A method of risk management in the decision-making stage of bridge construction technology based on ontology

By building a knowledge base and semantic web rules for bridge construction technical risks, the problem of risk management in bridge construction is solved, the integration and reasoning of risk information is realized, and the accuracy and efficiency of construction decision-making are improved.

CN117933689BActive Publication Date: 2024-10-01DALIAN MARITIME UNIVERSITY
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202311306943.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-10-10
Publication Date
2024-10-01
Estimated Expiration
2043-10-10

AI Technical Summary

Technical Problem

Risk management in bridge construction is difficult to integrate cross-domain and multi-source risk information, making risk identification and assessment difficult. Existing methods rely on expert experience and have scattered records, making it difficult to discover connections between factors.

Method used

An ontology-based risk management method in the decision-making stage of bridge construction technology is adopted. By building a knowledge base of bridge construction technology risks, defining entity classes and class relationships, obtaining risk chains and constructing semantic network rules, and conducting consistency tests to support decision-making.

Benefits of technology

It realizes knowledge integration, search and reasoning of bridge construction technical risks, helps managers make reasonable decisions, and improves the efficiency and accuracy of risk management.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117933689B_ABST
    Figure CN117933689B_ABST
Patent Text Reader

Abstract

The present invention discloses a method for risk management in the technical decision-making stage of bridge construction based on ontology. The method comprises the following steps: constructing a bridge construction technical ontology knowledge base by introducing multiple technical knowledge sources of a knowledge base of bridge construction technical risks, defining the relationship between entity classes and classes of the bridge construction technical ontology knowledge base, obtaining a bridge construction technical risk chain based on the bridge construction technical ontology knowledge base, constructing a bridge construction technical risk semantic web rule based on the bridge construction technical risk chain, performing an ontology consistency check on the bridge construction technical risk semantic web rule, and making a decision on a bridge construction technical risk plan based on the bridge construction technical risk semantic web rule after the consistency check, and making a decision on a bridge construction technical risk plan by combining semantic web rules with semantic query rules for bridge construction technology, realizing the functions of knowledge integration, search and reasoning of bridge construction technical risks, facilitating bridge management personnel to manage bridge construction technical risks and make reasonable decisions on bridge construction technology.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of bridge construction technology, and in particular to a method for risk management in the decision-making stage of ontology bridge construction technology. Background Art

[0002] Bridge risk management is divided into risk identification, risk assessment and risk response. The existing risk management method is to make judgments based on the experts' own knowledge and experience. The risk management records are also scattered, making it difficult to find the connection between various factors to determine the key influencing relationship of bridge risk, making it difficult for bridge construction personnel to manage the risk of construction technology. Therefore, in order to solve the problems of cross-domain and multi-source risk information dispersion and risk management difficulties, it is urgent to provide a risk management method based on the decision-making stage of ontology bridge construction technology to solve the above problems. Summary of the invention

[0003] The present invention provides a method for risk management based on the decision-making stage of bridge construction technology to overcome the above technical problems.

[0004] In order to achieve the above object, the technical solution of the present invention is:

[0005] A risk management method based on ontology in the technical decision-making stage of bridge construction, such as Figure 1 As shown, the following steps are included:

[0006] S1: Extract the technical concept knowledge and the relationship between the technical concept knowledge in the bridge construction technology process according to the knowledge base of bridge construction technical risks, and obtain the list of bridge construction technical vocabulary;

[0007] The knowledge base of bridge construction technical risks includes: bridge structure knowledge, bridge survey knowledge, bridge construction technical knowledge, bridge construction technical risk knowledge, bridge construction risk specification knowledge and bridge construction risk response measures knowledge;

[0008] S2: defining bridge construction technical risk data information according to the knowledge of the bridge construction technical vocabulary list; the bridge construction technical risk data information includes sample category information of bridge construction technical risks and information relationship between each sample category;

[0009] The bridge construction technology risk data information includes bridge structure entity information and bridge construction technology data information; and each bridge structure entity matches the corresponding bridge construction technology data information;

[0010] The data information of the bridge construction technology includes bridge structure survey information, bridge structure construction technology information, structure construction technology risk information and structure construction risk assessment / risk countermeasures information;

[0011] S3: defining bridge structure entity information according to the bridge structure composition based on the bridge structure entity extension rule, and defining entity data information of bridge construction technology using an attribute set according to the bridge structure entity; so as to construct a bridge construction technology ontology knowledge base;

[0012] S4: obtaining a bridge construction technology risk chain based on the bridge construction technology ontology knowledge base; and constructing a bridge construction technology risk semantic web rule based on the bridge construction technology risk chain;

[0013] S5: Performing an ontology consistency check on the bridge construction technology risk semantic web rules, and making a decision on the bridge construction technology risk plan based on the bridge construction technology risk semantic web rules after the consistency check.

[0014] Furthermore, the bridge structure entity information in S3 includes bridge pile foundation class, bridge cap class, bridge pier class and bridge box girder class;

[0015] The entity data information of the bridge construction technology includes bridge structure category, bridge component construction technology category and bridge construction technology risk category;

[0016] The bridge construction technology category includes pile foundation construction technology category, platform construction technology category, pier construction technology category and box girder construction technology category;

[0017] The box girder construction technology category includes cantilever construction technology category, top-pushing construction technology category, hole-by-hole construction technology category and support construction technology category;

[0018] The pile foundation construction technology category includes sinking pile technology category and bored pile technology category;

[0019] The bridge pier construction technology category includes assembly prefabrication technology category and on-site casting technology category;

[0020] The said foundation construction technology category includes casing technology category, direct excavation technology category, enclosure excavation technology category and caisson / caisson technology category;

[0021] The bridge construction technical risk categories include construction personnel risk category, construction method risk category, construction material risk category, construction environment risk category and construction equipment risk category.

[0022] Furthermore, the construction of the bridge construction technology ontology knowledge base described in S3 is specifically as follows:

[0023] S31: Based on the structural relationship of each unit of the bridge, the bridge structure entity is defined in the principle of from the whole to the part, from the bridge structure form, spatial structure, component components, and the construction sequence of structural units;

[0024] S32: defining entity classes and class hierarchies according to the entity data information of the bridge structure entity and the bridge construction technology, and determining parent-child relationships and parallel relationships between entity classes;

[0025] The attribute set extension method is used to define the entity data information of bridge construction technology, and the ontology model of bridge construction technology risk is obtained in the form of RDF triples;

[0026] The attribute set includes object attributes, data attributes, annotation attributes and attribute constraints;

[0027] The attribute constraint includes an is a attribute constraint, and the is a attribute constraint is used for an atomic relationship between two classes; and one class represents a parent class; and the other class represents a child class;

[0028] S33: Logical reasoning is performed on the ontology model of bridge construction technology risks through a reasoner based on description logic to obtain the bridge construction technology ontology knowledge base.

[0029] Furthermore, obtaining the bridge construction technical vocabulary list described in S1 includes the following steps:

[0030] S21: determining the domain and application scope of the bridge construction process according to the knowledge data of the knowledge base of the bridge construction technical risk, and acquiring an existing reusable ontology model based on the domain and application scope of the bridge construction process;

[0031] S22: using an enumeration method to obtain corresponding terminology keywords in the bridge construction process according to the existing reusable ontology model;

[0032] The terminology keywords include bridge structure terms for bridge construction technology, bridge survey information terms, bridge construction technology, construction technology risks, and risk assessment / risk countermeasure terms;

[0033] A bridge construction technology vocabulary list is established based on the terminology keywords obtained by the enumeration method.

[0034] Furthermore, the bridge construction technology risk chain described in S4 is specifically:

[0035] The bridge construction phases are divided according to the construction process of the bridge construction work; and the construction technology risk hazard sources, hazard source dependency and bridge component importance weights that affect the bridge structure are confirmed based on the analytic hierarchy process and expert experience;

[0036] An expert opinion questionnaire to determine the construction technology risk path during the bridge construction phase based on the construction technology hazard sources, the dependency of the hazard sources, and the importance weights of bridge components;

[0037] Based on the expert opinion questionnaire combined with the LEC method, the technical risks of bridge construction are evaluated; and the technical risk amounts at different construction technical operation stages during the bridge construction process are obtained.

[0038] Furthermore, the semantic web rules for constructing bridge construction technology risks described in S4 are specifically:

[0039] S41: Select the ontology modeling tool Protégé to encode the ontology model in the bridge construction technology risk chain, and use the SWRL semantics to express the bridge construction technology risk chain by using the semantic web technology through the rule editor in Protégé, and obtain the semantic web rules of bridge construction technology risks to achieve the semantic expression of each bridge construction technology risk knowledge and their mutual relationship;

[0040] The semantic web rules of bridge construction technical risks at least include a calculation rule for the amount of bridge component construction technical risks, a calculation rule for the amount of bridge construction scheme combination risks, and a reasoning rule for bridge construction risk response measures;

[0041] S42: Based on the semantic web rules of bridge construction technical risks, the combination of bridge construction technical entities with the optimal technical risk amount in different construction technical operation stages during the bridge construction process is queried based on the SWQRL plug-in in Protégé.

[0042] Furthermore, the semantic web rules of bridge construction technology risk described in S4 are subjected to ontology consistency check, specifically;

[0043] The Pellet plug-in is used to check the consistency of the statements / semantics of the ontology knowledge base of bridge construction technology and the risk reasoning rules of bridge construction technology.

[0044] Beneficial effects: The present invention discloses a method for risk management in the technical decision-making stage of bridge construction based on ontology, which constructs a bridge construction technology ontology knowledge base by introducing multiple technical knowledge sources of the knowledge base of bridge construction technology risks, and defines the relationship between entity classes and classes of the bridge construction technology ontology knowledge base, and obtains the bridge construction technology risk chain based on the bridge construction technology ontology knowledge base; and constructs the bridge construction technology risk semantic web rules based on the bridge construction technology risk chain; performs ontology consistency check on the bridge construction technology risk semantic web rules, and makes decisions on bridge construction technology risk plans based on the bridge construction technology risk semantic web rules after the consistency check; makes decisions on bridge construction technology by combining semantic web rules and semantic query rules, and realizes the functions of knowledge integration, search and reasoning of bridge construction technology risks, which is convenient for bridge management personnel to manage bridge construction technology risks and make reasonable decisions on bridge construction technology. BRIEF DESCRIPTION OF THE DRAWINGS

[0045] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative labor.

[0046] Figure 1 It is a flow chart of the method for risk management in the decision-making stage of bridge construction technology based on the present invention;

[0047] Figure 2 is a hierarchical diagram of the bridge construction technology class in this embodiment;

[0048] Figure 3 is a hierarchical diagram of bridge construction technical risk categories in this embodiment;

[0049] Figure 4 Create an interface diagram for the implementation example of the class in this embodiment;

[0050] Figure 5 This is a construction technology reasoning interface diagram that meets the construction conditions in this embodiment;

[0051] Figure 6 In this embodiment, it is determined whether the main body bridge construction technology needs to check the interface diagram;

[0052] Figure 7 This is a diagram of the bridge construction technology reasoning object attribute interface in this embodiment;

[0053] Figure 8 This is an interface diagram for calculating the risk amount of impact bored pile construction in this embodiment;

[0054] Fig. 9 This is an interface diagram of the danger level of impact bored piles in this embodiment;

[0055] Fig.10 This is an interface diagram of the risk countermeasures for impact bored piles in this embodiment;

[0056] Fig.11 This is an interface diagram of the construction technology risk of the entire bridge in this embodiment;

[0057] Fig.12 This is an interface diagram of the risk amount of the construction combination scheme in this embodiment;

[0058] Fig.13 This is the interface diagram before the consistency check result inference in this embodiment;

[0059] Fig.14 This is the interface diagram after the consistency check result is inferred in this embodiment;

[0060] Fig.15 This is a diagram of the inference log interface of the consistency check result in this embodiment. DETAILED DESCRIPTION

[0061] In order to make the purpose, technical solution and advantages of the embodiments of the present invention clearer, the technical solution in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0062] This embodiment provides a method for risk management in the bridge construction technology decision-making stage based on ontology, such as Figure 1 As shown, the following steps are included:

[0063] S1: Extract the technical concept knowledge and the relationship between the technical concept knowledge in the bridge construction technology process according to the knowledge base of bridge construction technical risks, and obtain the list of bridge construction technical vocabulary;

[0064] The knowledge base of bridge construction technical risks includes: bridge structure knowledge, bridge survey knowledge, bridge construction technical knowledge, bridge construction technical risk knowledge, bridge construction risk specification knowledge and bridge construction risk response measures knowledge;

[0065] Specifically, S21: determining the domain and application scope of the bridge construction process according to the knowledge data of the knowledge base of the bridge construction technology risk, and acquiring an existing reusable ontology model based on the domain and application scope of the bridge construction process;

[0066] The knowledge base of bridge construction technical risks covers five areas of knowledge. The first area is bridge engineering technology, such as bridge structure composition technology and bridge geological survey technology; the second area is knowledge of bridge construction technology; the third area is knowledge of bridge construction technical risk identification, risk assessment, etc.; the fourth area is bridge construction risk specifications, including risk quantity assessment standards, etc.; the fifth area is knowledge of bridge construction risk response measures;

[0067] S22: using an enumeration method to obtain corresponding terminology keywords in the bridge construction process according to the existing reusable ontology model; in the process of enumerating terms, the existing reusable ontology model can be used to search through several online ontology libraries, such as Ontolingua, DAML and DMOZ, to generate terminology keywords related to bridge construction technology, bridge structure, bridge construction technology risk, etc.;

[0068] The terminology keywords include bridge structure terms for bridge construction technology, bridge survey information terms, bridge construction technology, construction technology risks, and risk assessment / risk countermeasure terms;

[0069] A bridge construction technology vocabulary list is established based on the terminology keywords obtained by the enumeration method.

[0070] The terminology keywords include bridge structure terms for bridge construction technology, bridge survey information terms, bridge construction technology, construction technology risks, and risk assessment / risk countermeasure terms;

[0071] and establishing a bridge construction technology vocabulary list based on the terminology keywords obtained by the enumeration method;

[0072] Specifically, for bridge structure and bridge construction technology, a list of bridge construction technology terms is provided from the five aspects of "man, machine, material, method and environment", as shown in Table 1:

[0073] Table 1. WBS+RBS construction work and risk event vocabulary list

[0074]

[0075] S2: defining bridge construction technical risk data information according to the knowledge of the bridge construction technical vocabulary list; the bridge construction technical risk data information includes sample category information of bridge construction technical risks and information relationship between each sample category;

[0076] The bridge construction technology risk data information includes bridge structure entity information and bridge construction technology data information; and each bridge structure entity matches the corresponding bridge construction technology data information;

[0077] The data information of the bridge construction technology includes bridge structure survey information, bridge structure construction technology information, structure construction technology risk information and structure construction risk assessment / risk countermeasures information;

[0078] S3: defining the bridge structure entity information according to the bridge structure composition based on the bridge structure entity extension rule, and defining the entity data information of the bridge construction technology by adopting the attribute set extension method according to the bridge structure entity; so as to construct a bridge construction technology ontology knowledge base;

[0079] S4: obtaining a bridge construction technology risk chain based on the bridge construction technology ontology knowledge base; and constructing a bridge construction technology risk semantic web rule based on the bridge construction technology risk chain;

[0080] S5: Perform an ontology consistency check on the bridge construction technology risk semantic web rules, specifically using the Pellet plug-in to check the consistency between the ontology knowledge base of bridge construction technology and the statements / semantics of the bridge construction technology risk reasoning rules; and make decisions on the bridge construction technology risk plan based on the bridge construction technology risk semantic web rules after the consistency check.

[0081] This embodiment constructs a bridge construction technology ontology knowledge base by introducing multiple technical knowledge sources of the knowledge base of bridge construction technology risks, defines the entity classes and class relationships of the bridge construction technology ontology knowledge base, obtains the bridge construction technology risk chain based on the bridge construction technology ontology knowledge base; and constructs the bridge construction technology risk semantic web rules based on the bridge construction technology risk chain; performs ontology consistency check on the bridge construction technology risk semantic web rules, and makes decisions on bridge construction technology risk plans based on the bridge construction technology risk semantic web rules after the consistency check; makes bridge construction technology decisions by combining semantic web rules and semantic query rules, realizing the functions of knowledge integration, search and reasoning of bridge construction technology risks, which is convenient for bridge management personnel to manage bridge construction technology risks and make reasonable decisions on bridge construction technology.

[0082] In a specific embodiment, Figures 2 to 3 As shown, the bridge structure entity information in S3 includes bridge pile foundation class, bridge cap class, bridge pier class and bridge box girder class;

[0083] The entity data information of the bridge construction technology includes bridge structure category, bridge component construction technology category and bridge construction technology risk category;

[0084] The bridge construction technology category includes pile foundation construction technology category, platform construction technology category, pier construction technology category and box girder construction technology category;

[0085] The box girder construction technology category includes cantilever construction technology category, top-pushing construction technology category, hole-by-hole construction technology category and support construction technology category;

[0086] The pile foundation construction technology category includes sinking pile technology category and bored pile technology category;

[0087] The bridge pier construction technology category includes assembly prefabrication technology category and on-site casting technology category;

[0088] The said foundation construction technology category includes casing technology category, direct excavation technology category, enclosure excavation technology category and caisson / caisson technology category;

[0089] The bridge construction technical risk categories include construction personnel risk category, construction method risk category, construction material risk category, construction environment risk category and construction equipment risk category.

[0090] In a specific embodiment, the construction of the bridge construction technology ontology knowledge base in S3 is specifically:

[0091] S31: Based on the structural relationship of each unit of the bridge, the bridge structure entity is defined in the principle of from the whole to the part, from the bridge structure form, spatial structure, component components, and the construction sequence of structural units;

[0092] S32: defining entity classes and class hierarchies according to the entity data information of the bridge structure entity and the bridge construction technology, and determining parent-child relationships and parallel relationships between entity classes;

[0093] The attribute set extension method is used to define the entity data information of bridge construction technology, and the ontology model of bridge construction technology risk is obtained in the form of RDF triples;

[0094] The attribute set includes object attributes, data attributes, annotation attributes and attribute constraints;

[0095] The attribute constraint includes an is a attribute constraint, and the is a attribute constraint is used for an atomic relationship between two classes; and one class represents a parent class; and the other class represents a child class;

[0096] S33: Logical reasoning is performed on the ontology model of bridge construction technology risks through a reasoner based on description logic to obtain the bridge construction technology ontology knowledge base.

[0097] Specifically, the classes and class hierarchies of the ontology are defined according to the entity data information of the bridge structure entity and the bridge construction technology, and the parent-child relationship and parallel relationship between the classes are determined; in order to formally describe the domain concepts and semantic relationships from the perspective of structural division, we will use a top-down hierarchical method to divide the bridge structure, bridge construction technology and bridge construction technology risks; bridge components include pile foundations, abutments, piers and main beams, and bridge component construction technologies include pile foundation construction technology, abutment construction technology, pier construction technology and main beam construction technology. Due to the rapid development of bridge construction technology, the collected bridge construction technologies are mature construction technologies in construction projects. The final construction technology risk ontology includes construction personnel risk, construction method risk, construction material risk, construction environment risk and construction equipment risk. The definition of attribute relationship is specifically that the attribute relationship connects two classes or a class and its attributes to form an RDF triple form - subject-attribute-object. There are three types of attributes in the ontology structure, namely object attributes, data attributes and annotation attributes. Object attributes define the semantic relationship between classes. As shown in Table 2, the domain is the ontology of highway beam bridge construction methods, and the scope is the ontology of construction technology risk classes. The two ontologies are connected through the object attribute "risky". Table 3 shows the explanation of data attributes in the OWL semantic structure. The data attribute indicates that the data attribute "underground pipeline risk amount" is a subordinate data attribute of "construction environment risk", and the value type of this data attribute is decimal; the annotation attribute is usually an explanation of the entities and attributes in the ontology;

[0098] Table 2. OWL structure of object properties

[0099]

[0100]

[0101] Table 3. OWL structure of data attributes

[0102]

[0103] After the bridge construction technology risk framework is built, the first reasoning selection of bridge construction technology is carried out based on the bridge survey information ontology and bridge component ontology; Figure 5 As shown, the pile 1 class has the requirements that the soil layer is soft rock, the hole diameter is greater than or equal to 1800mm and the drilling depth is greater than 50m. The HermiT 1.4.3.456 reasoner in Protégé is used to infer that the three construction technologies of impact bored piles, positive cycle rotary bored piles and submersible drilling rigs meet the requirements. The ontology model of bridge construction technology risk is logically inferred by the reasoner based on description logic to obtain the implementation example of the bridge construction technology ontology knowledge base; because the instance is the representative of the class, as shown in Figure 4 As shown, "Construction Plan_1" is an instance of the "Construction Plan" class. "Construction Plan_1" has the "Risk Amount" data attribute, and assigns the value of "Risk Amount" to 75.0. Secondly, the attributes of the instance should conform to the definition of the class to which it belongs and inherit the object attributes of the class. For example, "Construction Plan" has the "Construction Risk" object attribute, and "Construction Plan_1" is an instance of "Construction Plan", so "Construction Plan_1" also has the "Construction Risk" object attribute. Finally, creating an instance requires determining the number, name, and attributes of the instance. The number of instances depends on the complexity and scale of the project. The naming convention is flexible, but it should be consistent.

[0104] In a specific embodiment, the bridge construction technology risk chain obtained in S4 is specifically:

[0105] The bridge construction phases are divided according to the construction process of the bridge construction work; and the construction technology risk hazard sources, hazard source dependency and bridge component importance weights that affect the bridge structure are confirmed based on the analytic hierarchy process and expert experience;

[0106] An expert opinion questionnaire to determine the construction technology risk path during the bridge construction phase based on the construction technology hazard sources, the dependency of the hazard sources, and the importance weights of bridge components;

[0107] Based on the expert opinion questionnaire combined with the LEC method, the technical risks of bridge construction are evaluated; and the technical risk amounts at different construction technical operation stages during the bridge construction process are obtained.

[0108] And the technical risks of bridge construction were evaluated by expert questionnaire and LEC method, as shown in Table 4;

[0109] Table 4. LEC risk assessment of pile foundation

[0110]

[0111]

[0112] The analytic hierarchy process is used to assign weights to bridge construction risks and bridge component importance, as shown in Table 5;

[0113] Table 5. Weight table of bridge sub-projects

[0114]

[0115] In a specific embodiment, the semantic web rules for constructing bridge construction technology risks in S4 are specifically:

[0116] S41: Select the ontology modeling tool Protégé to encode the ontology model in the bridge construction technology risk chain, and use the SWRL semantics to express the bridge construction technology risk chain by using the semantic web technology through the rule editor in Protégé, and obtain the semantic web rules of bridge construction technology risks to achieve the semantic expression of each bridge construction technology risk knowledge and their mutual relationship;

[0117] The semantic web rules of bridge construction technical risks at least include a calculation rule for the amount of bridge component construction technical risks, a calculation rule for the amount of bridge construction scheme combination risks, and a reasoning rule for bridge construction risk response measures;

[0118] S42: According to the semantic web rules of bridge construction technical risks, based on the SWQRL plug-in in Protégé, query the combination of bridge construction technical entities with the optimal technical risk amount in different construction technical operation stages during the bridge construction process to find the response strategy.

[0119] Specifically, according to the existing industry specifications or literature summary, risk response measures are proposed based on the technical risk amount X of different construction technical operation stages in the corresponding beam construction process, as shown in Table 6;

[0120] Table 6. Risk response strategies

[0121]

[0122] Specifically, after the ontology model of bridge construction technology risk is constructed, the rules are constructed according to the provisions of bridge risk in national standards and specifications, as shown in Table 7, which mainly include the risk amount of bridge components, the risk amount of bridge construction technology solutions, and the risk level and countermeasures rules. In Protégé, there are multiple built-in reasoners, such as Pellet, HermiT1.4.3.456 and ELK 0.4.3. The most commonly used one is Pellet reasoner, which supports SPQARL query and search for static information. SQWRL further embeds SPARQL query in the rules, so as to realize reasoning and query at the same time. Both SWRL and SQWRL use logical connections to express rules. The rules are divided into left and right sides, which are connected by “->”. The specific implementation process: the atoms on the left and right sides of the rule are connected by “^”. When the left part is satisfied, the result on the right side can be inferred. Atomic assertions are connected by "?" and include: 1) class atoms that specify the direct class of an instance; 2) object attribute atoms that connect two instances with object attributes; 3) data type attribute atoms that assign attributes to instances; and 4) built-in atoms that support calculation operations such as arithmetic, sorting, and selection. The inference results are as follows: Figure 6-11 shown.

[0123] Table 7. SWRL rules for risk reasoning in bridge construction technology

[0124]

[0125]

[0126] Specifically, Rule 1: Bored piles (impact bored piles) -> Need to check (impact bored piles, true)

[0127] The rule is explained as follows: If bored piles have the construction technology of impact bored piles, then the technology needs to be checked;

[0128] Rule 2: Bored piles (impact bored piles) ^ need to be checked (impact bored piles, true) —> construction material risk (construction material risk) ^ construction environment risk (construction environment risk) ^ risky (impact bored piles, construction equipment risk) ^ risky (impact bored piles, construction personnel risk) ^ risky (impact bored piles, construction environment risk) ^ risky (impact bored piles, construction method risk) ^ risky (impact bored piles, construction material risk) ^ construction personnel risk (construction personnel risk) ^ construction method risk (construction method risk) ^ construction equipment risk (construction equipment risk)

[0129] The rules are explained as follows: Impact bored piles mainly inspect the risks of construction personnel, construction materials, construction equipment, construction methods and construction environment.

[0130] Rule 3: Highway beam bridge construction method (?A)^swrlb:multiply(?S1,?u11,?w1)^swrlb:add(?SZ,?S1,?S2)^Risk amount of unreasonable construction technology (?A,?u12)^Risk weight of immature construction technology (?A,?w1)^Risk amount of immature construction technology (?A,?u11)^Risk weight of unreasonable construction technology (?A,?w2)^swrlb:multiply(?S2,?u12,?w2)->Risk amount of construction method (?A,?SZ)

[0131] The calculation expression corresponding to Rule 3 is: Construction method risk = unreasonable construction technology risk * unreasonable construction technology risk weight + immature construction technology risk * immature construction technology risk weight

[0132] Rule 4: Highway beam bridge construction method (?A)^Construction material risk (?A,?d)^swrlb:multiply(?bb,?b,?b1)^Construction equipment risk (?A,?c)^swrlb:multiply(?ee,?e,?e1)^swrlb:multiply(?dd,?d,?d1)^Construction method risk (?A,?b)^swrlb:multiply(?aa,?a,?a1)^Construction equipment risk weight ( ? A,? c1)^Construction personnel risk weight (? A,? e1)^Construction environment risk amount (? A,? a)^Construction personnel risk amount (? A,? e)^Construction material risk weight (? A,? d1)^swrlb:multiply(?cc,?c,?c1)^Construction method risk weight (? A,? b1)^swrlb:add(?K,?aa,?bb,?cc,?dd,?ee)^Construction environment risk weight (? A,? a1)->Construction risk amount (? A,? K)

[0133] The calculation expression corresponding to Rule 4 is: Construction risk amount = construction personnel risk amount * construction personnel risk weight + construction material risk amount * construction equipment risk weight + construction equipment risk amount * construction material risk weight + construction method risk amount * construction method risk weight + construction environment risk amount * construction environment risk weight;

[0134] Rule 5: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 20) ^ construction risk amount (?A,?a) -> risk level (?A, "slightly dangerous") ^ risk countermeasures (?A, "risk can be ignored")

[0135] The rule is explained as follows: According to the risk assessment standard, if the risk is less than 20, the risk level is slightly dangerous, and the risk countermeasure is to ignore the risk;

[0136] Rule 6: Highway beam bridge construction method (?A) ^ swrlb: greaterThan (?a, 20) ^ construction risk amount (?A,?a) ^ swrlb: lessThan (?a, 70) -> Danger level (?A, "general danger") ^ risk countermeasures (?A, "strengthen monitoring and form records")

[0137] The rule is explained as follows: According to the risk assessment standard, if the risk amount is less than 70 and greater than 20, the danger level is general danger, and the risk countermeasure is to strengthen monitoring and keep records.

[0138] Rule 7: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 160) ^ swrlb: greaterThan (?a, 70) ^ Construction risk amount (?A,?a) -> Danger level (?A, "significant danger") ^ Risk countermeasures (?A, "take appropriate protective measures during construction")

[0139] The rule is explained as follows: According to the risk assessment standard, if the risk amount is less than 160 and greater than 70, the degree of danger is significant, and the risk countermeasure is to take corresponding protective measures during the construction process.

[0140] Rule 8: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 320) ^ construction risk amount (?A,?a) ^ swrlb: greaterThan (?a, 160) -> Danger level (?A, "highly dangerous") ^ risk countermeasures (?A, "modify the construction plan")

[0141] The rule is explained as follows: According to the risk assessment standard, if the risk is less than 320 and greater than 160, the danger level is high and the risk countermeasure is to modify the construction plan.

[0142] Rule 9: Highway beam bridge construction method (?A) ^ construction risk (?A,?a) ^ swrlb:greaterThan(?a,320)->danger level (?A, "very dangerous") ^ risk countermeasures (?A, "this construction method is prohibited")

[0143] The rule is explained as follows: According to the risk assessment standard, if the risk is greater than 320, the danger level is very dangerous and the risk countermeasure is to prohibit the use of this construction method.

[0144] Rule 10: Construction combination scheme_1 (?A)^ impact bored pile (?B)^ construction risk (?B,?b)^ pile foundation weight (?B,?bb)^ direct excavation method (?C)^ pedestal weight (?C,?cc)^ construction risk (?C,?c)^ combined steel formwork (?D)^ construction risk (?D,?d)^ pier weight (?D,?dd)^ bracket construction method (?E)^ construction risk (?E,?e)^ main beam weight (?E,?ee) ^swrlb:multiply(?bbb,?b,?bb)^swrlb:multiply(?ccc,?c,?cc)^swrlb:multiply(?ddd,?d,?dd)^swrlb:multiply(?eee,?e,?ee)^swrlb:add(?a,?bbb,?ccc,?ddd,?eee)->Construction technical risk of the whole bridge (?A,?a)

[0145] The rule is explained as follows: Construction technical risk of the entire bridge = risk of impact bored piles * risk weight of impact bored piles + risk of abutments * risk weight of abutments + risk of piers * risk weight of piers + risk of main beams * risk weight of main beams

[0146] Rule 11: Construction plan (?A) ^ technical risk of the whole bridge construction (?A,?a) ^ swrlb:lessThan(?a,160)->sqwrl:select(?A,?a)

[0147] The rules are interpreted as: Fig.12 As shown in the figure, if the construction technology risk of the whole bridge is less than 160, the construction plan can be selected. Using the SWQRL plug-in in Protégé, the rules 1-11 are constructed to infer the construction combination plan with a risk less than 160.

[0148] In a specific embodiment, the semantic web rules of bridge construction technology risk described in S5 are subjected to ontology consistency check, specifically: using the Pellet plug-in to check the consistency of the statements / semantics of the ontology knowledge base of bridge construction technology and the reasoning rules of bridge construction technology risk.

[0149] In order to check the quality of the bridge construction technical risk ontology model, consistency checks are required at the grammatical and semantic levels. The consistency check can be automatically verified by using the Pellet reasoner in the Protégé environment, and the corresponding results are shown in the figure below. Figure 13 to Figure 14 As shown in the figure, the conceptual hierarchy of the bridge construction technology risk ontology is unchanged before and after ontology reasoning. The results show that the bridge construction technology risk ontology meets the requirements of logical axioms at the semantic level. Fig.15 As shown, the reasoning log shows no syntax errors, which confirms that the bridge construction technology risk ontology model complies with the OWL syntax rules at the syntax level. These results confirm that the bridge construction technology risk ontology passes the consistency check.

[0150] Since bridge risk management is divided into risk identification, risk assessment and risk response. The existing risk management method is to make judgments based on the experts' own knowledge and experience. The risk management records are also scattered, and it is difficult to intuitively observe the connections between various knowledge. It is difficult for bridge construction personnel to manage the risks of construction technology. Therefore, in order to solve the problems of cross-domain and multi-source risk information dispersion and risk management difficulties, a method for constructing a bridge construction technology risk ontology is proposed. The present invention constructs an ontology for various information sources in the bridge field through the technical knowledge of bridge construction technology risks, and constructs the connections between them. It performs reasoning through the establishment of rules, and realizes the functions of knowledge integration, search and reasoning of bridge construction technology risks, which is convenient for bridge management personnel to manage bridge construction technology risks and make reasonable decisions on bridge construction technology.

[0151] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A method for risk management in the decision-making stage of bridge construction technology based on ontology, characterized in that: The following steps are involved: S1: Extract the technical concept knowledge and the relationship between the technical concept knowledge in the bridge construction technology process according to the knowledge base of bridge construction technical risks, and obtain the list of bridge construction technical vocabulary; The knowledge base of bridge construction technical risks includes: bridge structure knowledge, bridge survey knowledge, bridge construction technical knowledge, bridge construction technical risk knowledge, bridge construction risk specification knowledge and bridge construction risk response measures knowledge; The method of obtaining a bridge construction technical vocabulary list comprises the following steps: S21: determining the domain and application scope of the bridge construction process according to the knowledge data of the knowledge base of the bridge construction technical risk, and acquiring an existing reusable ontology model based on the domain and application scope of the bridge construction process; S22: using an enumeration method to obtain corresponding terminology keywords in the bridge construction process according to the existing reusable ontology model; The terminology keywords include bridge structure terms for bridge construction technology, bridge survey information terms, bridge construction technology, construction technology risks, and risk assessment / risk countermeasure terms; and establishing a bridge construction technology vocabulary list based on the terminology keywords obtained by the enumeration method; S2: defining bridge construction technical risk data information according to the knowledge of the bridge construction technical vocabulary list; the bridge construction technical risk data information includes sample category information of bridge construction technical risks and information relationship between each sample category; The bridge construction technology risk data information includes bridge structure entity information and bridge construction technology data information; and each bridge structure entity matches the corresponding bridge construction technology data information; The data information of the bridge construction technology includes bridge structure survey information, bridge structure construction technology information, structure construction technology risk information and structure construction risk assessment / risk countermeasures information; S3: defining bridge structure entity information according to the bridge structure composition based on the bridge structure entity extension rule, and defining entity data information of bridge construction technology using an attribute set according to the bridge structure entity; so as to construct a bridge construction technology ontology knowledge base; The construction of the bridge construction technology ontology knowledge base is specifically as follows: S31: Based on the structural relationship of each unit of the bridge, the bridge structure entity is defined in the principle of from the whole to the part, from the bridge structure form, spatial structure, component components, and the construction sequence of structural units; S32: defining entity classes and class hierarchies according to the entity data information of the bridge structure entity and the bridge construction technology, and determining parent-child relationships and parallel relationships between entity classes; The attribute set extension method is used to define the entity data information of bridge construction technology, and the ontology model of bridge construction technology risk is obtained in the form of RDF triples; The attribute set includes object attributes, data attributes, annotation attributes and attribute constraints; The attribute constraint includes an is a attribute constraint, and the is a attribute constraint is used for an atomic relationship between two classes; and one class represents a parent class; and the other class represents a child class; S33: performing logical reasoning on the ontology model of bridge construction technology risk through a reasoner based on description logic to obtain a bridge construction technology ontology knowledge base; S4: obtaining a bridge construction technology risk chain based on the bridge construction technology ontology knowledge base; The bridge construction technology risk chain is obtained by dividing the bridge construction stages according to the construction process of the bridge construction work; and confirming the construction technology risk hazard sources, hazard source dependency and bridge component importance weights that affect the bridge structure based on the hierarchical analysis method and expert experience value; An expert opinion questionnaire to determine the construction technology risk path during the bridge construction phase based on the construction technology hazard sources, the dependency of the hazard sources, and the importance weights of bridge components; Based on the expert opinion questionnaire combined with the LEC method, the technical risk of bridge construction is evaluated; the technical risk amount at different construction technical operation stages during the bridge construction process is obtained; Based on the bridge construction technology risk chain, the semantic web rules of bridge construction technology risk are constructed, specifically: S41: Select the ontology modeling tool Protégé to encode the ontology model in the bridge construction technology risk chain, and use the SWRL semantics to express the bridge construction technology risk chain by using the semantic web technology through the rule editor in Protégé, and obtain the semantic web rules of bridge construction technology risks to achieve the semantic expression of each bridge construction technology risk knowledge and their mutual relationship; The semantic web rules of bridge construction technical risks at least include a calculation rule for the amount of bridge component construction technical risks, a calculation rule for the amount of bridge construction scheme combination risks, and a reasoning rule for bridge construction risk response measures; S42: Based on the semantic web rules of bridge construction technical risks, the combination of bridge construction technical entities with the optimal technical risk amount in different construction technical operation stages during the bridge construction process is queried based on the SWQRL plug-in in Protégé; The semantic web rules for bridge construction technical risks specifically include: Rule 1: Bored piles (impact bored piles) -> Check required (impact bored piles, true) The rule is explained as follows: If bored piles have the construction technology of impact bored piles, then the technology needs to be checked; Rule 2: Bored piles (impact bored piles) ^ need to be checked (impact bored piles, true) —> construction material risk (construction material risk) ^ construction environment risk (construction environment risk) ^ risky (impact bored piles, construction equipment risk) ^ risky (impact bored piles, construction personnel risk) ^ risky (impact bored piles, construction environment risk) ^ risky (impact bored piles, construction method risk) ^ risky (impact bored piles, construction material risk) ^ construction personnel risk (construction personnel risk) ^ construction method risk (construction method risk) ^ construction equipment risk (construction equipment risk); The rules are explained as follows: impact bored piles mainly check the risks of construction personnel, construction materials, construction equipment, construction methods and construction environment; Rule 3: Highway beam bridge construction method (?A)^swrlb:multiply(?S1,?u11,?w1)^swrlb:add(?SZ,?S1,?S2)^Unreasonable construction technology risk amount (?A,?u12)^Immature construction technology risk weight (?A,?w1)^Immature construction technology risk amount (?A,?u11)^Unreasonable construction technology risk weight (?A,?w2)^swrlb:multiply(?S2,?u12,?w2)->Construction method risk amount (?A,?SZ); The calculation expression corresponding to Rule 3 is: Construction method risk amount = unreasonable construction technology risk amount * unreasonable construction technology risk weight + immature construction technology risk amount * immature construction technology risk weight; Rule 4: Highway beam bridge construction method (?A)^construction material risk (?A,?d)^swrlb:multiply(?bb,?b,?b1)^construction equipment risk (?A,?c)^swrlb:multiply(?ee,?e,?e1)^swrlb:multiply(?dd,?d,?d1)^construction method risk (?A,?b)^swrlb:multiply(?aa,?a,?a1)^construction equipment risk weight (? A,? c1)^Construction personnel risk weight (?A,?e1)^Construction environment risk amount (?A,?a)^Construction personnel risk amount (?A,?e)^Construction material risk weight (?A,?d1)^swrlb:multiply(?cc,?c,?c1)^Construction method risk weight (?A,?b1)^swrlb:add(?K,?aa,?bb,?cc,?dd,?ee)^Construction environment risk weight (?A,?a1)->Construction risk amount (?A,?K); The calculation expression corresponding to Rule 4 is: Construction risk amount = construction personnel risk amount * construction personnel risk weight + construction material risk amount * construction equipment risk weight + construction equipment risk amount * construction material risk weight + construction method risk amount * construction method risk weight + construction environment risk amount * construction environment risk weight; Rule 5: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 20) ^ construction risk amount (?A,?a) -> risk level (?A, "slightly dangerous") ^ risk countermeasures (?A, "risk can be ignored") The rule is explained as follows: According to the risk assessment standard, if the risk is less than 20, the risk level is slightly dangerous, and the risk countermeasure is to ignore the risk; Rule 6: Highway beam bridge construction method (?A) ^ swrlb: greaterThan (?a, 20) ^ construction risk amount (?A,?a) ^ swrlb: lessThan (?a, 70) -> Danger level (?A, "general danger") ^ risk countermeasures (?A, "strengthen monitoring and form records"); The rule is explained as follows: According to the risk assessment standard, if the risk is less than 70 and greater than 20, the risk level is general risk, and the risk countermeasure is to strengthen monitoring and form records; Rule 7: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 160) ^ swrlb: greaterThan (?a, 70) ^ Construction risk amount (?A,?a) -> Danger level (?A, "significant danger") ^ Risk countermeasures (?A, "take appropriate protective measures during construction") The rule is explained as follows: According to the risk assessment standard, if the risk is less than 160 and greater than 70, the risk level is significant, and the risk countermeasure is to take corresponding protective measures during the construction process; Rule 8: Highway beam bridge construction method (?A) ^ swrlb: lessThan (?a, 320) ^ construction risk amount (?A,?a) ^ swrlb: greaterThan (?a, 160) -> Danger level (?A, "highly dangerous") ^ risk countermeasures (?A, "modify the construction plan") The rule is explained as follows: According to the risk assessment standard, if the risk is less than 320 and greater than 160, the risk level is high and the risk countermeasure is to modify the construction plan; Rule 9: Highway beam bridge construction method (?A) ^ construction risk (?A,?a) ^ swrlb:greaterThan(?a,320)->danger level (?A, "very dangerous") ^ risk countermeasures (?A, "this construction method is prohibited") The rule is explained as follows: According to the risk assessment standard, if the risk is greater than 320, the risk level is very dangerous and the risk countermeasure is to prohibit the use of the construction method; Rule 10: Construction combination scheme_1(?A)^Impact bored pile(?B)^Construction risk(?B,?b)^Pile foundation weight(?B,?bb)^Direct excavation method(?C)^Cap weight(?C,?cc)^Construction risk(?C,?c)^Combined steel formwork(?D)^Construction risk(?D,?d)^Pier weight(?D,?dd)^Support construction method(?E)^Construction risk(?E,?e)^Main beam weight(?E,?ee)^ swrlb:multiply(?bbb,?b,?bb)^swrlb:multiply(?ccc,?c,?cc)^swrlb:multiply(?ddd,?d,?dd)^swrlb:multiply(?eee,?e,?ee)^swrlb:add(?a,?bbb,?ccc,?ddd,?eee)->Construction technical risk of the whole bridge (?A,?a); The rule is explained as follows: The construction technical risk of the entire bridge = the risk amount of impact bored piles * the risk weight of impact bored piles + the risk amount of abutments * the risk weight of abutments + the risk amount of piers * the risk weight of piers + the risk amount of main beams * the risk weight of main beams; Rule 11: Construction plan (?A)^Technical risk of whole bridge construction (?A,?a)^swrlb:lessThan(?a,160)->sqwrl:select(?A,?a); The rule is explained as follows: if the construction technology risk of the whole bridge is less than 160, the construction plan is selected, and the SWQRL plug-in in Protégé is used to construct rules 1-11 to infer the construction combination plan with a risk less than 160; S5: Performing an ontology consistency check on the bridge construction technology risk semantic web rules, and making a decision on the bridge construction technology risk plan based on the bridge construction technology risk semantic web rules after the consistency check.

2. The method for risk management based on the decision-making stage of bridge construction technology according to claim 1 is characterized in that: The bridge structure entity information in S3 includes bridge pile foundation class, bridge abutment class, bridge pier class and bridge box girder class; The entity data information of the bridge construction technology includes bridge structure category, bridge component construction technology category and bridge construction technology risk category; The bridge construction technology category includes pile foundation construction technology category, platform construction technology category, pier construction technology category and box girder construction technology category; The box girder construction technology category includes cantilever construction technology category, top-pushing construction technology category, hole-by-hole construction technology category and support construction technology category; The pile foundation construction technology category includes sinking pile technology category and bored pile technology category; The bridge pier construction technology category includes assembly prefabrication technology category and on-site casting technology category; The said foundation construction technology category includes casing technology category, direct excavation technology category, enclosure excavation technology category and caisson / caisson technology category; The bridge construction technical risk categories include construction personnel risk category, construction method risk category, construction material risk category, construction environment risk category and construction equipment risk category.

3. The method for risk management in the decision-making stage of bridge construction technology based on ontology according to claim 1 is characterized in that: The semantic web rules of bridge construction technology risk described in S4 are subjected to ontology consistency check, specifically; The Pellet plug-in is used to check the consistency of the statements / semantics of the ontology knowledge base of bridge construction technology and the risk reasoning rules of bridge construction technology.