A cofferdam structure and its usage method
By using a rectangular trough made of PE woven fabric and a cofferdam structure with lightweight stainless steel portal components, the problem of low construction efficiency of straw bag cofferdams was solved, mechanized construction was achieved, construction efficiency was improved and costs were reduced.
Patent Information
- Application Number
- CN202311520150.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-15
- Publication Date
- 2026-11-10
- Estimated Expiration
- 2043-11-15
AI Technical Summary
The existing straw bag cofferdam construction is inefficient and cannot be mechanized, resulting in delays in the construction period.
Rectangular troughs made of PE woven fabric and lightweight stainless steel portal frames are connected by straps and lifting straps to form a detachable cofferdam structure. Combined with mechanical filling of mud and sand and stitching connections, rapid construction is achieved.
It improves construction efficiency, reduces labor requirements, has a simple and low-cost overall structure, is easy to install and dismantle, and is suitable for rapid construction.
Smart Images

Figure CN117286900B_ABST
Abstract
Description
Technical Field
[0001] This invention relates to the field of cofferdam construction technology, and in particular to a cofferdam structure and its usage method. Background Technology
[0002] A cofferdam is a temporary retaining structure built in hydraulic engineering projects to construct permanent hydraulic facilities. Its function is to prevent water and soil from entering the construction site, facilitating drainage, excavation of the foundation pit, and construction of the structure. It is primarily used in hydraulic engineering structures and is generally dismantled after use, except when it is part of a permanent building. The cofferdam's height is higher than the highest water level that may occur during the construction period. Currently, for water depths of 0-3m, sandbag cofferdams are commonly used for foundation construction. However, sandbag cofferdam construction requires a large amount of manual labor for bag filling, transportation, and stacking, resulting in low efficiency and the inability to be mechanized, leading to delays in the construction period.
[0003] This invention employs a method for using an open-type woven fabric cofferdam, which can ensure the requirements of mechanical operation and utilize the water filtration characteristics of the filling material to quickly and easily complete the cofferdam work. Summary of the Invention
[0004] The purpose of this invention is to provide a cofferdam structure and its construction method.
[0005] The present invention is achieved by means of the following measures: a cofferdam structure, characterized in that it includes a rectangular trough surrounded by four sides and a bottom surface, wherein the sides and the bottom surface are thin sheets made of PE woven fabric.
[0006] It also includes a positioning structure, which is a portal frame, and the length of the two sides of the portal frame is greater than the height of the rectangular groove. The outer wall of the rectangular groove and the portal frame are connected by several detachable connectors. The portal frame can be made of lightweight stainless steel.
[0007] The sheet has a width of 4-8m and a length of 50m-150m, and can be used to manufacture rectangular grooves of different sizes.
[0008] The height of the rectangular trench is determined according to the requirements of the cofferdam, and is generally higher than the required height of the cofferdam.
[0009] The connector is a strap installed on the outer wall of the rectangular groove.
[0010] The side of the portal frame is provided with a connecting hole through which the strap passes.
[0011] The weight of the PE woven fabric is 90-200 grams per square meter.
[0012] The rectangular groove is connected on two opposite sides by a lifting strap made of PE woven fabric. The lifting strap is made of double-layer PE woven fabric and weighs 200 grams per square meter. The lifting strap is connected to the top of the gate component by several detachable connectors, which are straps, and the top of the gate component is provided with connecting holes through which the straps pass.
[0013] The lifting straps are arranged along the length of the rectangular groove and the distance between two adjacent lifting straps is 2-3m. The width of the lifting straps is not less than 20cm.
[0014] The rectangular trough is filled with a lightweight, waterproof material, such as dry clay, which can be used to lift the lifting strap directly during rescue operations, quickly blocking water. The lifting strap is used as a lifting strap, so it is best to use four layers of 200g PE fabric with closed-loop stitching.
[0015] A method of using the aforementioned cofferdam structure, characterized in that the specific steps include: S1. Arrange several portal frames along the length of the rectangular trough and nail the bottom of the portal frames into the riverbed; the portal frames can position the rectangular trough and determine the position of the cofferdam.
[0016] S2. Connect the portal frame to the outer wall of the rectangular groove through the connector; S3. Initial positioning soil is added to the rectangular trough to open up the bottom of the rectangular trough; the initial positioning soil is used to open up the bottom of the rectangular trough and prevent the rectangular trough from moving when mechanically filling mud and sand. The thickness of the positioning soil is generally one-fifth of the depth of the rectangular trough.
[0017] S4. Fill the rectangular tank with mud and sand to a suitable height. The mud and sand can be directly filled into the tank by mechanical means or by a mud pump. S5. Repeat steps S1-S4 to continue construction of the next section of the cofferdam structure; S6. Two adjacent cofferdam structures are connected by stitching; generally, the stitching is performed along the four edges of the adjacent ends.
[0018] S7. After the initial cofferdam has settled and stabilized, supplementary silt and sand filling shall be carried out. S8. Check the elastic band of the straps and tighten any loose straps again to form a dike.
[0019] The beneficial effects of the technical solution provided by the embodiments of the present invention are as follows: a rectangular trough is made of PE woven fabric, and mud and sand can be filled into the rectangular trough by mechanical operation, which can quickly form a cofferdam; it saves labor and improves construction efficiency; the overall structure is simple, the manufacturing cost is low, and it is easy to install and dismantle; it has important significance and promotion value for rapid construction operations. Attached Figure Description
[0020] To more clearly illustrate the technical solution of the present invention, the accompanying drawings used in the embodiments will be briefly introduced below. Obviously, the drawings listed below are only some embodiments of the present invention. For those skilled in the art, other drawings can be obtained based on these drawings without creative effort.
[0021] Figure 1 This is a schematic diagram of the overall structure of an embodiment of the present invention; Figure 2 This is a schematic diagram of the structure after multiple cofferdam structures are spliced together; Figure 3 This is a structural diagram of the rectangular groove and lifting belt; Figure 4 This is a schematic diagram of a portal frame structure with connecting holes; Figure 5 This is a schematic diagram of the structure after the rectangular trench is filled with positioning soil.
[0022] The components represented by each number in the attached diagram are as follows: 1. Rectangular groove; 2. Portal component; 3. Strap; 4. Lifting belt; 5. Positioning soil; 201. Connecting hole. Detailed Implementation
[0023] To make the objectives, technical solutions, and advantages of this invention clearer, the invention will be further described in detail below with reference to embodiments. Of course, the specific embodiments described herein are merely illustrative and not intended to limit the invention.
[0024] Example 1: See Figures 1-5 A cofferdam structure, characterized in that it includes a rectangular trough 1 formed by four sides and a bottom surface, wherein the sides and bottom surface are thin sheets made of PE woven fabric.
[0025] It also includes a positioning structure, which is a portal frame 2, and the length of the two sides of the portal frame 2 is greater than the height of the rectangular groove 1; The outer wall of the rectangular channel 1 and the portal frame 2 are connected by several detachable connectors. The portal frame 2 can be made of lightweight stainless steel.
[0026] The width of the sheet is 4-8m and the length is 50m-150m. Rectangular troughs of different sizes can be manufactured according to different dimensions.
[0027] The height of the rectangular trench 1 is determined according to the requirements of the cofferdam, and is generally higher than the required height of the cofferdam.
[0028] The connector is a strap 3 set on the outer wall of the rectangular groove 1.
[0029] The side of the gantry 2 is provided with a connecting hole 201 through which the strap 3 passes.
[0030] The weight of PE woven fabric is 90-200 grams per square meter.
[0031] The two opposite sides of the rectangular groove 1 are connected by lifting straps 4 made of PE woven fabric. The lifting straps 4 are made of double-layer PE woven fabric and weigh 200 grams per square meter. The lifting straps 4 are connected to the top of the gate component 2 by several detachable connectors, which are straps 3, and the top of the gate component 2 is provided with connecting holes 201 through which the straps 3 pass.
[0032] The lifting belt 4 is arranged along the length of the rectangular trough 1 and the distance between two adjacent lifting belts 4 is 2-3m. The width of the lifting belt 4 is not less than 20cm.
[0033] The rectangular trough 1 is filled with a lightweight, waterproof material, such as dry clay, which can be used to lift the lifting strap 4 directly during rescue operations to quickly block water. At this time, the lifting strap 4 is used as a lifting strap, so it is best to use 4 layers of 200g PE fabric with closed-loop stitching for the lifting strap 4.
[0034] Example 2: See Figures 1-5 Based on Embodiment 1, a method for using a cofferdam structure is provided, characterized by the following specific steps: S1. Arrange several portal frames 2 along the length of the rectangular trough 1, and nail the bottom of the portal frames 2 into the riverbed; the portal frames 2 can locate the position of the rectangular trough 1 and determine the position of the cofferdam.
[0035] S2. Connect the portal frame 2 to the outer wall of the rectangular groove 1 via a connector; S3. Fill the rectangular trough 1 with initial positioning soil 5 to open up the bottom of the rectangular trough 1; the initial positioning soil 5 is used to open up the bottom of the rectangular trough 1 to prevent the rectangular trough 1 from moving when mechanically filling mud and sand. The thickness of the positioning soil 5 is generally one-fifth of the depth of the rectangular trough 1.
[0036] S4. Fill the rectangular tank 1 with mud and sand to a suitable height. You can directly fill (pour) mud and sand into the tank using machinery or a mud pump. S5. Repeat steps S1-S4 to continue construction of the next section of the cofferdam structure; S6. Two adjacent cofferdam structures are connected by stitching; generally, the stitching is performed along the four edges of the adjacent ends.
[0037] S7. After the initial cofferdam has settled and stabilized, supplementary silt and sand filling shall be carried out. S8. Check the elastic band of the strap 3 and tighten any loose straps 3 a second time to form a dike.
[0038] Example 3: Based on Embodiment 1, a method for using a cofferdam structure is provided, characterized by the following specific steps: S1. Insert temporary limiting stakes (bamboo stakes or wooden stakes are preferred) into the water. S2. After tying a 15mm thick nylon rope every 10m, wrap the rectangular trough around the bottom of the sand cylinder, and use a mud pump to pump mud and sand into the sand cylinder from the top. S3. After the mud and sand have completely settled, the rectangular tank is welded to the outer wall of the sand cylinder by thermoplastic welding. S4. Continue installing the upper sand cylinder, place the rectangular trough between the upper and lower sand cylinders and tie it to the limit stake, ensuring that the side wall of the rectangular trough can be wrapped around the connection, and continue to use the mud pump to pump mud and sand from the top of the upper sand cylinder to the sand cylinder. S5. After the mud and sand have completely settled, the rectangular tank is welded to the connection between the upper sand cylinder and the lower sand cylinder by thermoplastic welding. Repeat steps S4-S5 to continue installing the sand cylinder until the appropriate height is reached.
[0039] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc., made within the spirit and principles of the present invention should be included within the protection scope of the present invention.
Claims
1. A method of using a cofferdam structure, characterized in that, The cofferdam structure comprises a rectangular trough enclosed by four sides and a bottom surface, wherein the sides and bottom surface are thin sheets made of PE woven fabric. The specific steps for using a cofferdam structure include: S1. Insert temporary limiting stakes into the water; S2. After tying a 15mm thick nylon rope every 10m, wrap the rectangular trough around the bottom of the sand cylinder, and use a mud pump to pump mud and sand into the sand cylinder from the top. S3. After the mud and sand have completely settled, the rectangular tank is welded to the outer wall of the sand cylinder by thermoplastic welding. S4. Continue installing the upper sand cylinder, place the rectangular trough between the upper and lower sand cylinders and tie it to the limit stake, ensuring that the side wall of the rectangular trough can be wrapped around the connection, and continue to use the mud pump to pump mud and sand from the top of the upper sand cylinder to the sand cylinder. S5. After the mud and sand have completely settled, the rectangular tank is welded to the connection between the upper sand cylinder and the lower sand cylinder by thermoplastic welding. Repeat steps S4-S5 to continue installing the sand cylinder until the appropriate height is reached.
2. The method of using the cofferdam structure according to claim 1, characterized in that, The width of the sheet is 4-8m and the length is 50m-150m.
3. The method of using the cofferdam structure according to claim 1, characterized in that, The weight of the PE woven fabric is 90-200 grams per square meter.
Citation Information
Patent Citations
Temporary flood barrier constructed by soil engineering filling bags and gate-shaped steel frames
CN105507205A
Combined box-type flood control sub-dike and emergency rescue method thereof
CN112081068A