inventory management method and algorithm of the workshop spare parts warehouse, the spare parts demand of the workshop automated production line equipment can be effectively and accurately predicted, and the production and equipment management departments of manufacturing enterprises can reasonably arrange spare parts purchase and storage plans, providing intelligent decision-making and data support. And it can achieve the following revolutionary technical effects: 1. Accurately and systematically establish equipment spare parts ledgers; 2. Accurately locate and evaluate equipment failure points and risk points, and store corresponding spare parts; 3. Realize the small-scale, comprehensive and systematic demand forecast of equipment spare parts and components; 4. Realize early warning and prompts of the safety line of equipment inventory. 5. According to the equipment maintenance and repair plan, real-time data updates and prompts.

[0067] like Figure 2 As shown, the present application provides a device for automatically managing the safety inventory of a workshop spare parts warehouse, the device comprising:

[0068] The first processing module is used to obtain a list of components of the equipment to be predicted in the workshop based on the equipment tree;

[0069] The second processing module is used to obtain a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information and health index of the equipment to be predicted and the component list;

[0070] The third processing module is used to obtain the spare parts requirement list of the spare parts safety stock list based on the failure rate and health index of the spare parts, the list of component parts, the maintenance information of the equipment to be predicted and the spare parts safety stock list, wherein the spare parts requirement list includes the quantity of spare parts in the spare parts safety stock list.

[0071] Furthermore, the first processing module is specifically configured to count all leaf nodes in the device tree of the device to be predicted, and obtain a component list of the device to be predicted.

[0072] Furthermore, the second processing module is specifically used to obtain the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted based on the established expert database;

[0073] Determine the spare parts life cycle of the components of the equipment to be predicted based on the life cycle analysis of the equipment to be predicted and the life cycle analysis of the components of the equipment to be predicted, and determine whether the spare parts of the components are safety stocks based on the spare parts life cycle, the alarm data information and health index of the equipment to be predicted, the inventory model and the component list;

[0074] If the spare parts of the component are in safety stock, the spare parts information of the component is stored in a first spare parts safety stock list; otherwise, the spare parts information of the component is stored in a second spare parts safety stock list.

[0075] Further, the third processing module is specifically used to obtain the critical period of the device to be predicted based on the life cycle of the component of the device to be predicted and the critical coefficient of the component of the device to be predicted;

[0076] After dividing the life cycle of the equipment to be predicted by using the critical cycle of the equipment to be predicted, the spare parts cycle of the components of the equipment to be predicted is obtained.

[0077] An automatic safety inventory management device for a workshop spare parts warehouse proposed based on the above embodiment includes obtaining a component list of the equipment to be predicted in the workshop based on the equipment tree; obtaining a spare parts safety inventory list of the equipment to be predicted based on an established expert database, the alarm data information of the equipment to be predicted, the health index and the component list; obtaining a spare parts requirement list of the spare parts safety inventory list based on the failure rate of the spare parts, the health index, the component list, the maintenance information of the equipment to be predicted and the spare parts safety inventory list, wherein the spare parts requirement list includes the number of spare parts in the spare parts safety inventory list. The present application establishes a spare parts list based on the on-site equipment list; automatically generates a spare parts safety inventory list and quantity recommendations, as well as a safety inventory early warning prompt based on the system expert database, mechanism model, equipment risk diagnosis and statistics; the system associates equipment maintenance and preventive maintenance activities with the expert database, automatically generates a spare parts requirement list, and associates it with the spare parts warehouse management system, thereby realizing dynamic association and management of spare parts inventory management. Through the automatic safety inventory management method and algorithm of the workshop spare parts warehouse, the spare parts demand of the workshop automated production line equipment can be effectively and accurately predicted, and the production and equipment management departments of manufacturing enterprises can reasonably arrange spare parts purchase and storage plans, providing intelligent decision-making and data support. And it can achieve the following revolutionary technical effects: 1. Accurately and systematically establish equipment spare parts ledgers; 2. Accurately locate and evaluate equipment failure points and risk points, and store corresponding spare parts; 3. Realize the small-scale, comprehensive and systematic demand forecast of equipment spare parts and components; 4. Realize early warning and prompts of the safety line of equipment inventory. 5. According to the equipment maintenance and repair plan, real-time data updates and prompts.

[0078] In the above embodiments, the description of each embodiment has its own emphasis. For parts that are not described or recorded in detail in a certain embodiment, reference can be made to the relevant descriptions of other embodiments.

[0079] Those of ordinary skill in the art will appreciate that the units and algorithm steps of each example described in conjunction with the embodiments disclosed herein can be implemented in electronic hardware, or a combination of computer software and electronic hardware. Whether these functions are performed in hardware or software depends on the specific application and design constraints of the technical solution. Professional and technical personnel can use different methods to implement the described functions for each specific application, but such implementation should not be considered to be beyond the scope of this application.

[0080] In the embodiments provided in the present application, it should be understood that the disclosed devices / terminal equipment and methods can be implemented in other ways. For example, the device / terminal equipment embodiments described above are only schematic. For example, the division of the modules or units is only a logical function division. There may be other division methods in actual implementation, such as multiple units or components can be combined or integrated into another system, or some features can be ignored or not executed. Another point is that the mutual coupling or direct coupling or communication connection shown or discussed can be through some interfaces, indirect coupling or communication connection of devices or units, which can be electrical, mechanical or other forms.

[0081] The units described as separate components may or may not be physically separated, and the components shown as units may or may not be physical units, that is, they may be located in one place or distributed on multiple network units. Some or all of the units may be selected according to actual needs to achieve the purpose of the solution of this embodiment.

[0082] In addition, each functional unit in each embodiment of the present application may be integrated into one processing unit, or each unit may exist physically separately, or two or more units may be integrated into one unit. The above-mentioned integrated unit may be implemented in the form of hardware or in the form of software functional units.

[0083] If the integrated module / unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium.

[0084] Based on such understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, and can also be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may include: any entity or device capable of carrying the computer program code, recording medium, U disk, mobile hard disk, disk, optical disk, computer memory, read-only memory (ROM, Read-Only Memory), random access memory (RAM, Random Access Memory), electric carrier signal, telecommunication signal and software distribution medium. It should be noted that the content contained in the computer-readable medium can be appropriately increased or decreased according to the requirements of legislation and patent practice in the jurisdiction. For example, in some jurisdictions, according to legislation and patent practice, computer-readable media do not include electric carrier signals and telecommunication signals.

[0085] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

[0086] The above are only specific implementations of the present application, but the protection scope of the present application is not limited thereto. Any technician familiar with the technical field can easily think of various equivalent modifications or replacements within the technical scope disclosed in the present application, and these modifications or replacements should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be based on the protection scope of the claims.

Claims

1. A method for automatically managing the safety inventory of a workshop spare parts warehouse, characterized in that: The method comprises: Obtain a list of components of the equipment to be predicted in the workshop based on the equipment tree; Obtain a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information of the equipment to be predicted, the health index and the component list; According to the failure rate and health index of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety stock list, a spare parts demand list of the spare parts safety stock list is obtained, wherein the spare parts demand list includes the quantity of the spare parts in the spare parts safety stock list; The step of obtaining a list of components of the equipment to be predicted in the workshop based on the equipment tree specifically includes: According to the device tree of the device to be predicted, all leaf nodes in the device tree are counted to obtain a list of components of the device to be predicted; The step of obtaining a spare parts safety inventory list of the equipment to be predicted based on the established expert database, the received alarm data information of the equipment to be predicted, the health index and the component list specifically includes: Acquire the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted based on an established expert database; Determine the spare parts life cycle of the components of the equipment to be predicted based on the life cycle analysis of the equipment to be predicted and the life cycle analysis of the components of the equipment to be predicted, and determine whether the spare parts of the components are safety stocks based on the spare parts life cycle, the alarm data information and health index of the equipment to be predicted, the inventory model and the component list; If the spare parts of the component are in safety stock, the spare parts information of the component is stored in a first spare parts safety stock list; otherwise, the spare parts information of the component is stored in a second spare parts safety stock list; The determining of the spare parts cycle of the component of the equipment to be predicted according to the life cycle of the equipment to be predicted and the life cycle of the component of the equipment to be predicted specifically includes: Obtaining a critical period of the device to be predicted based on the life cycle of the component of the device to be predicted and the critical coefficient of the component of the device to be predicted; After dividing the life cycle of the equipment to be predicted by using the critical cycle of the equipment to be predicted, the spare parts cycle of the components of the equipment to be predicted is obtained; The determining whether the spare parts of the component are safety stocks according to the spare parts cycle, the alarm data information and health index of the equipment to be predicted, the inventory model and the component list specifically includes: Taking the life cycle of the device to be predicted and the life cycle of the components of the device to be predicted as a first parameter set; Using the alarm data information and health index of the device to be predicted as a second parameter set; Inputting the first parameter set and the second parameter set into an established inventory model to determine whether the spare parts of the component are safety stocks, wherein the inventory model is established based on a convolutional neural network; The step of obtaining a spare parts requirement list of the spare parts safety inventory list according to the failure rate and health index of the spare parts, the component list, the maintenance information of the equipment to be predicted and the spare parts safety inventory list specifically includes: Calculating the variance value of the actual failure rate of all the spare parts and the preset failure rate, if the variance value is greater than the preset variance value, setting the spare parts rate of all the spare parts to be the first preset value, otherwise the spare parts rate of all the spare parts is the preset value of the spare parts; Determine the key time points and spare parts maintenance list of the spare parts according to the maintenance information of the equipment to be predicted; The spare parts requirement list is obtained according to the spare parts rate of the spare parts, the component list, the spare parts time point of the equipment to be predicted, and the spare parts maintenance list.