Methods and apparatus for managing engineering
By dividing the project into construction work packages and using a grid to display the construction status and the status of the work front, the problem of difficulty in identifying the construction status in the existing technology is solved, and the automated management of the construction schedule and risk identification are realized.
Patent Information
- Application Number
- CN202280028272.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-24
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2042-08-24
AI Technical Summary
Existing construction project management systems struggle to collect and merge drawings and material status in real time, leading to difficulties in identifying construction status, identifying high-risk sub-projects, and managing construction status and constructability information intuitively.
The project is divided into the smallest unit areas and construction work packages by dividing the project into units. Combined with design information, the construction status and front-line status are displayed in a grid form using display units. The construction progress is calculated by simulating procurement and material matching, and the risk level is identified.
It enables automated management of construction schedules, collects and shares project information, identifies construction risk levels, automatically calculates the number of work fronts, and supports proactive construction management.
Smart Images

Figure CN117136372B_ABST
Abstract
Description
Technical Field
[0001] This disclosure relates to apparatus and methods for managing engineering projects, which are used to develop project schedules and manage performance status through information exchange during design, procurement, and construction. Background Technology
[0002] Construction project management systems often fail to consider drawings and material status, or only consider either material status or drawings. Therefore, for smooth construction, a comprehensive project management system configured to collect and merge all drawings and material statuses in real time is needed.
[0003] Furthermore, because the construction project is being carried out simultaneously in dozens of areas, it is difficult to identify the construction status and the constructability of sub-projects in any given area, and this information is collected manually. In addition, it is difficult to visually identify sub-projects with high risks. Summary of the Invention
[0004] Technical issues
[0005] Preferred embodiments of this disclosure provide an apparatus and method for managing projects by intuitively identifying construction status and the constructability of the project, and classifying and identifying risk levels.
[0006] Technical solution
[0007] According to a preferred embodiment of this disclosure, the project management device includes: a partitioning unit configured to divide a project into n construction work packages (CWPs) based on the construction type constituting the project, the minimum unit area for managing the project, and design information; and a display unit configured to display the project status and work front status. The statuses classify n Construction Work Plans (CWPs) and display them in a grid. When the construction type is piping, the work front status is calculated based on both the present and future. When calculating the work front status based on the future, the work front status of each individual component is calculated by three independent sequential simulations. The work front status of each individual component is calculated by matching the procured and planned materials with the line group based on a preferred order. Then, the work front status of each individual component is added together based on the CWP to obtain the CWP-based work front status. The three independent sequential simulations are performed in the following order: welding drawings, i.e., detailed drawings for performing actual line-based construction, where the line is a separate component of the pipe; ISO drawings, which serve as drawings before preparing detailed construction drawings; and 3D drawings, which serve as drawings before preparing line drawings.
[0008] Beneficial effects
[0009] In a preferred embodiment of this disclosure, the project management device can collect construction schedule plans and performance data, and can automatically calculate the daily work front quantity (the quantity that can be constructed). Furthermore, it classifies and manages risk levels based on the construction status and work front status (the status of the quantity that can be constructed).
[0010] In a preferred embodiment of this disclosure, the project management device can automatically collect and share information on design drawings, material procurement, and construction in a construction project, thus enabling the development of a construction plan through proactive construction management.
[0011] In a preferred embodiment of this disclosure, the project management device can define construction work packages (CWPs) as construction objectives, where each CWP corresponds to a bundle of individual constituent units defined in the design. Therefore, based on the construction objectives, design, procurement, and construction data can be automatically collected by a given system.
[0012] In a preferred embodiment of this disclosure, the engineering management device can simultaneously reflect drawing and material data received from the operating system used by the person in charge. Therefore, the work front line, which is a separate unit, can be used independently according to the three types of drawing, materials, and drawing and materials.
[0013] In addition, the project management device can automatically output six statuses of CWP (before start, start this month, in progress, late start, late end, and completed) based on the current month and future time points (three months later) by using performance data (start date, end date, and actual quantity) of individual construction targets automatically collected according to the planned schedule. Attached Figure Description
[0014] Figure 1 This is a diagram illustrating the internal configuration of an engineering management device according to a preferred embodiment of the present disclosure.
[0015] Figure 2 A system diagram of an engineering management apparatus according to a preferred embodiment of the present disclosure is provided.
[0016] Figures 3A to 3C A diagram illustrating the sequence and criteria for calculating construction status in an engineering management apparatus according to a preferred embodiment of the present disclosure.
[0017] Figure 4 A diagram illustrating the planning standards for a Construction Work Package (CWP) according to a preferred embodiment of the present disclosure.
[0018] Figure 5 The diagram illustrates an example of an enterprise resource planning (ERP) database automatically collecting construction performance, design performance, and procurement performance based on individual constituent units according to a preferred embodiment of the present disclosure.
[0019] Figure 6 A graph is provided to illustrate the necessary and resulting data according to a preferred embodiment of the present disclosure, wherein the necessary and resulting data are required to output the working front-line status.
[0020] Figure 7 The diagram illustrates the necessary data required for calculating the work front status according to a preferred embodiment of the present disclosure, as well as examples of work front types for construction.
[0021] Figure 8 A diagram illustrating an example of calculating the number of work fronts based on construction type according to a preferred embodiment of this disclosure.
[0022] Figure 9A and Figure 9B The figure illustrates an example of determining a CWP-based construction state after determining the construction state of individual constituent units according to a preferred embodiment of the present disclosure.
[0023] Figures 10A to 10CThe diagram illustrates an example of performing three simulations sequentially according to the order of drawings (3D, ISO, and welding drawings) for lines as individual constituent units in order to calculate future construction quantities, according to a preferred embodiment of the present disclosure.
[0024] Figure 11A and Figure 11B A flowchart illustrating the process of simulating the current number of working fronts according to a preferred embodiment of the present disclosure.
[0025] Figure 12A and Figure 12B A diagram illustrating an example of a CWP for pipes and steel frames categorized according to a preferred embodiment of the present disclosure, based on a future work front type 1.
[0026] Figures 13 to 15 A diagram illustrating the display unit of an engineering management apparatus according to a preferred embodiment of the present disclosure.
[0027] Best mode
[0028] According to a preferred embodiment of this disclosure, the project management device includes: a partitioning unit configured to partition a project into n construction work packages (CWPs) based on the construction type constituting the project, the smallest unit area for managing the project, and design information; and a display unit configured to classify the n CWPs according to the construction status and the work front status and display the n CWPs in a grid format, wherein, when the construction type is pipeline, the work front status is calculated based on both the present and the future. When calculating the work front status, the work front status of individual constituent units is calculated by matching the procured and planned materials with the line group based on a preferred order through three independent sequential simulations. Then, the work front status of individual constituent units is added together based on CWP to obtain the CWP-based work front status. The three independent sequential simulations are performed in the following order: welding drawings, i.e., detailed drawings for performing actual line-based construction, where the line is a separate constituent unit of the pipeline; ISO drawings, which serve as drawings before preparing detailed construction drawings; and 3D drawings, which serve as drawings before preparing line drawings.
[0029] In a preferred embodiment of this disclosure, the horizontal axis of the grid form of the display unit represents the construction status based on the stage, and the vertical axis of the grid form of the display unit represents the work front status based on the stage, wherein each grid frame of the grid form indicates information on the construction status and work front status, as well as information on the number of CWPs with the construction status and work front status.
[0030] In a preferred embodiment of this disclosure, the display unit displays risk information by using the position of the grid frame in the grid form.
[0031] In a preferred embodiment of this disclosure, when the information on the number of CWPs in each grid frame is clicked, only the CWP corresponding to the grid frame is selected from the n CWPs by filtering, and the detailed information of the selected CWP is displayed.
[0032] In a preferred embodiment of this disclosure, when the construction type includes piping, steel frame, machinery, and civil engineering, while considering at least one of drawing and materials according to the construction type of the project, the work front status of each individual constituent unit is first calculated based on the construction type, and then the work front status of each individual constituent unit is added together based on the CWP to obtain the CWP-based work front status.
[0033] According to a preferred embodiment of this disclosure, the project management method includes: dividing a project into n construction work packages (CWPs) by a partitioning unit based on the construction type constituting the project, the smallest unit area for managing the project, and design information; and classifying the n CWPs according to the construction status and the work front status by a display unit and displaying the n CWPs in a grid form on the display unit, wherein, when the construction type is pipeline, the work front status is calculated based on the present and the future, wherein, when calculating the work front status based on the future, the work front status of each individual constituting unit is calculated by matching the procured and planned materials with the line group based on a preferred order through three independent sequential simulations, and then the work front status of each individual constituting unit is added based on the CWPs to obtain the work front status based on the CWPs, wherein...
[0034] The three independent sequential simulations are performed in the following order: welding drawings, i.e., detailed drawings for performing actual line-based construction, where the lines are individual constituent units of the pipes; ISO drawings, which serve as drawings prior to the preparation of detailed construction drawings; and 3D drawings, which serve as drawings prior to the preparation of line drawings.
[0035] According to a preferred embodiment of this disclosure, the project management method includes: dividing a project into n construction work packages (CWPs) by a partitioning unit based on the construction type constituting the project, the smallest unit area for managing the project, and design information; and classifying the n CWPs according to the construction status and work front status by a display unit and displaying the n CWPs in a grid form on the display unit, wherein the horizontal axis of the grid form represents the construction status based on the stage, and the vertical axis of the grid form represents the work front status based on the stage, wherein each grid frame of the grid form indicates information on the construction status and work front status, as well as information on the number of CWPs with the construction status and work front status. Detailed Implementation
[0036] In the following description, this disclosure will be made readily understandable and applicable to those skilled in the art to which this disclosure pertains.
[0037] Figure 1 A diagram illustrating the internal configuration of an engineering management device 100 according to a preferred embodiment of the present disclosure. Figure 2 A system diagram of an engineering management device 100 according to a preferred embodiment of the present disclosure is provided.
[0038] The project management device 100 provides a platform for automatically collecting and sharing drawing data 210, material data 220, and construction information data 230 through an Enterprise Resource Planning (ERP) system used by the design, procurement, and construction managers to manage construction projects. The project management device 100 can calculate the work front quantity (workable quantity) by pre-executing construction management based on the collected work data, and can prepare a construction schedule based on the calculated quantity.
[0039] In a preferred embodiment of this disclosure, the project management device 100 includes a partitioning unit 110 and a display unit 120.
[0040] Division unit 110 divides a project into n sub-projects (Construction Work Packages, CWPs) based on the project's construction type, the smallest unit area used to manage the project, and design information. Display unit 120 categorizes the n CWPs based on their construction status and work front status (the number of workable units) and displays them in a grid format. An example of display unit 120 is shown below. Figures 13 to 15 middle.
[0041] In a preferred embodiment of this disclosure, the CWP can be used as a basic unit for project management. Referring to Table 1, each CWP can be defined as a group of individual constituent units. Figures 3A to 3C Based on the smallest unit area, a construction project 310 can be divided into 70 to 90 CWPs 311, and then further divided into 700 to 900 CWPs based on design information. An identification code can be assigned to each CWP 312 for differentiation. Additionally, each CWP can be mapped along with information about the area to which it belongs and the project to which it belongs.
[0042] Table 1
[0043]
[0044] In Table 1, Mhr refers to the amount of work a person does per hour.
[0045] In a preferred embodiment of this disclosure, the database can automatically collect plans 321, 322, and 323 developed for CWP. (As shown in...) Figure 4 In the example, the standards used for construction plan 410, design plan 420, and procurement plan 430 are all based on CWP. Each CWP is planned based on the same design information. In this case, the design information can be information about individual constituent units 401 such as lines, components, projects, and foundations.
[0046] When Figure 4 As shown, when a plan is developed for each CWP (Contract Development and Construction), performance information entered by the responsible personnel for design, construction, and procurement is automatically collected in the ERP database based on the plan. An example of collecting performance information in the ERP database is shown below. Figure 5 In the middle, the S-AWP project management device matches performance information automatically collected through the ERP database.
[0047] like Figure 5 In the example shown, when the execution results are entered into individual constituent units 501 of the company's data ERP 500 by each responsible person and collected, the construction status of the CWP can be classified based on the collected execution results. Based on the construction status of the CWP, the construction status of each individual constituent unit of the CWP is collected (S910), and the results are output based on the CWP (S920), as follows... Figure 9A and Figure 9B The example shown is illustrated in Table 2, which displays the construction status of each CWP based on monthly cut-offs: progress status based on future cut-offs and progress status based on today's current month.
[0048] Table 2
[0049]
[0050] Reference Figure 9A and Figure 9B The S-AWP project management device can divide the CWP construction schedule into six phases 921 to 926. Figure 4 The construction status of each CWP shown can also be used for CWP filtering based on the cutoff point. Figure 9A and Figure 9BThe six stages shown are "Before Start" 921, "Target Start to Deadline" 922, "In Progress" 923, "Late Start" 924, "Late Completion" 925, and "Completed" 926. "Before Start" 921 refers to the state where none of the individual components of the CWP have started. "Target Start to Deadline" 922 refers to the state where, from the start date of the CWP construction plan to a deadline such as this month's M, next month's M+1, the month after next's M+2, etc., none of the individual components have started. "In Progress" 923 refers to the state where at least one individual component of the CWP is in progress or completed without a late completion. "Late Start" 924 refers to the state where all individual components have started late but therefore have not been delayed in progress, termination, or completion. "Late Completion" 925 refers to the state where one or more individual components have been delayed in termination. Finally, "Completed" 926 refers to the state where all individual structural units have been completed.
[0051] Figure 6 The necessary data 610 and result data 620 required to output the work front status (workable quantity status) according to a preferred embodiment of this disclosure are shown. The project management device S-AWP can independently calculate the future work front status 612 based on the current and future deadlines using the current work front status 611 indicating the prepared drawings and materials, and the estimated time of arrival (ETA) and estimated drawing release date 613 as future-based data. The current work front status 611 refers to the quantity that can be started, and the future work front status 612 is used to determine the priority of design and procurement.
[0052] To enable proactive construction management, the S-AWP project management system calculates the number of work fronts for each construction type based on construction, design, and procurement information collected from each ERP database. Work front status 621 is determined by comparing the CWP-based construction plan with the CWP-based work front count.
[0053] A future plan (construction plan) is developed for each CWP by calculating the daily target construction quantity and today's target construction quantity from the total construction quantity planned over a period between the start and end dates of the target plan. The daily target construction quantity can be determined by "total planned construction quantity / (start date of the target plan - end date of the target plan)". However, the daily target construction quantity can vary depending on the allocation method. The cumulative daily target construction quantity refers to the cumulative daily target construction quantity based on today.
[0054] The CWP (Construction Work) front line can be determined using different information based on the characteristics of the construction type. For example... Figure 7 As shown,
[0055] Based on the characteristics of the construction type, the CWP work front can be classified into three types: Type 1 (Category 1) considering both drafting and materials; Type 2 (Category 2) considering only materials; and Type 3 (Category 3) considering only drafting. Figure 8 As shown, the CWP work front can be calculated by operation 810, which calculates the work front of each individual unit according to the construction type, and operation 820, which adds the work fronts 810 together based on the CWP.
[0056] The following is an example of calculating the working frontline based on individual constituent units. Figures 10A to 10C An example is shown in which the future construction quantity is calculated according to a preferred embodiment of this disclosure by performing three sequential simulations for lines as individual constituent units in the order of drawing (3D, ISO, and welding drawings). (Refer to...) Figures 10A to 10C In the example of pipeline construction, the construction priority of lines, as individual constituent units, is set between the start and end dates of the pipeline CWP plan. Furthermore, after collecting information on the drawing status, bill of materials (BOM), and the number of welds for each line from the ERP, the welding drawings are prepared using the information on the status shown in Figure 3. In Table 3, "Spool" refers to the line segment unit used for line fabrication and construction when outputting the welding drawings, and "Joint" refers to the weld joint area indicated in the welding drawings for actual construction.
[0057] Table 3
[0058]
[0059] Once the welding drawings are ready, calculate the piping work front for the shop and on-site. Prepare material lists for both the shop and on-site, and specify materials to exclude from the simulation. Calculate the required quantities for both future and present-day work. Future-based and present-based calculations are performed using different design and procurement information in the simulation shown in Table 4.
[0060] As an example, Table 4 shows the data required to calculate the future construction quantity status and the current construction quantity status. As an example, Table 5 shows the welding drawing materials matched for calculating the future construction quantity status. As an example, Table 6 shows the matching of ISO drawings and 3D materials for calculating the future construction quantity. Table 7 shows the resulting data obtained by calculating the future construction quantity status. Figure 8 This provides a reference for calculating future construction quantities.
[0061] Table 4
[0062]
[0063]
[0064] Table 5
[0065]
[0066] Table 6
[0067]
[0068]
[0069] Table 7
[0070]
[0071] Table 8
[0072]
[0073]
[0074] In a preferred embodiment of this disclosure, simulation can be performed using only welding diagrams when calculating the current construction quantity status. Table 8 shows the matching of procured and received materials to the line based on a preferred order, using welding diagram simulations based on the current individual constituent units. As an example, Table 9 shows the calculation results for the current construction quantity status. As an example, Table 10 shows the results of the current construction quantity calculation. Table 11 shows the criteria used for calculating the current construction quantity. Figure 11A and Figure 11B A flowchart illustrating a process simulating a current pipeline work frontline according to a preferred embodiment of this disclosure is provided. Even in steel framing, mechanical, and civil engineering, construction quantity status is calculated and categorized based on individual constituent units.
[0075] Table 9
[0076]
[0077] Table 10
[0078]
[0079] Table 11
[0080]
[0081] After calculating and classifying the construction quantity status based on individual constituent units of steel frames, machinery, and civil engineering, the work front is classified based on CWP. In this case, such as Figure 8 The example shown categorizes frontline work types according to construction type. Figure 12A and Figure 12B The preferred embodiment of the present disclosure shows that, in piping and steel frame work, the work front status is classified as CWP-based work front type 1 based on future and present work front status.
[0082] Figures 13 to 15 A display unit of an engineering management apparatus according to a preferred embodiment of the present disclosure is shown.
[0083] Reference Figure 13 and Figure 14 Describe an example of how CWPs are categorized and displayed in a grid format based on their construction status and frontline work status.
[0084] The display unit S1300 classifies the n CWPs based on the construction status S1310 and the frontline work status S1320.
[0085] CWP is displayed in a grid format. Figure 13 This section shows an example of classifying 792 CWP1301 units based on their construction status and frontline work status. Figure 13 In the diagram, the horizontal axis, in grid form, represents the construction status S1310 according to the stage, and the vertical axis, also in grid form, represents the work front status S1320 according to the stage. (See reference...) Figure 14 In the direction to the right along the horizontal axis (x-axis), the construction state S1410 where construction has started is shown, and then the construction state S1420 where construction has not started is shown.
[0086] The display unit 1300 indicates only a set of grid frames representing the construction status, and each grid frame contains information about the number of CWPs belonging to the corresponding construction progress stage. For example, Figure 13 This shows a set of six grid boxes: "Completed" 1311, "Late Completion" 1312, "Late Start" 1313, "In Progress" 1314, "Target Start" 1315, and "Before Start" 1316. (See reference...) Figure 13 Of the 792 CWPs in 1301, 175 were in “Late Completion” 1312, 95 were in “Late Start” 1313, 138 were in “In Progress” 1314, 57 were in “Target Start” 1315, and 105 were in “Before Start” 1316.
[0087] "Completed" 1311 means execution is complete. "Delayed Completion" 1312 means that while "Target Plan Completion" has entered the plan, the completion of at least one individual component is delayed in terms of performance. In the individual component category, foundation refers to civil engineering, component refers to steel frame work, project refers to machinery, and line refers to piping. "Delayed Start" 1313 means that while "Target Plan Start" has entered the plan, the start of all individual components is delayed in terms of performance. "In Progress" 1314 means that...
[0088] The "Target Plan Start" has arrived or is still pending this month, next month, or the month after next (M+1 / 2 / 3), and at least one individual component of the construction has commenced or been completed in terms of performance. "Target Start" 1315 refers to a state where "Target Plan Start" has been incorporated into the plan but construction has not yet commenced in terms of performance. Furthermore, "Before Start" 1316 refers to a state where "Target Plan Start" has not yet been incorporated into the plan and construction has not yet commenced in terms of performance.
[0089] The work front S1320 is classified as “W / FC” 1321, “without W / FE” 1322, and “without W / FP” 1323.
[0090] "W / FC" 1321 means that there is sufficient CWP at the work front, "W / FE" 1322 means that there is a CWP with a drafting shortage or a total shortage at the work front, and "W / FP" 1323 means that there is a CWP with a material shortage or a total shortage at the work front.
[0091] In a preferred embodiment of this disclosure, each grid cell indicates information about the construction status and the work front status. Additionally, each grid cell indicates the number of CWPs in both the construction status and the work front status.
[0092] For example, the first grid frame 1341 indicates "late completion" as a construction status, "no W / FP" 1323 as a work front status, and 63 (1341a)) as the number of CWPs. In a preferred embodiment of this disclosure, the risk level can be determined from the grid frame position in the grid pattern.
[0093] Grid frames 1341, 1342, 1343, and 1344, included in the first region 1340 of the grid panel 1330, are of high risk 1345. Figure 13Of the 792 CWPs, 222 have been completed, and 570 are in progress. Of these 570 CWPs, 138 are located in Zone 1340. In other words, approximately 25% of the 570 CWPs are classified as high-risk. Grid boxes 1351, 1352, 1353, and 1354, included in Zone 2, are classified as medium-risk (1355). Figure 13 Of the 570 CWPs currently in progress, 161 are included in Zone 2, 1350. In other words, approximately 29% of the 570 CWPs are classified as medium-risk CWPs. Grid boxes 1361, 1362, 1363, and 1364, included in Zone 3, are low-risk (1365). Figure 13 In the 570 ongoing CWPs,
[0094] 78 CWPs are included in Zone 3, 1360. In other words, approximately 15% of the 570 CWPs are classified as low-risk CWPs. Grid boxes 1371, 1372, and 1373, included in another zone 1370, are considered risk-free. Figure 13 Of the 570 CWPs currently in progress, approximately 31% are classified as risk-free CWPs.
[0095] In a preferred embodiment of this disclosure, the grid plate 1330 may use different colors to display a first area 1340, a second area 1350, a third area 1360, and another area 1370.
[0096] Figure 15 The grid frame of the display unit according to a preferred embodiment of the present disclosure has a filtering function. When the information 1542a indicating the number of CWPs in the grid frame 1542 of the grid panel is clicked, only one CWP corresponding to the grid frame 1542 is selected from n CWPs by filtering, and the detailed information of that CWP is displayed. When multiple CWPs are selected by filtering, the detailed information of each of the multiple CWPs is displayed. The detailed information includes construction type 1501, CWP boundary 1502 indicating the smallest unit area for project management, CWP identification code 1503 for identifying each CWP, CWP category 1504, individual constituent unit identification number 1505, construction schedule information 1520, and material quantity information 1530. The construction schedule information 1520 includes information on construction status 1521, target planned start date 1522, target planned end date 1523, actual construction start date 1524, and actual construction end date 1525. Material quantity information 1530 includes frontline work status information 1531, total material quantity information 1532, and target material quantity information 1533.
[0097] The method according to embodiments of this disclosure can be implemented as program instructions executable on various computers.
[0098] It may be recorded on a computer-readable medium. The computer-readable medium may store one or a combination of program instructions, data files, data structures, etc. The program instructions recorded on the computer-readable medium may be specifically designed and prepared for this disclosure, or may be known and available to those skilled in the art of computer software.
[0099] Although embodiments of the present disclosure have been described with reference to the accompanying drawings, the present disclosure is not limited to these embodiments.
[0100] Furthermore, those skilled in the art can make various changes in form and detail therein.
Claims
1. An engineering management device, comprising: The unit is configured to divide a project into n construction work packages (CWPs) based on the construction type that constitutes the project, the smallest unit area used to manage the project, and design information. as well as The display unit is configured to classify the n CWPs according to their construction status and frontline work status, and to display the n CWPs in a grid format. The construction types mentioned include pipelines, steel frames, machinery, and civil engineering. The project management device, while considering at least one of drawing and materials according to the construction type of the project, first calculates the front-line status of each individual component based on the construction type, and then adds the front-line status of each individual component based on the CWP to obtain the CWP-based front-line status. When the construction type is pipeline, the engineering management device calculates the front-line status of each individual component of the pipeline based on both current and future data, and the design information includes 3D, ISO drawings, and welding diagrams for each individual component of the pipeline. Specifically, when calculating the front-line status based on future needs, the engineering management device simulates the front-line status of each individual component unit in three independent sequences according to the priority of the lines. Specifically, in the simulation of welding diagrams, the materials required for each spool of the line are matched with the already arrived and expected-to-arrive purchased materials; in the simulation of ISO drawing and 3D modeling, the materials required for each line are matched with the already arrived and expected-to-arrive purchased materials. The three independent sequential simulations are performed in the order of welding drawings, ISO drawings, and 3D modeling. The welding drawings are detailed drawings used for performing line-based actual construction, where the lines are individual structural units of the pipes. The ISO drawings are prepared before the detailed construction drawings are made. The 3D modeling is prepared before the line drawings are made. Wherein, the horizontal axis of the grid represents the construction status based on the stage, and the vertical axis of the grid represents the work front status based on the stage. Each grid cell in the grid indicates information about the construction status and work front status, as well as information about the number of CWPs with the construction status and work front status. The diagram shows the construction status of projects that have started, in the rightward direction along the horizontal axis, followed by the construction status of projects that have not yet started. The display unit displays risk information by using the position of the grid frame in the grid form.
2. The engineering management device according to claim 1, wherein, When the information on the number of CWPs in each grid box is clicked, the CWPs corresponding to the grid box are selected from the n CWPs by filtering, and the detailed information of the selected CWPs is displayed.
3. The engineering management device according to claim 1, wherein, The display unit further includes a set of grid frames that indicate only the construction status, and the set of grid frames includes information on the number of CWPs with the corresponding construction status.
4. The engineering management device according to claim 1, wherein, When calculating the current state of the work front, only the welding diagram is simulated, and the materials required for each spool of the line are matched with the purchased materials that have arrived, according to the priority of the lines.
5. An engineering management method, comprising: A project is divided into n construction work packages (CWPs) based on the construction type that constitutes the project, the smallest unit area used to manage the project, and design information. as well as The display unit categorizes the n CWPs according to their construction status and frontline work status, and displays the n CWPs in a grid format on the display unit. The construction types mentioned include pipelines, steel frames, machinery, and civil engineering. Specifically, while considering at least one of drawing and materials based on the construction type of the project, the front-line status of each individual component is first calculated based on the construction type. Then, the front-line status of each individual component is added together based on the CWP to obtain the CWP-based front-line status. When the construction type is pipeline, the front-line status of each individual component of the pipeline is calculated based on both the present and future, and the design information includes 3D, ISO drawings, and welding diagrams for the lines that are individual components of the pipeline. Specifically, when calculating the front-line status based on future needs, the front-line status of each individual component unit is simulated in three independent sequences according to the priority of the lines. In the simulation of the welding diagram, the materials required for each spool of the line are matched with the already arrived and expected-to-arrive purchased materials. In the simulation of ISO drawing and 3D modeling, the materials required for each line are matched with the already arrived and expected-to-arrive purchased materials. The three independent sequential simulations are performed in the order of welding drawings, ISO drawings, and 3D modeling. The welding drawings are detailed drawings for performing line-based actual construction, where the lines are individual structural units of the pipeline. The ISO drawings are drawn before preparing detailed construction drawings. The 3D modeling is drawn before preparing line drawings. Wherein, the horizontal axis of the grid represents the construction status based on the stage, and the vertical axis of the grid represents the work front status based on the stage. Each grid cell in the grid indicates information about the construction status and work front status, as well as information about the number of CWPs with the construction status and work front status. The diagram shows the construction status of projects that have started, followed by the construction status of projects that have not yet started, in the rightward direction along the horizontal axis; and... The display unit displays risk information by using the position of the grid frame in the grid form.
6. An engineering management method, comprising: A project is divided into n construction work packages (CWPs) based on the construction type that constitutes the project, the smallest unit area used to manage the project, and design information. as well as The display unit categorizes the n CWPs according to their construction status and frontline work status, and displays the n CWPs in a grid format on the display unit. Wherein, the horizontal axis of the grid represents the construction status based on the stage, and the vertical axis of the grid represents the work front status based on the stage. Each grid cell in the grid indicates information about the construction status and work front status, as well as information about the number of CWPs with the construction status and work front status. In the rightward direction along the horizontal axis, the construction status of construction that has started is shown, and then the construction status of construction that has not started is shown. The display unit displays risk information by using the position of the grid frame in the grid form; and When the information about the number of CWPs in the grid box is clicked, only the CWP corresponding to the grid box is selected from the n CWPs by filtering, and the detailed information of the selected CWP is displayed.
7. A recording medium having a program recorded thereon for performing the engineering management method according to claim 5 or 6.
Citation Information
Patent Citations
Boiler small-diameter pipeline construction method based on BIM technology
CN107256318A
Construction project management system and method
US20050171790A1
Project management device, project management method, and recording medium
WO2021064876A1