Unit plate transfer track system and construction method
By using the unit plate adaptation track system in super high-rise buildings, changing the force transmission direction and guide rail design of the wire rope, the problems of high installation difficulty and cost of traditional lifting equipment in the lifting of super large unit plates are solved, and safe and efficient lifting is achieved Effect.
Patent Information
- Application Number
- CN202311573683.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-11-23
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2043-11-23
Smart Images

Figure CN117759039B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of curtain wall construction, and in particular to a unit plate transfer track system and a construction method. Background Art
[0002] In recent years, with the development of urban construction and the advancement of construction technology, super-high-rise buildings have become one of the main directions of building structure development. People's aesthetic requirements for buildings are getting higher and higher, and various buildings with strong three-dimensional visual effects have emerged in large numbers.
[0003] The building of this project has 55 floors, with every 12 floors forming a bucket. The whole building is composed of 5 bucket-shaped shapes tilted outwards. There is a 3.5m stepback between the facades where the bottom of the upper bucket and the top of the lower bucket meet. Each bucket tilts 2m outwards from the lowest floor to the top floor. The maximum unit plate is 6500mm wide, 6435mm high, and weighs about 2.5t. It is an oversized, overwide, and overweight unit plate. The general unit plate hoisting equipment has limited carrying capacity, and most of them are only suitable for buildings with relatively flat facade shapes. However, the facade shape of the building in this project has complex situations of outward inclination and inward retraction in the direction of curtain wall entry and exit.
[0004] Traditional curtain wall unit panels are generally installed by cantilever crane or ring rail hoisting for vertical transportation. If this scheme adopts the above-mentioned conventional unit panel hoisting equipment scheme for construction, on the one hand, due to the long overhang distance, the requirements on the bearing capacity of the structural components of the hoisting equipment and the reliability of the connection between the hoisting equipment and the main structure are high, the installation is difficult and the safety cannot be guaranteed; on the other hand, if hoisting equipment is installed in each bucket, the construction period will be extended, resulting in increased construction costs. Summary of the invention
[0005] The present invention provides a unit plate transfer track system and a construction method, which have the advantages of low installation difficulty, high safety and low construction cost.
[0006] The technical problems to be solved are: the overhang distance of the lifting equipment is too long, the installation is difficult, and the safety cannot be guaranteed; if lifting equipment is installed in each bucket, the construction period will be extended, resulting in increased construction costs; the vertical lifting problem of oversized, overwide, and overweight unit panels in the outward-inclined curtain wall project.
[0007] In order to solve the above technical problems, the present invention adopts the following technical solutions:
[0008] The present invention discloses a unit plate transfer track system, comprising a guide rail, a mounting keel fixed at the bottom of the guide rail, a transfer keel fixed at intervals on the mounting keel for fixing to a building structure, and a pulley assembly slidably mounted on the side of the guide rail, wherein a force-bearing pulley resting against the mounting keel is mounted on the pulley assembly, the pulley assembly is used to pass a steel wire rope of a hoisting device, and the force-bearing pulley is used to travel on the mounting keel.
[0009] The present invention provides a unit plate transfer track system. Further, the guide rail is hollow inside, and a slide groove penetrating the inside is opened on the side of the guide rail along its length direction. A slider is slidably provided inside the guide rail, and the slider is connected to an external pulley assembly through a connecting block penetrating the slide groove.
[0010] The present invention provides a unit plate transfer track system. Further, the pulley assembly comprises a bottom plate, two side plates fixed on the bottom plate, and a main pulley installed between the two side plates, and the connecting block is fixed on the bottom plate.
[0011] The present invention provides a unit plate transfer track system. Further, a connecting plate is fixedly provided on the bottom plate, and the force-bearing pulleys are respectively installed at both ends of the connecting plate.
[0012] The present invention provides a unit plate transfer track system, and further, the force-bearing pulleys are arranged in pairs at the ends of the connecting plates.
[0013] The present invention provides a unit plate transfer track system. Further, the side plate is provided with an anti-slip device for preventing the steel wire rope from being detached from the main pulley.
[0014] The present invention provides a unit plate transfer track system. Further, the anti-slip device comprises ear plates respectively fixed on the side plates and a limiting rod connected between the ear plates.
[0015] The present invention provides a unit plate transfer track system. Further, the limit rod is a screw rod, which is fixed on the ear plate through a nut.
[0016] The present invention provides a construction method, comprising the following steps:
[0017] S1. Install cantilever hoisting equipment on the top surface of the building structure, horizontally install the transfer track system along the outline of the building structure at the protruding position of the building structure facade, and fix the transfer keel to the protruding building structure;
[0018] S2. Pass the wire rope of the hoisting equipment through the main pulley and change the direction of the inclined wire rope so that the unit plate located in the lower bucket can be hoisted vertically;
[0019] S3. Connect the unit panels and lift them vertically. After lifting them to the installation layer, the staff at the installation layer controls the wire rope to move the unit panels horizontally along the guide rails to the installation position. At the same time, the wire rope is loosened as the unit panels move horizontally. After they are moved into place, the unit panels are disassembled and the next unit panel is lifted.
[0020] Compared with the prior art, the present invention has the following beneficial effects:
[0021] 1. The present application sets a main pulley at the protruding part of the building structure facade in the vertical hoisting path of the traditional hoisting equipment to change the force transmission direction of the wire rope, change the direction of the inclined wire rope of the top hoisting equipment, and realize vertical hoisting of the unit plate located in the lower bucket; and slides with the guide rail set in the horizontal direction to set a reliable translation track for the main pulley, while changing the vertical hoisting direction, it can ensure that the main pulley can move smoothly in the horizontal direction, and in the super high-rise unit curtain wall building with non-coplanar vertical direction and outward or inward façade shape, it can realize the vertical and horizontal hoisting of super large unit plates;
[0022] 2. This application is applicable to super high-rise unit curtain wall buildings with non-coplanar curtain walls and outward or inward inclined facades. On the basis of the traditional vertical lifting of unit panels, the transfer system of this application solves the problem of non-coplanar lifting of unit panels, achieving the purpose of reducing costs and increasing efficiency;
[0023] 3. Compared with traditional lifting equipment, this application solves the problem of lifting unit plates that are not coplanar, and reduces the installation density of lifting equipment; compared with ring rail lifting equipment, it solves the problem of installing lifting equipment in each bucket, extending the construction period, and increasing construction costs. By using a transfer device, the requirements for the external cantilever distance of the lifting equipment are reduced, and the requirements for the bearing capacity of the structural components of the lifting equipment, the reliability of the connection between the lifting equipment and the building structure, etc. are reduced. It has the advantages of low installation difficulty, high safety, and low construction cost;
[0024] 4. This application has a wider scope of application and can be used for relatively complex building structure outlines; the mechanical structure is simple, easy to install, and the installation cost is low; the connection is reliable and the safety is high;
[0025] 5. Compared with the prior art, the present application adds a transfer system in the middle of the lifting wire rope, so that a set of lifting equipment can be used to realize the vertical lifting of multiple non-coplanar curtain walls. In practical applications, the present device improves the installation efficiency of the unit panels and reduces the number of hook changes during the lifting, transportation and installation of the unit panels.
[0026] The present invention will be further described below in conjunction with the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1This is a schematic diagram of the transfer track installation structure of the present invention;
[0028] Figure 2 It is a structural schematic diagram of the present invention highlighting the transfer track;
[0029] Figure 3 It is a plan view of the transfer track of the present invention.
[0030] Reference numerals:
[0031] 1. Guide rail; 2. Install keel; 3. Transfer keel; 4. Pulley assembly; 4.1. Bottom plate; 4.2. Side plate; 4.3. Main pulley; 4.4. Slider; 4.5. Connecting block; 5. Force pulley; 6. Building structure; 7. Wire rope; 8. Connecting plate; 9. Anti-slip device; 9.1. Ear plate; 9.2. Limit rod. DETAILED DESCRIPTION
[0032] like Figure 1-Figure 3 As shown, the present invention discloses a unit plate transfer track system and a construction method, the system includes a guide rail 1, an installation keel 2, a transfer keel 3, a pulley assembly 4 and a force pulley 5, the guide rail 1 is used to be set at a protruding position of the facade of the building structure 6, and is horizontally arranged along the facade of the building structure 6, so that the wire rope 7 can move horizontally smoothly in the direction of the guide rail 1; the interior of the guide rail 1 is hollow, and a slide groove that penetrates the interior is opened on the side along its length direction.
[0033] The installation keel 2 is arranged along the length direction of the guide rail 1 at the bottom of the guide rail 1, and the installation keel 2 is reliably connected to the guide rail 1 by welding. The transfer keel 3 is fixedly arranged at intervals on the side of the installation keel 2, and is used to be fixedly connected to the building structure 6. The transfer keel 3 is perpendicular to the installation keel 2. The installation keel 2 is used to withstand the pressure generated by the hoisting unit plate at the transfer system, and then this pressure is reliably transmitted to the building structure 6 through the transfer keel 3 perpendicular to the curtain wall direction.
[0034] The pulley assembly 4 is slidably matched with the guide rail 1, and is used to pass the steel wire rope 7, change the direction of the inclined steel wire rope 7 of the top hoisting equipment, so that the unit plate located in the lower bucket can be vertically hoisted. At the same time, the pulley assembly 4 enables the steel wire rope 7 to be lifted and lowered vertically smoothly during hoisting; in addition, the pulley assembly 4 is slidably matched with the guide rail 1, which can enable the unit plate to move horizontally along the guide rail 1, reducing the installation density of the hoisting equipment. The pulley assembly 4 includes a bottom plate 4.1, two side plates 4.2 vertically fixed on the bottom plate 4.1, and a main pulley 4.3 installed between the two side plates 4.2 through a rotating shaft. A slider 4.4 is slidably provided inside the guide rail 1, and the slider 4.4 is connected to the bottom plate 4.1 through a connecting block 4.5 that penetrates the slide groove, and the connecting block 4.5 is fixedly connected to the bottom plate 4.1.
[0035] The force pulley 5 is installed on the bottom plate 4.1, and can slide horizontally along the installation keel 2 to transfer the pressure of the unit plate at the transfer system to the installation keel 2. The force pulley 5 and the slider 4.4 cooperate with each other to limit the position of the pulley assembly 4 to prevent the pulley assembly 4 from shaking during operation. A connecting plate 8 is fixedly installed on the bottom of the side plate 4.2 on the bottom plate 4.1, and the two ends of the connecting plate 8 extend out of the side plate 4.2 area to both sides. The force pulleys 5 are respectively installed at the two ends of the connecting plate 8, and the force pulleys 5 are arranged in pairs at the ends of the connecting plate 8.
[0036] The side plate 4.2 is provided with an anti-slip device 9 for preventing the steel wire rope 7 from being detached from the main pulley 4.3. The anti-slip device 9 comprises ear plates 9.1 respectively fixed on the side plate 4.2 and a limit rod 9.2 connected between the ear plates 9.1. The steel wire rope 7 is located between the main pulley 4.3 and the limit rod 9.2, so as to prevent the steel wire rope 7 from being detached. Furthermore, the limit rod 9.2 is a screw rod, which is fixed to the ear plate 9.1 by a nut.
[0037] In one embodiment of the present application, since the unit panels are heavy, the transition system is subjected to greater pressure during operation, and therefore, both the installation keel 2 and the transition keel 3 are made of 80*80*5mm steel square tubes.
[0038] The working principle is that a main pulley 4.3 is arranged at a protruding part of the facade of the building structure 6 in the vertical lifting path of the traditional lifting equipment to change the force transmission direction of the wire rope 7, and change the direction of the inclined wire rope 7 of the top lifting equipment to realize vertical lifting of the unit plate located in the lower bucket; and a reliable translation track is arranged for the main pulley 4.3 by slidingly cooperating with the guide rail 1 arranged in the horizontal direction, while changing the vertical lifting direction, it can ensure that the main pulley 4.3 can move smoothly in the horizontal direction, and in super-high-rise unit curtain wall buildings with non-coplanar vertical directions and outward or inward-inclined facades, vertical and horizontal lifting of super-large unit plates can be realized; the various components of the device have reliable connections to meet the bearing capacity requirements.
[0039] This application is applicable to super-high-rise unit curtain wall buildings whose curtain walls are not coplanar along the vertical direction and whose facades are outward or inward inclined. Based on the vertical lifting of traditional unit panels, the transfer system of this application solves the lifting problem of non-coplanar unit panels, thereby achieving the purpose of reducing costs and increasing efficiency.
[0040] Compared with traditional lifting equipment, it solves the lifting problem of non-coplanar unit plates and reduces the installation density of lifting equipment.
[0041] Compared with the ring rail lifting equipment, it solves the problem of installing lifting equipment in each bucket, extending the construction period and increasing the construction cost. In addition, by using the adapter, it reduces the requirements for the external cantilever distance of the lifting equipment, reduces the bearing capacity of the structural components of the lifting equipment, and the reliability of the connection between the lifting equipment and the building structure. It has the advantages of low installation difficulty, high safety and low construction cost.
[0042] The construction method includes the following steps:
[0043] S1. Install cantilever hoisting equipment on the top surface of the building structure, horizontally install the transfer track system along the outline of the building structure at the protruding position of the building structure facade, and fix the transfer keel to the protruding building structure;
[0044] S2. Pass the wire rope of the hoisting equipment through the main pulley and change the direction of the inclined wire rope so that the unit plate located in the lower bucket can be hoisted vertically;
[0045] S3. Connect the unit panels and lift them vertically. After lifting them to the installation layer, the staff at the installation layer controls the wire rope to move the unit panels horizontally along the guide rails to the installation position. At the same time, the wire rope is loosened as the unit panels move horizontally. After they are moved into place, the unit panels are disassembled and the next unit panel is lifted.
[0046] The embodiments described above are merely descriptions of preferred implementation modes of the present invention and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.
Claims
1. A unit plate transfer track system, characterized by: The invention comprises a guide rail (1), a mounting keel (2) fixed at the bottom of the guide rail (1), a transfer keel (3) fixed at intervals on the mounting keel (2) for fixing to a building structure (6), and a pulley assembly (4) slidably mounted on the side of the guide rail (1), wherein a force pulley (5) is mounted on the pulley assembly (4) and abuts against the mounting keel (2), wherein the pulley assembly (4) is used to pass a steel wire rope (7) of a lifting device, and the force pulley (5) is used to travel on the mounting keel (2); the guide rail (1) is hollow inside, and a slide groove that penetrates the inside is opened on the side of the guide rail (1) along its length direction, and the guide rail (1) 1) A slider (4.4) is provided inside for sliding, and the slider (4.4) is connected to an external pulley assembly (4) through a connecting block (4.5) penetrating a slide groove; the pulley assembly (4) comprises a bottom plate (4.1), two side plates (4.2) fixed on the bottom plate (4.1), and a main pulley (4.3) installed between the two side plates (4.2), and the connecting block (4.5) is fixed on the bottom plate (4.1); a connecting plate (8) is fixed on the bottom plate (4.1), and the force pulleys (5) are respectively installed at both ends of the connecting plate (8); the force pulleys (5) are arranged in pairs at the ends of the connecting plate (8).
2. A unit plate transfer track system according to claim 1, characterized in that: The side plate (4.2) is provided with an anti-slip device (9) for preventing the steel wire rope (7) from being detached from the main pulley (4.3).
3. A unit plate transfer track system according to claim 2, characterized in that: The anti-slip device (9) comprises ear plates (9.1) respectively fixed on the side plates (4.2) and a limiting rod (9.2) connected between the ear plates (9.1).
4. A unit plate transfer track system according to claim 3, characterized in that: The limiting rod (9.2) is a screw rod, which is fixed on the ear plate (9.1) through a nut.
5. A construction method, comprising the unit plate transfer track system according to any one of claims 1 to 4, characterized in that: The following steps are involved: S1. Install a cantilever hoisting device on the top surface of the building structure (6), horizontally install a transfer track system along the outline of the building structure (6) at a protruding position of the facade of the building structure (6), and fix the transfer keel (3) to the protruding building structure (6); S2, passing the steel wire rope (7) of the hoisting equipment through the main pulley (4.3), changing the direction of the inclined steel wire rope (7), so that the unit plate located in the lower bucket can be lifted vertically; S3, connect the unit panels, and vertically hoist the unit panels. After hoisting to the installation layer, the staff at the installation layer controls the steel wire rope (7) to horizontally move the unit panels along the guide rail (1) to the installation position. At the same time, the steel wire rope (7) is loosened as the unit panels move horizontally. After the units are moved into place, the unit panels are disassembled and the next unit panel is hoisted.
Citation Information
Patent Citations
Cantilever steel beam double-track curtain wall hoisting system and curtain wall plate hoisting method
CN113914638A
Building outer inclined curved surface curtain wall installation construction device and construction method thereof
CN114482576A
Hoisting equipment for super high-rise variable cross-section unit type glass curtain wall
CN115626567A
Locate fixed pulley on superstructure flange roof beam
CN206927521U
Super-thick unit plate hoisting rail device
CN212356271U