Methods to shorten power outage time due to tree branch felling along power lines

By acquiring power line corridor data, determining the location of tree branches and power outage areas, recording the felling time, optimizing the tree felling process, and using cluster analysis to identify typical data information, the problem of long felling time in power line corridors was solved, power outage time was shortened, and the electricity user experience was improved.

CN117371588BActive Publication Date: 2026-11-17STATE GRID ZHEJIANG ELECTRIC POWER CO LTD TAIZHOU LUQIAO DISTRICT POWER SUPPLY CO +1
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202311310882.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-10
Publication Date
2026-11-17
Estimated Expiration
2043-10-10

AI Technical Summary

Technical Problem

The time-consuming process of cutting down tree branches along power lines leads to prolonged power outages, impacting the electricity experience for users.

Method used

By acquiring power line corridor data, the location of branches to be cut and the power outage area are determined. The cutting time for each branch is recorded, and the time-consuming processes are analyzed and optimized. Cluster analysis is used to find typical data information as a reference to optimize the branch cutting process and reduce time.

Benefits of technology

It shortened the power outage time for tree branch felling, improved the power user experience, and enhanced the efficiency of analysis and research as well as the targeted nature of process optimization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117371588B_ABST
    Figure CN117371588B_ABST
Patent Text Reader

Abstract

This invention discloses a method for shortening power outage time due to tree branch felling along power line corridors, overcoming the shortcomings of existing technologies. The method includes: Step 1, acquiring power line corridor data, including the location of utility poles and transmission lines; Step 2, determining the tree branches to be felled based on the location of the utility poles and transmission lines; Step 3, determining the area requiring power outage based on the location of the felled branches; Step 4, acquiring the felling time for each branch and calculating the average felling time for all branches. If the felling time of a particular branch exceeds the average felling time by a factor exceeding a set first threshold, the felling data is recorded and sent to relevant personnel. These personnel identify the steps requiring time reduction and record the time-reduction measures. These measures are used to optimize the felling process for future felling of the same type of branches to reduce time; Step 5, the tree branch felling process is completed, and power is restored to the affected area.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of power system safe operation technology, and in particular to a method for shortening power outage time due to tree branch felling along power line corridors. Background Technology

[0002] With social development, electricity users have placed higher demands on the quality and efficiency of power supply services. In Zhejiang, during the annual flood and typhoon season, a large number of trees and branches near power line corridors need to be cut down. However, the work has encountered the problem of lengthy tree felling times. Furthermore, the corresponding power lines need to be shut down during tree felling to ensure the safety of the operation. Therefore, the long time required for tree felling results in prolonged power outages, impacting the electricity user experience. Summary of the Invention

[0003] The purpose of this invention is to overcome the shortcomings of existing technologies where the time required for felling tree branches along power lines results in prolonged power outages, which negatively impacts the electricity user experience. This invention provides a method to shorten the power outage time caused by felling tree branches along power lines.

[0004] The objective of this invention is achieved through the following technical solution: Methods to shorten power outage time due to tree branch felling along power line corridors include the following steps: Step 1: Obtain power line corridor data, including the location of utility poles and transmission lines; Step 2: Determine the tree branches that need to be cut down based on the location of the power transmission lines on the utility poles; Step 3: Determine the areas requiring power outages based on the location of the branches to be cut; Step 4: Perform the branch felling process, obtain the felling time of each branch and calculate the average felling time of all branches. If the felling time of a certain branch exceeds the average felling time by more than the set first threshold, record the felling data and send it to the relevant personnel. The relevant personnel will identify the process that needs to be shortened and record the time-shortening measures. The time-shortening measures will be used to optimize the branch felling process to reduce time when felling the same type of branches again in the future. Step 5: The tree branch felling process is completed, and power is restored to the affected area.

[0005] This solution first locates the trees to be felled, allowing for the precise calculation of the areas requiring power outages. This avoids unnecessary power outages that could negatively impact users' electricity experience. Simultaneously, by recording the time spent on each branch felling process, time-consuming steps can be identified. This allows relevant personnel to pinpoint the causes and optimize these steps. In the future, when felling the same type of branches, the optimized felling process can be used, reducing felling time and consequently minimizing power outages, thus improving the user experience.

[0006] Preferably, step 4 includes power outage, safety measures installation, guide rope installation on branches, branch sawing, removal of safety measures, and power restoration. This detailed breakdown of the branch-cutting process allows for a clear understanding of the specific time required for each step, enabling relevant personnel to promptly identify time-consuming steps and implement targeted measures to reduce their duration.

[0007] As a preferred method, the method for shortening the power outage time due to tree branch felling along power lines also includes data on all felled branches, including the location of the branches, the species of the trees to which the branches correspond, the age of the trees to which the branches correspond, and the time required for each step in the tree branch felling process. The data on felled tree branches were normalized. Clustering is performed based on the normalized location of the branches, the species of the trees corresponding to the branches, the age of the trees corresponding to the branches, and the time required for each step in the branch felling process. The data information of the felled branches corresponding to each cluster center is then used as typical data information.

[0008] In this solution, all data on tree branch felling can be clustered to find typical data information to facilitate the analysis and research of the time occupied by the tree branch felling process, without having to study the tree branch felling process corresponding to all the data on tree branch felling, thus improving the efficiency of analysis and research.

[0009] Preferably, if the difference between the felling time corresponding to a certain typical data point and the average felling time exceeds a set second threshold, then the typical data point is used as reference data, and the branch felling procedure corresponding to the reference data is used as a reference branch felling procedure. When felling branches of the same type again in the future, the branches will be felled using the reference branch felling procedure. This solution cleverly determines the reference data, allowing for future reference when felling branches of the same type, further reducing felling time.

[0010] Preferably, the same type of felling is defined as the same location area and the same tree species corresponding to the same branches.

[0011] Preferably, the definition of the same felling type also includes that the difference between the ages of the trees corresponding to the branches is less than the age threshold.

[0012] The beneficial effects of this invention are: This invention employs an optimized branch felling process to reduce felling time, thereby reducing the time required for power outages and improving the electricity user experience. Furthermore, the detailed branch felling process allows for a clear understanding of the specific time required for each step, facilitating timely identification of time-consuming steps and enabling targeted measures to reduce their duration. Attached Figure Description

[0013] Figure 1 This is a flowchart of the present invention. Detailed Implementation

[0014] The present invention will be further described below with reference to the accompanying drawings and embodiments.

[0015] Example: Methods to shorten power outage time due to tree branch felling along power lines, such as... Figure 1 As shown, it includes the following steps: Step 1: Obtain power line corridor data, including the location of utility poles and transmission lines; Step 2: Determine the tree branches that need to be cut down based on the location of the power transmission lines on the utility poles; Step 3: Determine the areas requiring power outages based on the location of the branches to be cut; Step 4: Perform the branch felling process, obtain the felling time of each branch and calculate the average felling time of all branches. If the felling time of a certain branch exceeds the average felling time by more than the set first threshold, record the felling data and send it to the relevant personnel. The relevant personnel will identify the process that needs to be shortened and record the time-shortening measures. The time-shortening measures will be used to optimize the branch felling process to reduce time when felling the same type of branches again in the future. Step 5: The tree branch felling process is completed, and power is restored to the affected area.

[0016] This solution first locates the trees to be felled, allowing for the precise calculation of the areas requiring power outages. This avoids unnecessary power outages that could negatively impact users' electricity experience. Simultaneously, by recording the time spent on each branch felling process, time-consuming steps can be identified. This allows relevant personnel to pinpoint the causes and optimize these steps. In the future, when felling the same type of branches, the optimized felling process can be used, reducing felling time and consequently minimizing power outages, thus improving the user experience.

[0017] In step 4, the tree branch felling process includes power outage, safety measures installation, guide rope installation on the branches, branch sawing, removal of safety measures, and power restoration. This detailed breakdown of the tree branch felling process allows for a clear understanding of the specific time required for each step, enabling relevant personnel to promptly identify time-consuming steps and implement targeted measures to reduce their duration.

[0018] The method to shorten the power outage time due to tree branch felling along power lines also includes data on all felled branches, including the location of the branches, the species of the trees to which the branches correspond, the age of the trees to which the branches correspond, and the time required for each step in the tree felling process. The data on felled tree branches were normalized. Clustering is performed based on the normalized location of the branches, the species of the trees corresponding to the branches, the age of the trees corresponding to the branches, and the time required for each step in the branch felling process. The data information of the felled branches corresponding to each cluster center is then used as typical data information.

[0019] In this solution, all data on tree branch felling can be clustered to find typical data information to facilitate the analysis and research of the time occupied by the tree branch felling process, without having to study the tree branch felling process corresponding to all the data on tree branch felling, thus improving the efficiency of analysis and research.

[0020] If the difference between the felling time corresponding to a certain typical data point and the average felling time exceeds a set second threshold, then the typical data point is used as reference data, and the felling procedure corresponding to the reference data is used as the reference felling procedure. When felling branches of the same type again in the future, the branches will be felled using the reference felling procedure. This solution cleverly determines the reference data, allowing for future reference when felling branches of the same type, further reducing felling time.

[0021] The same type of felling is defined as the same location area and the same tree species corresponding to the same branches.

[0022] The definition of the same felling type also includes the difference between the age of the trees corresponding to the branches being less than the age threshold.

[0023] In a specific embodiment, statistics were compiled on 598 tree-line conflicts handled during a certain period of flood and typhoon prevention. Among them, the felling work of 486 trees that required fixing guide ropes was investigated according to the work procedures, as shown in the table below: Survey form by work process Serial Number Process Time (minutes) Proportion Cumulative percentage 1 Power outage 1.00 2.24% 2.24% 2 Deploy safety measures 5.30 11.88% 14.12% 3 Tree branches are equipped with guide ropes 28.4 63.68% 77.8% 4 sawing tree branches 4.30 9.64% 87.44% 5 Removal of safety measures 4.60 10.31% 97.75% 6 Power transmission line 1.00 2.25% 100% total 44.6 100% The process tolerance table is shown below: Process range table Serial Number Process Longest duration (minutes) Shortest time (minutes) Time difference (minutes) 1 Power outage 1.2 0.9 0.3 2 Deploy safety measures 5.5 4.8 0.7 3 Tree branches are equipped with guide ropes 36 9.8 26.2 4 sawing tree branches 5.2 3.9 1.3 5 Removal of safety measures 5.4 4.7 0.7 6 Power transmission line 1.1 0.9 0.2 It can be seen that installing guide ropes on tree branches takes the longest time, and the process of installing guide ropes on tree branches has the greatest variation. It can be seen that the time taken is mainly determined by the process of installing guide ropes on tree branches. Therefore, in this embodiment, the data of tree branches with less time spent on the process of installing guide ropes on tree branches can be selected as typical data. When cutting the same type of tree branches again in the future, the tree branches can be cut by referring to the tree branch cutting process, which saves cutting time, thereby reducing power outage time and improving the power user experience.

[0024] According to embodiments of this application, the processes described above with reference to the flowcharts can be implemented as computer software programs. For example, embodiments of this application include computer program products comprising a computer program carried on a computer-readable medium, the computer program including a computer program for performing the methods shown in the flowcharts. In such embodiments, the computer program can be downloaded and installed from a network via communication section 509, and / or installed from removable medium 511. When the computer program is executed by central processing unit (CPU) 501, it performs various functions defined in the system of this application.

[0025] It should be noted that the computer-readable medium shown in the embodiments of this application can be a computer-readable signal medium or a computer-readable storage medium, or any combination of the two. A computer-readable storage medium can be, for example,—but not limited to—an electrical, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any combination thereof. More specific examples of a computer-readable storage medium may include, but are not limited to: an electrical connection having one or more wires, a portable computer disk, a hard disk, random access memory (RAM), read-only memory (ROM), erasable programmable read-only memory (EPROM), flash memory, optical fiber, portable compact disc read-only memory (CD-ROM), optical storage device, magnetic storage device, or any suitable combination thereof. In this application, a computer-readable storage medium can be any tangible medium containing or storing a program that can be used by or in conjunction with an instruction execution system, apparatus, or device. In this application, a computer-readable signal medium can include a data signal propagated in baseband or as part of a carrier wave, carrying a computer-readable computer program. The transmitted data signal can take various forms, including but not limited to electromagnetic signals, optical signals, or any suitable combination thereof. The computer-readable signal medium can also be any computer-readable medium other than a computer-readable storage medium, which can send, propagate, or transmit a program for use by or in connection with an instruction execution system, apparatus, or device. The computer program contained on the computer-readable medium can be transmitted using any suitable medium, including but not limited to wireless, wired, etc., or any suitable combination thereof.

[0026] The flowcharts and block diagrams in the accompanying drawings illustrate the architecture, functionality, and operation of possible implementations of systems, methods, and computer program products according to various embodiments of this application. Each block in a flowchart or block diagram may represent a module, segment, or portion of code, which contains one or more executable instructions for implementing a specified logical function. It should also be noted that in some alternative implementations, the functions indicated in the blocks may occur in a different order than those indicated in the drawings. For example, two consecutively indicated blocks may actually be executed substantially in parallel, and they may sometimes be executed in reverse order, depending on the functions involved. It should also be noted that each block in a block diagram or flowchart, and combinations of blocks in a block diagram or flowchart, can be implemented using a dedicated hardware-based system that performs the specified function or operation, or using a combination of dedicated hardware and computer instructions.

[0027] The units described in the embodiments of this application can be implemented in software or hardware, and the described units can also be located in a processor. The names of these units do not necessarily limit the specific unit itself.

[0028] In another aspect, this application also provides a computer-readable medium, which may be included in the electronic device described in the above embodiments; or it may exist independently and not assembled into the electronic device. The computer-readable medium carries one or more programs that, when executed by the electronic device, cause the electronic device to perform the methods described in the above embodiments.

[0029] It should be noted that although several modules or units for the device used to perform actions have been mentioned in the detailed description above, this division is not mandatory. In fact, according to the embodiments of this application, the features and functions of two or more modules or units described above can be embodied in one module or unit. Conversely, the features and functions of one module or unit described above can be further divided and embodied by multiple modules or units.

[0030] Through the above description of the embodiments, those skilled in the art will readily understand that the exemplary embodiments described herein can be implemented by software or by combining software with necessary hardware. Therefore, the technical solutions according to the embodiments of this application can be embodied in the form of a software product, which can be stored in a non-volatile storage medium (such as a CD-ROM, USB flash drive, external hard drive, etc.) or on a network, including several instructions to cause a computing device (such as a personal computer, server, touch terminal, or network device, etc.) to execute the method according to the embodiments of this application.

[0031] Other embodiments of this application will readily occur to those skilled in the art upon consideration of the specification and practice of the embodiments disclosed herein. This application is intended to cover any variations, uses, or adaptations of this application that follow the general principles of this application and include common knowledge or customary techniques in the art not disclosed herein.

[0032] It should be understood that this application is not limited to the precise structure described above and shown in the accompanying drawings, and various modifications and changes can be made without departing from its scope. The scope of this application is limited only by the appended claims.

Claims

1. A method to shorten power outage time due to tree branch felling along power line corridors, characterized by: Includes the following steps: Step 1: Obtain power line corridor data, including the location of utility poles and transmission lines; Step 2: Determine the tree branches that need to be cut down based on the location of the power transmission lines on the utility pole; Step 3: Determine the areas requiring power outages based on the location of the branches to be cut; Step 4: Perform the branch felling process, obtain the felling time of each branch and calculate the average felling time of all branches. If the felling time of a certain branch exceeds the average felling time by more than the set first threshold, record the felling data and send it to the relevant personnel. The relevant personnel will identify the process that needs to be shortened and record the time-shortening measures. The time-shortening measures will be used to optimize the branch felling process to reduce time when felling the same type of branches again in the future. Step 5: The tree branch felling process is completed, and power is restored to the affected area; The data for all felled branches also includes the location of the branch, the species of the tree to which the branch belongs, the age of the tree to which the branch belongs, and the time required for each step in the branch felling process. The data on felled tree branches were normalized. Clustering is performed based on the location of the normalized branches, the species of the trees corresponding to the branches, the age of the trees corresponding to the branches, and the time required for each step in the branch felling process. Data information of felled branches corresponding to each cluster center is then obtained as typical data information. If the difference between the felling time corresponding to a certain typical data point and the average felling time exceeds the set second threshold, then the typical data point will be used as reference data, and the branch felling process corresponding to the reference data will be used as the reference branch felling process; when felling branches of the same type again in the future, the branches will be felled by referring to the branch felling process.

2. The method for shortening power outage time due to tree branch felling along power line corridors according to claim 1, characterized in that, In step 4, the tree branch felling process includes power outage, setting up safety measures, installing guide ropes on the branches, sawing the branches, removing the safety measures, and powering back on the line.

3. The method for shortening power outage time due to tree branch felling along power line corridors according to claim 1, characterized in that, The same type of felling is defined as the same location area and the same tree species corresponding to the same branches.

4. The method for shortening power outage time due to tree branch felling along power line corridors according to claim 3, characterized in that, The definition of the same felling type also includes the difference between the age of the trees corresponding to the branches being less than the age threshold.

Citation Information

Patent Citations

  • Power channel corridor routing-inspection method based on tilt photography three-dimensional reconstruction technology

    CN106441233A

  • Power transmission line tree barrier felling planning method based on hyperspectral remote sensing technology

    CN110009146A