A floating breakwater for offshore photovoltaic power generation and construction method thereof

By introducing flexible partitions and drive components into the floating breakwater, adjusting the attitude and volume of the floating box, combining the cable assembly and connecting column structure, the problem of insufficient protection of existing floating breakwaters when the waves are large, achieving higher Flexibility and defense capabilities ensure the safety of offshore photovoltaic equipment.

CN117779684BActive Publication Date: 2024-12-06TIANJIN UNIVERSITY OF SCIENCE & TECHNOLOGY ASSET MANAGEMENT CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410159162.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-04
Publication Date
2024-12-06
Estimated Expiration
2044-02-04

AI Technical Summary

Technical Problem

The existing floating breakwater cannot effectively protect offshore photovoltaic equipment when the waves are large, and its adjustment flexibility is insufficient, so it cannot effectively deal with different wave conditions.

Method used

A floating breakwater including upper and lower floating boxes, flat panels and anchor blocks is designed. By setting flexible partitions and driving components in the floating box, the amount and volume of sea water in the storage cavity is adjusted, and the overall adjustment of the floating box posture is achieved. The defense capability is enhanced through a combined structure of cable assembly and connecting posts.

Benefits of technology

It realizes effective protection of offshore photovoltaic equipment when the waves are large, increases the adjustable attitude and flexibility of the floating box, improves the blocking ability of the waves, and ensures the safety of photovoltaic equipment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117779684B_ABST
    Figure CN117779684B_ABST
Patent Text Reader

Abstract

A floating breakwater for an offshore photovoltaic power plant comprises a pontoon, a flat plate and a plurality of anchor blocks arranged up and down, the pontoon, the flat plate and the anchor blocks are connected by a cable assembly, a plurality of flexible baffles are arranged in the pontoon, the plurality of flexible baffles separate the inner cavity of the pontoon into a plurality of accommodating cavities, the bottom of the accommodating cavity is provided with a water inlet and an outlet, the top is provided with an air inlet and an air outlet, and a driving assembly is also arranged in the pontoon, the driving assembly is used to drive the deformation of the flexible baffle, and the volume of the accommodating cavity can be changed during the deformation of the flexible baffle. The present invention provides a floating breakwater for an offshore photovoltaic power plant and a construction method, which can fully protect the offshore photovoltaic equipment by adjusting the posture of the pontoon as a whole, and the adjustment flexibility is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of breakwaters, in particular to a floating breakwater for an offshore photovoltaic power plant and a construction method thereof. Background Art

[0002] Energy shortage and pollution have always been important issues that need to be addressed for social development. As a clean energy source, solar energy is the main object of research and development in my country, among which photovoltaic power generation is the main way to utilize solar energy. Compared with traditional onshore photovoltaics, under the same lighting conditions, offshore photovoltaics can not only be laid on a large scale, but also are not limited by site space, and have the advantages of long sunshine time and high radiation. Moreover, my country has a long coastline and vast sea areas. Therefore, offshore photovoltaic technology has developed rapidly. However, in offshore photovoltaic power plants, photovoltaic equipment needs to be exposed to a humid and windy marine environment for a long time, and withstand the impact of waves, wind and other unfavorable conditions. In order to protect photovoltaic equipment, breakwaters have become an important part of offshore photovoltaic power plants.

[0003] As a coastal protection engineering structure, breakwaters are divided into fixed and floating types. Fixed breakwaters can only be deployed in shallow water areas, not in deep water areas, because deep water areas have great requirements on the strength and construction of breakwaters, and the investment cost is very high. Fixed breakwaters will also affect the normal activities of marine organisms. Compared with fixed breakwaters, floating breakwaters are composed of floating structures and mooring systems. They eliminate waves through the interaction between floating bodies and waves. They have low construction costs and are less affected by seabed geological conditions and water depth. They are easy to transport and dismantle, and can be reused to achieve seawater exchange functions, reducing the impact on the ecology.

[0004] The existing floating breakwater mainly includes a floating body, a sway control plate and an anchor base distributed up and down. The floating body mainly adopts a box-type structure, and the buoyancy is adjusted by changing the amount of gas inside. The main way to change the amount of gas inside is to extract seawater into the interior and discharge the gas. Although the effect of controlling the buoyancy can be achieved, because the seawater inside is evenly distributed, the buoyancy at each position of the floating body is the same, so that the floating body can only remain in a horizontal state. When the waves are large, it is easy to pass over the floating body and directly impact the protected photovoltaic equipment, causing damage to the photovoltaic equipment. Summary of the invention

[0005] In order to address the deficiencies in the prior art, the present invention provides a floating breakwater for an offshore photovoltaic power plant and a construction method, which can fully protect the offshore photovoltaic equipment by adjusting the posture of the pontoon as a whole, and has high adjustment flexibility.

[0006] In order to achieve the above-mentioned purpose, the specific scheme adopted by the present invention is: a floating breakwater for an offshore photovoltaic power plant, comprising a pontoon, a flat plate and a plurality of anchor blocks arranged up and down, the pontoon, the flat plate and the anchor blocks are connected by a cable assembly, a plurality of flexible baffles are arranged in the pontoon, and the plurality of flexible baffles divide the inner cavity of the pontoon into a plurality of accommodating cavities, a water inlet and an outlet are arranged at the bottom of the accommodating cavity, and an air inlet and an exhaust port are arranged at the top, and a driving assembly is also arranged in the pontoon, and the driving assembly is used to drive the deformation of the flexible baffle, and the volume of the accommodating cavity can be changed during the deformation of the flexible baffle.

[0007] Preferably, the driving assembly includes a plurality of linear drivers corresponding to the flexible baffles, and the output ends of the linear drivers are fixedly connected to the flexible baffles via connecting sheets.

[0008] Preferably, the flexible baffles are arranged in an even number, and every two of the flexible baffles form a group. The driving assembly includes at least one conveying pump, and the conveying pump is arranged correspondingly between the two flexible baffles in the same group. The conveying pump is connected to a guide pipe, and a guide cover is arranged on each side of the guide pipe. The two guide covers are fixedly connected to the two flexible baffles in the same group, and the guide cover and the flexible baffles enclose a guide chamber, and the guide chamber is connected to the guide pipe and a guide valve is arranged at the connecting position.

[0009] Preferably, the buoyancy box and the flat plate are connected via a plurality of connecting columns, the connecting columns comprising an upper mounting sleeve, a lower mounting sleeve and a column body, the upper mounting sleeve is fixedly connected to the buoyancy box, the lower mounting sleeve is fixedly connected to the flat plate, two ends of the column body are respectively inserted into the upper mounting sleeve and the lower mounting sleeve, and the column body comprises a flexible center rod and a flexible sleeve sleeved around the flexible center rod.

[0010] Preferably, a protective sleeve is fixed on the peripheral side wall of the flexible central rod, a distance is left between the protective sleeve and the flexible sheath to form a cavity, the flexible central rod and the two ends of the flexible sheath are fixedly connected by end plates, and the end plates close the cavity.

[0011] Preferably, a plurality of connecting fibers are fixedly connected between the protective cover and the flexible sheath, the plurality of connecting fibers are evenly divided into a plurality of groups, the plurality of groups of connecting fibers are evenly distributed along the circumferential direction of the flexible center rod, and the connecting fibers in the same group are distributed along the axial direction of the flexible center rod.

[0012] Preferably, the outer side of the end plate is connected to a mounting plate via connecting bolts, and the peripheral side wall of the mounting plate is detachably connected to an inner sleeve, and the inner sleeve can be inserted into the upper mounting sleeve or the lower mounting sleeve and fixed.

[0013] Preferably, the cable assembly includes a main cable movably connected to the buoy, a secondary cable movably connected to the flat plate, and a connecting cable movably connected to the anchor block, and the main cable, the secondary cable and the connecting cable are connected.

[0014] Preferably, a liquid level sensor is provided in the accommodating cavity, a fluid replenishing mechanism is fixedly provided on the buoyancy tank, the fluid replenishing mechanism comprises a plurality of fluid replenishing pumps correspondingly connected to the accommodating cavities, and all the fluid replenishing pumps and all the liquid level sensors are commonly connected to a controller.

[0015] A construction method for installing the above-mentioned floating breakwater for an offshore photovoltaic power plant comprises the following steps:

[0016] S1. Determine parameter requirements;

[0017] S2, fixing the anchor block;

[0018] S3, moving the floating breakwater to an installation position, and making the pontoon float vertically on the sea surface;

[0019] S4, filling the accommodating chamber with water to make the buoyancy box sink, and stopping filling water when the buoyancy box is submerged in the seawater;

[0020] S5, connecting the buoyancy box, the flat plate and the anchor block by using the cable assembly;

[0021] S6. Based on the parameter requirement, drain the water in the accommodating chamber to make the buoyancy box float up, until the position of the buoyancy box meets the parameter requirement.

[0022] The floating breakwater of the present invention forms a plurality of accommodating chambers by arranging flexible partitions inside the pontoon, and adjusts the buoyancy at various positions of the pontoon by changing the amount of seawater extracted from the accommodating chambers. The posture of the pontoon can be adjusted as a whole, and the wave-facing area can be increased to prevent the waves from passing over the pontoon when the waves are large, thereby achieving full protection for the offshore photovoltaic equipment. In addition, the flexible partitions can be deformed to change the volumes of different accommodating chambers, and the flexibility is higher when adjusting the amount of seawater in the accommodating chambers, so that the pontoon can achieve more postures. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1It is a three-dimensional diagram of the overall structure of the floating breakwater;

[0025] Figure 2 It is a side view of the overall structure of the floating breakwater;

[0026] Figure 3 It is a top view of the overall structure of the floating breakwater;

[0027] Figure 4 This is a simplified diagram of the installation method of the connecting column;

[0028] Figure 5 It is a schematic diagram of the arrangement of multiple floating breakwaters;

[0029] Figure 6 It is a schematic diagram of the state changes during the construction of the floating breakwater;

[0030] Figure 7 It is a structural schematic diagram of the connecting column;

[0031] Figure 8 It is a schematic diagram of the structure of the first type of drive assembly;

[0032] Fig. 9 Schematic diagram of the structure of the second drive component.

[0033] Figure markings: 1-floating tank, 101-tank, 102-linear drive, 103-connecting plate, 104-water inlet and outlet, 105-flexible partition, 106-delivery pump, 107-guide pipe, 108-guide cover, 109-guide chamber, 110-guide valve, 2-flat plate, 3-upper mounting sleeve, 4-lower mounting sleeve, 5-connecting column, 501-inner sleeve, 502-mounting hole, 503-mounting plate, 504-end plate, 505-connecting bolt, 506-flexible sleeve, 507-flexible center rod, 508-cavity, 509-connecting fiber, 510-protective cover, 6-fastening bolt, 7-fastening nut, 8-lifting ring, 9-anchor block, 10-main cable, 11-auxiliary cable, 12-connecting cable, 13-shackle, 14-clip. DETAILED DESCRIPTION

[0034] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0035] like Figures 1 to 5As shown in Figures 7 to 9, a floating breakwater for an offshore photovoltaic power plant includes a pontoon 1, a flat plate 2 and a plurality of anchor blocks 9 arranged up and down, the pontoon 1, the flat plate 2 and the anchor blocks 9 are connected by a cable assembly, a plurality of flexible baffles 105 are arranged in the box body 101 of the pontoon 1, and the plurality of flexible baffles 105 divide the inner cavity of the pontoon 1 into a plurality of accommodating cavities, a water inlet and outlet 104 is arranged at the bottom of the accommodating cavity, and an air inlet and outlet is arranged at the top, a driving assembly is also arranged in the pontoon 1, and the driving assembly is used to drive the flexible baffle 105 to deform, and the volume of the accommodating cavity can be changed during the deformation process of the flexible baffle 105.

[0036] In the floating breakwater of the present invention, the buoyancy of the pontoon 1 is adjusted by changing the amount of water in the internal accommodating chamber, and the position of the pontoon 1 is adjusted by changing the size of the buoyancy of the pontoon 1, thereby ensuring that the cable assembly is always in a tensioned state, fully realizing the function of preventing wave invasion, and protecting the photovoltaic components of the offshore photovoltaic power plant. When the waves are large, in order to prevent the waves from crossing the floating breakwater and directly invading the photovoltaic power plant, the present invention separates a plurality of accommodating chambers inside the pontoon 1 by a plurality of flexible partitions 105, and can change the amount of water in different accommodating chambers to adjust the buoyancy of different positions of the pontoon 1, so that the pontoon 1 can be tilted on the sea surface, thereby increasing the wave-facing area and achieving a better function of blocking the waves. On the other hand, the present invention sets a driving component, and the driving component can drive the flexible partition 105 to deform, thereby changing the volume of the accommodating chamber, so that the adjustment range of the buoyancy of each accommodating chamber changes, improves the overall flexibility, and finally expands the overall adjustable tilt angle range of the pontoon 1.

[0037] The number of accommodating cavities and the number of flexible partitions 105 in the pontoon 1 can be determined according to the size of the pontoon 1 and actual needs. For a large-sized pontoon 1, more accommodating cavities can be formed by setting more flexible partitions 105, which can improve the flexibility of the adjustment process.

[0038] The detailed structures of two specific drive components are provided below.

[0039] The first driving assembly includes a plurality of linear actuators 102 corresponding to the flexible partition 105, and the output end of the linear actuator 102 is fixedly connected to the flexible partition 105 through a connecting piece 103. The linear actuator 102 can adopt a conventional linear driving device such as a cylinder, a hydraulic cylinder or an electric push rod, and the flexible partition 105 is pushed or pulled to deform by changing the overall length of the linear actuator 102, so as to achieve the effect of adjusting the volume of the accommodating cavity. In a specific embodiment, the flexible partition 105 can be set to two, and three accommodating cavities arranged along a straight line can be separated, and the linear actuator 102 is correspondingly set to two, and the two linear actuators 102 are respectively fixedly set in the two accommodating cavities located at both ends, and are respectively connected to the two flexible partitions 105. The two flexible partitions 105 can be driven to deform individually by the two linear actuators 102, so that the volume of the three accommodating cavities can be adjusted flexibly.

[0040] The specific setting form of the second driving component is: the flexible baffles 105 are set to an even number, and every two flexible baffles 105 form a group. The driving component includes at least one delivery pump 106, and the delivery pump 106 is correspondingly arranged between the two flexible baffles 105 in the same group. The delivery pump 106 is connected to the guide pipe 107, and a guide cover 108 is arranged on both sides of the guide pipe 107. The two guide covers 108 are fixedly connected to the two flexible baffles 105 in the same group, and the guide covers 108 and the flexible baffles 105 enclose a guide chamber 109, and the guide chamber 109 is connected to the guide pipe 107 and a guide valve 110 is arranged at the connecting position. When it is necessary to drive the flexible baffle 105 to deform, the water or air in a accommodating cavity in which it is located is input into the guide tube 107 by using the delivery pump 106, and then the guide valve 110 between the guide cover 108 connected to the flexible baffle 105 to be driven and the guide tube 107 is opened, so that the water or gas delivered by the delivery pump 106 can enter the guide chamber through the guide valve 110, and then squeeze the flexible baffle 105 to deform it.

[0041] Compared with the two different drive components, the first drive component has a simpler structure and is easy to install and control, but the linear drive 102 requires a higher energy supply and a higher sealing and waterproofing requirement, and the cost is also higher; in the second drive component, only the delivery pump 106 has a larger energy demand, while the diverter valve 110 has a smaller energy demand, so the overall energy supply required is small, but the overall structure is more complicated and the installation is more difficult. The first or second drive component can be selected according to actual needs.

[0042] Considering that the relative position and posture of the pontoon 1 and the flat plate 2 will change during the impact of the waves, in order to avoid deformation caused by excessive force on the pontoon 1 and the flat plate 2 during such changes, the pontoon 1 and the flat plate 2 are connected by a plurality of connecting columns 5, the connecting column 5 includes an upper mounting sleeve 3, a lower mounting sleeve 4 and a column body, the upper mounting sleeve 3 is fixedly connected to the pontoon 1, the lower mounting sleeve 4 is fixedly connected to the flat plate 2, the two ends of the column body are respectively inserted into the upper mounting sleeve 3 and the lower mounting sleeve 4, and the column body includes a flexible central rod 507 and a flexible sheath 506 sleeved on the side of the flexible central rod 507. The flexible column body composed of the flexible central rod 507 and the flexible sheath 506 can be deformed, and in the process of the relative position and posture change between the pontoon 1 and the flat plate 2, the impact force on the pontoon 1 and the flat plate 2 can be absorbed by deformation, thereby protecting the pontoon 1 and the flat plate 2, and after the waves subside, it can be restored and drive the pontoon 1 and the flat plate 2 to restore, so as to maintain the stability of the overall shape of the floating breakwater.

[0043] Furthermore, a protective cover 510 is fixedly provided on the peripheral side wall of the flexible central rod 507, and a distance is left between the protective cover 510 and the flexible sheath 506 to form a cavity 508. The two ends of the flexible central rod 507 and the flexible sheath 506 are fixedly connected by end plates 504, and the end plates 504 close the cavity 508. By providing the cavity 508 and closing the cavity 508, the buoyancy of the connecting column 5 as a whole can be increased, thereby cooperating with the buoyancy box 1 to improve the performance of preventing wave invasion. The protective cover 510 and the flexible sheath 506 can jointly protect the flexible central rod 507 from being damaged by seawater erosion.

[0044] In order to further ensure that the connection column 2 can be smoothly restored after deformation, multiple connection fibers 509 are fixedly connected between the protective cover 510 and the flexible sheath 506. The multiple connection fibers 509 are evenly divided into multiple groups. The multiple groups of connection fibers 509 are evenly distributed along the circumferential direction of the flexible center rod 507, and the connection fibers 509 in the same group are distributed along the axial direction of the flexible center rod 507. The connection line 509 can pull the flexible center rod 507 and the flexible sheath 506 through its own elastic force, and pull the two to restore after the two are deformed and the waves subside. The multiple connection fibers 509 can pull the two to restore from different directions and positions, thereby fully ensuring that the connection column 5 can be smoothly restored after deformation.

[0045] In the present invention, the flexible center rod 507 can be formed by bundling multiple elastic metal wires, such as stainless steel wires. The protective cover 510 and the flexible sheath 506 can both be made of rubber material resistant to seawater corrosion. The connecting fiber 509 can be made of polymer elastic fiber. All of these are existing materials and will not be described in detail here.

[0046] The specific connection method of the connecting column 5 and the upper mounting sleeve 3 and the lower mounting sleeve 4 is as follows: the outer side of the end plate 504 is connected to the mounting plate 503 by a connecting bolt 505, and the peripheral side wall of the mounting plate 503 is detachably connected to the inner sleeve 501, and the inner sleeve 501 can be inserted into the upper mounting sleeve 3 or the lower mounting sleeve 4 and fixed. The fixing method is to use the fastening bolt 6 and the fastening nut 7 to achieve the fixing, and the upper mounting sleeve 3, the lower mounting sleeve 4 and the inner sleeve 501 are all provided with a mounting hole 502 for the fastening bolt 6 to pass through.

[0047] The specific structure of the cable assembly is as follows: the cable assembly includes a main cable 10 movably connected to the buoy 1, an auxiliary cable 11 movably connected to the flat plate 2, and a connecting cable 12 movably connected to the anchor block 9, and the main cable 10, the auxiliary cable 11 and the connecting cable 12 are connected.

[0048] In the present invention, the flat plate 2 can also be reinforced by adding a grid-shaped reinforcement frame made of steel material, which can be added to the lower surface of the flat plate 2, or a space can be opened inside the flat plate 2 to fix the grid-shaped reinforcement frame to the space, or the flat plate 2 can be directly formed by welding plates inside each grid based on the grid-shaped reinforcement frame. Reinforcing the flat plate 2 with the grid-shaped reinforcement frame can prevent the large-sized flat plate 2 from being damaged by the impact of waves due to insufficient strength.

[0049] More specifically, in the case of a seawater depth of 13m, in a specific embodiment, the pontoon 1 is 19.4m long perpendicular to the wave direction, 7.5m wide along the wave direction, and 1.4m high; the flat plate 2 is 19.4m long perpendicular to the wave direction, 7.5m wide along the wave direction, and 0.01m thick; the distance between the pontoon 1 and the flat plate 2 is 2.5m; the number of connecting columns 5 is set to five, and is evenly distributed along the length direction of the pontoon 1, the outer diameter of the protective cover 510 is 0.8m, the outer diameter of the flexible cover 506 is 0.96m, and the overall height is 2.5m; the height of the upper installation sleeve 3 and the lower installation sleeve 4 are both 0.6m. The number of anchor blocks 9 is 4, the number of main cables 10, auxiliary cables 11 and connecting cables 12 are all 4, and the diameters are all 0.16m, wherein the main cable 10 is 4.2m long, the auxiliary cable 11 is 2.6m long, and the connecting cable 12 is 10.8m long; the diameter of the fastening bolt 7 and the fastening nut 8 is 0.16m. Four lifting rings 8 are fixedly arranged at the bottom of the buoy 1 and the bottom of the flat plate 2, and the distance between them and the long side perpendicular to the wave direction is 0.28m, and the distance between them and the wide side along the wave direction is 4.85m. The size of the hollow part of the lifting ring 8 should be larger than the diameter of the main cable 10, the auxiliary cable 11 and the connecting cable 12; the connecting positions of the main cable 10, the auxiliary cable 11 and the connecting cable 12 are connected by a shackle 13. When the main cable 10, the auxiliary cable 11 and the connecting cable 12 are connected to the lifting ring 8, the end parts are wound around a ring structure and fixed by a buckle 14. The number of the shackles 13 is 4, and the number of the buckles 14 is 24.

[0050] In order to achieve precise control of the buoyancy of the float 1, a liquid level sensor is provided in the accommodating chamber, and a liquid replenishing mechanism is fixedly provided on the float 1. The liquid replenishing mechanism includes a plurality of liquid replenishing pumps connected to the corresponding accommodating chambers. The liquid replenishing pumps fill water into the accommodating chambers through the water inlet and outlet 104. All the liquid replenishing pumps and all the liquid level sensors are connected to a controller.

[0051] like Figure 6 As shown, the present invention further provides a construction method for installing the above-mentioned floating breakwater for an offshore photovoltaic power plant, the method comprising the following steps: Figure 6 From top to bottom in the figure is the state change process of the floating breakwater during construction.

[0052] S1. Determine parameter requirements based on the actual situation of the offshore photovoltaic power plant. The parameter requirements include the mooring force value required for each cable of the cable assembly when it is tensioned, which is 2624 kN in this embodiment.

[0053] S2. Fix the anchor block 9.

[0054] S3, moving the floating breakwater to the installation position, and making the pontoon 1 float vertically on the sea surface.

[0055] S4, filling water into the accommodating chamber to make the buoyancy box 1 sink, and stopping filling water when the buoyancy box 1 is submerged in the sea water.

[0056] S5. Connect the buoyancy box 1, the flat plate 2 and the anchor block 9 using a cable assembly.

[0057] S6. Based on the parameter requirements, the water in the accommodating chamber is discharged to make the buoyancy box 1 float up, until the position of the buoyancy box 1 meets the parameter requirements.

[0058] The various embodiments in this specification are described in a progressive manner, and each embodiment focuses on the differences from other embodiments. The same or similar parts between the various embodiments can be referenced to each other.

[0059] The above description of the disclosed embodiments enables one skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to one skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but rather to the widest scope consistent with the principles and novel features disclosed herein.

Claims

1. A floating breakwater for an offshore photovoltaic power plant, comprising a buoyancy box (1), a flat plate (2) and a plurality of anchor blocks (9) arranged in an upper and lower manner, wherein the buoyancy box (1), the flat plate (2) and the anchor blocks (9) are connected by a cable assembly, characterized in that: A plurality of flexible baffles (105) are arranged in the buoyancy box (1), and the plurality of flexible baffles (105) divide the inner cavity of the buoyancy box (1) into a plurality of accommodating cavities. The bottom of the accommodating cavity is provided with a water inlet and outlet (104), and the top is provided with an air inlet and outlet. The buoyancy box (1) is also provided with a driving component, and the driving component is used to drive the flexible baffles (105) to deform. During the deformation process of the flexible baffles (105), the volume of the accommodating cavity can be changed; The buoyancy box (1) and the flat plate (2) are connected via a plurality of connection columns (5), the connection columns (5) comprising an upper mounting sleeve (3), a lower mounting sleeve (4) and a column body, the upper mounting sleeve (3) being fixedly connected to the buoyancy box (1), the lower mounting sleeve (4) being fixedly connected to the flat plate (2), the two ends of the column body being respectively inserted into the upper mounting sleeve (3) and the lower mounting sleeve (4), the column body comprising a flexible central rod (507) and a flexible sheath (506) sleeved around the flexible central rod (507); A protective sleeve (510) is fixedly sleeved on the peripheral side wall of the flexible central rod (507), and a distance is left between the protective sleeve (510) and the flexible sheath (506) to form a cavity (508). The two ends of the flexible central rod (507) and the flexible sheath (506) are fixedly connected via an end plate (504), and the end plate (504) closes the cavity (508).

2. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: The driving assembly comprises a plurality of linear drivers (102) corresponding to the flexible baffles (105), and the output ends of the linear drivers (102) are fixedly connected to the flexible baffles (105) via connecting sheets (103).

3. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: The flexible baffles (105) are arranged in an even number, and every two of the flexible baffles (105) form a group. The driving component comprises at least one delivery pump (106), and the delivery pump (106) is arranged between the two flexible baffles (105) in the same group. The delivery pump (106) is connected to a flow guide pipe (107), and a flow guide cover (108) is arranged on both sides of the flow guide pipe (107). The two flow guide covers (108) are fixedly connected to the two flexible baffles (105) in the same group, and the flow guide covers (108) and the flexible baffles (105) enclose a flow guide chamber (109). The flow guide chamber (109) is connected to the flow guide pipe (107), and a flow guide valve (110) is arranged at the connection position.

4. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: A plurality of connecting fibers (509) are fixedly connected between the protective sleeve (510) and the flexible sheath (506); the plurality of connecting fibers (509) are evenly divided into a plurality of groups; the plurality of groups of connecting fibers (509) are evenly distributed along the circumferential direction of the flexible center rod (507); and the connecting fibers (509) in the same group are distributed along the axial direction of the flexible center rod (507).

5. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: The outer side of the end plate (504) is connected to a mounting plate (503) via connecting bolts (505); the peripheral side wall of the mounting plate (503) is detachably connected to an inner sleeve (501); the inner sleeve (501) can be inserted into and fixed in the upper mounting sleeve (3) or the lower mounting sleeve (4).

6. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: The cable assembly comprises a main cable (10) movably connected to the buoy (1), a secondary cable (11) movably connected to the flat plate (2), and a connecting cable (12) movably connected to the anchor block (9), and the main cable (10), the secondary cable (11) and the connecting cable (12) are connected.

7. A floating breakwater for an offshore photovoltaic power plant according to claim 1, characterized in that: A liquid level sensor is arranged in the accommodating cavity, and a liquid replenishing mechanism is fixedly arranged on the floating box (1), wherein the liquid replenishing mechanism comprises a plurality of liquid replenishing pumps correspondingly connected to the accommodating cavities, and all the liquid replenishing pumps and all the liquid level sensors are connected to a controller.

8. A construction method for installing a floating breakwater for an offshore photovoltaic power plant as claimed in claim 1, characterized in that: The method comprises the following steps: S1. Determine parameter requirements; S2, fixing the anchor block (9); S3, moving the floating breakwater to an installation position, and making the pontoon (1) float vertically on the sea surface; S4, filling the containing chamber with water to make the buoyancy box (1) sink, and stopping the filling of water when the buoyancy box (1) is submerged in the sea water; S5. Using the cable assembly to connect the buoyancy box (1), the flat plate (2) and the anchor block (9); S6. Based on the parameter requirement, drain the water in the accommodating chamber to make the buoyancy box (1) float, until the position of the buoyancy box (1) meets the parameter requirement.