A temporary surcharge structure

By combining flexible mesh with irregularly shaped steel, a continuous temporary slope retaining wall is formed, which solves the problems of high construction cost, low safety and poor flexibility of traditional temporary slope retaining structures, and realizes the construction of a fast, safe and environmentally friendly temporary surcharge structure.

CN118029355BActive Publication Date: 2026-11-17CHINA RAILWAY SHANGHAI DESIGN INST GRP CO LTD
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410162895.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-02-05
Publication Date
2026-11-17
Estimated Expiration
2044-02-05

AI Technical Summary

Technical Problem

Traditional temporary slope retaining structures suffer from high construction costs, low levels of mechanization, long construction periods, high risks, environmental unfriendliness, high pollution, difficulty in dismantling, and poor flexibility, making them unsuitable for the rapid and flexible needs of foundation treatment.

Method used

Flexible mesh and irregularly shaped steel are connected to form a triangular temporary retaining wall unit, forming a continuous temporary slope retaining wall. Wedge-shaped clamping strips and elastic fasteners are used to fix and adjust the mesh and steel. Combined with the insertion depth and position flexibility of the irregularly shaped steel, a stable and adjustable temporary surcharge structure is constructed.

Benefits of technology

It enables rapid implementation, flexible adjustment, and efficient support of temporary surcharge structures, reduces construction costs and environmental risks, improves construction safety and efficiency, and adapts to the changing needs of foundation treatment.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118029355B_ABST
    Figure CN118029355B_ABST
Patent Text Reader

Abstract

This invention relates to the field of foundation treatment engineering technology, and in particular to a temporary surcharge structure, comprising a surcharge carrier and a temporary slope retaining wall for supporting it. The temporary slope retaining wall is composed of continuous temporary retaining wall units, wherein each temporary retaining wall unit includes a flexible mesh and irregularly shaped steel sections. The irregularly shaped steel sections have openings, and the flexible mesh is fastened into the openings of the irregularly shaped steel sections. The flexible mesh moves back and forth among several irregularly shaped steel sections arranged in a triangular pattern, and is fastened to each irregularly shaped steel section one by one, so that the flexible mesh forms several triangular filling spaces with the irregularly shaped steel sections. The filling spaces are filled with backfill soil. The advantages of this invention are: it enables rapid construction of the temporary surcharge structure, while improving the construction accuracy of the temporary surcharge structure, and facilitating design and implementation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This invention relates to the field of foundation treatment engineering technology, and in particular to a temporary surcharge structure. Background Technology

[0002] my country has a vast territory with numerous cities and populations distributed along the coast, rivers, and lakes. These areas are widely covered with soft clay soil strata composed of marine, lacustrine, and fluvial sediments. Soft clay soil strata are characterized by poor permeability, high compressibility, low strength, and high water content. Furthermore, they are generally buried at shallow depths. When encountering thick strata, buildings and structures on them are prone to significant settlement and differential settlement, which often lasts for a long time, significantly affecting the durability of buildings and reducing their normal service life.

[0003] Currently, the most common method for surcharge on foundations is to use loose materials such as stones and soil. Simply piling these materials on the foundation is convenient and economical, but it is prone to collapse, which can cause serious property damage and casualties. Therefore, because loose materials lack self-stability, temporary slope supports are needed at their edges to prevent them from falling.

[0004] However, traditional temporary slope supports often use reinforced concrete structures. While these structures ensure safety, they are costly to construct, have low levels of mechanization, and long construction periods. This not only consumes valuable foundation treatment time but also poses a significant risk; in the event of an emergency, it can actually delay the project. Furthermore, reinforced concrete structures are environmentally unfriendly, causing high pollution and energy consumption. After use, they are difficult to dismantle and cannot be reused, generating large amounts of construction waste that must be discarded or further processed, hindering energy conservation and emission reduction. In addition, once traditional temporary slope supports are constructed, their designs are difficult to modify, resulting in poor flexibility. Summary of the Invention

[0005] The purpose of this invention is to address the shortcomings of the prior art by providing a temporary surcharge structure. This structure uses temporary mesh panels and irregularly shaped steel sections to form triangular temporary retaining wall units. Continuous temporary retaining wall units together form a temporary slope retaining wall, enabling the rapid implementation of the temporary surcharge structure.

[0006] The objective of this invention is achieved through the following technical solutions: A temporary surcharge structure, characterized in that it includes a surcharge carrier and a temporary slope retaining wall for supporting it. The temporary slope retaining wall is composed of continuous temporary retaining wall units, wherein each temporary retaining wall unit includes a flexible mesh and irregularly shaped steel sections. The irregularly shaped steel sections have openings, and the flexible mesh is fastened into the openings of the irregularly shaped steel sections. The flexible mesh moves back and forth among several irregularly shaped steel sections arranged in a triangular pattern and is fastened to each irregularly shaped steel section one by one, so that the flexible mesh forms several triangular filling spaces in the cooperation of several irregularly shaped steel sections. The filling spaces are filled with backfill soil.

[0007] The flexible mesh is clamped in the opening of the profiled steel by a wedge-shaped clamping strip. The shape and size of the wedge-shaped clamping strip are matched with the shape and size of the opening of the profiled steel. The clamping refers to the deformation of the flange at the opening of the profiled steel when the flexible mesh is pressed into the opening of the profiled steel by the wedge-shaped clamping strip.

[0008] The irregular steel profile is provided with a spring clip fastener, which corresponds to the opening position of the irregular steel profile and contacts the flange at the opening position of the irregular steel profile to apply force to clamp the flexible mesh.

[0009] The elastic clip fastener is either a W-type elastic clip fastener or a U-type elastic clip fastener.

[0010] The W-shaped elastic clip fastener includes a W-shaped elastic clip and a bolt. The W-shaped elastic clip is fixed to the profiled steel by the bolt and its flange is pressed.

[0011] The U-shaped elastic clip fastener includes a U-shaped elastic clip and an elastic clip support. The elastic clip support is fixed on the irregular steel profile, and the U-shaped elastic clip is inserted into the elastic clip support and presses against the flange of the irregular steel profile.

[0012] The advantages of this invention are: 1) It enables the continuous use of flexible mesh without the need to process it into a fixed width according to engineering requirements, thus avoiding the difficulty of reusing mesh of specific specifications and facilitating temporary and rapid adjustments on the construction site.

[0013] 2) It simplifies the requirements for assembling retaining wall units. In general temporary slope retaining wall schemes, the retaining wall units vary in size in non-straight sections, and the retaining wall units need to be accurately positioned to assemble the corner positions of the retaining wall. The retaining wall units assembled by continuous flexible mesh are no longer restricted by the structure of the units, which facilitates the design and construction of retaining wall corners and ensures the positional accuracy of temporary slope retaining walls.

[0014] 3) The slope retaining wall units can be assembled on-site, which is highly flexible; the irregular steel sections can be constructed first, and then the retaining wall units can be built on-site according to the position of the irregular steel sections. The insertion position of the irregular steel sections into the ground can be adjusted according to the actual situation on site, avoiding the problem of mismatch between the design position and the actual position of the temporary slope retaining wall units.

[0015] 4) I-beams are conventional steel structural components. By further processing the flange shape on the basis of existing I-beams, production and processing can be facilitated and production efficiency can be improved.

[0016] 5) The wedge-shaped section clamping strip is used in conjunction with the special-shaped I-beam, making it easy to replace a damaged individual profile.

[0017] 7) The width of the wire mesh is not affected by the height limit of the retaining wall because the connection between the wire mesh and the steel profile is flexible, and the retaining wall can be assembled from wire mesh of different widths.

[0018] 8) The insertion depth of the steel profile into the stratum is not controlled by the flexible mesh and can be flexibly adjusted according to the anti-slip requirements.

[0019] 9) The temporary retaining wall unit has a triangular structure, which provides better stability; the separation between each unit is smaller, the steel nodes between the two rows of retaining wall units correspond to each other, the straight flanges of the irregular steel can fit together, and the fit between the two rows of retaining wall units is good.

[0020] 10) The connection between the flexible mesh and the irregular steel is more convenient. The length of the mesh between the irregular steel can be adjusted arbitrarily, which makes it convenient to construct the steel first and then wrap the flexible mesh, avoiding the problem of mismatch in the size of the temporary retaining wall units during construction.

[0021] 11) By setting elastic fasteners on irregular steel sections, the flexible mesh can be secured and is also easy to adjust. Attached Figure Description

[0022] Figure 1 This is a schematic diagram of the node structure of the irregular steel and flexible mesh in this invention; Figure 2 This is a schematic diagram of the vertical connection between the irregular steel profile and the flexible mesh of the present invention. Figure 3 This is a schematic diagram illustrating the field use of the present invention; Figure 4 This is a schematic diagram of the flexible mesh wedged into the irregular steel profile of the present invention; Figure 5 This is a schematic diagram of the structure of the double-row retaining wall unit arrangement according to the present invention; Figure 6 This is a schematic diagram of the arrangement and multi-layer stacking of double-row retaining wall units according to the present invention; Figure 7 This is a structural diagram of the present invention when using a W-type elastic bar fastener; Figure 8 for Figure 7 Elevation diagram; Figure 9 This is a structural diagram of the present invention when a U-shaped elastic bar fastener is used; Figure 10 for Figure 9 Elevation diagram. Detailed Implementation

[0023] The features and other related features of the present invention will be further described in detail below with reference to the accompanying drawings and embodiments, so as to facilitate understanding by those skilled in the art: like Figure 1-10 As shown in the figure, the markings 1-10 represent: flexible mesh 1, special-shaped steel 2, wedge-shaped cross-section clamping strip 3, temporary retaining wall unit 4, slack soil 5, backfill 6, W-shaped elastic bar 7, bolt 8, U-shaped elastic bar 9, and elastic bar support 10.

[0024] Example: Figure 6 As shown, the temporary surcharge structure in this embodiment is set on the foundation to be treated for preloading, thereby achieving the purpose of drainage and consolidation. Specifically, the temporary surcharge structure includes surcharge soil 5 as the surcharge carrier and temporary retaining wall unit 4. The surcharge soil 5 is arranged on the foundation to be treated as surcharge weight, while the temporary retaining wall unit 4 is set at the boundary of the foundation to be treated, and it also serves as surcharge weight. At the same time, the temporary retaining wall unit 4 supports the surcharge soil 5 on the inner side, improving the effect of preloading. Especially when using loose materials such as the surcharge soil 5 in this embodiment, the temporary retaining wall unit 4 can effectively support the surcharge soil 5.

[0025] Combination Figures 1 to 5 As shown, the temporary retaining wall unit 4 in this embodiment is composed of a flexible mesh 1 and a special-shaped steel section 2, which are fastened together by a wedge-shaped clamping strip 3. Specifically, as shown... Figure 4 As shown, the special-shaped steel section 2 has openings on both sides. The size of the wedge-shaped section clamping strip 3 is slightly smaller than the envelope space of the opening on the flange of the special-shaped steel section 2, but slightly larger than the inlet position of the opening. The flexible mesh 1 passes around the wedge-shaped section clamping strip 3. When the wedge-shaped section clamping strip 3 is pressed into the opening of the special-shaped steel section 2, the flange position at the opening of the special-shaped steel section 2 is slightly deformed. After the wedge-shaped section clamping strip 3 is pressed in, the flange of the special-shaped steel section 2 generates a clamping force on the flexible mesh 1 by means of its material. The flexible mesh 1 is then clamped between the special-shaped steel section 2 and the wedge-shaped section clamping strip 3, thereby realizing the connection between the flexible mesh 1 and the special-shaped steel section 2 and the fixation of the flexible mesh 1 itself.

[0026] Combination Figure 1 and Figure 3As shown, several irregular steel sections 2 are set in the foundation to be treated. The irregular steel sections 2 are mainly arranged in a triangular shape and inserted into the stratum of the foundation to be treated. The irregular steel sections 2 provide the temporary retaining wall unit 4 with uprightness and anti-slip capability. The specifications of the irregular steel sections 2 and the insertion depth into the stratum need to be determined according to the stress calculation. For example, irregular I-beams or irregular H-beams are used.

[0027] like Figure 1 As shown, taking the node position of a single temporary retaining wall unit 4 as an example, the flexible mesh 1 passes back and forth between the three irregular steel sections 2 and is clamped to each of the irregular steel sections 2 by the wedge-shaped cross-section clamping strips 3. At this time, the flexible mesh 1 forms a triangular filling space at the node position between the three irregular steel sections 2, that is, the node position of a single temporary retaining wall unit 4 is a triangular structure. This filling space is used for filling the soil 6, so that the temporary retaining wall unit 4 itself can be loaded and weighed on the foundation to be treated, and has a certain rigidity to effectively support the loaded soil 5.

[0028] like Figure 5 As shown in the figure, this is the structure of a double-row temporary retaining wall unit arrangement. These two rows of temporary retaining wall units are two rows of temporary retaining wall units at the same height, one in front of the other. Taking one row of temporary retaining wall units as an example, and using the direction shown in the figure as an explanation, when the upper and lower rows of irregular steel sections 2 of a row of temporary retaining wall units 4 are staggered to form multiple sets of connected triangular shapes, the flexible mesh 1 can pass back and forth between each irregular steel section 2, and the flexible mesh 1 is locked with the openings of each irregular steel section 2, so that one flexible mesh 1 can be used continuously to enclose and form the filling space of each triangle; that is to say, in Figure 5 The row of temporary retaining wall units shown includes several irregularly shaped steel sections 2 and a continuous flexible mesh 1, which allows the flexible mesh 1 to be used continuously without needing to be cut and processed to a fixed width according to engineering requirements. This expands the application range of the flexible mesh 1 and also facilitates the rapid adjustment of the temporary retaining wall units 4 on the construction site.

[0029] like Figure 6 As shown, when the surcharge soil 5 is designed to have a certain height according to the preload requirements, and exceeds the height of a single flexible mesh 1, the temporary retaining wall unit 4 can also be stacked in the height direction. Specifically, longer irregular steel sections 2 are inserted into the stratum of the foundation to be treated, with the length of each irregular steel section 2 protruding above the ground exceeding the design height of the surcharge soil 5. Then, two flexible meshes 1 are sequentially installed between each irregular steel section 2 along the height direction, thereby increasing the height of the temporary retaining wall unit 4. For example... Figure 6 As shown, a raised retaining wall consisting of two flexible mesh panels 1 is installed on one side adjacent to the slab soil 5. Furthermore, for the horizontal expansion of the temporary retaining wall unit 4, it adopts... Figure 5The method shown is intended to improve the retaining capacity of temporary slope retaining walls.

[0030] like Figure 3 As shown, when applying the temporary retaining wall unit 4 in this embodiment, since the flexible mesh 1 is continuous and is clamped and positioned by the irregular steel 2, the corner position of the temporary slope retaining wall can be achieved by designing and arranging the positions of the irregular steel 2. Figure 3 The rounded transition shown can be adjusted according to the design requirements when applied. For example, a right-angle transition can also be achieved. However, regardless of the corner transition method used, it is still necessary to ensure that the entire continuous flexible mesh 1 moves back and forth from each of the irregular steel sections 2 and encloses a triangular filling space. After the filling soil 6 is filled, the triangular structure has stronger stability and effectively improves the support effect of the temporary retaining wall unit 4.

[0031] like Figure 5 As shown, when two rows of temporary retaining wall units 4 are spliced, the irregular steel sections 2 at adjacent positions can be connected to form an integral structure to improve the integrity between the two rows of temporary retaining wall units 4. Alternatively, at the corresponding node positions of the two rows of temporary retaining wall units 4, the irregular steel sections 2 that originally had only two openings can be replaced with irregular steel sections 2 that have four openings to meet the connection requirements at that node position.

[0032] Combination Figures 7 to 10 As shown, in this embodiment, a spring clip fastener is provided between the flexible mesh 1 and the irregular steel section 2. The spring clip fastener presses the flange at the opening of the irregular steel section 2, thereby improving the tightness of the flexible mesh 1. It also facilitates adjustment of the flexible mesh 1 in some situations. In this embodiment, the spring clip fastener that can be used includes... Figure 7 and Figure 8 The W-type elastic fastener shown and Figure 9 and Figure 10 The U-shaped elastic fastener shown.

[0033] Specifically, such as Figure 7 and Figure 8 As shown, a W-shaped elastic clip 7 and a bolt 8 are installed on the irregular steel section 2. The contact point of the W-shaped elastic clip 7 mates with the irregular flange of the irregular steel section 2, and the bolt 8 is used to firmly fix the W-shaped elastic clip 7 to the outside of the irregular flange of the irregular steel section 2. At this time, by tightening the bolt 15 to press the W-shaped elastic clip 7, the force of the W-shaped elastic clip pressing the steel section flange can be adjusted, thereby controlling the deformation of the flange of the irregular steel section 2. Moreover, during installation, the compression degree of the flexible mesh 1 can be further controlled by controlling the deformation of the irregular steel section flange, so as to adapt it to the filling requirements of the backfill 6. In addition, the use of elastic clip fasteners can balance the deformation of the flanges on both sides of the web of the irregular steel section 2, preventing the flange skewing caused by the change in the thickness of the flexible mesh 1.

[0034] like Figure 9 and Figure 10 As shown, the irregular steel section 2 is equipped with a U-shaped elastic clip 9 and an elastic clip support 10. The elastic clip support 10 is used to firmly fix the U-shaped elastic clip 9 to the outside of the irregular flange of the irregular steel section 2. The U-shaped elastic clip 9 is inserted into the elastic clip support 10, and its contact point matches the irregular flange of the irregular steel section 2. Compared with the W-type elastic clip fastener, since the shape of the U-shaped elastic clip 9 is fixed, it can be inserted into the elastic clip support 10 to press the flange of the irregular steel section 2. Therefore, its elastic clip pressure is relatively fixed, and the deformation constraint of the flange of the irregular steel section 2 is also basically determined, realizing the deformation control of the flange of the irregular steel section 2. Although its on-site adjustment capability is relatively less than that of the W-type elastic clip fastener, its construction is more convenient. At the same time, during installation, when multiple U-shaped elastic clips 9 are set in the vertical height direction of the irregular steel section 2, the elastic clip pressure that each U-shaped elastic clip 9 can apply to the irregular steel section 2 is uniform, thereby ensuring that the overall pressure on the irregular steel section 2 is uniform.

[0035] In this embodiment, during construction, irregular steel sections 2 are driven into the site according to the design boundary range of the site to be treated, and the layout of each irregular steel section 2 is determined according to the design requirements; the flexible mesh 1 is clamped to each irregular steel section 2 through the wedge-shaped cross-section clamping strip 3 to form a temporary slope retaining wall; the sludge 5 is filled into the temporary slope retaining wall, and the sludge 5 is supported by the temporary slope retaining wall.

[0036] Although the above embodiments have described the concept and embodiments of the present invention in detail with reference to the accompanying drawings, those skilled in the art will recognize that various improvements and modifications can still be made to the present invention without departing from the scope of the claims, and therefore will not be elaborated here.

Claims

1. A temporary surcharge structure, characterized in that: The structure includes a support structure and a temporary slope retaining wall for supporting it. The temporary slope retaining wall is composed of continuous temporary retaining wall units, wherein each temporary retaining wall unit includes a flexible mesh and irregularly shaped steel sections. The irregularly shaped steel sections have openings, and the flexible mesh is fastened into the openings of the irregularly shaped steel sections. The flexible mesh moves back and forth among several irregularly shaped steel sections arranged in a triangular pattern and is fastened to each irregularly shaped steel section one by one, so that the flexible mesh forms several triangular filling spaces with the irregularly shaped steel sections. The filling spaces are filled with backfill soil.

2. The temporary surcharge structure according to claim 1, characterized in that: The flexible mesh is clamped in the opening of the profiled steel by a wedge-shaped clamping strip. The shape and size of the wedge-shaped clamping strip are matched with the shape and size of the opening of the profiled steel. The clamping refers to the deformation of the flange at the opening of the profiled steel when the flexible mesh is pressed into the opening of the profiled steel by the wedge-shaped clamping strip.

3. A temporary surcharge structure according to claim 1, characterized in that: The irregular steel profile is provided with a spring clip fastener, which corresponds to the opening position of the irregular steel profile and contacts the flange at the opening position of the irregular steel profile to apply force to clamp the flexible mesh.

4. A temporary surcharge structure according to claim 3, characterized in that: The elastic clip fastener is either a W-type elastic clip fastener or a U-type elastic clip fastener.

5. A temporary surcharge structure according to claim 4, characterized in that: The W-shaped elastic clip fastener includes a W-shaped elastic clip and a bolt. The W-shaped elastic clip is fixed to the profiled steel by the bolt and its flange is pressed.

6. A temporary surcharge structure according to claim 4, characterized in that: The U-shaped elastic clip fastener includes a U-shaped elastic clip and an elastic clip support. The elastic clip support is fixed on the irregular steel profile, and the U-shaped elastic clip is inserted into the elastic clip support and presses against the flange of the irregular steel profile.

Citation Information

Patent Citations

  • Flexible self-bearing retaining wall

    CN104120735A

  • Retaining wall structure with punching holed steel-plate box units and its construction method

    KR1020080046351A