A method for the layout and support of roadways suitable for weakly cemented coal mining faces.
By calculating the angle of the roadway and controlling the surrounding rock, optimizing the layout and support of the roadway, the safety and cost issues in the mining of weakly cemented coal seams were solved, and safe and efficient mining was achieved.
Patent Information
- Application Number
- CN202310955600.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-08-01
- Publication Date
- 2026-11-17
- Estimated Expiration
- 2043-08-01
AI Technical Summary
In coal seam mining in weak cementation areas, an excessively large angle in the side roadway leads to excessive pressure during mining, causing safety issues. An excessively small angle results in long roadways and high costs, affecting the safe and efficient mining of the working face.
By calculating the pressure step distance and the weight of the overlying strata, a reasonable range of the waist tunnel angle is determined. During the tunneling process, the support is designed according to the suspension theory and the loosening ring theory. Combined with borehole pressure relief, the opening position of the waist tunnel and the cross-sectional size of the tunnel are optimized, and the surrounding rock control and support design are carried out.
It achieved safe control of the surrounding rock in the tunnel, improved mining efficiency, reduced comprehensive support costs, solved the problem of difficult mining continuity, and ensured the safe and rapid passage of the working face.
Smart Images

Figure CN117090595B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of mining engineering technology, and in particular to a method for the layout and support of roadways suitable for weakly cemented coal mining faces. Background Technology
[0002] In coal seam mining areas with weak cementation, the shallow double-lane layout becomes less suitable as mining depth increases, leading to tight mining and excavation succession. The use of a waist-lane tunnel in the coal face can effectively solve this problem. Since the roof and floor of coal mines are mostly composed of weakly cemented soft rock, a double-lane layout with a wide coal face necessitates the use of a waist-lane tunnel to address the mining and excavation succession issue.
[0003] When the angle of the waist roadway is too large, it needs to be adjusted during mining to prevent excessive pressure from causing large-scale roof collapse, fall, or even crushing the hydraulic supports, leading to safety issues and seriously affecting the safe and efficient mining of the working face. When the angle of the waist roadway is too small, the waist roadway is long, resulting in a long construction period, high costs, and rendering it impractical. To ensure the safe and smooth mining of the working face through the waist roadway, it is necessary to provide a waist roadway layout method and surrounding rock control method to ensure the safe, smooth, and stable passage of the waist roadway, maximize work efficiency, reduce comprehensive support costs, and effectively solve the problem of mining continuity. Summary of the Invention
[0004] In order to rationally arrange the waist roadway, effectively control the surrounding rock of the waist roadway, and improve the mining efficiency, this invention provides a waist roadway arrangement and support method suitable for weak cemented coal mining faces. The specific technical solution is as follows.
[0005] A method for the layout and support of roadways suitable for weakly cemented coal mining faces, comprising the following steps:
[0006] S1. Determine the angle of the tunnel, including calculating the pressure step distance and the weight of the overlying strata, and calculating and determining the angle range based on the number of supports within the range;
[0007] S2. Determine the opening location of the waist roadway. Based on the arrangement of the conveyor belt roadway excavation and the mining direction of the previous working face, determine the farthest and shortest distances of the waist roadway opening.
[0008] S3. Determine the cross-sectional dimensions of the tunnel. The dimensions of the tunnel end face are determined based on ventilation, pedestrian and vehicle passage requirements.
[0009] S4. Determine the surrounding rock control and support design for the tunnel, including designing according to the suspension theory and loosening zone theory during tunneling, verifying the roof support during mining, and drilling to relieve pressure in risk areas.
[0010] Preferably, the determination of the angle of the waist alley includes:
[0011] S11. Determine the pressure step distance L based on mine monitoring results and mining design.ci Length L of hydraulic support section a Based on geometric relationships:
[0012]
[0013] Where α is the angle between the waist lane and the roadway, and 0 < α < 90°;
[0014] S12. Determine the length L1 of the hydraulic support and calculate the number of hydraulic supports.
[0015] S13. Based on the working resistance f of the hydraulic support, determine the overall bearing capacity of the support as follows:
[0016] S14. Determine the thickness of the overlying fractured rock strata as H, H = h1 + h2, where h1 is the thickness of the immediate top and h2 is the thickness of the basic top.
[0017] S15. Determine the weight F0 of the overlying strata, F0 = γ(h1 + h2) × L ci ×L a , where γ is the average unit weight of the overlying strata;
[0018] S16. According to the force-resistance equation of the support:
[0019]
[0020] Where F 煤 This represents the bearing capacity of the triangular coal seam in front of the support.
[0021] Preferably, the waist-alley angle α satisfies the following relationship
[0022]
[0023] Calculate and determine the minimum angle of the waist lane.
[0024] Preferably, the selection of the location of the waist alley opening includes:
[0025] The farthest distance S′ of the opening of the alleyway is determined as follows:
[0026]
[0027] The farthest distance S″ of the opening of the alleyway is determined as:
[0028]
[0029] Among them, the distance from the opening position to the longwall face is S, the width of the longwall face is S1, the safe distance between the opening of the waist roadway and the longwall face is S2, the length of the waist roadway is S3, the time to complete the waist roadway is t, the waist roadway excavation speed is v1, the longwall face mining speed is v2, and the waist roadway angle is α.
[0030] Preferably, when the conveyor belt roadway reaches the stable area of the goaf, a side roadway is excavated at an angle in the direction of the goaf roadway, and a return air roadway is simultaneously excavated from the side roadway in the direction of the goaf roadway to the working face.
[0031] Furthermore, it is preferable that during the mining process, the peak value of the support pressure on the waist roadway is F. 支承 After support, the internal friction angle and cohesion of the rock mass increase, which increases the uniaxial compressive strength of the rock mass and the shear strength reaches τ1.
[0032] The middle section of the alleyway is also preferred:
[0033] When τ1>F 支承 At 2 o'clock, basic support was completed;
[0034] When τ1≤F 支承 When the shear strength is τ1, reinforcement is required, including adding anchor bolts, installing individual columns, and setting up timber piers for reinforcement, to ensure that the shear strength of the top rock stratum τ1 > F. 支承 / 2.
[0035] Furthermore, the locations at both ends of the alleyway are preferred:
[0036] At the junction of the roadway and the main roadway, single pillars are installed along the mining side of the main roadway, at the corners of the roadway, and in the center of the roadway. The reasonable support strength P of the end roadway is calculated and determined to be greater than the reasonable support strength. The rated working resistance of the support is selected as T, and the support load after the pillar is installed is determined to be T. The support load T is less than the rated working resistance of the support, and the support is completed.
[0037] A further preferred option is that the reasonable support strength in the advance range is P = ghγk, where h is the roadway height, γ is the unit weight of the roof strata, and k is the ratio of the thickness of the overlying strata to the mining height.
[0038] The support load after the support column is installed is T = PLB, where L is the length of the support bearing range and B is the width of the support top beam.
[0039] A further preferred option is that at the junction of the waist roadway and the roadway, the weight of the roof strata is M, the bearing capacity of the hydraulic support within the pressure step distance is F, and the coal bearing capacity is F1. When F+F1 is less than M, reinforcement support is required. The required support bearing capacity is M-(F+F1). The support strength is increased by installing timber stacks or supports to complete the support.
[0040] The beneficial effects of the waist roadway layout and support method for weakly cemented coal mining faces provided by this invention include:
[0041] (1) The reasonable layout of the waist roadway effectively solved the problem of the difficulty of coal mine mining continuity and provided support for safe and efficient coal mine production.
[0042] (2) The range of the waist tunnel angle is calculated by pressing the step distance during the mining period and combined with the relationship of rock mechanics during the mining period to ensure the rationality of the waist tunnel angle; the surrounding rock control scheme during the waist tunnel excavation and mining is integrated to realize the integrated design of the waist tunnel surrounding rock control and ensure the safety of the entire process of waist tunnel construction and use.
[0043] (3) This method can perform the support strength calculation in advance when passing through the waist roadway, so that the mining face can pass through the waist roadway safely and quickly, thereby accelerating the mining progress of the working face, greatly saving costs and improving mining efficiency. Attached Figure Description
[0044] Figure 1 This is a flowchart of the layout and support methods for the waist roadway in weakly cemented coal mining faces.
[0045] Figure 2 This is a flowchart for calculating the angle of the waist alley;
[0046] Figure 3 Schematic diagram of the working face and the side tunnel layout;
[0047] Figure 4 This is a schematic diagram showing the location of the opening in the alleyway;
[0048] Figure 5 This is a schematic diagram of the layout of the alleyway openings;
[0049] Figure 6 This is a schematic diagram of the stress analysis of the support structure;
[0050] Figure 7 This is a schematic diagram of the support structure and stress analysis;
[0051] Figure 8 This is the support verification flowchart;
[0052] Figure 9 This is a schematic diagram of the stress analysis of the tunnel;
[0053] Figure 10 This is a schematic diagram of the layout of the alleyway;
[0054] In the diagram: 1-Waistway, 2-Gateway, 3-Cutoff, 4-Hydraulic support, 5-Direct roof, 6-Basic roof, 7-Goaf, 8-Coal body, 9-Anchor bolt, 10-Anchor cable, 11-Single pillar, 12-Advanced support. Detailed Implementation
[0055] Combination Figures 1 to 10 As shown, the specific implementation method of the waist roadway layout and support method for weakly cemented coal mining faces provided by the present invention is as follows.
[0056] Example 1
[0057] A method for the layout and support of roadways suitable for weakly cemented coal mining faces, comprising the following steps:
[0058] S1. Determine the angle of the tunnel, including calculating the pressure step distance and the weight of the overlying strata, and calculating and determining the angle range based on the number of supports within the range;
[0059] Based on experience and practical considerations, the layout of waist-shaped tunnels requires consideration of factors such as the tunnel opening location, angle, and width. Specifically, when designing the tunnel angle, it's crucial to avoid excessively small angles. A small angle results in a long tunnel length, prolonged construction period, high costs, and diminished practical value. Conversely, an excessively large angle necessitates adjustment during mining to prevent excessive pressure leading to large-scale roof collapses, falls, or even exceeding the rated working resistance of the hydraulic supports, causing safety issues and severely impacting safe and efficient mining operations. Based on these two aspects, the angle range for the waist-shaped tunnels is designed. The determination of the waist-shaped tunnel angle includes:
[0060] S11. Based on the on-site mine monitoring results and mining design, combined with theoretical analysis, determine the pressure step distance L. ci Length L of hydraulic support section a Based on geometric relationships:
[0061]
[0062] Where α is the angle between the waist lane and the roadway, and 0 < α < 90°;
[0063] S12. Determine the length L1 of the hydraulic support and calculate the number of hydraulic supports.
[0064] S13. Based on the working resistance f of the hydraulic support, determine the overall bearing capacity of the support as follows:
[0065] S14. Determine the thickness of the overlying fractured rock strata as H, H = h1 + h2, where h1 is the thickness of the immediate top and h2 is the thickness of the basic top.
[0066] S15. Determine the weight F0 of the overlying strata, F0 = γ(h1 + h2) × L ci ×L a , where γ is the average unit weight of the overlying strata;
[0067] S16. To prevent the hydraulic supports at the working face from being crushed, the relationship between the waist tunnel and the support is determined based on the forces acting on the supports:
[0068]
[0069] Where F 煤 This represents the bearing capacity of the triangular coal seam in front of the support.
[0070] The angle α of the waist alley satisfies the following relationship
[0071]
[0072] Calculate and determine the minimum angle of the waist lane.
[0073] This process calculates the pressure step distance and the weight of the overlying rock strata, and determines whether the angle requirement is met based on the number of supports within the range. According to force balance, the weight of the overlying rock strata should be less than the rated working resistance of the hydraulic supports. During the design phase, the pressure step distance L during the mining process needs to be measured. ci To determine the type of support, collect parameters such as support length L1 and rated working resistance f, obtain the direct roof thickness h1 and basic roof thickness h2, and finally obtain the average unit weight γ of the overlying strata and the bearing capacity F of the coal seam. 煤 Substitute the values into the formula to calculate the minimum angle requirement.
[0074] When the waist roadway is excavated to the goaf along the roadway at a certain angle, it must be located in a stable position of the surrounding rock on the goaf side. Therefore, the location of the waist roadway opening is crucial. The distance from the opening location to the longwall face is S, the width of the longwall face is S1, the safe distance between the waist roadway opening and the longwall face is S2, the length of the waist roadway is S3, the time to complete the waist roadway excavation is t, the waist roadway excavation speed is v1, the longwall face mining speed is v2, and the waist roadway angle is α. The selection of the waist roadway opening location includes:
[0075] When the conveyor belt roadway is excavated to the direction of the previous working face's mining operation, the length of the waist roadway... Then the time it takes for the alley to be dug Time for pushing through the safe distance The farthest distance S′ of the opening of the alleyway is determined as follows:
[0076]
[0077] When the conveyor belt roadway is excavated to a point opposite to the mining direction of the previous working face, similarly, the farthest distance S″ for determining the opening of the waist roadway can be:
[0078]
[0079] When the conveyor belt roadway reaches the stable area of the goaf, the waist roadway is obliquely excavated in the direction of the goaf roadway. At the same time, the return air roadway is excavated from the waist roadway to the working face. After the inner section of the return air roadway is completed, the goaf in the outer section also enters the stable state of the surrounding rock. Excavating the outer section of the roadway from the inside to the outside and from the outside to the inside can significantly improve the problem of coal mine mining continuity.
[0080] S2. Determine the opening location of the waist roadway. Based on the arrangement of the conveyor belt roadway excavation and the mining direction of the previous working face, determine the farthest and shortest distances of the waist roadway opening.
[0081] S3. Determine the cross-sectional dimensions of the tunnel. The dimensions of the tunnel end face are determined based on ventilation, pedestrian and vehicle passage requirements.
[0082] S4. Determine the surrounding rock control and support design for the tunnel, including designing according to the suspension theory and loosening zone theory during tunneling, verifying the roof support during mining, and drilling to relieve pressure in risk areas.
[0083] The support during tunneling is designed according to the suspension theory or the loosening ring theory.
[0084] When the conveyor belt roadway reaches the stable area of the goaf, the waist roadway is excavated at an angle in the direction of the goaf roadway. At the same time, the goaf roadway is excavated from the waist roadway to the working face as the return air roadway.
[0085] During the mining process, the waist roadway is affected by the support pressure, and the peak value of the support pressure is F. 支承 To prevent the roof from collapsing under the support pressure, the strength of the roof support needs to be tested. After basic support is provided, the internal friction angle and cohesion of the rock mass increase, thereby increasing the uniaxial compressive strength of the rock mass and reaching the shear strength τ1.
[0086] The middle section of Yaoxiang Alley:
[0087] When τ1>F 支承 When the support reaches 2 / 2, the basic support is completed, and the support of special areas can be appropriately strengthened.
[0088] When τ1≤F 支承 When the shear strength is τ1, reinforcement is required, including adding anchor bolts, installing individual columns, and setting up timber piers for reinforcement, to ensure that the shear strength of the top rock stratum τ1 > F. 支承 / 2.
[0089] The two ends of the alley:
[0090] At the junction of the roadway and the main roadway, single pillars are installed along the mining sidewalls of the main roadway, at the corners of the roadway, and in the center of the roadway. At the end roadway, the reasonable support strength for the advance range is calculated using the formula P = ghγk (where P is the reasonable support strength within the advance range of the roadway, h is the roadway height, γ is the unit weight of the roof strata, and k is the ratio of the thickness of the overlying strata to the mining height). The calculated support strength should be greater than P. Using the rated working resistance of the support as T, the support strength after installing the pillars is calculated as T = PLB (where T is the support load, L is the length of the support's bearing capacity, and B is the width of the support's top beam). The calculated support load T is less than the rated working resistance of the support, thus meeting the support requirements.
[0091] At the junction of the waist roadway and the roadway, the weight of the roof strata is M, the bearing capacity of the hydraulic support within the pressure step distance is F, and the coal bearing capacity is F1. When F+F1 is less than M, the support needs to be reinforced. The required support bearing capacity is M-(F+F1). The support strength is increased by installing timber stacks or supports to meet the support requirements.
[0092] For areas with potential safety risks, large-diameter boreholes and other pressure relief measures are taken in advance. The mining process is adjusted in real time based on the mining pressure manifestation during the mining process.
[0093] This method effectively solves the problem of difficult coal mine excavation continuity by rationally arranging the waist roadways, providing support for safe and efficient coal mine production. By calculating the step distance during mining and combining it with the relationship of rock mechanics during mining, the range of waist roadway angles is calculated to ensure the rationality of the waist roadway angles. The method integrates the surrounding rock control schemes during waist roadway excavation and mining to achieve integrated design of waist roadway surrounding rock control, ensuring safety throughout the construction and use of waist roadways, saving costs and improving mining efficiency.
[0094] Example 2
[0095] Taking the 11307 working face of a certain mine as an example, this paper illustrates an application example of the waist roadway layout and support method for weakly cemented coal mining faces provided by the present invention.
[0096] Layout of the roadway: In the 11307 working face of a certain mine, the pressure step distance is approximately 20m, which is taken as 20m; the support model is ZY13000 / 24 / 50D, the rated working resistance is 13000KN, and the support width is 1750mm; the thickness of the direct roof plus the basic roof is taken as 30m; the average unit weight of the overlying strata is approximately 25KN / m³. 3 According to calculations, the bearing capacity of the coal seam at this location is approximately 95,000 kN. Substituting this into the formula, the minimum angle of the side roadway is approximately 57°. Based on design calculations and empirical analysis, the angle of the side roadway is determined to be 60°. When the conveyor belt roadway reaches 1500 m, it will advance towards the return air roadway at a 60° angle, and continue advancing towards the working face of the return air roadway to reach the inner section of the return air roadway.
[0097] Based on the requirements for ventilation, pedestrian access, and vehicle traffic, and taking into account the actual site conditions, the tunnel dimensions were determined to be 5100×3900mm.
[0098] Surrounding rock control:
[0099] Support design during tunneling: Based on suspension theory, the selection of anchor bolts is calculated and determined. The fine wire anchor bolts are arranged in a rectangular pattern, with a row spacing of 700×1000mm at the top and 800×1000mm at the side; used in conjunction with other anchor bolts. The anchor cables are spaced 1500×1000mm apart and arranged in a 4-3-4 configuration.
[0100] Design of reinforcement support during mining: For the middle section, the basic support is insufficient to meet the safety requirements during the passage through the waist roadway. Reinforcement is achieved by installing individual pillars and timber stacks. Three rows of individual pillars are installed on the west side of the waist roadway, with a pillar spacing of 1000mm and a row spacing of 1000mm, totaling 50 individual pillars and 240 timber stacks. For the end roadways, the support strength is calculated to be greater than 934.92 KN / m using the formula P = ghγk. 2 The current support cannot meet the support safety requirements. At the junction of the waist roadway and the roadway, an advanced support is installed along the mining direction of the roadway. After installation, the support load T is 10174.97KN, which is less than the rated working resistance of the reinforcement support of 13000KN, thus meeting the support requirements. Inside the waist roadways at both ends, a row of connected timber stacks is installed on the east side of the waist roadway to finally meet the support requirements.
[0101] This method allows for advance calculation of support strength when passing through the cross-tunnel, enabling the longwall face to pass through the cross-tunnel safely and quickly, thus improving longwall mining efficiency.
[0102] Of course, the above description is not intended to limit the present invention, and the present invention is not limited to the examples given above. Any changes, modifications, additions or substitutions made by those skilled in the art within the scope of the present invention should also fall within the protection scope of the present invention.
Claims
1. A method of arranging and supporting a breast entryway suitable for use in weakly cemented coal mining faces, characterized by the steps of include: S1. Determine the angle of the tunnel, including calculating the pressure step distance and the weight of the overlying strata, and calculating and determining the angle range based on the number of supports within the range; S2. Determine the opening location of the waist roadway. Based on the arrangement of the conveyor belt roadway excavation and the mining direction of the previous working face, determine the farthest and shortest distances of the waist roadway opening. S3. Determine the cross-sectional dimensions of the tunnel. The dimensions of the tunnel end face are determined based on ventilation, pedestrian and vehicle passage requirements. S4. Determine the surrounding rock control and support design for the tunnel, including designing according to the suspension theory and loosening zone theory during tunneling, verifying the roof support during mining, and drilling to relieve pressure in risk areas; The determination of the angle of the waist alley includes: S11. Determine the step distance L of the pressure according to the mine monitoring results and mining design ci , the length L of the hydraulic support supporting section a ; According to the geometric relationship: ; Where α is the angle between the waist lane and the roadway, and 0 < α < 90°; S12. Determine the length L1 of the hydraulic support, and calculate the number of hydraulic supports as ; S13. According to the hydraulic support working resistance f, the carrying capacity of the support as a whole is determined as ; S14. Determine the thickness of the overlying fractured rock layer as H, H = h1 + h2, where h1 is the thickness of the immediate top and h2 is the thickness of the basic top. S15. Determine the overburden weight F0, F0= γ (h1+ h2) x L ci x L a where γ is the average unit weight of the overburden. S16. According to the force-resistance equation of the support: ; wherein is the bearing capacity of the triangular coal body in front of the support.
2. The method according to claim 1, characterized in that, The selection of the location of the alleyway opening includes: The farthest distance S from the opening of the alleyway is determined as follows: ; Alternatively, the farthest distance S' of the opening of the alleyway can be determined as: ; Among them, the distance from the opening position to the longwall face is S, the width of the longwall face is S1, the safe distance between the opening of the waist roadway and the longwall face is S2, the length of the waist roadway is S3, the time to complete the waist roadway is t, the waist roadway excavation speed is v1, the longwall face mining speed is v2, and the waist roadway angle is α.
3. A gate layout and support method for use on a weakly bonded coal face as claimed in claim 2 wherein, When the conveyor belt roadway reaches the stable area of the goaf, the waist roadway is excavated at an angle in the direction of the goaf roadway. At the same time, the return air roadway is excavated from the waist roadway to the working face.
4. The method according to claim 1, characterized in that, During the mining process, the peak value of the support pressure of the waist lane is F 支承 , the internal friction angle and cohesion of the rock mass after supporting increase, which increases the uniaxial compressive strength of the rock mass and the shear strength reaches τ1.
5. The method according to claim 1, characterized in that, The middle section of the aforementioned alley: When τ1>F 支承 / 2, the basic support is completed. When τ1≤F 支承 / 2, the support needs to be reinforced, the anchor rod and cable support is increased, the single column is set, the wood pile support is set to make the top rock layer shear strength τ1>F 支承 / 2.
6. The method of arranging and supporting the waist entry according to claim 1, characterized in that, The locations at both ends of the alley: At the junction of the roadway and the main roadway, single pillars are installed along the mining side of the main roadway, at the corners of the roadway, and in the center of the roadway. The reasonable support strength P of the end roadway is calculated and determined to be greater than the reasonable support strength. The rated working resistance of the support is selected as T, and the support load after the pillar is installed is determined to be T. The support load T is less than the rated working resistance of the support, and the support is completed.
Citation Information
Patent Citations
Ventilation method for use during mining of easily spontaneous combustion coal seam face
CN104594937A
Main control and roadway retaining method for anchor injection and top-cutting in deep mining roadway
CN108678769A