A micro pump automated liquid cooling system and its use method

By introducing a filling mechanism and an adjustable heat-conducting structure into the micro-pump automated liquid cooling system, the problems of coolant replacement and dust cleaning are solved, and the convenience and functionality of the system are improved.

CN117905688BActive Publication Date: 2024-10-29DONGGUAN SHENGXINDA TRADING CO LTD
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202311823063.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-12-27
Publication Date
2024-10-29
Estimated Expiration
2043-12-27

AI Technical Summary

Technical Problem

The existing micro-pump automated liquid cooling system has deficiencies in filling coolant, adjusting the heat transfer area and cleaning the heat exchanger, and fails to effectively solve the problems of coolant replacement and dust cleaning.

Method used

A micro-pump automated liquid cooling system including a filling mechanism and a positioning component is designed. The filling component and the positioning component are used to realize the convenient filling of coolant. The adjustable heat-conducting sheet and elastic band structure are used to adjust the heat-conducting area. The cooperation of the insertion rod and the elastic band realizes the cleaning of the heat exchanger.

Benefits of technology

It realizes the convenient replacement of coolant, flexible adjustment of the heat transfer area and effective cleaning of the heat exchanger, improving the functionality and ease of use of the system.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117905688B_ABST
    Figure CN117905688B_ABST
Patent Text Reader

Abstract

The present invention discloses a micro pump automated liquid cooling system and a method for using the same, and relates to the technical field of micro pump automated liquid cooling systems, including a fixed plate, a water tank is arranged on the top of the fixed plate, a filling mechanism is installed through the front of the water tank, the filling mechanism includes a filling assembly and a positioning assembly, the filling assembly is used to provide a channel for the coolant to enter the water tank, and the positioning assembly is used to provide a filling support function. The present invention is provided with a filling mechanism, and the staff can open the opening of the filling assembly provided in the filling mechanism, and then insert the opening of the tank filled with coolant toward the water tank into the inner side of the filling assembly, and then use the positioning assembly to position and support the tank filled with coolant, so that the coolant can pass through the filling assembly and enter the inner side of the water tank, so that the device can easily replace the filling coolant.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of micro pump automated liquid cooling systems, in particular to a micro pump automated liquid cooling system and a use method thereof. Background Art

[0002] The micropump automated liquid cooling system is one of the indispensable devices in liquid cooling work. It can utilize coolant for cooling work and can also perform heat exchange cooling on the coolant so that the coolant can be recycled. Usually the coolant needs to be refilled and replaced, and the heat conduction area of ​​the cooling head is fixed. A micropump automated liquid cooling system and its use method can provide convenience for the staff.

[0003] The defects of the existing micro pump automated liquid cooling system are:

[0004] 1. Application document: US20090074595A1, discloses a small liquid cooling device. The above-mentioned public document mainly considers the problem of driving the working fluid to flow unidirectionally through the channel defined in the piezoelectric micropump, and does not consider the problem of how to add the coolant.

[0005] 2. Patent document: CN107039370B, discloses a microfluidic cooling system driven by a bubble micropump. The above-mentioned public document mainly considers how to use the temperature difference caused by the heat generated by the chip as the energy source for the operation of the micropump without consuming additional energy, but does not consider how to adjust the heat conduction area.

[0006] 3. Patent document: CN106098657B, discloses a small liquid cooling system and method driven by an electro-hydraulic micro pump. The above-mentioned public document mainly considers the problem of how to directly integrate with the chip or the flow channel, but does not consider the problem of how to clean the dust adhering to the heat exchanger.

[0007] 4. Application document: CN104681514A, discloses a water-cooling solution for FC packaged chips. The above-mentioned public document mainly considers how to improve the heat dissipation efficiency, but does not consider how to support the facilities for placing the clean heat exchanger. Summary of the invention

[0008] The object of the present invention is to provide a micro pump automated liquid cooling system and a method of using the same to solve the problems raised in the above background technology.

[0009] To achieve the above object, the present invention provides the following technical solutions: a micro-pump automated liquid cooling system and a method of using the same, comprising a fixing plate, a water tank is arranged on the top of the fixing plate, a filling mechanism is installed through the front of the water tank, the filling mechanism comprises a filling assembly and a positioning assembly, the filling assembly is used to provide a channel for the coolant to enter the water tank, and the positioning assembly is used to provide a filling support function;

[0010] The filling assembly includes a funnel that passes through the front of the water tank, an arc plate is installed on the front of the funnel, a positioning plate is installed on the front of the arc plate, a closed cover is installed on the top of the funnel, the closed cover is located above and behind the arc plate, an elastic rope is installed on the front of the closed cover, and both ends of the elastic rope are connected to the inner side of the arc plate;

[0011] The positioning assembly includes a support plate installed on the top of the funnel, a side wing is installed on one side of the support plate, a support plate is welded on the other side of the support plate, a holding belt is fixed to one end of the side wing, a magnet is installed on one side of the holding belt, a connecting belt is fixed to one end of the support plate, a groove is opened on one side of the connecting belt, and an iron sheet is adhered to the inner side of the groove.

[0012] Preferably, a plurality of fixing holes are formed through one side of the fixing plate, and a micro pump is welded to the inner side of the bottom wall of the fixing plate.

[0013] Preferably, a connecting pipe is installed at the input end of the micro pump, and the connecting pipe is connected to the discharge end of the water tank.

[0014] Preferably, the input end of the water tank is connected to a water pipe, one end of the water pipe is connected to a connecting seat, and the top of the connecting seat is connected to a heat exchanger.

[0015] Preferably, four plug rods are movably placed passing through the interior of the heat exchanger, positioning grooves are respectively opened on the outer sides of the four plug rods, arc rods are welded on the front sides of the plug rods, pull rods are installed on the front sides of the arc rods and connected to each other, pull rings are installed on the outer sides of the pull rods, an elastic band is placed on the inner side of each of the positioning grooves, and support bars are connected to each other at both ends of the elastic band, the support bars are respectively located at the top, bottom and both sides of the heat exchanger, a brush is installed on the side of the support bar close to the heat exchanger, and a handle is installed on the outer side of the support bar.

[0016] Preferably, the input end of the connecting seat is connected to a connecting pipe, one end of the connecting pipe is installed with a cooling head, a copper sheet is fitted and fixed on the top of the cooling head, and four heat conducting sheets are installed on the outside of the copper sheet.

[0017] Preferably, a storage groove is provided on the outer side of the heat conductive sheet, a guide groove is provided on the inner side of the heat conductive sheet, the guide groove is connected with the storage groove, a fitting groove is provided on the inner side of the heat conductive sheet, the fitting groove is connected with the guide groove, a heat transfer sheet is placed on the inner side of the storage groove, guide blocks are installed on the front and back sides of the heat transfer sheet, a fitting block is installed on the end of the guide block away from the heat transfer sheet, the guide block is located on the inner side of the guide groove, the heat transfer sheet is located on the inner side of the fitting groove, an inner copper plate is inlaid on the top of the heat transfer sheet, a rubber block is adhered to the front and back sides of the inner copper plate, and the rubber block is fitted with the heat transfer sheet, a clearance groove is provided on the top of the inner copper plate, a connecting rod is fixed on the inner side of the clearance groove, a pull plate is installed on the side of the heat transfer sheet away from the heat conductive sheet, and a mounting hole is provided through the inside of the heat conductive sheet.

[0018] Preferably, the method of using the micro pump automated liquid cooling system is as follows:

[0019] S1. First, the staff needs to firmly install the fixing plate at the work site, then install the heat exchanger at the work site, then connect the connecting pipe with the water tank and the micro pump, connect the water pipe with the water tank and the connecting seat, then connect the connecting pipe with the connecting seat and the output end of the cooling head, and then use another connecting pipe to connect the input end of the cooling head and the output end of the micro pump;

[0020] S2. Then the staff needs to pull the elastic rope to make the elastic rope move and deform together with the sealing cover, open the top opening of the funnel, and then insert the can filled with coolant into the inner side of the funnel, and then make the holding belt and the connecting belt hold the outer side of the can filled with coolant, so that the holding belt drives the magnet to move and place it on the inner side of the groove, and use the magnetic force to adsorb on the iron sheet, so that the coolant can pass through the funnel and fall to the inner side of the water tank under the action of the tilt angle and gravity, so as to facilitate the filling of coolant into the water tank;

[0021] S3. Then, the staff can pull the heat transfer sheet away from the heat conductive sheet according to the actual situation, so that the heat transfer sheet moves out from the inside of the storage slot to the outside, and then use fingers to hook the connecting rod to pull the inner copper plate upward, so that the inner copper plate moves out from the inside of the storage slot to a part of the outside, ensuring that the inner copper plate fits the object to be cooled, so that the heat can be transferred to the heat transfer sheet through the inner copper plate, and then the heat transfer sheet will conduct the heat to the inner copper plate in conjunction with the fitting block, and then the inner copper plate will transfer the heat to the cooling head through the copper sheet;

[0022] S4, then start the micro pump, so that the coolant absorbs the heat on the copper sheet in the cooling head and carries it, and then enters the inner side of the heat exchanger through the connecting seat, and then the heat exchanger is started, and the wind is used to cool the coolant after absorbing heat in the heat exchanger, and then passes through the water pipe into the inner side of the water tank for storage and recycling;

[0023] S5. At the same time, the staff needs to make the pull rod drive the arc rod to move together, so that the insertion rod passes through the heat exchanger, and at the same time move the elastic band to the inner side of the positioning groove and place it, so that the insertion rod uses the positioning groove to support the placement of the elastic band.

[0024] Preferably, in step S5, the following steps are also included:

[0025] S51. The staff can pull the pull rod toward the front through the pull ring according to the actual needs, so that the plug rod is pulled out of the heat exchanger to the outside, the elastic band is separated from the plug rod, and the support bar drives the brush to approach the heat exchanger. Then the staff holds the pull handle and pulls the support bar back and forth so that the brush can brush off the dust stuck to the heat exchanger.

[0026] Compared with the prior art, the present invention has the following beneficial effects:

[0027] 1. The present invention is provided with a filling mechanism, so that a worker can open the opening of the filling assembly provided in the filling mechanism, and then insert the opening of the coolant filling tank toward the water tank into the inner side of the filling assembly, and then use the positioning assembly to position and support the coolant filling tank, so that the coolant can pass through the filling assembly into the inner side of the water tank, so that the device can easily replace the coolant filling.

[0028] 2. The present invention provides a storage groove, and the staff can pull the heat transfer plate in the direction away from the heat conductive plate through the pull plate according to the actual needs, so that the heat transfer plate drives the heat transfer plate to move out from the inside of the storage groove to the outside under the moving guiding action of the guide block and the guide groove. Then, the hand is inserted into the inner side of the give way groove, and the connecting rod is hooked with the finger to pull the inner copper plate upward, so that the inner copper plate drives the rubber block to move upward together, so that the inner copper plate moves out from the inner side of the storage groove to a part of the outside, and the rubber block is used to use the rebound force and friction force to cling to the heat transfer plate, and then the cooling head is moved, so that the cooling head drives the copper plate and the heat conductive plate to fit the object to be cooled, and at the same time ensures that the inner copper plate is fit to the object to be cooled, so that the heat can be transferred to the heat transfer plate through the inner copper plate, and then the heat transfer plate will conduct the heat to the inner copper plate in conjunction with the fitting block, and then the inner copper plate transfers the heat to the cooling head through the copper plate, and the inner copper plate is used to expand the heat conduction area, so that the device can conveniently adjust the heat conduction area and improve flexibility.

[0029] 3. The present invention is equipped with an elastic band, so that the staff can pull the pull rod toward the front through the pull ring according to the actual needs, so that the pull rod drives the arc rod to move toward the front under the action of external force, so that the arc rod pulls the insertion rod toward the front, so that the insertion rod is pulled out of the heat exchanger to the outside, and at the same time, the elastic band will move out from the inner side of the positioning groove by utilizing the inclination angle of the positioning groove, so that the elastic band is separated from the insertion rod, and then the elastic band stretched by the insertion rod will rebound by utilizing the elastic force, so that the elastic band pulls the support bar by utilizing the rebound force, so that the support bar drives the brush to approach the heat exchanger, and then the staff holds the pull handle and pulls the support bar back and forth, so that the support bar drives the brush to contact with the heat exchanger and move back and forth, so that the brush can brush off the dust stuck to the heat exchanger.

[0030] 4. The present invention uses an insertion rod that penetrates the heat exchanger. The staff needs to move the pull rod through the pull ring, so that the pull rod drives the arc rod to move together, and the arc rod drives the insertion rod to move together, so that the insertion rod penetrates the heat exchanger. At the same time, the insertion rod will use external force to push the elastic band to deform, so that the elastic band moves to the inner side of the positioning groove and is placed, so that the insertion rod uses the positioning groove to support the placement of the elastic band, so that the device can conveniently support the placement of facilities for cleaning the heat exchanger, thereby improving functionality. BRIEF DESCRIPTION OF THE DRAWINGS

[0031] Figure 1 is an axonometric view of the present invention;

[0032] Figure 2 It is a schematic diagram of the three-dimensional structure of the arc rod of the present invention;

[0033] Figure 3 It is a schematic diagram of the three-dimensional structure of the funnel of the present invention;

[0034] Figure 4 It is a schematic diagram of the three-dimensional structure of the holding belt of the present invention;

[0035] Figure 5 It is a schematic diagram of the three-dimensional structure of the support bar of the present invention;

[0036] Figure 6 It is a schematic diagram of the three-dimensional structure of the inner cylinder plate of the present invention;

[0037] Figure 7 It is a schematic diagram of the guide groove structure of the present invention;

[0038] Figure 8 It is a flow chart of the present invention.

[0039] In the figure: 1, fixing plate; 2, fixing hole; 3, micro pump; 4, connecting pipe; 5, water tank; 6, funnel; 7, arc plate; 8, positioning plate; 9, closed cover; 10, elastic rope; 11, support plate; 12, side wing; 13, support plate; 14, holding belt; 15, magnet; 16, connecting belt; 17, groove; 18, iron sheet; 19, water pipe; 20, connecting seat; 21, heat exchanger; 22, plug rod; 23, positioning groove; 24, arc Rod; 25, pull rod; 26, pull ring; 27, elastic band; 28, support bar; 29, brush; 30, pull handle; 31, connecting pipe; 32, cooling head; 33, copper sheet; 34, heat conducting sheet; 35, storage slot; 36, guide slot; 37, fitting slot; 38, heat transfer sheet; 39, guide block; 40, fitting block; 41, inner copper plate; 42, rubber block; 43, clearance slot; 44, connecting rod; 45, pull plate; 46, mounting hole. DETAILED DESCRIPTION

[0040] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0041] In the description of the present invention, it should be noted that the terms "upper", "lower", "inner", "outer", "front end", "rear end", "two ends", "one end", "the other end" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first" and "second" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.

[0042] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "provided with", "connected", etc. should be understood in a broad sense. For example, "connected" means fixed connection, detachable connection, or integral connection; mechanical connection, electrical connection; direct connection, indirect connection through an intermediate medium, and internal communication between two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention are understood according to specific circumstances.

[0043] See also Figure 1 , an embodiment provided by the present invention:

[0044] A micro pump automatic liquid cooling system and a method for using the same, comprising a fixing plate 1, a plurality of fixing holes 2 are formed through one side of the fixing plate 1, a micro pump 3 is welded to the inner side of the bottom wall of the fixing plate 1, a connecting pipe 4 is installed at the input end of the micro pump 3, the connecting pipe 4 is connected to the discharge end of a water tank 5, a water pipe 19 is connected to the input end of the water tank 5, one end of the water pipe 19 is connected to a connecting seat 20, and a heat exchanger 21 is connected to the top of the connecting seat 20;

[0045] The fixing plate 1 can provide a stable support for the micro pump 3, and can provide a space for the fixing hole 2. The fixing hole 2 can provide a through channel for the fixing component. The micro pump 3 can stably support the water tank 5. The water tank 5 can provide a storage space for the coolant. The connecting seat 20 can provide a circulation channel for the coolant, so that the coolant can enter the heat exchanger 21 and be discharged. The staff needs to first use the fixing component to firmly install the fixing plate 1 to the workplace from the fixing hole 2, and then use the fixing component to install the heat exchanger 21 to the workplace, and then connect the connecting pipe 4, the water tank 5 and the micro pump 3, connect the water pipe 19 to the water tank 5 and the connecting seat 20, and then connect the connecting pipe 31 to the connecting seat 20 and the output end of the cooling head 32, and then use Another connecting pipe 31 connects the input end of the cooling head and the output end of the micro pump 3, and then the micro pump 3 is started. The micro pump 3 will suck out the coolant stored in the water tank 5 through the connecting pipe 4 and transport it to the cooling head through one of the connecting pipes 31, so that the coolant absorbs the heat on the copper sheet 33 in the cooling head 32 and carries it, and then passes through the cooling head 32 and enters the inner side of the connecting seat 20 through the connecting pipe 31, and enters the inner side of the heat exchanger 21 through the connecting seat 20. Then the heat exchanger 21 is started, and the wind force is used to perform heat exchange cooling on the coolant after absorbing heat in the heat exchanger 21. Then the cooled coolant will pass through the connecting seat 20 into the inner side of the water pipe 19, and pass through the water pipe 19 into the inner side of the water tank 5 for storage and recycling.

[0046] See also Figure 1 , Figure 3 and Figure 4 An embodiment provided by the present invention:

[0047] It includes a fixing plate 1, a water tank 5 is arranged on the top of the fixing plate 1, a filling mechanism is installed through the front of the water tank 5, the filling mechanism includes a filling component and a positioning component, the filling component is used to provide a channel for the coolant to enter the water tank 5, and the positioning component is used to provide a filling support function, the filling component includes a funnel 6 that passes through the front of the water tank 5, an arc plate 7 is installed on the front of the funnel 6, a positioning plate 8 is installed on the front of the arc plate 7, a closed cover 9 is installed on the top of the funnel 6, and the closed cover 9 is located at the upper rear of the arc plate 7. An elastic rope 10 is installed on the front of the closed cover 9, and both ends of the elastic rope 10 are connected to the inner side of the arc plate 7. The positioning assembly includes a support plate 11 installed on the top of the funnel 6, a side wing 12 is installed on one side of the support plate 11, and a support plate 13 is welded on the other side of the support plate 11. A holding belt 14 is fixed to one end of the side wing 12, and a magnet 15 is installed on one side of the holding belt 14. A connecting belt 16 is fixed to one end of the support plate 13, and a groove 17 is opened on one side of the connecting belt 16. An iron sheet 18 is adhered to the inner side of the groove 17;

[0048] The water tank 5 can stably support the funnel 6. The funnel 6 has a certain inclination angle and can stably support the arc plate 7. The arc plate 7 cooperates with the funnel 6 to provide support for the closed cover 9. The closed cover 9 can stably support the elastic rope 10. The support plate 11 can stably support the side wings 12 and the support plate 13 under the support of the funnel 6. The support plate 13 can stably support the connecting belt 16. The side wings 12 can stably support the holding belt 14. The staff needs to pull the elastic rope 10 to the back under the support of the funnel 6 and the arc plate 7, so that the elastic rope 10 is stretched and deformed under the action of external force. At the same time, the elastic rope 10 will drive the closed cover 9 to move and deform together, so as to open the top opening of the funnel 6, and then put the tank filled with coolant into the coolant tank. The magnet 15 is inserted into the inner side of the funnel 6 and placed on the inner side of the arc plate 7 for support. Then the staff needs to pull the holding belt 14 and the connecting belt 16 to bend and deform under the support of the support plate 11, the side wing 12 and the support plate 13, so that the holding belt 14 and the connecting belt 16 are held on the outside of the tank filled with coolant, and the holding belt 14 drives the magnet 15 to move and be placed on the inner side of the groove 17, and use the magnetic force to adsorb on the iron sheet 18, so that the support plate 11 and the side wing 12, the support plate 13, the holding belt 14, the connecting belt 16 and the arc plate 7 cooperate to provide support for the tank filled with coolant, so that the coolant can pass through the funnel 6 and fall to the inner side of the water tank 5 under the action of the tilt angle and gravity, thereby facilitating the filling of coolant into the water tank 5.

[0049] See also Figure 1 and Figure 2 , an embodiment provided by the present invention:

[0050] The heat exchanger 21 includes four insert rods 22 which are movably placed inside the heat exchanger 21, positioning grooves 23 are respectively provided on the outer sides of the four insert rods 22, arc rods 24 are respectively welded on the front sides of the insert rods 22, pull rods 25 are installed on the front sides of the arc rods 24, and pull rings 26 are installed on the outer sides of the pull rods 25;

[0051] The heat exchanger 21 can provide a through channel for the insertion rod 22, the insertion rod 22 can provide a starting space for the positioning groove 23, the positioning groove 23 can provide a positioning function for the elastic band 27, and cooperate with the insertion rod 22 to provide support for the elastic band 27, the insertion rod 22 can firmly support the arc rod 24, the staff needs to move the pull rod 25 through the pull ring 26, so that the pull rod 25 drives the arc rod 24 to move together, and the arc rod 24 drives the insertion rod 22 to move together, so that the insertion rod 22 penetrates the heat exchanger 21, and at the same time, the insertion rod 22 will use external force to push the elastic band 27 to deform, so that the elastic band 27 moves to the inner side of the positioning groove 23 and is placed, so that the insertion rod 22 uses the positioning groove 23 to support the placement of the elastic band 27.

[0052] See also Figure 1 and Figure 5An embodiment provided by the present invention includes an elastic band 27, an elastic band 27 is placed inside each positioning groove 23, and two ends of the elastic band 27 are connected to each other with stays 28, and the stays 28 are respectively located at the top, bottom and both sides of the heat exchanger 21, and a brush 29 is installed on a side of the stay 28 close to the heat exchanger 21, and a handle 30 is installed on the outside of the stay 28;

[0053] The elastic band 27 can provide support for the support bar 28. The elastic band 27 has a certain elasticity and can be extended and retracted under the action of external force. It will rebound after the external force disappears. The support bar 28 can firmly support the brush 29 and the handle 30. The staff can pull the pull rod 25 to the front through the pull ring 26 according to the actual needs, so that the pull rod 25 drives the arc rod 24 to move to the front under the action of external force, so that the arc rod 24 pulls the plug rod 22 to the front, so that the plug rod 22 is pulled out of the heat exchanger 21 to the outside, and the elastic band 27 will use the inclination angle of the positioning groove 23 to move out from the inner side of the positioning groove 23, so that the elastic band 27 is separated from the insertion rod 22, and then the elastic band 27 stretched by the insertion rod 22 will rebound by elastic force, so that the elastic band 27 uses the rebound force to pull the support bar 28, so that the support bar 28 drives the brush 29 to approach the heat exchanger 21, and then the staff holds the handle 30 to pull the support bar 28 back and forth, so that the support bar 28 drives the brush 29 to contact the heat exchanger 21 and move back and forth, so that the brush 29 can brush off the dust stuck to the heat exchanger 21.

[0054] See also Figure 1 , Figure 6 and Figure 7 , an embodiment provided by the present invention:

[0055] The invention comprises a connection base 20, the input end of the connection base 20 is connected to a connection pipe 31, one end of the connection pipe 31 is installed with a cooling head 32, a copper sheet 33 is fixedly attached to the top of the cooling head 32, four heat conducting sheets 34 are installed on the outer side of the copper sheet 33, a receiving groove 35 is provided on the outer side of the heat conducting sheet 34, a guide groove 36 is provided inside the heat conducting sheet 34, the guide groove 36 is connected with the receiving groove 35, a fitting groove 37 is provided inside the heat conducting sheet 34, the fitting groove 37 is connected with the guide groove 36, a heat transfer sheet 38 is placed on the inner side of the receiving groove 35, and the front and back sides of the heat transfer sheet 38 are provided with heat transfer sheets 38. A guide block 39 is installed, and a fitting block 40 is installed at one end of the guide block 39 away from the heat transfer sheet 38. The guide block 39 is located on the inner side of the guide groove 36, and the heat transfer sheet 38 is located on the inner side of the fitting groove 37. An inner copper plate 41 is inlaid on the top of the heat transfer sheet 38, and a rubber block 42 is adhered to the front and back of the inner copper plate 41, and the rubber block 42 fits with the heat transfer sheet 38. A clearance groove 43 is opened on the top of the inner copper plate 41, and a connecting rod 44 is fixed on the inner side of the clearance groove 43. A pull plate 45 is installed on the side of the heat transfer sheet 38 away from the heat conductive sheet 34, and a mounting hole 46 is opened through the inside of the heat conductive sheet 34;

[0056] The connecting seat 20 can provide support for the connecting pipe 31, the cooling head 32 can provide support for the copper sheet 33, and can use the coolant to absorb the heat on the copper sheet 33, the heat conductive sheet 34 can provide an opening space for the guide groove 36, the guide groove 36 can provide a moving guide for the guide block 39, the heat conductive sheet 34 can provide an opening space for the fitting groove 37, the fitting groove 37 can provide a moving guide for the fitting block 40, and can fit with the fitting block 40 for heat transfer, the staff can pull the pull rod 25 toward the front through the pull ring 26 according to the actual needs, so that the pull rod 25 drives the arc rod 24 to move toward the front under the action of external force, The arc rod 24 pulls the insertion rod 22 toward the front, so that the insertion rod 22 is pulled out of the heat exchanger 21 to the outside. At the same time, the elastic band 27 will use the inclination angle of the positioning groove 23 to move out from the inner side of the positioning groove 23, so that the elastic band 27 is separated from the insertion rod 22. Then, the elastic band 27 stretched by the insertion rod 22 will rebound by elastic force, so that the elastic band 27 uses the rebound force to pull the support bar 28, so that the support bar 28 drives the brush 29 to approach the heat exchanger 21. Then the staff holds the handle 30 and pulls the support bar 28 back and forth, so that the support bar 28 drives the brush 29 to contact the heat exchanger 21 and move back and forth, so that the brush 29 can brush off the dust stuck to the heat exchanger 21.

[0057] Further, the method of using the micro pump automated liquid cooling system is as follows:

[0058] S1. First, the staff needs to firmly install the fixing plate 1 at the work site, then install the heat exchanger 21 at the work site, then connect the connecting pipe 4, the water tank 5 and the micro pump 3, connect the water pipe 19, the water tank 5 and the connecting seat 20, then connect the connecting pipe 31, the connecting seat 20 and the output end of the cooling head 32, and then use another connecting pipe 31 to connect the input end of the cooling head 32 and the output end of the micro pump 3;

[0059] S2. Then the staff needs to pull the elastic rope 10, so that the elastic rope 10 moves and deforms together with the sealing cover 9, opens the top opening of the funnel 6, and then inserts the can filled with coolant into the inner side of the funnel 6, and then makes the holding belt 14 and the connecting belt 16 hold the outer side of the can filled with coolant, so that the holding belt 14 drives the magnet 15 to move and place it on the inner side of the groove 17, and uses the magnetic force to adsorb on the iron sheet 18, so that the coolant can pass through the funnel 6 and fall to the inner side of the water tank 5 under the action of the tilt angle and gravity, so as to facilitate the filling of coolant into the water tank 5;

[0060] S3. Then, the staff can pull the heat transfer sheet 38 away from the heat conductive sheet 34 according to the actual situation, so that the heat transfer sheet 38 moves out from the inside of the storage slot 35 to the outside, and then hook the connecting rod 44 with fingers to pull the inner copper plate 41 upward, so that the inner copper plate 41 moves out from the inside of the storage slot 35 to a part of the outside, so that the inner copper plate 41 is in contact with the object to be cooled, so that the heat can be transferred to the heat transfer sheet 38 through the inner copper plate 41, and then the heat transfer sheet 38 will conduct the heat to the inner copper plate 41 in conjunction with the bonding block 40, and then the inner copper plate 41 will transfer the heat to the cooling head 32 through the copper sheet 33;

[0061] S4, then start the micro pump 3, so that the coolant absorbs the heat on the copper sheet 33 in the cooling head 32 and carries it, and then enters the inner side of the heat exchanger 21 through the connecting seat 20, and then the heat exchanger 21 is started, and the wind force is used to perform heat exchange cooling on the coolant after absorbing heat in the heat exchanger 21, and then passes through the water pipe 19 to enter the inner side of the water tank 5 for storage and recycling;

[0062] S5. At the same time, the staff needs to make the pull rod 25 drive the arc rod 24 to move together, so that the insertion rod 22 penetrates the heat exchanger 21, and at the same time move the elastic band 27 to the inner side of the positioning groove 23 for placement, so that the insertion rod 22 uses the positioning groove 23 to support the placement of the elastic band 27.

[0063] Furthermore, in step S5, the following steps are also included:

[0064] S51. The staff can pull the pull rod 25 toward the front through the pull ring 26 according to the actual needs, so that the insertion rod 22 is pulled out of the heat exchanger 21 to the outside, and the elastic band 27 is separated from the insertion rod 22, so that the support bar 28 drives the brush 29 to approach the heat exchanger 21, and then the staff holds the pull handle 30 and pulls the support bar 28 back and forth, so that the brush 29 can brush off the dust stuck to the heat exchanger 21.

[0065] Working principle: Before using the micropump automated liquid cooling system, it is necessary to check whether there are any problems that affect the use of the micropump automated liquid cooling system. When the staff needs to use the micropump automated liquid cooling system, they should first use the fixing components to firmly install the fixing plate 1 to the workplace from the fixing hole 2, and then use the filling mechanism to fill the coolant into the water tank 5, and use the fixing components to fix the heat exchanger 21 to the workplace, and then pull out the inner copper plate 41 according to the actual needs to adjust the heat absorption area, and use the fixing components to fix the heat conductive plate 34 to the object to be cooled, and finally start the micro pump 3 and the heat exchanger 21 to perform heat exchange liquid cooling.

[0066] It will be apparent to those skilled in the art that the invention is not limited to the details of the exemplary embodiments described above and that the invention may be implemented in other specific forms without departing from the spirit or essential features of the invention. Therefore, the embodiments should be considered in all respects as exemplary and non-restrictive, and the scope of the invention is defined by the appended claims rather than the foregoing description, and it is intended that all variations within the meaning and range of equivalent elements of the claims be included in the invention. Any reference numeral in a claim should not be considered to limit the claim to which it relates.

Claims

1. A micro pump automated liquid cooling system, characterized in that: It comprises a fixing plate (1), a water tank (5) is arranged on the top of the fixing plate (1), a filling mechanism is installed through the front of the water tank (5), the filling mechanism comprises a filling component and a positioning component, the filling component is used to provide a channel for the coolant to enter the water tank (5), and the positioning component is used to provide a filling support function; The filling assembly comprises a funnel (6) penetrating the front of the water tank (5), an arc plate (7) is installed on the front of the funnel (6), a positioning plate (8) is installed on the front of the arc plate (7), a closed cover (9) is installed on the top of the funnel (6), the closed cover (9) is located at the upper rear of the arc plate (7), an elastic rope (10) is installed on the front of the closed cover (9), and both ends of the elastic rope (10) are connected to the inner side of the arc plate (7); The positioning assembly comprises a support plate (11) installed on the top of the funnel (6), a side wing (12) is installed on one side of the support plate (11), a support plate (13) is welded on the other side of the support plate (11), a holding belt (14) is fixed to one end of the side wing (12), a magnet (15) is installed on one side of the holding belt (14), a connecting belt (16) is fixed to one end of the support plate (13), a groove (17) is opened on one side of the connecting belt (16), and an iron sheet (18) is adhered to the inner side of the groove (17); A plurality of fixing holes (2) are formed through one side of the fixing plate (1), and a micro pump (3) is welded to the inner side of the bottom wall of the fixing plate (1); The input end of the micro pump (3) is provided with a connecting pipe (4), and the connecting pipe (4) is connected to the discharge end of the water tank (5); The input end of the water tank (5) is connected to a water pipe (19), one end of the water pipe (19) is connected to a connecting seat (20), and the top of the connecting seat (20) is connected to a heat exchanger (21); Four insertion rods (22) are movably placed inside the heat exchanger (21), and positioning grooves (23) are respectively opened on the outer sides of the four insertion rods (22). Arc rods (24) are respectively welded to the front sides of the insertion rods (22), and pull rods (25) are installed on the front sides of the arc rods (24) and connected to each other. Pull rings (26) are installed on the outer sides of the pull rods (25). An elastic band (27) is placed on the inner side of each positioning groove (23), and support bars (28) are connected to each other at both ends of the elastic band (27). The support bars (28) are respectively located at the top, bottom and both sides of the heat exchanger (21), and a brush (29) is installed on the side of the support bar (28) close to the heat exchanger (21), and a pull handle (30) is installed on the outer side of the support bar (28); The input end of the connection seat (20) is connected to a connection pipe (31), one end of the connection pipe (31) is mounted with a cooling head (32), a copper sheet (33) is fixedly attached to the top of the cooling head (32), and four heat conducting sheets (34) are mounted on the outside of the copper sheet (33); The heat conducting sheet (34) is provided with a receiving groove (35) on the outside, a guide groove (36) is provided on the inside of the heat conducting sheet (34), the guide groove (36) is connected to the receiving groove (35), a bonding groove (37) is provided on the inside of the heat conducting sheet (34), the bonding groove (37) is connected to the guide groove (36), a heat transfer sheet (38) is placed on the inside of the storage groove (35), guide blocks (39) are installed on the front and back sides of the heat transfer sheet (38), a bonding block (40) is installed on one end of the guide block (39) away from the heat transfer sheet (38), and the guide block (39) is located in the guide groove ( 36), the heat transfer sheet (38) is located on the inner side of the fitting groove (37), an inner copper plate (41) is inlaid on the top of the heat transfer sheet (38), a rubber block (42) is adhered to the front and back sides of the inner copper plate (41), and the rubber block (42) fits with the heat transfer sheet (38), a clearance groove (43) is opened on the top of the inner copper plate (41), a connecting rod (44) is fixed on the inner side of the clearance groove (43), a pull plate (45) is installed on the side of the heat transfer sheet (38) away from the heat conductive sheet (34), and a mounting hole (46) is opened through the inside of the heat conductive sheet (34).

2. According to the method for using a micro pump automated liquid cooling system according to claim 1, the method for using the micro pump automated liquid cooling system is as follows: S1. First, the staff needs to firmly install the fixing plate (1) at the work site, then install the heat exchanger (21) at the work site, then connect the connecting pipe (4) with the water tank (5) and the micro pump (3), connect the water pipe (19) with the water tank (5) and the connecting seat (20), then connect the connecting pipe (31) with the connecting seat (20) and the output end of the cooling head (32), and then use another connecting pipe (31) to connect the input end of the cooling head (32) and the output end of the micro pump (3); S2. The staff then needs to pull the elastic rope (10) so that the elastic rope (10) moves and deforms together with the sealing cover (9), opens the top opening of the funnel (6), and then inserts the can filled with coolant into the inner side of the funnel (6). Then, the holding belt (14) and the connecting belt (16) are held on the outer side of the can filled with coolant, so that the holding belt (14) drives the magnet (15) to move and place it on the inner side of the groove (17), and uses magnetic force to adsorb it on the iron sheet (18), so that the coolant passes through the funnel (6) and falls to the inner side of the water tank (5) under the action of the tilt angle and gravity, thereby facilitating the filling of coolant into the water tank (5); S3. Then, the staff pulls the heat transfer sheet (38) away from the heat conductive sheet (34) according to actual needs, so that the heat transfer sheet (38) moves out from the inside of the storage slot (35) to the outside, and then hooks the connecting rod (44) with fingers to pull the inner copper plate (41) upward, so that the inner copper plate (41) moves out from the inside of the storage slot (35) to a part of the outside, ensuring that the inner copper plate (41) fits the object to be cooled, so that the heat is transferred to the heat transfer sheet (38) through the inner copper plate (41), and then the heat transfer sheet (38) transfers the heat to the inner copper plate (41) in cooperation with the fitting block (40), and then the inner copper plate (41) transfers the heat to the cooling head (32) through the copper sheet (33); S4, then starting the micro pump (3), so that the coolant absorbs the heat on the copper sheet (33) in the cooling head (32) and carries it, and then enters the inner side of the heat exchanger (21) through the connecting seat (20), and then the heat exchanger (21) is started, and the coolant after absorbing heat is subjected to heat exchange cooling in the heat exchanger (21) by using wind power, and then passes through the water pipe (19) and enters the inner side of the water tank (5) for storage and recycling; S5. At the same time, the staff needs to make the pull rod (25) drive the arc rod (24) to move together, so that the insertion rod (22) penetrates the heat exchanger (21), and at the same time move the elastic band (27) to the inner side of the positioning groove (23) for placement, so that the insertion rod (22) uses the positioning groove (23) to support the placement of the elastic band (27).

3. The method for using a micro pump automated liquid cooling system according to claim 2, characterized in that: In step S5, the following steps are also included: S51. According to actual needs, the staff pulls the pull rod (25) forward through the pull ring (26) to pull the insertion rod (22) out of the heat exchanger (21) to the outside, separates the elastic band (27) from the insertion rod (22), and causes the support bar (28) to drive the brush (29) toward the heat exchanger (21). Then, the staff holds the pull handle (30) and pulls the support bar (28) back and forth, so that the brush (29) brushes off the dust adhering to the heat exchanger (21).

Citation Information

Patent Citations

  • Water-cooling heat dissipation scheme of FC (Flip Chip) encapsulation chip

    CN104681514A

  • A small liquid cooling system and method driven by an electro-hydraulic micropump

    CN106098657B

  • A microchannel cooling system driven by bubble micropumps

    CN107039370B

  • Miniaturized liquid cooling device having droplet generator and pizeoelectric micropump

    US20090074595A1

  • Water cooling system for throat pipe of spraying head of fused deposition type 3D printer

    CN106393668A