Track slab multi-point collaborative intelligent lifting equipment and method
By setting up a lift jack at the four corners of the inner side of the track plate and monitoring the hydraulic pressure and displacement sensors in real time, using an intelligent measurement and control system, the problems of low repair efficiency and insufficient accuracy in the existing technology are solved, and efficient and accurate Push and fall back operations to adapt to various terrain environments.
Patent Information
- Application Number
- CN202310814060.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-05
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2043-07-05
AI Technical Summary
The prior art cannot quickly and accurately complete the repair and positioning of prefabricated track plates within a limited sunroof time, resulting in low efficiency and large errors, which affect driving safety and passenger comfort.
Design a multi-point synergistic intelligent jacking device and method for track plates. Four jacks are placed at the four corners on the inner side of the track plates, and the hydraulic value and displacement sensor measurement value of each jack are monitored and adjusted in real time. , ensure the coordination and accuracy of the hoisting process, and use intelligent measurement and control systems to achieve efficient hoisting and falling operations.
It realizes the efficient and accurate completion of track plate lifting work within the skylight time, with the advantages of small size, high efficiency, intelligent coordination and simple operation, adapts to the terrain environment of various track plate laying, reduces manpower investment, improves construction efficiency and accuracy sex.
Smart Images

Figure CN116730236B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field, and in particular to a multi-point coordinated intelligent lifting device and method for a track plate. Background Art
[0002] Precast track slabs are a type of precast concrete element widely used in railway construction. With the acceleration of urbanization, the demand for urban rail transit construction is increasing, and the application market for precast track slabs is also expanding. In addition, the country has given strong support to urban rail transit construction, and the introduction of relevant policies has also promoted the application of precast track slabs. Today, precast track slabs have played an important role in high-speed rail lines, subway lines, and urban rail transit lines due to their high construction efficiency, high flatness, and high stability.
[0003] Prefabricated track slabs are increasingly used in rail transit projects, and with them come some problems. After the construction of prefabricated track slabs, due to uneven or unstable lower foundations, environmental changes, construction quality and other issues, the prefabricated track slabs may sink over time, affecting driving safety and passenger comfort. At this time, the sunken track slabs need to be repaired and reset. In this regard, the current common practice is to use cranes, hoists, manual hydraulic jacks and other methods to repair them during the skylight period according to the conditions of the construction site. However, the existing methods cannot guarantee the rapid and accurate completion of the repair and positioning of prefabricated track slabs within the limited skylight time due to reasons such as bulky equipment, low efficiency and large errors.
[0004] To this end, in view of the above-mentioned defects, the designers of the present invention have conducted intensive research and design, and integrated many years of experience and achievements in related industries to research and design a track plate multi-point collaborative intelligent jacking equipment and method to overcome the above-mentioned defects. Summary of the invention
[0005] The purpose of the present invention is to provide a track plate multi-point coordinated intelligent jacking equipment and method, which has the advantages of small size, high efficiency, intelligent coordination, simple operation, etc., and can use a small amount of manpower to complete the track plate jacking work efficiently and with high precision within the skylight time.
[0006] To achieve the above object, the present invention discloses a multi-point coordinated intelligent lifting method for a track plate, which is characterized by comprising the following steps:
[0007] Step 1: Preparation step, that is, transporting the lifting equipment to the destination and placing four lifting jacks at the four inner corners of the track plate;
[0008] Step 2: The main lifting equipment starts working and inputs the target lifting height L of the four lifting jacks. n , start the lifting process;
[0009] Step 3: Collect the oil pressure value P of each jack when the lifting jack is started 0n , so as to monitor the oil pressure value P of each jack in real time during the subsequent lifting process 1n ;
[0010] Step 4: Calculate the force value F of each lifting jack in real time during the lifting process △n When the lifting jacks are lifted to a certain height and touch the lower surface of the track plate, the lifting jacks will be blocked and the force value F △n Increase, so set a critical threshold F 临界 When the force value of a certain lifting jack reaches the critical force threshold, it is determined that the corresponding lifting jack has completed the positioning work and the lifting action of the jack is stopped;
[0011] Step 5: Repeat step 4 for each lifting jack until all lifting jacks have completed the positioning stage and stopped lifting, completing the overall positioning;
[0012] Step 6: Start the actual lifting and record the measured values L of the jack displacement sensors corresponding to the four lifting jacks at this time 0n , and the actual lifting process begins from this point. At this time, the initial operating speed of the four-way lifting jack is V 0n ;
[0013] Step 7: Real-time monitoring of the measured value L of each jack displacement sensor during the lifting process 1n , and simultaneously calculate the actual lifting amount L of the corresponding points of the four jacks △n升 The actual lifting amount is calculated as L △n升 =L 1n -L 0n ; Combined with the target lifting height L of each lifting jack n , calculate the lifting progress Per of each lifting jack 3 n升 for According to the lifting progress of the four-way lifting jack n升 Determine whether the track plate is tilted due to the uncoordinated lifting of the jacks. If tilted, jump to step eight; if not, jump to step nine.
[0014] Step 8: After the track plate tilts, correct the tilt by adjusting the running speed of the corresponding lifting jack;
[0015] Step 9: In order to improve the control accuracy of the lifting height and the stability of the lifting, when the lifting height is close to the target lifting height, the speed of each lifting jack is reduced as a whole until it reaches the target lifting height smoothly;
[0016] Step 10: According to the lifting progress of each lifting jack n升 Determine whether any jack has reached the target lifting height. If Per n升 ≥1, the jack has reached the target lifting height, stop the lifting action of the corresponding lifting jack, if Per n升 <1, the jack has not reached the target lifting height, continue lifting;
[0017] Step 11: Determine whether all jacks have reached the target lifting height;
[0018] If yes, complete the lifting work of the target track plate;
[0019] If no, jump to step 7 and continue the intelligent lifting work;
[0020] Step 12: After the track slab is lifted, start the track slab repair work;
[0021] Step 13: After completing the repair work of the target track plate, proceed with the fallback process;
[0022] Step 14: Take the current height of the track plate as the starting point and n The target falling distance of the track plate is used to realize the falling of the track plate according to the lifting trajectory;
[0023] Step 15: During the fall of the track plate, monitor the measured value L of each jack displacement sensor in real time. 1n , and simultaneously calculate the actual fall amount L of the corresponding points of the four jacks △n落 , the actual fall is L △n落 =L 0n +L n -L 1n ;
[0024] Combined with the target drop height L of each lifting jack n , calculate the return progress Per of each lifting jack n落 for
[0025] According to the lifting progress of the four-way lifting jack n落 Determine whether the track plate is tilted due to the uncoordinated fall of the jacks. If tilted, jump to step 16; if not, jump to step 17;
[0026] Step 16: After the track plate tilts, it is necessary to correct the tilt by adjusting the running speed of the corresponding lifting jack;
[0027] Step 17: During the falling process of the track plate, calculate the force value F of each lifting jack in real time △nWhen the lifting jack falls back to the lower surface of the track plate and contacts the upper surface of the repaired track plate groove, the lifting jack will cause a force value F △n Suddenly decrease, take the critical stress threshold F in step 4 临界 When the force on a certain lifting jack drops to the critical threshold, it is determined that the corresponding lifting jack has completed the falling back work, and the falling back action of the jack is stopped;
[0028] Step 18: Determine whether all jacks have stopped falling back. If so, complete the falling back of the target track plate. If not, jump to step 15 to continue the falling back process.
[0029] Step 19: After the track plate is lowered, set all lifting jacks to fall back at the maximum speed to complete the jack reset.
[0030] Among them: the force value of the lifting jack in step 4 is calculated by the hydraulic oil contact surface in the jack cylinder and the corresponding oil pressure value of the jack. The hydraulic oil contact surface in the jack cylinder belongs to the production size of the jack and is a known value. The known contact surface diameter is D. Combined with the real-time monitoring of the oil pressure values of each jack P 1n , four-way jack corresponds to P 11 , P 12 , P 13 , P 14 , calculate the real-time force change of the jack as
[0031] (1) If F △n ≥F 临界 , stop lifting the corresponding jack;
[0032] (2) Otherwise, continue lifting.
[0033] Among them: The tilt determination method in step 7 is as follows:
[0034] The lifting progress of the four-way lifting jack 1升 , Per 2升 , Per 3升 , Per 4升 Sort by size and get the fastest progress Per max升 and the slowest progress Per min升 , the maximum progress difference between the four lifting jacks is Per △max升 =Per max升 -Per min升 ;
[0035] Set a maximum progress difference threshold Per △临界 :
[0036] (1) If Per △max升 ≥Per△临界 , determine that the track plate is tilted, and jump to step eight;
[0037] (2) Otherwise, no tilt, jump to step 9.
[0038] Among them: In step eight, according to the real-time lifting progress of the four-way lifting jack, Per n升 Calculate the average progress Per 平均 for Then calculate the difference between the lifting progress of each jack and the average progress Per △n升 Per △n升 =Per n升 -Per 平均 , thus, the adjusted speed V of the lifting jack 3 is calculated 1n V 1n =V 旧n +Per △n升 *eps;
[0039] Where: V 旧n The speed before the jack is adjusted is V when the speed is adjusted for the first time. 旧n Equal to the initial running speed V 0n , eps is the speed adjustment calculation coefficient.
[0040] Among them: In step 9, according to the lifting progress of the jack, set the speed reduction threshold Per 降 During the lifting process, the lifting progress of each lifting jack 3 is compared in real time. n升 ≥Per 降 If the speed is lowered, the process will be started; otherwise, the process will go to step 7.
[0041] Where: Per 降 The deceleration threshold is a fixed value. When the lifting progress exceeds this value, the lifting jack starts the deceleration process;
[0042] For the lifting jack 3 that enters the deceleration process, its running speed V 1n Adjust to V 1n降 V 1n降 =V 1n *eps 降 ;
[0043] Among them: eps 降 It is the speed reduction coefficient, which is a fixed value. The specific value is determined according to the user's choice of the running speed level. It is divided into three gears: fast, medium and slow. Each gear corresponds to a different speed reduction coefficient.
[0044] Wherein: the method for determining the tilt in step 15 is as follows:
[0045] The four-way lifting jack will be lowered 1落 , Per 2落 , Per 3落 , Per 4落 Sort by size and get the fastest progress Per max落 and the slowest progress Per min落 , the maximum progress difference between the four lifting jacks is Per △max落 =Per max落 -Per min落 , take the maximum progress difference threshold Per △临界 ;
[0046] (1) If Per △max落 ≥Per △临界 , the track plate tilts, jump to step 16;
[0047] (2) Otherwise, no tilt, jump to step 17.
[0048] Wherein: In step 16, according to the real-time lifting progress Per of the four-way lifting jack 3 n落 Calculate the average progress Per 平均 :
[0049]
[0050] Then calculate the difference between the lifting progress of each jack and the average progress Per △n落 :
[0051] Per △n落 =Per n落 -Per 平均
[0052] Thus, the adjusted speed V of the lifting jack 3 is calculated. 1n for:
[0053] V 1n =V 旧n +Per △n落 *eps
[0054] Where: eps is the speed adjustment calculation coefficient.
[0055] Also disclosed is a jacking device for a multi-point coordinated intelligent jacking method of a track plate, comprising a jacking device host, a measurement and control flat plate and a jacking jack, wherein the jacking device host and the measurement and control flat plate are connected via wireless communication, and the jacking device host is connected to the jacking jack via a jack oil pipe, and is characterized in that:
[0056] The front end of the main body of the jacking device is provided with a jack placement area to accommodate the jacking jack for movement, and the rear part of the main body of the jacking device may be provided with a push handle, and the bottom part thereof is provided with a plurality of universal wheels.
[0057] Wherein: the lifting jack comprises a jack displacement sensor, a jack lifting foot, a jack lifting head and a jack lifting column, the jack lifting foot and the jack lifting head are integrally arranged and formed with a vertical steel structure. The structure is characterized in that the top end of the jacking column is connected to the jacking head by a screw rod.
[0058] From the above content, it can be seen that the track plate multi-point coordinated intelligent lifting device and method of the present invention have the following effects:
[0059] 1. With the advantages of small size, high efficiency, intelligent coordination, and simple operation, it can use a small amount of manpower to complete the track plate lifting work efficiently and accurately within the skylight time.
[0060] 2. It has the advantages of synchronization, intelligence, and precision of cranes and hoisting equipment for lifting track plates, and portability and versatility of manual hydraulic jacks for lifting track plates, and can adapt to the construction under the current terrain environment for track plate laying. The equipment is equipped with an intelligent measurement and control system, which can start and stop automatically with one button, and can accurately and conveniently complete the track plate lifting operation with less manpower input.
[0061] The details of the present invention can be obtained from the following description and the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] Figure 1 A side front schematic diagram of the track plate multi-point collaborative intelligent jacking equipment of the present invention is shown.
[0063] Figure 2 A side and rear schematic diagram of the track plate multi-point coordinated intelligent jacking equipment of the present invention is shown.
[0064] Figure 3 A working principle diagram of the track plate multi-point coordinated intelligent jacking device of the present invention is shown.
[0065] Figure 4 A cross-sectional view showing the structural relationship between the jack and the track plate of the present invention.
[0066] Figure 5 A top view showing the structural relationship between the jack and the track plate of the present invention.
[0067] Figure 6 A cross-sectional view of a track slab in a tunnel before being jacked up by the track slab multi-point coordinated intelligent jacking equipment of the present invention is shown.
[0068] Figure 7The multi-point collaborative intelligent lifting flow chart of the present invention is shown.
[0069] Figure 8 The multi-point collaborative intelligent reset process of the present invention is shown. Description of the drawings:
[0071] 1: main unit of the lifting device; 11: pusher; 12: universal wheel; 13: power plug; 14: jack placement area; 15: reading area; 16: control area; 17: jack oil pipe interface; 18: oil level gauge; 2: measurement and control plate; 3: lifting jack; 31: jack displacement sensor; 32: jack lifting foot; 33: jack lifting head; 34: jack lifting column; 4: jack oil pipe; 5: track plate; 6: tunnel wall; 7: track plate groove. DETAILED DESCRIPTION
[0072] See also Figure 1 , Figure 2 and Figure 3 , showing the track plate multi-point collaborative intelligent jacking equipment and method of the present invention.
[0073] The track plate multi-point collaborative intelligent jacking device and method include a jacking device host 1, a measurement and control flat panel 2 and a jacking jack 3. The jacking device host 1 and the measurement and control flat panel 2 can be connected via wireless communication, and the jacking device host 1 is connected to the jacking jack 3 via a jack oil pipe 4.
[0074] The front end of the jacking device main unit 1 may be provided with a jack placement area 14 to facilitate the storage and movement of the jacking jack 3 therein; the rear portion of the jacking device main unit 1 may be provided with a push handle 11, and a plurality of universal wheels 12 may be provided at the bottom thereof; before performing maintenance work on the track plate 5, all relevant equipment may be carried like a cart to the location of the target track plate 5, which can save time, effort and maintenance costs; a power plug 13 and a control area 16 are provided on the side of the jacking device main unit 1, a reading area 15 is provided on the top surface, and a jack oil pipe interface 17 and an oil level gauge 18 are provided on the front portion.
[0075] After the track plate 5 is installed on site, the surrounding and lower parts of the track plate 5 are filled with medium such as concrete and rubber pads, which are tightly fitted to the outer periphery of the track plate 5 to form a tightly fitted track plate groove 7. Figure 6 When the track plate 5 needs to be repaired due to sinking, damage or other defects, the track plate 5 is often lifted from the track plate groove 7. When the track plate 5 is lifted, the track plate 5 is too tightly fitted around, and a slight tilt during lifting will cause the track plate 5 to be stuck in the track plate groove 7 and unable to move.
[0076] The lifting jack 3 comprises a jack displacement sensor 31, a jack lifting foot 32, a jack lifting head 33 and a jack lifting column 34. The jack lifting foot 32 and the jack lifting head 33 are integrally arranged to form a vertical steel structure in the shape of The top end of the jacking column 34 is connected to the jacking head 33 by a screw rod.
[0077] Therefore, the track plate multi-point coordinated intelligent lifting device of the present invention monitors the lifting height, speed and force of each lifting jack 3 in real time through the measurement and control flat plate 2, calculates the lifting trend of each jack in real time and adjusts the speed, maintains the coordination between each lifting jack 3, and ensures that the whole process can be completed smoothly. Figure 7 and Figure 8 Therefore, the track plate multi-point coordinated intelligent lifting method of the present invention comprises the following steps:
[0078] Step 1: Preparation step, that is, transport the lifting equipment to the destination, place the four lifting jacks 3 at the four inner corners of the track plate 5 (such as Figure 5 As shown), the jacking feet 32 of the four jacking jacks 3 are extended to the bottom of the edge of the track plate 5 (as shown in FIG. Figure 4 shown).
[0079] Among them: the placement relationship between the four lifting jacks 3 and the track plate 5 is as follows: Figure 5 As shown, after the jacking starts, the main jacking device 1 supplies oil to the four jacking jacks 3 respectively, and the jack jacking column 34 drives the jack jacking head 33 to jack up under the oil pressure drive, and the jack jacking head 33 then drives the jack jacking foot 32 to jack up.
[0080] Step 2: The lifting equipment host 1 starts working, the control panel 2 can be turned on, and the control program can be started on the control panel 2. The control program can establish a wireless communication connection with the lifting equipment host 1, and the target lifting height L of the four lifting jacks 3 is input in the operation interface of the control program. n (The four-way lifting jacks correspond to L1, L2, L3, and L4 respectively), click Start to carry out the lifting process, and preferably, one-click intelligent lifting is started on the measurement and control tablet 2.
[0081] Among them: From step 1, it can be seen that the jacking foot 32 of the jack does not directly contact the track plate 5 before jacking. There is still a distance from the start of the jacking foot 32 to the actual start of jacking of the track plate 5. The jacking foot 32 needs to be jacked for a distance first, and then it starts to really jack up after contacting the track plate 5. This part is called the positioning stage of the jacking jack 3. In this positioning stage, the jacking jack 3 is in a 0-load state, and the oil pressure of each jack is stable.
[0082] Among them: the target lifting height refers to the height to which the track plate 5 is lifted. Obviously, this height does not include the lifting distance of the lifting jack 3 in the positioning stage, and the track plate 5 does not move in the positioning stage. The target lifting heights L1, L2, L3, and L4 are the elongation differences of the corresponding lifting jacks 3 from the end of the positioning stage to the completion of the final lifting.
[0083] Step 3: Collect the oil pressure values P of each jack when the lifting jack 3 is just started 0n (Four-way jack corresponds to P 01 , P 02 , P 03 , P 04 ). In the subsequent lifting process, the oil pressure value P of each jack is monitored in real time. 1n (Four-way jack corresponds to P 11 , P 12 , P 13 , P 14 ).
[0084] Step 4: Calculate the force value F of each lifting jack 3 in real time during the lifting process △n When the lifting jack 3 is lifted to a certain height and contacts the lower surface of the track plate 5, each lifting jack 3 will be blocked from lifting and the force value F △n Increase, so set a critical threshold F 临界 When the force value of a certain lifting jack 3 reaches the critical force threshold, it is determined that the corresponding lifting jack 3 has completed the positioning work, and the lifting action of the jack is stopped.
[0085] Among them: the force value of the lifting jack 3 can be calculated by the hydraulic oil contact surface in the jack cylinder and the corresponding oil pressure value of the jack. The hydraulic oil contact surface in the jack cylinder belongs to the production size of the jack and is a known value. The known contact surface diameter is D. Combined with the real-time monitoring of the oil pressure values P of each jack 1n (Four-way jack corresponds to P 11 , P 12 , P 13 , P 14 ), calculate the real-time force change of the jack as
[0086] (1) If F △n ≥F 临界 , stop lifting the corresponding jack;
[0087] (2) Otherwise, continue lifting.
[0088] Step 5: Repeat step 4 for each lifting jack until all the lifting jacks 3 have completed the positioning stage and stopped lifting, completing the overall positioning and starting the subsequent intelligent lifting process.
[0089] Step 6: From this step, the track plate 5 begins to actually lift, and the measured values L of the jack displacement sensors 31 corresponding to the four lifting jacks 3 are recorded at this time. 0n (Four-way jack corresponds to L 01 , L 02 , L 03 , L 04 ), and the actual lifting process begins from this point. At this time, the initial operating speed of the four-way lifting jack 3 is V 0n (Four-way jack corresponds to V 01 , V 02 , V 03 , V 04 ).
[0090] Step 7: Real-time monitoring of the measured value L of each jack displacement sensor 31 during the lifting process 1n (Four-way jack corresponds to L 11 , L 12 , L 13 , L 14 ), and simultaneously calculate the actual lifting amount L of the corresponding points of the four jacks △n升 The actual lifting amount is calculated as L △n升 =L 1n -L 0n .
[0091] Combined with the target lifting height L of each lifting jack 3 n (Four jacks correspond to L1, L2, L3, L4), calculate the lifting progress Per of each lifting jack 3 n升 for
[0092]
[0093] According to the lifting progress of four-way lifting jack 3 n升 Determine whether the track plate 5 is tilted due to the jacking uncoordinated. The determination method is as follows:
[0094] Set the lifting progress of four-way lifting jack 3 to Per 1升 , Per 2升 , Per 3升 , Per 4升 Sort by size and get the fastest progress Per max升 and the slowest progress Per min升 , the maximum progress difference between the four lifting jacks 3 is Per △max升 =Per max升 -Per min升 .
[0095] Set a maximum progress difference threshold Per△临界 :
[0096] (1) If Per △max升 ≥Per △临界 , determine that the track plate 5 is tilted, and jump to step eight;
[0097] (2) Otherwise, no tilt, jump to step 9.
[0098] Among them: before the track plate 5 is lifted, due to uneven sinking, the track plate 5 may be in a tilted state, and the plate is filled with fillers such as rubber pads around it, forming a tightly fitting track plate groove 7 around and below the track plate 5, and there is no gap or a very small gap between the track plate 5 and the track plate groove 7. If the lifting of the four jacks is not coordinated, the track plate 5 may be tilted, causing the track plate 5 to be stuck in the track plate groove 7 due to the tilt and unable to go up or down. Therefore, during the lifting process of the track plate 5, the lifting actions of the four jacks should be adaptively coordinated according to the initial posture of the track plate 5 to ensure coordinated lifting of multiple points to achieve accuracy and safety during the lifting process.
[0099] Step 8: After the track plate 5 is tilted, the tilt is corrected by adjusting the running speed of the corresponding lifting jack 3.
[0100] Among them: the running speed of the jack depends on the speed at which the main engine 1 of the lifting equipment presses the hydraulic oil into the jack. The hydraulic oil flow of each jack is controlled by a hydraulic electromagnetic proportional valve, which is determined by the opening and closing degree of the hydraulic electromagnetic proportional valve, and the opening and closing degree of the hydraulic electromagnetic proportional valve changes with the input control voltage. It can be seen that the running speed of the jack cannot be directly controlled, but is indirectly controlled by the input voltage of the hydraulic electromagnetic proportional valve. Due to factors such as the production error of the jack and the different working pressures of the corresponding oil circuits of each jack, there is no clear conversion relationship between the input voltage value of the hydraulic electromagnetic proportional valve and the running speed of the jack, which greatly increases the difficulty of coordination. Therefore, in order to ensure the coordinated lifting between the various jacks, a set of intelligent lifting methods for the lifting jack 3 is designed to achieve dynamic and real-time adjustment of the corresponding running speed according to the tilt posture of the track plate 5.
[0101] Specifically, according to the real-time lifting progress Per of the four-way lifting jack 3 n升 Calculate the average progress Per 平均 for
[0102] Then calculate the difference between the lifting progress of each jack and the average progress Per △n升 Per △n升 =Per n升 -Per 平均 .
[0103] Thus, the adjusted speed V of the lifting jack 3 is calculated. 1n V 1n =V 旧n +Per △n升 *eps.
[0104] Where: V 旧n The speed before the jack is adjusted is V when the speed is adjusted for the first time. 旧n Equal to the initial running speed V 0n .
[0105] Among them: eps is the speed adjustment calculation coefficient, which is a fixed value. The specific value depends on the user's choice of the running speed level. It is divided into three gears: fast, medium and slow. Each gear corresponds to a fixed calculation coefficient.
[0106] Step 9: To improve the control accuracy of the lifting height and the lifting stability, when the lifting height approaches the target lifting height (for example, when the lifting height reaches 10% of the target lifting height), the speed of each lifting jack 3 is reduced as a whole until the target lifting height is reached smoothly.
[0107] According to the lifting progress of the jack, set the speed reduction threshold Per 降 During the lifting process, the lifting progress of each lifting jack 3 is compared in real time. n升 ≥Per 降 If the speed is lowered, the process goes to step 7.
[0108] Where: Per 降 The deceleration threshold is a fixed value. When the lifting progress exceeds this value, the lifting jack starts the deceleration process.
[0109] For the lifting jack 3 that enters the deceleration process, its running speed V 1n Adjust to V 1n降 V 1n降 =V 1n *eps 降 .
[0110] Among them: eps 降 It is the speed reduction coefficient, which is a fixed value. The specific value is determined according to the user's choice of the running speed level. It is divided into three gears: fast, medium and slow. Each gear corresponds to a different speed reduction coefficient.
[0111] Step 10: According to the lifting progress of each lifting jack 3 n升 Determine whether any jack has reached the target lifting height.
[0112] If Per n升≥1, the jack has reached the target lifting height, and the lifting action of the corresponding lifting jack 3 is stopped.
[0113] If Per n升 <1, the jack has not reached the target lifting height, continue lifting.
[0114] Step 11: Determine whether all jacks have reached the target lifting height.
[0115] If yes, the intelligent lifting work of the target track plate 5 is completed.
[0116] If no, jump to step 7 and continue the intelligent lifting work.
[0117] Step 12: After the track plate 5 is lifted, the maintenance personnel start to repair the track plate 5.
[0118] Step 13: After completing the repair work of the target track plate 5, the return process is carried out. You can click the descend button on the measurement and control flat panel 2 to start the one-key return process.
[0119] Step 14: When the track plate 5 falls back, since the repair work has been done in the track plate groove 7, and the height of the four corners of the track plate groove 7 is unknown, it is impossible to determine how far the four corners of the track plate 5 need to fall back. However, it is foreseeable that if the track plate 5 falls back according to the lifting trajectory, it will not cause tilting or jamming in the track plate groove 7. Therefore, take the current height of the track plate 5 as the starting point and take L n (The four jacks correspond to L1, L2, L3, and L4) is the target falling distance of the track plate 5, so that the track plate 5 can fall back according to the jacking trajectory.
[0120] Among them: When the track plate 5 falls back, the actual height of the four corners falling back is usually less than L n However, to ensure that the track plate 5 falls back smoothly, L n The target fall distance is L. After the track plate 5 is completed, the actual fall distance of the lifting jack 3 is less than L. n It doesn't matter anymore, just continue to lower until the jack stroke returns to zero.
[0121] Step 15: During the falling process of the track plate 5, the measured values L of the displacement sensors 31 of each jack are monitored in real time. 1n (Four-way jack corresponds to L 11 , L 12 , L 13 , L 14 ), and simultaneously calculate the actual fall amount L of the corresponding points of the four jacks △n落 , the actual fall is L △n落 =L 0n +L n -L1n .
[0122] Combined with the target fall height L of each lifting jack 3 n (The four jacks correspond to L1, L2, L3, and L4), calculate the return progress Per of each lifting jack 3 n落 for
[0123]
[0124] According to the lifting progress of four-way lifting jack 3 n落 Determine whether the track plate 5 is tilted due to the uncoordinated fall of the jacks. The determination method is as follows:
[0125] Set the return progress of the four-way lifting jack 3 to Per 1落 , Per 2落 , Per 3落 , Per 4落 Sort by size and get the fastest progress Per max落 and the slowest progress Per min落 , the maximum progress difference between the four lifting jacks 3 is Per △max落 =Per max落 -Per min落 .
[0126] Take the maximum progress difference threshold Per in step 7 △临界 :
[0127] (1) If Per △max落 ≥Per △临界 , the track plate 5 tilts, and the process jumps to step 16;
[0128] (2) Otherwise, no tilt, jump to step 17.
[0129] Step 16: After the track plate 5 is tilted, it is necessary to correct the tilt by adjusting the running speed of the corresponding lifting jack 3. The speed adjustment is based on the principle of accelerating if the progress is too slow and decelerating if the progress is too fast.
[0130] According to the real-time lifting progress of the four-way lifting jack 3 n落 Calculate the average progress Per 平均 :
[0131]
[0132] Then calculate the difference between the lifting progress of each jack and the average progress Per △n落 :
[0133] Per △n落 =Per n落 -Per平均
[0134] Thus, the adjusted speed V of the lifting jack 3 is calculated. 1n for:
[0135] V 1n =V 旧n +Per △n落 *eps
[0136] Where: eps is the speed adjustment calculation coefficient, and its value is the same as the eps definition in step 8.
[0137] Step 17: During the falling process of the track plate 5, the force value F of each lifting jack 3 is calculated in real time. △n When the lifting jack 3 falls back to the lower surface of the track plate 5 and contacts the upper surface of the repaired track plate groove 7, the lifting jack 3 will cause the force value F △n Suddenly decrease, take the critical stress threshold F in step 4 临界 When the force on a certain lifting jack 3 drops to the critical force threshold, it is determined that the corresponding lifting jack 3 has completed the falling work, and the falling action of the jack is stopped.
[0138] Step 18: Determine whether all jacks have stopped falling.
[0139] If yes, the one-key return operation of the target track plate 5 is completed.
[0140] If not, jump to step 15 to continue the fallback process.
[0141] Step 19: At this point, the four corners of the track plate 5 have contacted the track plate groove 7, completing the intelligent coordinated fall of the track plate 5, and then setting all the lifting jacks 3 to fall back at the maximum speed until the extension of all the lifting jacks 3 returns to zero, completing the jack reset.
[0142] It can be seen that the present invention has the following advantages:
[0143] 1. With the advantages of small size, high efficiency, intelligent coordination, and simple operation, it can use a small amount of manpower to complete the track plate lifting work efficiently and accurately within the skylight time.
[0144] 2. It has the advantages of synchronization, intelligence, and precision of cranes and hoisting equipment for lifting track plates, and portability and versatility of manual hydraulic jacks for lifting track plates, and can adapt to the construction under the current terrain environment for track plate laying. The equipment is equipped with an intelligent measurement and control system, which can start and stop automatically with one button, and can accurately and conveniently complete the track plate lifting operation with less manpower input.
[0145] It is obvious that the above description and record are only examples and are not intended to limit the disclosure, application or use of the present invention. Although the embodiments have been described in the embodiments and described in the drawings, the present invention is not limited to the specific examples of the teachings of the present invention as the best mode currently considered by the drawings and described in the embodiments, and the scope of the present invention will include any embodiment falling within the previous description and the attached claims.
Claims
1. A multi-point coordinated intelligent lifting method for a track plate, characterized in that: The following steps are included: Step 1: Preparation step, that is, transporting the lifting equipment to the destination and placing four lifting jacks at the four inner corners of the track plate; Step 2: The main lifting equipment starts working and inputs the target lifting height L of the four lifting jacks. n , start the lifting process; Step 3: Collect the oil pressure value P of each jack when the lifting jack is started 0n , so as to monitor the oil pressure value P of each jack in real time during the subsequent lifting process 1n ; Step 4: Calculate the force value F of each lifting jack in real time during the lifting process △n When the lifting jacks are lifted to a certain height and touch the lower surface of the track plate, the lifting jacks will be blocked and the force value F △n Increase, so set a critical threshold F 临界 When the force value of a certain lifting jack reaches the critical force threshold, it is determined that the corresponding lifting jack has completed the positioning work and the lifting action of the jack is stopped; Step 5: Repeat step 4 for each lifting jack until all lifting jacks have completed the positioning stage and stopped lifting, completing the overall positioning; Step 6: Start the actual lifting and record the measured values L of the jack displacement sensors corresponding to the four lifting jacks at this time 0n , and the actual lifting process begins from this point. At this time, the initial operating speed of the four-way lifting jack is V 0n ; Step 7: Real-time monitoring of the measured value L of each jack displacement sensor during the lifting process 1n , and simultaneously calculate the actual lifting amount L of the corresponding points of the four jacks △n升 The actual lifting amount is calculated as L △n升 =L 1n -L 0n ; Combined with the target lifting height L of each lifting jack n , calculate the lifting progress Per of each lifting jack (3) n升 Per n升 = According to the lifting progress of the four-way lifting jack n升 Determine whether the track plate is tilted due to the uncoordinated lifting of the jacks. If tilted, jump to step eight; if not, jump to step nine. Step 8: After the track plate tilts, correct the tilt by adjusting the running speed of the corresponding lifting jack; Step 9: In order to improve the control accuracy of the lifting height and the stability of the lifting, when the lifting height is close to the target lifting height, the speed of each lifting jack is reduced as a whole until it reaches the target lifting height smoothly; Step 10: According to the lifting progress of each lifting jack n升 Determine whether any jack has reached the target lifting height. If Per n升 ≥1, the jack has reached the target lifting height, stop the lifting action of the corresponding lifting jack, if Per n升 <1, the jack has not reached the target lifting height, continue lifting; Step 11: Determine whether all jacks have reached the target lifting height; If yes, complete the lifting work of the target track plate; If no, jump to step 7 and continue the intelligent lifting work; Step 12: After the track slab is lifted, start the track slab repair work; Step 13: After completing the repair work of the target track plate, proceed with the fallback process; Step 14: Take the current height of the track plate as the starting point and n The target falling distance of the track plate is used to realize the falling of the track plate according to the lifting trajectory; Step 15: During the fall of the track plate, monitor the measured value L of each jack displacement sensor in real time. 1n , and simultaneously calculate the actual fall amount L of the corresponding points of the four jacks △n落 , the actual fall is L △n落 =L 0n +L n -L 1n ; Combined with the target drop height L of each lifting jack n , calculate the return progress Per of each lifting jack n落 for According to the lifting progress of the four-way lifting jack n落 Determine whether the track plate is tilted due to the uncoordinated fall of the jacks. If tilted, jump to step 16; if not, jump to step 17; Step 16: After the track plate tilts, it is necessary to correct the tilt by adjusting the running speed of the corresponding lifting jack; Step 17: During the falling process of the track plate, calculate the force value F of each lifting jack in real time △n When the lifting jack falls back to the lower surface of the track plate and contacts the upper surface of the repaired track plate groove, the lifting jack will cause a force value F △n Suddenly decrease, take the critical stress threshold F in step 4 临界 When the force on a certain lifting jack drops to the critical threshold, it is determined that the corresponding lifting jack has completed the falling back work, and the falling back action of the jack is stopped; Step 18: Determine whether all jacks have stopped falling back. If so, complete the falling back of the target track plate. If not, jump to step 15 to continue the falling back process. Step 19: After the track plate is lowered, set all lifting jacks to fall back at the maximum speed to complete the jack reset.
2. The multi-point coordinated intelligent lifting method of the track plate according to claim 1, characterized in that: In step 4, the force value of the lifting jack is calculated by the hydraulic oil contact surface in the jack cylinder and the corresponding oil pressure value of the jack. The hydraulic oil contact surface in the jack cylinder belongs to the production size of the jack and is a known value. The known contact surface diameter is D. Combined with the real-time monitoring of the oil pressure values P of each jack 1n , four-way jack corresponds to P 11 , P 12 , P 13 , P 14 , calculate the real-time force change of the jack as (1) If F △n ≥F 临界 , stop lifting the corresponding jack; (2) Otherwise, continue lifting.
3. The track slab multi-point coordinated intelligent lifting method according to claim 1, characterized in that: The tilt determination method in step 7 is as follows: The lifting progress of the four-way lifting jack 1升 , Per 2升 , Per 3升 , Per 4升 Sort by size and get the fastest progress Per max升 and the slowest progress Per min升 , the maximum progress difference between the four lifting jacks is Per △max升 =Per max升 -Per min升 ; Set a maximum progress difference threshold Per △临界 : (1) If Per △max升 ≥Per △临界 , determine that the track plate is tilted, and jump to step eight; (2) Otherwise, no tilt, jump to step 9.
4. The track slab multi-point coordinated intelligent lifting method according to claim 1, characterized in that: In step eight, according to the real-time lifting progress of the four-way lifting jack, n升 Calculate the average progress Per 平均 for Then calculate the difference between the lifting progress of each jack and the average progress Per △n升 Per △n升 =Per n升 -Per 平均 , thus, the adjusted speed V of the lifting jack (3) is calculated 1n V 1n =V 旧n +Per △n升 *eps; Where: V 旧n The speed before the jack is adjusted is V when the speed is adjusted for the first time. 旧n Equal to the initial running speed V 0n , eps is the speed adjustment calculation coefficient.
5. The track slab multi-point coordinated intelligent lifting method according to claim 1, characterized in that: In step 9, set the speed reduction threshold Per according to the lifting progress of the jack. 降 During the lifting process, the lifting progress of each lifting jack (3) is compared in real time. n升 ≥Per 降 If the speed is lowered, the process will be started; otherwise, the process will go to step 7. Where: Per 降 The deceleration threshold is a fixed value. When the lifting progress exceeds this value, the lifting jack starts the deceleration process; For the lifting jack (3) that is in the deceleration process, its running speed V 1n Adjust to V 1n降 V 1n降 =V 1n *eps 降 ; Among them: eps 降 It is the speed reduction coefficient, which is a fixed value. The specific value is determined according to the user's choice of the running speed level. It is divided into three gears: fast, medium and slow. Each gear corresponds to a different speed reduction coefficient.
6. The multi-point coordinated intelligent lifting method of the track plate according to claim 1, characterized in that: The method for determining the tilt in step 15 is as follows: The four-way lifting jack will be lowered 1落 , Per 2落 , Per 3落 , Per 4落 Sort by size and get the fastest progress Per max落 and the slowest progress Per min落 , the maximum progress difference between the four lifting jacks is Per △max落 =Per max落 -Per min落 , take the maximum progress difference threshold Per △临界 ; (1) If Per △max落 ≥Per △临界 , the track plate tilts, jump to step 16; (2) Otherwise, no tilt, jump to step 17.
7. The track slab multi-point coordinated intelligent lifting method according to claim 1, characterized in that: In step 16, according to the real-time lifting progress of the four-way lifting jack (3), n落 Calculate the average progress Per 平均 : Then calculate the difference between the lifting progress of each jack and the average progress Per △n落 : For △n落 =For n落 -For 平均 Thus, the adjusted speed V of the lifting jack 3 is calculated. 1n for: V 1n =V 旧n +Per △n落 *eps Where: eps is the speed adjustment calculation coefficient.
8. A lifting device for realizing the multi-point coordinated intelligent lifting method of the track plate described in any one of claims 1 to 7, comprising a lifting device host, a measurement and control flat panel and a lifting jack, wherein the lifting device host and the measurement and control flat panel are connected via wireless communication, and the lifting device host is connected to the lifting jack via a jack oil pipe, characterized in that: The front end of the main body of the jacking device is provided with a jack placement area to accommodate the jacking jack for movement, and the rear part of the main body of the jacking device may be provided with a push handle, and the bottom part thereof is provided with a plurality of universal wheels.
9. The jacking device of the track slab multi-point coordinated intelligent jacking method according to claim 8, characterized in that: The lifting jack comprises a jack displacement sensor, a jack lifting foot, a jack lifting head and a jack lifting column. The jack lifting foot and the jack lifting head are integrally arranged and are formed with a vertical steel structure. The structure is characterized in that the top end of the jacking column is connected to the jacking head by a screw rod.