A construction method for controlling tunnel floor heave

By laying a combination method of steel structure support and filler on the tunnel floor, the problems of difficult and high cost of tunnel floor treatment in the prior art are solved, and the effects of simple construction, high material recycling and high treatment strength are achieved. Reduce the treatment cost and adjust the bearing capacity and deformation resistance of the tunnel floor plate through prestressing.

CN117948186BActive Publication Date: 2024-12-03CHINA UNIV OF MINING & TECH +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410127197.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-01-30
Publication Date
2024-12-03
Estimated Expiration
2044-01-30

AI Technical Summary

Technical Problem

The existing technology is difficult to construct when controlling the tunnel bottoms, and the materials cannot be recycled and reused, so it cannot effectively control the deformation of the surrounding rock of the tunnel bottom plate.

Method used

The combination method of steel structure support and filler is adopted, including laying filler in the excavation area of ​​the tunnel bottom plate and placing steel structure support, applying prestress, using anchor pallets and steel bar warp and weft grid to provide support, and the filling is made of rock and coal Garrot and waste reinforced concrete, the bearing capacity and deformation amount are adjusted by prestressing, and the bottom plate stability is monitored in combination with the pressure detection box.

Benefits of technology

It achieves the effects of simple construction, recyclable materials and high treatment strength, reduces the treatment cost, and increases the bearing capacity and deformation resistance of the tunnel floor by adjusting the anchor prestress.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN117948186B_ABST
    Figure CN117948186B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of tunnel surrounding rock control, and specifically discloses a construction method for controlling tunnel floor heave, comprising the following steps: determining the tunnel floor heave area and the excavation depth H; excavating a lower excavation area with a depth of H; laying a layer of filler in the lower excavation area and leveling it; placing a steel structure support body on the leveled filler, the steel structure support body comprising an upper and lower layer of steel bar warp and weft mesh, a steel belt and an anchor tray, and a plurality of anchors connecting the upper and lower layers, wherein the plurality of anchors have a spacing; laying a middle layer of filler; applying prestress to the anchors; laying the last layer of filler and leveling it. The construction method for controlling tunnel floor heave of the present invention is simple to construct, the required construction materials can be recycled and reused, and the construction filler is easy to obtain and has low cost. At the same time, the repair support body based on the construction method has high strength, and the bearing capacity and deformation can be affected by adjusting the prestress of the anchor, thereby increasing the bearing capacity of the tunnel floor.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel surrounding rock control, and in particular to a construction method for controlling tunnel floor heave. Background Art

[0002] Floor heave in soft rock roadway is a common problem in coal mining. Roadway floor heave is the most difficult part of surrounding rock deformation to control, and the management of roadway floor heave has always been a difficult problem. As a common problem in roadway engineering, floor heave has brought a series of troubles to engineering construction and production. At present, there are many methods for controlling floor heave, but due to the complexity of the surrounding rock properties, failure mechanism, stress state and geological environment of the roadway floor under high stress, the mechanical mechanism and method of floor heave control become complicated.

[0003] In the prior art, methods such as adding anchor rods, grouting, concrete arching, cutting, drilling, etc. are usually adopted to reinforce or relieve pressure on the bottom plate of the tunnel. For example, the prior art with announcement number CN101886545B proposes a method of treating the bottom heave of soft rock tunnels by using micro-crushed stone pipe injection piles. Although a certain effect of controlling the deformation of the surrounding rock has been achieved, this method requires special equipment and special materials for construction, and its construction is difficult. In addition, the construction materials cannot be recycled and reused, the construction cost is high, and the expected effect cannot be achieved.

[0004] In view of this, how to reduce construction difficulty and construction cost while ensuring the treatment effect has become a technical problem in this field. Summary of the invention

[0005] The present invention aims to solve one of the technical problems in the related art to at least a certain extent. To this end, one purpose of the present invention is to propose a construction method for treating tunnel floor heave, which has the advantages of convenient construction, reusable materials, and high treatment strength, thereby achieving the purpose of effectively preventing and controlling tunnel floor heave and reducing treatment costs.

[0006] To achieve the above object, the present invention provides the following solution: The present invention provides a construction method for treating tunnel floor heave, comprising the following steps:

[0007] Determine the tunnel floor heave area and determine the excavation depth H;

[0008] Excavate a downcut area with a depth of H;

[0009] Laying a layer of fill material in the excavated area and leveling it;

[0010] Placing a steel structure support on the leveled filler, the steel structure support comprising an upper and lower layer of steel bars, a steel belt and an anchor tray, and a plurality of anchors connecting the upper and lower layers, wherein the plurality of anchors have spacing between them;

[0011] Lay the middle layer of filler;

[0012] Applying prestress to the anchor rod;

[0013] Lay the final layer of filler and level it.

[0014] Preferably, the excavation depth H is determined by drilling three vertical downward holes in the tunnel floor, wherein the length of the holes is three times the width of the tunnel, and using sonic velocity measurement to obtain the damage depth of the tunnel floor bulge layer as the excavation depth.

[0015] Preferably, 500 mm is excavated on both sides of the excavation area to expand the scope of repair and treatment, and form support force from both sides of the bottom of the tunnel to improve the overall anti-deformation strength.

[0016] Preferably, the spacing between the anchor trays is greater than or equal to 3 times the average diameter of the filler particles and less than the excavation depth H / 2. Reasonable setting of the spacing between two adjacent anchors can provide the connection strength of the steel structure support on the one hand, and on the other hand, consider the coordination with the filler to ensure that the filler filled in the steel structure support is in close and full contact with each other, so that the filler forms a whole through the anchor, steel belt, and steel warp and weft mesh.

[0017] Preferably, the filler is one or more of rock, coal gangue, and waste reinforced concrete. The filler needs to be made of relatively hard rock to ensure that the filler has sufficient strength to prevent the filler from having too low strength and resulting in insufficient bearing capacity.

[0018] Preferably, the thickness of the first layer of filler laid in the excavated area is the length of the exposed end of the anchor rod extending out of the anchor rod tray, that is, the length of the end of the anchor rod extending out of the anchor rod tray.

[0019] Preferably, the steel structure support body is an arched structure with a downward depression in the middle. The steel structure support body with an arched structure has a greater bearing capacity at the arch bottom position, and the maximum deformation that can be tolerated is increased, which is helpful to treat the tunnel floor bulge with a central bulge.

[0020] Preferably, when laying the middle layer of filler, at least one pressure detection box is placed, and the force-bearing surface of the pressure detection box is oriented horizontally and perpendicular to the direction of the tunnel. Preferably, when laying the filler, a certain amount of pressure detection boxes are placed to detect internal pressure changes. If the pressure keeps increasing, it proves that the bottom plate is stable. If the pressure suddenly decreases and then continues to decrease and no longer increases, the area should be repaired.

[0021] Preferably, the construction method further comprises vibrating and compacting the filler in layers to make the fillers in close contact with each other. The filler is formed into a whole by anchor rods, steel belts, and steel warp and weft meshes. When the bottom slab of the tunnel swells, the filler is stressed to form an arched structure, making its structural strength higher.

[0022] Preferably, the above-mentioned construction method also includes: after completing the tunnel floor heave treatment of the construction method once, if the tunnel floor continues to deform severely or the data read by the pressure detection box suddenly decreases significantly and no longer increases, the floor heave area is cleared and the steps of the construction method are repeated.

[0023] The present invention discloses the following technical effects:

[0024] The construction method for treating tunnel floor heave of the present invention is simple to construct, the required construction materials can be recycled, and the construction filling materials are easy to obtain and low in cost. At the same time, the repair support body based on the construction method has high strength, and the bearing capacity and deformation can be affected by adjusting the prestress of the anchor rod, thereby increasing the bearing capacity of the tunnel floor. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0026] Figure 1 The flowchart of the construction method for treating tunnel floor heave of the present invention;

[0027] Figure 2 Schematic diagram of tunnel floor bulge in an embodiment of the present invention;

[0028] Figure 3 Schematic diagram of the tunnel floor heave excavation area in an embodiment of the present invention;

[0029] Figure 4 This is a schematic diagram of the completion of the tunnel floor in one embodiment of the present invention;

[0030] Figure 5 This is a schematic diagram of the structure of a steel structure support body in an embodiment of the present invention;

[0031] Figure 6 A schematic diagram of the completion of the tunnel floor in another embodiment of the present invention;

[0032] Figure 7 Schematic diagram of a simulation model of a floor heave region in an embodiment of the present invention;

[0033] Figure 8 It is a schematic diagram of simulated force analysis of the floor heave area in an embodiment of the present invention;

[0034] Fig. 9 This is a data diagram of simulated anchor bolt preload and bearing capacity in an embodiment of the present invention;

[0035] Among them, 1. Bottom heave area; 2. Tunnel surrounding rock; 3. Tunnel bottom plate; 4. Steel structure support; 5. Filler; 6. Pressure detection box; 41. Anchor rod; 42. Anchor rod tray; 43. Steel belt; 44. Steel warp and weft mesh. DETAILED DESCRIPTION

[0036] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0037] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.

[0038] Reference Figure 2 As shown, the present invention provides a construction method for controlling tunnel floor heave, comprising the following steps:

[0039] Step S1, determining the tunnel floor heave area 1 and the excavation depth H.

[0040] In some embodiments, according to actual working conditions, the area of ​​the tunnel floor 3 to be excavated is measured by acoustic wave velocity measurement. The better the surrounding rock quality, the faster the acoustic wave propagation speed, thereby determining the floor excavation depth H (in m).

[0041] In some embodiments, the excavation depth H is obtained by drilling three vertical downward holes in the tunnel floor 3, with the length of the hole being 3 times the width of the tunnel. The ultrasonic velocity measurement method is used to obtain the damage depth of the bottom bulge rock layer of the tunnel floor, that is, the desired excavation depth.

[0042] Step S2: excavate the bottom heave area 1 to excavate a lower excavation area with a depth of H, such as Figure 2 and Figure 3 shown.

[0043] In some embodiments, a width of L (in mm) is excavated on both sides of the left and right sides of the down-dig area, so that the width of the down-dig area is greater than the width of the tunnel, and both sides are widened by L.

[0044] In some embodiments, L=500 mm.

[0045] Step S3, laying a layer of filler 5 in the excavated area of ​​the tunnel floor 3 and leveling it, and the laying depth can be the length of the exposed end of the anchor rod 41.

[0046] In some embodiments, the filler 5 is selected from one or more of rock, coal gangue, and waste reinforced concrete. The criterion for selecting the filler 5 is that it has a certain hardness. It can be materials such as rock, coal gangue, waste reinforced concrete, and a mixture of the above materials to ensure that the filler 5 has sufficient strength and prevent the filler 5 from being too low in strength and resulting in insufficient bearing capacity.

[0047] Step S4: placing the steel structure support 4 on the leveled filler 5 and laying a middle layer of filler 5.

[0048] The steel structure support body 4 includes an upper support body and a lower support body and a plurality of anchor rods 41 connecting the upper support body and the lower support body, wherein the anchor rods 41 have spaced intervals.

[0049] In some embodiments, the upper support body includes an upper layer of steel bars 44, steel belts 43, and anchor trays 42, and the lower support body includes a lower layer of steel bars 44, steel belts 43, and anchor trays 42; Figure 5 As shown, the steel belt 43 is located on the outside of the steel warp and weft mesh 44, the anchor tray 42 is located on the outside of the steel belt 43, and there are multiple anchor trays 42 distributed at intervals. Both ends of the anchor 41 respectively penetrate the steel warp and weft mesh 44, the steel belt 43 and the anchor tray 42 of the two-layer support body, and are pre-tightened on the outside of the two anchor trays 42, thereby generating prestress on the filler 5 filled between the upper support body and the lower support body.

[0050] In some embodiments, step S4 includes:

[0051] Step S41, laying the lower layer of steel bars 44, steel belts 43, anchor tray 42, and placing anchors 41, with the anchors 41 spaced apart.

[0052] In some embodiments, the spacing between the anchor trays 42 is greater than or equal to 3 times the average diameter of the filler 5 particles and less than half of the excavation depth H.

[0053] Step S42 , laying a middle layer of filler 5 , the depth of which is the distance between the upper and lower layers of steel belts 43 in the steel structure support body 4 .

[0054] Step S43, laying the upper layer of steel bars 44, steel belts 43, and anchor trays 42 in sequence.

[0055] Step S44 , applying prestress to the anchor rod 41 .

[0056] In some embodiments, reference Figures 7 to 9 As shown, Figure 7 Schematic diagram of a simulation model of a floor heave region in an embodiment of the present invention; Figure 8 It is a schematic diagram of simulated force analysis of the floor heave area in an embodiment of the present invention;

[0057] Fig. 9 The figure is a data diagram of the simulated anchor preload and bearing capacity in the embodiment of the present invention. It can be seen from the simulation results of the numerical simulation software PFC that different anchor 41 prestresses have a great influence on the bearing capacity. When the prestress is 4N·m, the maximum bearing capacity is 4.56N and the maximum deformation is 12.82mm; when the prestress is 6N·m, the maximum bearing capacity is 6.61N and the maximum deformation is 20.58mm; when the prestress is 8N·m, the maximum bearing capacity is 13.44N and the maximum deformation is 29.32mm. It can be seen that the appropriate prestress can increase the bearing capacity of the tunnel floor 3.

[0058] Step S5, laying the last layer of filler 5 and leveling it.

[0059] In some embodiments, the laid filler 5 must be vibrated and compacted in layers to ensure close and full contact between the fillers 5. The filler 5 is formed into a whole through anchor rods 41, steel belts 43, and steel warp and weft meshes 44. When the tunnel floor 3 bulges, the filler 5 is stressed to form an arched structure, making its structural strength higher.

[0060] Further optimizing the scheme, in some embodiments, such as Figure 6 As shown, the bottom of the excavation area is a concave arc surface, and the steel structure support body 4 is also fixed into a downward concave arch structure, and the last layer of filler 5 needs to be leveled. The bottom of the steel structure support body 4 using this structure can withstand greater pressure and is more suitable for the treatment of bottom stress type tunnel floor bulge.

[0061] In some embodiments, at least one pressure detection box 6 is placed when laying the filler 5 to detect internal pressure changes. If the pressure continues to increase, it proves that the tunnel floor 3 is stable. If the pressure suddenly drops, the area should be repaired.

[0062] After the construction team has completed the treatment of the tunnel floor heave using the above method, if the tunnel floor 3 continues to deform seriously in the later stage, it is only necessary to clear the lower floor heave area 1 and repeat the above steps.

[0063] Compared with the prior art, the present invention has the following advantages and technical effects:

[0064] 1. High strength. Through the numerical simulation of particle flow simulation software PFC, it can be known that when the preload force is 8N·m, its bearing capacity is 13.5kN.

[0065] 2. Recyclable: when the mining of the working face is completed and the tunnel is no longer in use, the filler 5, anchor rod 41, steel belt 43, and steel bar warp and weft mesh 44 can be recycled and reused.

[0066] 3. Low cost, the required fillers 5 are all waste particles, such as rocks, coal gangue, waste reinforced concrete and other relatively hard particles.

[0067] The details not described in detail in the present invention are all conventional technical means known to those skilled in the art.

[0068] In the description of the present invention, it should be understood that the terms "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside" and "outside" etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present invention.

[0069] The embodiments described above are only descriptions of the preferred modes of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, various modifications and improvements made to the technical solutions of the present invention by ordinary technicians in this field should all fall within the protection scope determined by the claims of the present invention.

Claims

1. A construction method for treating tunnel floor heave, characterized in that: The following steps are involved: Determine the tunnel floor heave area and determine the excavation depth H; Excavate a downcut area with a depth of H; Laying a layer of fill material in the excavated area and leveling it; Placing a steel structure support on the leveled filler, the steel structure support comprising an upper and lower layer of steel bars, a steel belt and an anchor tray, and a plurality of anchors connecting the upper and lower layers, wherein the plurality of anchors have spacing between them; Lay the middle layer of filler; The specific steps of placing the steel structure support and laying the middle layer of filler are: laying the lower layer of anchor tray, steel belt, steel bar warp and weft mesh and placing the anchor, laying the middle layer of filler, and laying the upper layer of steel bar warp and weft mesh, steel belt, and anchor tray in sequence; Applying prestress to the anchor rod; Lay the final layer of fill and level it; The thickness of the first layer of filler laid in the excavated area is the length of the exposed end of the anchor rod extending out of the anchor rod tray.

2. The construction method for treating tunnel floor heave according to claim 1, characterized in that: The method of determining the excavation depth H includes drilling three vertical downward holes in the tunnel floor, wherein the length of the holes is three times the width of the tunnel, and using an acoustic wave velocity measurement method to obtain the damage depth of the bottom bulge rock layer of the tunnel floor as the excavation depth.

3. The construction method for treating tunnel floor heave according to claim 1, characterized in that: Excavate 500 mm on both sides of the left and right sides of the excavation area.

4. The construction method for treating tunnel floor heave according to claim 1, characterized in that: The spacing between the anchor trays is greater than or equal to 3 times the average diameter of the filler particles and less than the excavation depth H / 2.

5. The construction method for treating tunnel floor heave according to claim 1, characterized in that: The filler is one or more of rock, coal gangue, and waste reinforced concrete.

6. The construction method for treating tunnel floor heave according to claim 1, characterized in that: The steel structure support body is an arched structure with a downward depression in the middle.

7. The construction method for treating tunnel floor heave according to claim 1, characterized in that: When laying the middle layer of filler, at least one pressure detection box is placed, and the force-bearing surface of the pressure detection box is oriented horizontally and perpendicular to the direction of the tunnel.

8. The construction method for treating tunnel floor heave according to claim 1, characterized in that: The method also includes vibrating and compacting the fillers in layers to ensure close contact between the fillers.

9. The construction method for treating tunnel floor heave according to claim 1, characterized in that: Also includes: After completing the tunnel floor heave treatment of the construction method once, if the tunnel floor continues to deform severely or the data read by the pressure detection box suddenly decreases significantly and no longer increases, the floor heave area is cleared and the steps of the construction method are repeated.