A kind of watering device for civil construction

The civil construction pouring device addresses hollow steel cage issues by integrating concrete pouring and compaction through a vibrating plate and eccentric driving mechanism, ensuring solid concrete piers with improved efficiency and quality.

CN116950409BActive Publication Date: 2024-12-03ZHEJIANG ZHENZE CONSTR CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202310208076.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-07
Publication Date
2024-12-03
Estimated Expiration
2043-03-07

AI Technical Summary

Technical Problem

Traditional concrete pouring methods using ceiling or ground pumps result in hollow steel cages due to inadequate compaction, leading to unsolid concrete piers with unqualified quality, and subsequent vibration compaction either delays pouring or fails to ensure full compaction.

Method used

A civil construction pouring device with a concrete conveying pipe, vibrating plate, and eccentric driving mechanism that allows simultaneous concrete pouring and compaction, featuring a driving assembly with bevel gears and eccentric disks to ensure continuous compaction as the concrete is poured, and adjustable support arms for positional changes.

Benefits of technology

Ensures solid concrete piers by integrating pouring and compaction processes, enhancing efficiency and ensuring quality without delays, allowing for continuous operation and positional adjustments during pouring.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116950409B_ABST
    Figure CN116950409B_ABST
Patent Text Reader

Abstract

The invention discloses a pouring device for civil engineering construction, and relates to the technical field of pouring devices, comprising a concrete conveying pipe, wherein the concrete conveying pipe is connected to a pouring pipe, a dragon piece is arranged in the pouring pipe, a driving assembly is installed on the dragon piece in cooperation, a vibrating plate and a sliding plate are slidably connected to the outside of the pouring pipe, the pouring pipe is placed in a supporting frame, and then concrete is conveyed into the pouring pipe through the concrete conveying pipe, at which time a driving motor drives the dragon piece to rotate through a driving shaft, thereby realizing the conveying of concrete, and the concrete is discharged from the bottom of the pouring pipe, thereby realizing the pouring of a drainage concrete wall of a drainage system; during the pouring process, a main gear drives a driven gear to rotate, and drives an eccentric driving plate coaxially arranged with a second bevel gear to rotate under the meshing of a first bevel gear, the eccentric driving plate pushes a driving member downward, and the driving member slides downward against the sliding plate, and driven by a connecting rod, the vibrating plate performs a vibration compaction treatment on the poured concrete.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention specifically relates to the technical field of irrigation devices, in particular to a civil construction irrigation device. Background Art

[0002] Civil construction: refers to the construction of civil engineering projects, covering the construction of buildings, structures and engineering objects within the facilities and places within the scope of houses, roads, railways, airports, bridges, water conservancy, ports, tunnels, water supply and drainage, protection and other projects in various categories above ground, underground, on land, on water and underwater. It includes various technical activities such as survey, design, construction, maintenance and management in the process of engineering construction. In civil construction, the solidification of concrete is a particularly important part.

[0003] During the civil engineering, a drainage system is equipped. After the support is installed, concrete is poured. Before pouring concrete, the steel model needs to be buried underground, and a formwork is cast on the outside of the steel model before pouring. The traditional pouring method is to use a ceiling pump or a ground pump to pour concrete, but this pouring method can only transport concrete. During the pouring process, there will be hollowness inside the steel cage, resulting in an unsolid concrete pier, resulting in unqualified quality. Some construction units will use a vibrating machine to compact the poured concrete pier after pouring. However, if the poured concrete pier is vibrated again, the height of the concrete pier is large and the vibration range is small, so the compaction effect of the entire concrete pier cannot be guaranteed. If the concrete pier is vibrated halfway through the pouring, the pouring efficiency of the concrete pier will be delayed.

[0004] To this end, we provide a civil construction pouring device that can perform real-time vibration compaction when pouring concrete piers, and also achieves vibration compaction after pouring. There is no need for special vibration compaction, and the pouring of concrete is not delayed. This greatly improves the construction progress of the concrete pier and can ensure the pouring quality of the concrete pier. Summary of the invention

[0005] The purpose of the present invention is to provide a civil engineering construction pouring device to solve the problem that the traditional pouring method proposed in the above background technology is to use a ceiling pump or a ground pump to pour concrete, but this pouring method can only serve to transport concrete. During the pouring process, there will be a hollow situation inside the steel cage, which will lead to the concrete pier being not solid, resulting in unqualified quality; some construction units will use a vibrating machine to vibrate the poured concrete pier after the pouring is completed, but if the poured concrete pier is vibrated again, due to the large height of the concrete pier and the small vibration range, the vibration effect of the entire concrete pier cannot be guaranteed; if the concrete pier is vibrated halfway through the pouring, it will delay the pouring efficiency of the concrete pier.

[0006] To achieve the above object, the present invention provides the following technical solutions:

[0007] A civil construction pouring device comprises a concrete conveying pipe, wherein the concrete conveying pipe is connected to a pouring pipe, a dragon piece is arranged inside the pouring pipe; a driving assembly is mounted on the dragon piece; a vibrating plate and a sliding plate are slidably connected to the outside of the pouring pipe, wherein the sliding plate is located above the vibrating plate; a connecting rod is welded between the vibrating plate and the sliding plate; two driving members are fixed to the sliding plate by bolts;

[0008] The driving assembly includes a driving shaft welded to the dragon plate, a main gear is mounted on the driving shaft, and driven gears are meshed and connected on both sides of the main gear. The two driven gears are connected to the outer shell through a rotating shaft, and the driven gear is also coaxially provided with a first bevel gear; the first bevel gear is meshed and connected with a second bevel gear; the second bevel gear is connected to the outer shell through a rotating shaft, and an eccentric driving disk is coaxially provided.

[0009] As a further technical solution of the present invention, a driving member is arranged directly below the eccentric driving disk. The driving member is arranged in a T-shape, and an arc groove is opened on the top of the driving member.

[0010] As a further technical solution of the present invention, the shell is welded to the top of the casting pipe, and a tension spring is welded to the bottom of the shell. The tension spring is sleeved on the outside of the casting pipe, and the bottom of the tension spring is welded to the sliding plate.

[0011] As a further technical solution of the present invention, the concrete delivery pipe is mounted on the inner side of the bracket; the bracket is welded to the outer side of the casting pipe; and both sides of the lower end of the concrete delivery pipe are provided with oblique openings for facilitating concrete discharge.

[0012] As a further technical solution of the present invention, an annular sliding groove is provided on the outer side of the housing to facilitate the sliding of the slip ring, and a plurality of fixing holes are provided in the annular sliding groove.

[0013] As a further technical solution of the present invention, a driving motor is fixed to the top of the housing, and the output shaft of the driving motor is connected to the driving shaft through a coupling.

[0014] As a further technical solution of the present invention, the manipulator arm is provided with two arms, which are respectively welded on both sides of the slip ring; the manipulator arm comprises a support arm, which is provided in a C-shape, one end of which is welded to the slip ring, and the other end of which is matched with a handle;

[0015] The interior of the support arm is hollow, and the end of the support arm close to the handle is movably connected to a hand brake via a rotating shaft. One end of the hand brake extends into the interior of the support arm and is movably connected to the drive rod via a rotating shaft; a first drive block is welded to the end of the drive rod away from the hand brake, and a second drive block is fittedly connected to one side of the first drive block.

[0016] As a further technical solution of the present invention, the bottom of the second driving block is slidably connected to a slide groove provided inside the support arm; an insertion shaft matching the fixing hole is welded to one end of the second driving block away from the first driving block.

[0017] As a further technical solution of the present invention, a slope is provided at the position where the first driving block and the second driving block contact each other, and the first driving block and the second driving block are slidably connected via the slope.

[0018] As a further technical solution of the present invention, an opening groove is provided on the inner side of one end of the support arm close to the handle to facilitate the movement of the hand brake.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] 1. In the present invention, when pouring concrete piers, firstly, the concrete delivery pipe is connected to the delivery pipe of the sky pump or the ground pump, and then the pouring pipe is placed in the support frame, and then the concrete is transported to the pouring pipe through the concrete delivery pipe. At this time, the driving motor drives the dragon piece to rotate through the driving shaft, so as to realize the transportation of concrete, and the concrete is discharged from the bottom of the pouring pipe, so as to realize the pouring of the drainage concrete wall of the drainage system; during the pouring process, the main gear drives the driven gear to rotate, and drives the eccentric driving disk coaxially arranged with the second bevel gear to rotate under the meshing of the first bevel gear, and the eccentric driving disk pushes the driving member downward, and the driving member slides downward against the sliding disk, and driven by the connecting rod, the vibrating disk performs vibration compaction on the poured concrete, thereby realizing the simultaneous concrete and vibration compaction, without the need for subsequent separate vibration compaction, greatly improving the pouring and vibration compaction efficiency of the concrete wall, and accelerating the pouring progress;

[0021] 2. In the present invention, when the eccentric driving plate is separated from the driving member, the sliding plate drives the vibrating plate to move upward along the pouring pipe through the connecting rod under the pull of the tension spring, and the concrete discharged from the bottom of the pouring pipe is just located at the bottom of the vibrating plate, so that the equipment can be raised in height as the thickness of the concrete increases during the compaction process, ensuring that the equipment is always above the concrete to perform compaction treatment on the concrete;

[0022] 3. In the present invention, when vibrating and compacting concrete, the worker holds the operating arm to support the device, ensuring that the device is in a vertical state to vibrate and compact the concrete; as the pouring position changes, the worker needs to change the standing position, and since the slip ring is slidably connected to the housing, the worker holds the operating arm to arbitrarily change the standing position to support and compact the device;

[0023] 4. In the present invention, when it is necessary to move the compaction position of the equipment, the staff holds the handle and the hand brake with their hands, the hand brake flips, and the driving rod is pushed inward. At this time, the second driving block is pushed by the first driving block so that the plug shaft on the inner side of the second driving block is inserted into the fixed hole outside the annular slide groove, thereby realizing the fixation of the operating arm, the slip ring and the shell. Then the staff holds the two operating arms and pulls them left and right to change the casting position of the equipment, thereby realizing casting at different positions. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a three-dimensional structural schematic diagram of the present invention.

[0025] Figure 2 The present invention Figure 1 The left side structural diagram of .

[0026] Figure 3 The present invention Figure 1 Schematic diagram of the bottom structure.

[0027] Figure 4 The present invention Figure 1 Left view of .

[0028] Figure 5 The present invention Figure 4 AA section view.

[0029] Figure 6 The present invention Figure 5 BB cross-sectional view.

[0030] Figure 7 The present invention Figure 1 Schematic diagram of part of the structure.

[0031] Figure 8 The present invention Figure 1 Schematic diagram of the internal structure.

[0032] Fig. 9 It is a schematic diagram of the structure of the manipulator arm in the present invention.

[0033] In the figure: 1-concrete delivery pipe, 2-casting pipe, 3-bracket, 4-connecting rod, 5-vibrating plate, 6-dragon plate, 7-driving member, 8-manipulating arm, 9-slip ring, 10-housing, 11-driving motor, 12-driving assembly, 13-tension spring, 14-sliding plate, 15-annular slide groove, 16-fixing hole;

[0034] 121-driving shaft, 122-main gear, 123-driven gear, 124-first bevel gear, 125-second bevel gear, 126-eccentric driving disc;

[0035] 81 - support arm, 82 - handle, 83 - hand brake, 84 - driving rod, 85 - first driving block, 86 - second driving block. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] See also Figure 1-9 In an embodiment of the present invention, a civil construction pouring device includes a concrete conveying pipe 1, wherein the concrete conveying pipe 1 is connected to a pouring pipe 2, and a dragon piece 6 is arranged inside the pouring pipe 2; a driving assembly 12 is installed on the dragon piece 6; a vibrating plate 5 and a sliding plate 14 are slidably connected to the outside of the pouring pipe 2, wherein the sliding plate 14 is located above the vibrating plate 5; a connecting rod 4 is welded between the vibrating plate 5 and the sliding plate 14; two driving members 7 are fixed to the sliding plate 14 by bolts;

[0038] The driving assembly 12 includes a driving shaft 121 welded to the dragon piece 6, and a main gear 122 is mounted on the driving shaft 121. The two sides of the main gear 122 are meshed with driven gears 123. The two driven gears 123 are connected to the outer shell 10 through a rotating shaft, and the driven gear 123 is also coaxially provided with a first bevel gear 124; the first bevel gear 124 is meshed with a second bevel gear 125; the second bevel gear 125 is connected to the outer shell 10 through a rotating shaft, and is coaxially provided with an eccentric driving disk 126.

[0039] By adopting the above technical solution, when pouring the concrete pier, first connect the concrete delivery pipe 1 with the delivery pipe of the sky pump or the ground pump, then place the pouring pipe 2 in the support frame, and then the concrete is transported to the pouring pipe 2 through the concrete delivery pipe 1. At this time, the driving motor 11 drives the dragon piece 6 to rotate through the driving shaft 121, so as to realize the transportation of concrete, and the concrete is discharged from the bottom of the pouring pipe 2, so as to realize the pouring of the drainage concrete wall of the drainage system; during the pouring process, the main gear 122 drives the driven gear 123 to rotate, and drives the eccentric drive disk 126 coaxially arranged with the second bevel gear 125 to rotate under the engagement of the first bevel gear 124, and the eccentric drive disk 126 pushes the driving member 7 downward, and the driving member 7 slides downward against the sliding disk 14. Driven by the connecting rod 4, the vibrating disk 5 vibrates the poured concrete, thereby realizing the simultaneous pouring and vibrating of the concrete, without the need for subsequent separate vibrating treatment, which greatly improves the pouring and vibrating efficiency of the concrete wall and speeds up the pouring progress.

[0040] In this embodiment, a driving member 7 is disposed directly below the eccentric driving disk 126 . The driving member 7 is disposed in a T-shape, and an arc groove is formed on the top of the driving member 7 .

[0041] By adopting the above technical solution, the arc groove opened on the top of the driving member 7 is used to cooperate with the driving of the eccentric driving disk 126, and the two ends of the top of the driving member 7 are arranged in an arc shape, so that the cooperation between the eccentric driving disk 126 and the driving member 7 is smoother.

[0042] In this embodiment, the shell 10 is welded to the top of the casting pipe 2 , and a tension spring 13 is welded to the bottom of the shell 10 . The tension spring 13 is sleeved on the outside of the casting pipe 2 , and the bottom of the tension spring 13 is welded to the sliding plate 14 .

[0043] By adopting the above technical solution, when the eccentric driving disk 126 is separated from the driving member 7, the sliding disk 14 drives the vibrating disk 5 to move upward along the casting pipe 2 through the connecting rod 4 under the pull of the tension spring 13, and the concrete discharged from the bottom of the casting pipe 2 is just located at the bottom of the vibrating disk 5, so that the equipment can increase its height as the thickness of the concrete increases during the compaction process, ensuring that the equipment is always above the concrete and compacts the concrete.

[0044] In this embodiment, the concrete delivery pipe 1 is mounted on the inner side of the bracket 3; the bracket 3 is welded to the outer side of the casting pipe 2; and both sides of the lower end of the concrete delivery pipe 1 are provided with oblique openings for facilitating the discharge of concrete.

[0045] By adopting the above technical solution, since the concrete is discharged from the two sides and is located at the bottom of the vibration plate 5, and the vibration plate 5 is always in an up and down reciprocating state, the poured concrete is under the vibration plate 5, so that the whole equipment has the function of climbing, ensuring that the equipment is not submerged by concrete, and ensuring the normal pouring and compaction of the equipment

[0046] In this embodiment, an annular sliding groove 15 is provided on the outer side of the housing 10 to facilitate the sliding of the slip ring 9.

[0047] By adopting the above technical solution, when compacting the concrete, the staff holds the operating arm 8 to support the equipment to ensure that the equipment is in a vertical state to compact the concrete; a plurality of fixing holes 16 are opened in the annular slide groove 15; as the pouring position changes, the staff needs to change the standing position, and since the slip ring 9 is slidably connected to the outer shell 10, the staff holding the operating arm 8 can arbitrarily change the standing position to support and compact the equipment.

[0048] In this embodiment, a driving motor 11 is fixed to the top of the housing 10 , and the output shaft of the driving motor 11 is connected to the driving shaft 121 via a coupling.

[0049] In this embodiment, the control arm 8 is provided with two, which are respectively welded on both sides of the slip ring 9; the control arm 8 includes a support arm 81, which is arranged in a C-shape, one end of which is welded to the slip ring 9, and the other end of which is matched with a handle 82;

[0050] The interior of the support arm 81 is hollow, and one end of the support arm 81 close to the handle 82 is movably connected to a hand brake 83 via a rotating shaft. One end of the hand brake 83 extends into the interior of the support arm 81 and is movably connected to a driving rod 84 via a rotating shaft; a first driving block 85 is welded to one end of the driving rod 84 away from the hand brake 83, and a second driving block 86 is fittedly connected to one side of the first driving block 85.

[0051] To be more specific, the bottom of the second driving block 86 is slidably connected to the slide groove opened inside the support arm 81; the end of the second driving block 86 away from the first driving block 85 is welded with an insertion shaft that cooperates with the fixing hole 16; the position where the first driving block 85 and the second driving block 86 contact is provided with an inclined surface, and the first driving block 85 and the second driving block 86 are slidably connected through the inclined surface; the inner side of the end of the support arm 81 close to the handle 82 is provided with an open groove that facilitates the movement of the hand brake 83.

[0052] By adopting the above technical solution, when it is necessary to move the equipment to a compacting position, the staff will hold the handle 82 and the hand brake 83 with their hands, and the hand brake 83 will flip over to push the driving rod 84 inward. At this time, the second driving block 86 is pushed by the first driving block 85 so that the plug shaft inside the second driving block 86 is inserted into the fixing hole 16 outside the annular slide groove 15, thereby fixing the operating arm 8, the slip ring 9 and the outer shell 10. Then the staff can hold the two operating arms 8 and pull them left and right to change the casting position of the equipment, thereby realizing casting at different positions.

[0053] The working principle of the present invention is as follows: when pouring the concrete pier, firstly, the concrete delivery pipe 1 is connected to the delivery pipe of the sky pump or the ground pump, and then the pouring pipe 2 is placed in the support frame, and then the concrete is transported to the pouring pipe 2 through the concrete delivery pipe 1. At this time, the driving motor 11 drives the dragon piece 6 to rotate through the driving shaft 121, so as to realize the transportation of the concrete, and the concrete is discharged from the bottom of the pouring pipe 2, so as to realize the pouring of the drainage concrete wall of the drainage system; during the pouring process, the main gear 122 drives the driven gear 123 to rotate, and drives the eccentric driving disk 126 coaxially arranged with the second bevel gear 125 to rotate under the meshing of the first bevel gear 124, and the eccentric driving disk 126 pushes the driving member 7 downward, and the driving member 7 slides downward against the sliding disk 14, and driven by the connecting rod 4, the vibrating disk 5 performs a vibration compaction treatment on the poured concrete, thereby realizing the simultaneous pouring and compaction of the concrete, without the need for subsequent separate vibration compaction treatment, which greatly improves the pouring and compaction efficiency of the concrete wall and speeds up the pouring progress;

[0054] When the eccentric driving plate 126 is separated from the driving member 7, the sliding plate 14 drives the vibrating plate 5 to move upward along the pouring pipe 2 through the connecting rod 4 under the pull of the tension spring 13, and the concrete discharged from the bottom of the pouring pipe 2 is just located at the bottom of the vibrating plate 5, so that the equipment can be raised in height as the thickness of the concrete increases during the compaction process, ensuring that the equipment is always above the concrete to perform compaction on the concrete;

[0055] When vibrating the concrete, the worker holds the operating arm 8 to support the device to ensure that the device is in a vertical state to vibrate the concrete; as the pouring position changes, the worker needs to change the standing position. Since the slip ring 9 is slidably connected to the housing 10, the worker can hold the operating arm 8 to change the standing position arbitrarily to support the device for vibrating;

[0056] When the equipment needs to be moved to a new compacting position, the staff member holds the handle 82 and the hand brake 83 with their hands, and the hand brake 83 flips over to push the driving rod 84 inward. At this time, the second driving block 86 is pushed by the first driving block 85 so that the inner plug shaft of the second driving block 86 is inserted into the fixing hole 16 outside the annular groove 15, thereby fixing the operating arm 8, the slip ring 9 and the outer shell 10. Then the staff member holds the two operating arms 8 and pulls them left and right to change the casting position of the equipment, thereby realizing casting at different positions.

[0057] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention can be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered exemplary and non-limiting in all respects, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations falling within the meaning and scope of the equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered as limiting the claim to which it relates.

[0058] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A civil construction irrigation device, Features: The invention comprises a concrete conveying pipe (1), wherein the concrete conveying pipe (1) is connected to a casting pipe (2), wherein a dragon piece (6) is arranged inside the casting pipe (2); a driving assembly (12) is mounted on the dragon piece (6); a vibrating plate (5) and a sliding plate (14) are slidably connected to the outside of the casting pipe (2), wherein the sliding plate (14) is located above the vibrating plate (5); a connecting rod (4) is welded between the vibrating plate (5) and the sliding plate (14); and two driving members (7) are fixed to the sliding plate (14) by bolts; The driving assembly (12) comprises a driving shaft (121) welded to the dragon plate (6); a main gear (122) is mounted on the driving shaft (121); driven gears (123) are meshedly connected to the two sides of the main gear (122); the two driven gears (123) are connected to the housing (10) via a rotating shaft, and the driven gears (123) are also coaxially provided with a first bevel gear (124); the first bevel gear (124) is meshedly connected to the second bevel gear (125); the second bevel gear (125) is connected to the housing (10) via a rotating shaft, and is coaxially provided with an eccentric driving disc (126); A driving member (7) is arranged directly below the eccentric driving disk (126); the driving member (7) is arranged in a T-shape, and an arc-shaped groove is provided on the top of the driving member (7); The housing (10) is welded to the top of the casting pipe (2), and a tension spring (13) is welded to the bottom of the housing (10). The tension spring (13) is sleeved on the outside of the casting pipe (2), and the bottom of the tension spring (13) is welded to the sliding plate (14). The outer side of the housing (10) is provided with an annular groove (15) for facilitating the sliding of the slip ring (9), and a plurality of fixing holes (16) are provided in the annular groove (15). Two operating arms (8) are provided, which are respectively welded to two sides of the slip ring (9); the operating arm (8) comprises a support arm (81), which is arranged in a C-shape, one end of which is welded to the slip ring (9), and the other end of which is matched with a handle (82); The support arm (81) is hollow inside, and one end of the support arm (81) close to the handle (82) is movably connected to a hand brake (83) via a rotating shaft. One end of the hand brake (83) extends into the support arm (81) and is movably connected to a driving rod (84) via a rotating shaft. A first driving block (85) is welded to one end of the driving rod (84) away from the hand brake (83), and a second driving block (86) is attached to one side of the first driving block (85). The bottom of the second driving block (86) is slidably connected to a slide groove provided inside the support arm (81); an end of the second driving block (86) away from the first driving block (85) is welded with an insertion shaft that matches the fixing hole (16); A slope is provided at the position where the first driving block (85) and the second driving block (86) contact each other, and the first driving block (85) and the second driving block (86) are slidably connected via the slope; An opening groove is provided on the inner side of one end of the support arm (81) close to the handle (82) to facilitate the movement of the hand brake (83).

2. The civil construction watering device according to claim 1, Features: The concrete conveying pipe (1) is mounted on the inner side of the bracket (3); the bracket (3) is welded to the outer side of the pouring pipe (2); and both sides of the lower end of the concrete conveying pipe (1) are provided with oblique openings for facilitating the discharge of concrete.

3. The civil construction irrigation device according to claim 2, Features: A driving motor (11) is fixed to the top of the housing (10), and an output shaft of the driving motor (11) is connected to a driving shaft (121) via a coupling.

Citation Information

Cited By

  • Civil engineering pouring construction device and method

    CN120592227A