An integrated immersed tube formwork trolley with small space, large cross section and multiple working surfaces
By designing a modularly assembled integrated immersive tube formwork trolley with small space, large sections and multiple working surfaces, the problem of pouring large sections in small spaces and large sections in immersive tube tunnel construction has been solved, and the construction quality and efficiency have been improved, which has met the different cross-sectional forms. Quick pouring and safe operation.
Patent Information
- Application Number
- CN202311601943.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-28
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2043-11-28
AI Technical Summary
In the construction of immersed pipe tunnels, it is difficult for the existing technology to achieve pouring of large sections and multiple working surfaces in a small space, resulting in low construction safety and labor efficiency, and a high sense of responsibility and labor intensity to the workers.
Design a small space, large section, multi-working surface integrated immersive tube formwork trolley, adopting a modular and standardized assembly structure, including an external mold assembly, an external wall assembly, a central partition wall assembly, a vault and an inner wall The assembly, which realizes longitudinal movement and lateral adjustment through hydraulic cylinder and rotating plate telescopic parts, is suitable for different structural surfaces and cross-sectional forms, and achieves rapid assembly and mold release.
The trolley is realized to move and adjust itself, meet the requirements of different pouring lengths and cross-sections, improve the construction quality and concrete pouring speed, reduce the labor intensity of workers, and ensure construction safety and watertightness.
Smart Images

Figure CN117386408B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of tunnel construction, and in particular to an integrated immersed tube formwork trolley with a small space, a large cross-section and multiple working surfaces. Background Art
[0002] In the construction of immersed tube tunnels, the structural form of the trolley directly affects the quality of pipe segment prefabrication, the anti-seepage and anti-cracking performance of the pipe segment, construction safety and work efficiency, etc. At present, there are two main support systems in the entire immersed tube tunnel construction machinery industry. One is to use scaffolding plus combined formwork to cast the pipe segment in three times according to the bottom plate, side wall and top plate, which is time-consuming and labor-intensive, and has high labor intensity, and has high requirements for the sense of responsibility of the operators; the other is to use a trolley for integral casting, which has good casting effect and low labor intensity, but has high requirements for the construction site, which invisibly limits the formwork support system.
[0003] Therefore, affected by conditions such as limited space, insufficient water depth, and tensile stress of secondary pouring of pipe segments, it is necessary to design an integrated immersed tube formwork trolley with small space, large cross-section, and multiple working surfaces. Summary of the invention
[0004] The purpose of the present invention is to provide an integrated immersed tube formwork trolley with a small space, large cross-section and multiple working surfaces to solve the above-mentioned problems, so as to adapt to different casting lengths and different cross-sectional changes, and on the basis of ensuring construction safety, it can significantly improve the construction quality, increase the concrete pouring speed and reduce the labor intensity of workers.
[0005] To achieve the above-mentioned purpose, the present invention provides a small-space, large-section, multi-working-surface integrated immersed tube formwork trolley, comprising an outer mold assembly, the outer mold assembly is arranged outside the first lining, the inner sides of the two side walls of the first lining are respectively provided with outer wall assemblies, the sides of the two outer wall assemblies close to each other are both provided with arches and inner wall assemblies, a middle partition wall assembly is arranged between the bottom plate and the top beam in the middle of the first lining, and the second lining is cast together at the top of the arch and inner wall assembly and between the arch and inner wall assembly and the middle partition wall assembly;
[0006] The outer mold assembly, the outer side wall assembly, the middle partition wall assembly, the vault and the inner side wall assembly slide along the length direction of the first lining.
[0007] Preferably, the outer mold assembly includes a first track, the first track is fixedly connected to the ground, a first walking trolley is slidably connected to the top of the first track, a side wall outer mold is provided on the inner side of the first walking trolley, and the side wall outer mold is fitted with the outer sides of the two side walls of the first lining.
[0008] Preferably, the outer wall assembly includes a second track, the second track is fixedly connected to the base plate, a second walking trolley is slidably connected to the top of the second track, a side wall inner template is provided on the outer side of the second walking trolley, and the side wall inner template is fitted with the inner side of the side wall.
[0009] Preferably, the side wall inner formwork includes a side wall inner main formwork, the side wall inner main formwork is connected to the second walking trolley, the upper and lower ends of the side wall inner main formwork are respectively hinged with a side wall inner rotating formwork, the side wall inner rotating formwork and the second walking trolley are connected through a rotating plate telescopic part, and the side wall inner main formwork and the side wall inner rotating formwork are fitted with the inner side of the side wall.
[0010] Preferably, the middle partition wall assembly includes a third track, the third track is fixedly connected to the top of the middle part of the base plate, a third walking trolley is slidably connected to the third track, a top beam template is provided on the top of the third walking trolley, the top beam template is fitted with the bottom end of the top beam, middle partition wall templates are respectively provided on both sides of the third walking trolley, and the middle partition wall templates are fitted with the second lining side walls.
[0011] Preferably, the arch and inner wall assembly includes a fourth track, the fourth track is fixedly connected to the top of the base plate, the top of the fourth track is slidably connected to a fourth walking trolley, the top of the fourth walking trolley and the side away from the outer wall assembly are both provided with secondary casting formwork, and the secondary casting formwork is fitted with the second lining.
[0012] Preferably, the secondary pouring formwork includes a top formwork, the top formwork is connected to the fourth walking trolley, the top formwork is fitted with the bottom end of the second lining, the side of the top formwork away from the outer wall assembly is hinged with a middle partition wall outer formwork, the end of the middle partition wall outer formwork away from the top formwork is hinged with a bottom edge formwork, the middle partition wall outer formwork and the bottom edge formwork are fitted with the side wall of the second lining, and the middle partition wall outer formwork, the bottom edge formwork and the fourth walking trolley are connected by a transmission connection via a middle partition wall outer telescopic member.
[0013] Preferably, the rotating plate telescopic member and the middle partition wall outer telescopic member are hydraulic cylinders.
[0014] Preferably, the outer mold assembly, the outer wall assembly, the middle partition wall assembly, the vault and the inner wall assembly are all provided with steps and operating platforms.
[0015] Preferably, the outer mold assembly and the outer side wall assembly are fixed by anti-floating bolts, and the middle partition wall assembly, the arch and the inner side wall assembly are fixed by the anti-floating bolts.
[0016] Therefore, the present invention adopts a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley with the above structure, which has the following beneficial effects:
[0017] (1) The trolley of the present invention can realize longitudinal movement and lateral adjustment operations by itself. The main structure adopts a modular and standardized assembly type, which is suitable for different structural surfaces and quick assembly.
[0018] (2) The operating length of the trolley of the present invention should be adapted to the lining length, meet the requirements of different lining lengths and different cross-sectional forms, meet the requirements of combining the template with the main structure, and realize the rapid positioning and demoulding of the template.
[0019] (3) The present invention can realize the integrated lining requirements of the bottom plate, side wall and top plate, ensuring the casting quality.
[0020] (4) The present invention can realize one-time pouring of the entire section, meeting the needs of personnel for safe operation.
[0021] The present application utilizes these structures to realize an integrated immersed tube formwork trolley that can realize longitudinal movement and lateral adjustment operations by itself. The main structure adopts a modular and standardized assembly type, which is suitable for small spaces, large sections, and multiple working surfaces with different structural surfaces and quick assembly.
[0022] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a schematic diagram of the structure of the partial assembly of the present invention during the first lining;
[0024] Figure 2 It is a schematic diagram of the overall structure of the present invention;
[0025] Figure 3 is a structural schematic diagram of the outer wall assembly;
[0026] Figure 4 It is a structural schematic diagram of the vault and inner wall assembly.
[0027] Figure numerals: 1, outer formwork assembly; 2, first lining; 3, outer wall assembly; 5, middle partition wall assembly; 6, vault and inner wall assembly; 7, second lining; 101, first traveling trolley; 102, first track; 103, side wall outer formwork; 201, bottom plate; 202, side wall; 203, top beam; 301, second track; 302, second traveling trolley; 303, side wall inner formwork; 501, third track Track; 502, the third walking trolley; 503, the top beam formwork; 504, the middle partition wall formwork; 601, the fourth track; 602, the fourth walking trolley; 603, the secondary pouring formwork; 3031, the main formwork inside the side wall; 3032, the rotating formwork inside the side wall; 3033, the rotating plate telescopic part; 6031, the top formwork; 6032, the middle partition wall outer formwork; 6033, the middle partition wall outer telescopic part; 6034, the bottom edge formwork. DETAILED DESCRIPTION
[0028] The technical solution of the present invention is further described below through the accompanying drawings and embodiments.
[0029] Unless otherwise defined, the technical terms or scientific terms used in the present invention should be understood by people with ordinary skills in the field to which the present invention belongs. The words "first", "second" and similar words used in the present invention do not indicate any order, quantity or importance, but are only used to distinguish different components. "Include" or "comprise" and similar words mean that the elements or objects appearing before the word include the elements or objects listed after the word and their equivalents, without excluding other elements or objects. "Connect" or "connected" and similar words are not limited to physical or mechanical connections, but may include electrical connections, whether direct or indirect. "Up", "down", "left", "right" and the like are only used to indicate relative positional relationships. When the absolute position of the described object changes, the relative positional relationship may also change accordingly.
[0030] Example
[0031] Reference Figures 1 to 4 As shown, the present invention provides a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, comprising an outer mold assembly 1, the outer mold assembly 1 is arranged on the outside of the first lining 2, the inner sides of the two side walls 202 of the first lining 2 are respectively provided with outer wall assemblies 3, the sides of the two outer wall assemblies 3 close to each other are both provided with arch and inner wall assemblies 6, a middle partition wall assembly 5 is arranged between the bottom plate 201 and the top beam 203 in the middle of the first lining 2, and the second lining 7 is cast together at the top of the arch and inner wall assembly 6 and between the arch and inner wall assembly 6 and the middle partition wall assembly 5;
[0032] The outer mold assembly 1 , the outer side wall assembly 3 , the middle partition wall assembly 5 , the vault and the inner side wall assembly 6 slide along the length direction of the first lining 2 .
[0033] The present invention is prefabricated in an existing dock, which is 9.3m deep, 36m wide and 250m long. The side walls and bottom plate of the dock need to be protected before construction and restored after construction. Affected by the water depth, a cavity needs to be reserved on the top plate during the dock stage, and after the longitudinal and transverse beam frame structure is formed, it is towed out of the dock and then poured.
[0034] The overall structure of the present invention, i.e., the integrated immersed tube formwork trolley has a length of 19.5 m, a width of 35.52 m, and a height of 11.2 m, and is composed of an outer formwork assembly 1, an outer wall assembly 3, a middle partition wall assembly 5, and a vault and inner wall assembly 6 arranged along the length direction of the first lining 2. Each assembly is independent of each other, and the overall structure is as follows Figure 2 as shown in .
[0035] The first walking trolley 101, the second walking trolley 302, the third walking trolley 502, and the fourth walking trolley 602 in the present invention are all fully hydraulic self-propelled trolleys, with a maximum walking power of 30Kw, a rated pressure of the hydraulic system of 16MPa, and a power of 4.5Kw. Hydraulic cylinders and screw jacks are used to erect and demould each formwork (i.e.). The structure of the present invention has the advantages of simple operation, fast lining speed, and good pipe segment concrete forming.
[0036] A further optimized solution is that the outer mold assembly 1 includes a first track 102, which is fixedly connected to the ground. A first walking trolley 101 is slidably connected to the top of the first track 102. A side wall outer formwork 103 is provided on the inner side of the first walking trolley 101. The side wall outer formwork 103 is moved by a motor. After moving to a specified position, it is fixed to the second walking trolley 302 by a tension screw to improve the overall stability. The side wall outer formwork 103 fits against the outer sides of the two side walls 202 of the first lining 2.
[0037] The first traveling trolley 101 is composed of a tension truss and two transverse structures. The two transverse structures are arranged outside the two side walls 202 of the first lining 2, and the top ends thereof are connected by the tension truss.
[0038] According to a further optimization scheme, the outer wall assembly 3 includes a second track 301, which is fixedly connected to the bottom plate 201, and a second trolley 302 is slidably connected to the top of the second track 301. A side wall inner template 303 is provided on the outer side of the second trolley 302, and the side wall inner template 303 is fitted with the inner side of the side wall 202.
[0039] A further optimized solution is that the side wall inner template 303 includes a side wall inner main template 3031, which is connected to the second walking trolley 302, and the side wall inner rotating template 3032 is hinged at the upper and lower ends of the side wall inner main template 3031, and the side wall inner rotating template 3032 is connected to the second walking trolley 302 through a rotating plate telescopic member 3033, and the side wall inner main template 3031 and the side wall inner rotating template 3032 are fitted with the inner side of the side wall 202.
[0040] The rotating plate telescopic member 3033 can be used to push the rotating template 3032 in the side wall to fit and separate with the inner side of the side wall 202, thereby achieving a good lateral adjustment function. After the rotating template 3032 in the wall is retracted by the rotating plate telescopic member 3033, the second walking trolley 302 can be moved.
[0041] Further optimization scheme, the middle partition wall assembly 5 includes a third track 501, the third track 501 is fixedly connected to the top of the middle part of the bottom plate 201, and a third walking trolley 502 is slidably connected to the third track 501. A top beam template 503 is provided at the top of the third walking trolley 502. The top beam template 503 is fitted with the bottom end of the top beam 203, and the top beam template 503 is driven to move by a motor. The top template of the top beam template 503 serves as the bottom film of the beam, and the side template is the side template of the partition wall. Middle partition wall templates 504 are respectively provided on both sides of the third walking trolley 502. The middle partition wall template 504 is assembled with the top beam template 503, and is driven to move by a motor. The middle partition wall template 504 fits the side wall of the second lining 7.
[0042] A further optimized solution is that the arch and inner wall assembly 6 includes a fourth track 601, the fourth track 601 is fixedly connected to the top of the base plate 201, the top of the fourth track 601 is slidably connected to a fourth walking trolley 602, and the top of the fourth walking trolley 602 and the side away from the outer wall assembly 3 are both provided with a secondary casting template 603, and the secondary casting template 603 is fitted with the second lining 7.
[0043] Further optimization scheme, the secondary casting formwork 603 includes a top formwork 6031, the top formwork 6031 is connected to the fourth walking trolley 602, the top formwork 6031 is fitted with the bottom end of the second lining 7, the top formwork 6031 is the top formwork of the fourth walking trolley 602, and is moved by a motor drive, the side of the top formwork 6031 away from the outer wall assembly 3 is hinged with a middle partition wall outer formwork 6032, the end of the middle partition wall outer formwork 6032 away from the top formwork 6031 is hinged with a bottom edge formwork 6034, the middle partition wall outer formwork 6032 and the bottom edge formwork 6034 are fitted with the side wall of the second lining 7, and the middle partition wall outer formwork 6032 and the bottom edge formwork 6034 are connected to the fourth walking trolley 602 through a middle partition wall outer telescopic member 6033.
[0044] The middle partition wall outer telescopic member 6033 can be used to push the middle partition wall outer template 6032 and the bottom edge template 6034 to fit and separate with the side wall of the second lining 7, thereby achieving a good lateral adjustment function. After the middle partition wall outer template 6032 and the bottom edge template 6034 are retracted by the middle partition wall outer telescopic member 6033, the fourth walking trolley 602 can be moved.
[0045] According to a further optimized solution, the rotating plate telescopic member 3033 and the middle partition wall outer telescopic member 6033 are hydraulic cylinders.
[0046] To further optimize the solution, steps and operating platforms are provided on the outer mold assembly 1, the outer wall assembly 3, the middle partition wall assembly 5, the arch and the inner wall assembly 6.
[0047] Specifically, the first walking trolley 101 of the outer mold assembly 1, the second walking trolley 302 of the outer wall assembly 3, the third walking trolley 502 of the middle partition wall assembly 5, and the fourth walking trolley 602 of the arch and inner wall assembly 6 are all equipped with ladders and operating platforms to facilitate construction workers to climb and operate.
[0048] To further optimize the solution, the outer mold assembly 1 and the outer wall assembly 3 are fixed by anti-floating bolts, and the middle partition wall assembly 5, the arch and the inner wall assembly 6 are fixed by anti-floating bolts.
[0049] Specifically, the side wall outer formwork 103 of the outer formwork assembly 1 is fixed to the side wall inner formwork 303 in the outer wall assembly 3 by anti-floating bolts, and the middle partition wall formwork 504 of the middle partition wall assembly 5 is fixed to the secondary casting formwork 603 of the inner wall assembly 6 by anti-floating bolts.
[0050] The present invention performs pouring in a pouring sequence from one end to the other end, and the specific steps are as follows:
[0051] (1) Tie the bottom plate reinforcement and side wall reinforcement;
[0052] (2) Installing the second walking trolley 302, the third walking trolley 502 and the third walking trolley 602 on the inner wall;
[0053] (3) Install the second rail 301, the third rail 501 and the fourth rail 601, and tie the top plate reinforcement;
[0054] (4) Install the end steel shell, install the first walking trolley 101, the first track 102 and the side wall outer template 103, reinforce, and retest;
[0055] (5) pouring concrete, curing, and demoulding;
[0056] (6) Complete the casting of other pipe sections in sequence.
[0057] The concrete of the bottom plate 201, side wall 202, top beam 203 and the second lining 7 in the dock can be cast at one time to reduce the risk of water leakage caused by construction joints. Therefore, the trolley must have an independent track beam to support the trolley, and the track beam is supported on the bottom plate. In order to cope with different casting lengths and cross-sectional forms, the trolley must have the function of independent support and full-section casting.
[0058] The present invention is a formwork trolley specially designed for small space, large section, multi-working surface integrated concrete pouring. It has full hydraulic formwork and demoulding functions, large structural rigidity, high turnover rate, and can be quickly put in place and poured at a fast speed, so as to achieve a concrete structure that is solid inside and beautiful outside. The operator can vibrate or pour concrete on and off the trolley, solve the interference problem between the bottom plate 201 and the side wall 202 steel bar binding and other processes, realize parallel operation, and achieve the purpose of coordinated advancement of each process. When the concrete reaches the designed strength, each trolley is moved forward to carry out the next construction section.
[0059] The trolley of the present invention has the following advantages: (1) saving resources; (2) high efficiency of concrete pouring, and "integrated" simultaneous pouring of concrete on multiple working surfaces; (3) good water tightness, and multiple sections can be lined at the same time, without the need for additional waterproofing treatment at the joints of each section; (4) improving work efficiency, after the first section of the immersed tube concrete is poured, it can move to the next construction section by itself, without the need for additional disassembly and assembly work; (5) low labor intensity, each pouring space is lined with a fully hydraulic self-propelled trolley, and no additional manual demolding operations are required.
[0060] Therefore, the present invention adopts a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley with the above-mentioned structure, which can realize longitudinal movement and lateral adjustment operation by itself. The main structure adopts a modular and standardized assembly type, which is suitable for different structural surfaces and rapid assembly; the operating length of the trolley must be adapted to the lining length, meet the requirements of different lining lengths and different cross-sectional forms, meet the combination of the formwork and the main structure, and realize the rapid positioning and demolding of the formwork; can realize the integrated lining requirements of the bottom plate 201, side wall 202, top beam 203, and second lining 7 to ensure the casting quality; can realize one-time casting of the entire section and meet the safe operation needs of personnel.
[0061] The longitudinal movement function of the present invention is achieved by moving the first walking trolley 101, the second walking trolley 302, the third walking trolley 502, and the fourth walking trolley 602 along the corresponding tracks, while the lateral adjustment function is achieved by the rotating plate telescopic member 3033 pushing or contracting the rotating template 3032 inside the side wall and the telescopic member 6033 outside the middle partition wall pushing or contracting the bottom edge template 6034.
[0062] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the present invention rather than to limit it. Although the present invention has been described in detail with reference to the preferred embodiments, those skilled in the art should understand that they can still modify or replace the technical solution of the present invention with equivalents, and these modifications or equivalent replacements cannot cause the modified technical solution to deviate from the spirit and scope of the technical solution of the present invention.
Claims
1. A small space, large cross section, multi-working surface integrated immersed tube formwork trolley, Features: It comprises an outer mold assembly, which is arranged outside the first lining, and the inner sides of the two side walls of the first lining are respectively provided with outer wall assemblies, and the sides of the two outer wall assemblies close to each other are both provided with vaults and inner wall assemblies, and a middle partition wall assembly is arranged between the bottom plate and the top beam in the middle of the first lining, and the second lining is cast together at the top of the vault and inner wall assembly and between the vault and inner wall assembly and the middle partition wall assembly; The outer mold assembly, the outer wall assembly, the middle partition wall assembly, the vault and the inner wall assembly slide along the length direction of the first lining; The outer mold assembly includes a first track, the first track is fixedly connected to the ground, a first walking trolley is slidably connected to the top of the first track, a side wall outer template is provided on the inner side of the first walking trolley, and the side wall outer template is fitted with the outer sides of the two side walls of the first lining; The outer wall assembly includes a second track, the second track is fixedly connected to the bottom plate, a second walking trolley is slidably connected to the top of the second track, a side wall inner template is provided on the outer side of the second walking trolley, and the side wall inner template is fitted with the inner side of the side wall; The middle partition wall assembly includes a third track, the third track is fixedly connected to the top of the middle part of the bottom plate, a third walking trolley is slidably connected to the third track, a top beam template is provided on the top of the third walking trolley, the top beam template is fitted with the bottom of the top beam, and middle partition wall templates are respectively provided on both sides of the third walking trolley, and the middle partition wall templates are fitted with the secondary lining side walls; The vault and inner wall assembly includes a fourth track, the fourth track is fixedly connected to the top of the bottom plate, the top of the fourth track is slidably connected to a fourth walking trolley, the top of the fourth walking trolley and the side away from the outer wall assembly are both provided with secondary casting templates, and the secondary casting template is fitted with the second lining; The casting method using the above structure comprises the following steps: (1) Tie the bottom plate reinforcement and side wall reinforcement; (2) Install the second, third and fourth walking trolleys on the inner wall; (3) Install the second, third and fourth rails, and tie the top plate reinforcement; (4) Install the end steel shell, the first walking trolley, the first track and the side wall outer formwork, reinforce and re-measure; (5) pouring concrete, curing, and demolding; (6) Complete the casting of other pipe sections in sequence.
2. According to claim 1, a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, Features: The side wall inner template includes a side wall inner main template, which is connected to the second walking trolley. The upper and lower ends of the side wall inner main template are respectively hinged with side wall inner rotating templates. The side wall inner rotating template and the second walking trolley are connected by a rotating plate telescopic part. The side wall inner main template and the side wall inner rotating template are fitted with the inner side of the side wall.
3. According to claim 2, a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, Features: The secondary pouring formwork includes a top formwork, which is connected to the fourth walking trolley, and the top formwork is fitted with the bottom end of the second lining. The side of the top formwork away from the outer wall assembly is hinged with a middle partition wall outer formwork, and the end of the middle partition wall outer formwork away from the top formwork is hinged with a bottom edge formwork. The middle partition wall outer formwork and the bottom edge formwork are fitted with the side wall of the second lining, and the middle partition wall outer formwork, the bottom edge formwork and the fourth walking trolley are connected by a middle partition wall outer telescopic member.
4. According to claim 3, a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, Features: The rotating plate telescopic member and the middle partition wall outer telescopic member are hydraulic cylinders.
5. According to claim 4, a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, Features: The outer mold assembly, the outer side wall assembly, the middle partition wall assembly, the arch and the inner side wall assembly are all provided with steps and an operating platform.
6. According to claim 5, a small space, large cross-section, multi-working surface integrated immersed tube formwork trolley, Features: The outer mold assembly and the outer side wall assembly are fixed by anti-floating bolts, and the middle partition wall assembly, the arch and the inner side wall assembly are fixed by the anti-floating bolts.