A network hanging plugging method for drilling construction
Through the network suspension plugging method, the combination of leakage plugging agents with different particle sizes and high viscoelastic leakage plugging agents is used to form a viscoelastic gel and three-dimensional network, which solves the problem that traditional leakage plugging methods are difficult to achieve complete plugging, and improves the efficiency of plugging. Leakage success rate and adhesion of leakage plugging agent.
Patent Information
- Application Number
- CN202410594048.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-14
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-05-14
AI Technical Summary
It is difficult to achieve complete sealing with traditional drilling plugging methods. Chemical gel plugging has low adhesion and insufficient pressure-bearing capacity, making the success rate of plugging difficult to control.
The network suspension plugging method is adopted, by formulating a combination of leak plugging agents with different particle sizes and high viscoelastic leak plugging agents to form a viscoelastic gel and three-dimensional network. The pressure difference is used to enter the leak layer channel, fill the gaps and adhere closely to the formation. , to achieve the 'soft + hard bridge' effect.
It improves the success rate of leakage plugging, ensures that the leakage plugging agent adheres closely to the formation, forms a stable structure, and effectively controls leakage.
Smart Images

Figure CN118187750B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of drilling construction, in particular to a network hanging type leak plugging method for drilling construction. Background Art
[0002] The traditional plugging technology of bridging plugging is to select inert materials of different shapes and sizes for "hard bridging" plugging according to the properties of different leaking layers. However, its non-deformability causes micropores between its particles, making it difficult to achieve complete plugging. Chemical gel plugging, due to its certain deformability, can be used in conjunction with conventional plugging to fill the micropores formed by the bridge of conventional plugging agents. Compared with bridging plugging, the plugging effect is better, but due to its low adhesion to the formation and weak pressure bearing capacity, the plugging success rate is difficult to control.
[0003] The purpose of the invention is to provide a network suspension type plugging method to improve the success rate of drilling plugging. Summary of the invention
[0004] The object of the present invention is to provide a network suspension plugging method for drilling construction, so as to solve the problem of improving the success rate of drilling plugging proposed in the above background technology.
[0005] To achieve the above object, the present invention provides the following technical solutions:
[0006] A network hanging plugging method for drilling construction comprises the following steps:
[0007] Step 1: preparing mud through a preparation device, adjusting the proportion of the mud and adjusting its performance;
[0008] Step 2: preparing a network hanging plugging agent;
[0009] Step 3: Mix the plugging slurry with the mud through a stirring device and discharge the bubbles;
[0010] Step 4: Injecting the mixed slurry into the leakage zone through drilling equipment;
[0011] Step 5: Wait for the slurry to solidify;
[0012] Step 6: Check the plugging effect to ensure that the leakage has been effectively controlled; based on the inspection results, determine whether to make further adjustments or additional plugging operations.
[0013] As a further solution of the present invention: in step 3, after the mud and the plugging slurry are mixed in a specified ratio, it should be ensured that they are stirred evenly until there are no particles or bubbles. Uneven mixing may lead to uneven plugging effect and affect the plugging quality.
[0014] As a further scheme of the present invention: in step 2, preparing a network hanging plugging agent comprises the following steps: flushing clean water into a stirring device, adding 10-20 parts of large-particle gel plugging agent into the stirring device according to the added amount and stirring for 1-2 hours, adding 10-20 parts of medium-particle gel plugging agent, stirring for 10-20 minutes, adding 10-20 parts of small-particle gel plugging agent and stirring for 10-20 minutes, adding 20-30 parts of network plugging agent and 10-20 parts of high-viscosity elastic plugging agent and stirring for 10-20 minutes, adding 20-30 parts of inert plugging agent, stirring for 10-20 minutes, and preparing a network hanging plugging agent.
[0015] As a further solution of the present invention: in step four, after the plugging slurry is injected, it circulates to the leaking layer section, enters the leaking layer channel under the action of pressure difference and starts plugging, the viscoelastic gel formed by the high-viscoelastic plugging agent is suspended on the three-dimensional network formed by the network plugging agent, inert plugging agents of different particle sizes fill the network space, and gel plugging agents of various particle sizes further fill the remaining gaps to achieve "soft + hard bridging", and after standing for a certain period of time, the plugging agent and the formation are tightly attached to each other, and a structure is formed to achieve plugging.
[0016] As a further solution of the present invention: during the use of mud, the performance of the mud should be checked regularly, and new mud should be added in time as needed to replenish the mud lost due to circulation, filtration and evaporation; this can avoid dehydration or reduction of viscosity of the mud and ensure that the mud is always kept in the best working condition.
[0017] As a further solution of the present invention: During the injection process of step three, it is necessary to accurately control the injection speed, pressure and amount to ensure that the plugging slurry can be evenly distributed in the leakage channel.
[0018] As a further solution of the present invention: in step three, the stirring device separates the bubbles generated during the stirring process from the slurry through the vibration of the container side wall vibration component, and then the vacuum exhaust component exhausts air from the top surface of the container to generate vacuum negative pressure and discharge the air.
[0019] As a further solution of the present invention: by driving each vibration component to move up and down, uniform vibration of the stirring device as a whole is achieved, and sufficient discharge of bubbles is achieved.
[0020] As a further solution of the present invention: the stirring device comprises a stirring tank, the top of the stirring tank is snap-connected with a top cover, the edge of the top cover is fixedly connected with a sealing gasket, the middle of the top cover is fixedly connected with an exhaust pipe, and one end of the exhaust pipe is fixedly connected to the air inlet end of an external exhaust pump;
[0021] A stirring motor is fixedly installed at the bottom of the stirring tank, a transmission rod is fixedly connected to the output end of the stirring motor, a plurality of stirring rods are fixedly connected to the outer wall of the transmission rod, one end of each of the stirring rods is fixedly connected to a scraping rod, and each of the scraping rods is arranged in close contact with the inner wall of the stirring tank;
[0022] The outer wall of the mixing tank is fixedly connected with a plurality of vibration components, the vibration components include a sliding seat, one side of the sliding seat is slidably connected with a vibration plate, one side of the vibration plate is fixedly installed with a vibration motor, the output end of the vibration motor is fixedly connected with an eccentric wheel, and the outer side cover of the vibration component is provided with an outer cover plate;
[0023] A linear motor is fixedly installed in the middle of the outer wall of the stirring tank, and a push ring is fixedly connected to the output end of the linear motor. A connecting plate is fixedly connected to one side of several vibration plates, and several connecting plates are fixedly connected to the push ring.
[0024] As a further solution of the present invention: a mixing assembly is arranged in the preparation chamber, and the mixing assembly realizes the preparation of mud and mixed materials by driving the mixing frame to move back and forth.
[0025] As a further solution of the present invention: in step 1, the preparation device includes a preparation tank, which is divided into a preparation chamber and a pump chamber by a partition plate, and the input end of the slurry pump in the pump chamber is connected to the partition plate by a connecting pipe, and the port position of the connecting pipe is changed by sliding the partition plate to adjust the slurry extraction position;
[0026] The preparation device comprises a preparation tank, a partition plate is fixedly connected to one side of the inner wall of the preparation tank, the partition plate divides the inner cavity of the preparation tank into a preparation cavity and a pump chamber, a slurry pump is fixedly installed inside the pump chamber, an input end of the slurry pump is fixedly connected to a connecting pipe, one end of the connecting pipe is fixedly connected to the middle of the partition plate;
[0027] Mixing components are fixedly installed on both sides of the inner wall of the preparation cavity. The mixing components include a push guide rail. A mixing rack is slidably installed on the inner wall of the push guide rail. A plurality of mixing rods are fixedly connected to the inner wall of the mixing rack.
[0028] Compared with the prior art, the present invention has the following beneficial effects: the present invention prepares a new network suspension plugging agent by combining plugging agents of different particle sizes with network plugging agents and high-viscoelastic plugging agents, so that after the new plugging slurry is injected, it enters the leaking layer channel under the action of pressure difference to start plugging, and the viscoelastic gel formed by the high-viscoelastic plugging agent is suspended on the three-dimensional network formed by the network plugging agent, and inert plugging agents of different particle sizes fill the network space, and gel plugging agents of various particle sizes further fill the remaining gaps to achieve "soft + hard bridging", and after standing for a certain period of time and waiting for a period of time for the materials to fully solidify or react, the plugging agent can be tightly attached to the formation to form a stable structure, thereby achieving plugging, and the plugging success rate can be effectively improved;
[0029] The present invention mixes the mud and the plugging slurry in a specified ratio through a stirring device, and then uses the vibration of a container side wall vibration component to separate the bubbles generated in the stirring process from the slurry, and then uses a vacuum pumping component to evacuate the top surface of the container to generate a vacuum negative pressure to expel the air, so that the plugging agent obtained by stirring is free of particles or bubbles, thereby effectively improving the quality of the plugging agent and the plugging condensation effect. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a flowchart of the method of the present invention;
[0031] Figure 2 It is a three-dimensional diagram of the stirring device and the preparation device of the present invention;
[0032] Figure 3 is a cross-sectional view of the stirring device of the present invention;
[0033] Figure 4 It is a cross-sectional view of the vibration component of the present invention.
[0034] In the figure: 1. preparation device; 101. preparation tank; 102. partition plate; 103. connecting pipe; 104. mixing rack; 105. mixing rod; 2. stirring device; 201. stirring tank; 202. top cover; 203. exhaust pipe; 204. stirring motor; 205. stirring rod; 206. scraping rod; 207. discharge pipe; 210. vibration assembly; 211. outer cover plate; 212. vibration plate; 213. eccentric wheel; 214. connecting plate; 215. push ring. DETAILED DESCRIPTION
[0035] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Embodiment 1
[0036] Take Well A as an example, the diameter of the second opening wellbore is 215.9mm, and the loss of return occurs at 1580m, and the lithology is conglomerate. In order to prevent Well A from continuing to lose, the inventor of the present application can adopt a network suspension plugging method to plug the leakage.
[0037] See also Figure 1 , a network hanging plugging method for drilling construction, comprising the following steps:
[0038] Step 1: Prepare mud by the preparation device 1, adjust the proportion of the mud and adjust its performance; the mud performance adjustment operation can adopt existing technical means in the prior art, such as: swelling the mud; adjusting the pH of the mud; adding lubricant to improve the lubrication performance of the mud cake surface, reduce the sticking resistance of the mud in the well, thereby improving the anti-sticking ability of the mud; using a suitable fluid loss reducer can reduce the solid phase particles in the mud from entering the formation, while reducing the permeability of the mud cake and improving the quality of the mud cake;
[0039] During the use of mud, the performance of the mud should be checked regularly, and new mud should be added in time as needed to replenish the mud lost due to circulation, filtration and evaporation. This can avoid the dehydration of the mud or the reduction of viscosity, and ensure that the mud is always in the best working condition;
[0040] Step 2: prepare a network hanging plugging agent; the preparation of the network hanging plugging agent includes the following steps: pour clean water into the stirring device 2, add 20 parts of large-particle gel plugging agent into the stirring device according to the added amount and stir for 1.5 hours, add 10 parts of medium-particle gel plugging agent and 10 parts of small-particle gel plugging agent and stir for 20 minutes, add 20 parts of network plugging agent and stir for 20 minutes and 15 parts of high-viscosity elastic plugging agent and stir for 20 minutes, add 25 parts of inert plugging agent and stir for 20 minutes to prepare a network hanging plugging agent; the above-mentioned large-particle gel plugging agent, large-particle gel plugging agent The leak plugging agent, medium-sized gel plugging agent, small-sized gel plugging agent, network plugging agent and inert plugging agent are all implemented by existing technical means; when configuring, gel plugging agents of different particle sizes can be added together, gel plugging agents need time to form gel, and must be added first, the viscosity of high-viscoelastic plugging agent is too large, and adding high-viscoelastic plugging agent first will inhibit the speed and quality of gel formation of gel plugging agent; the order of adding network gel plugging agent and high-viscoelastic plugging agent can be reversed; inert plugging agent must be added last, because the inert plugging agent can be suspended in the plugging slurry only after the plugging slurry forms structural force;
[0041] Step 3: After mixing the mud and the plugging slurry in the specified proportion through the stirring device 2, ensure that the mixing is uniform until there are no particles or bubbles. Uneven mixing may lead to uneven plugging effect, affect the plugging quality, and be injected into the leakage layer through the drilling equipment;
[0042] Step 4: Inject the mixed slurry into the leakage zone through drilling equipment; during the injection process, the injection speed, pressure and amount need to be accurately controlled to ensure that the plugging slurry can be evenly distributed in the leakage channel;
[0043] Step 5: After the plugging slurry is injected, it circulates to the leaking layer section and enters the leaking layer channel under the action of pressure difference to start plugging. The viscoelastic gel formed by the high-viscoelastic plugging agent is suspended on the three-dimensional network formed by the network plugging agent. Inert plugging agents of different particle sizes fill the network space. The morphologically variable gel plugging agent further fills the remaining gaps to achieve "soft + hard bridging". After standing for a certain period of time, wait for a period of time for the material to fully solidify or react, so that the plugging agent and the formation are tightly attached together to form a stable structure to achieve plugging;
[0044] Step 6: Check the plugging effect to ensure that the leakage has been effectively controlled; based on the inspection results, determine whether further adjustments or additional plugging operations are necessary.
[0045] In step 1, refer to Figure 2 The preparation device 1 includes a preparation tank 101, a partition plate 102 is fixedly connected to one side of the inner wall of the preparation tank 101, and the partition plate 102 divides the inner cavity of the preparation tank 101 into a preparation cavity and a pump chamber. A slurry pump is fixedly installed inside the pump chamber, and a connecting pipe 103 is fixedly connected to the input end of the slurry pump, and one end of the connecting pipe 103 is fixedly connected to the middle of the partition plate 102; the port position of the connecting pipe 103 is changed by sliding the partition plate 102 to adjust the mud extraction position, so that the mud of a suitable depth in the preparation cavity can be selected and taken according to needs;
[0046] Mixing components are fixedly installed on both sides of the inner wall of the preparation chamber. The mixing components include a push guide rail, and a mixing rack 104 is slidably installed on the inner wall of the push guide rail. A plurality of mixing rods 105 are fixedly connected to the inner wall of the mixing rack 104. The mixing rack 104 is driven to move back and forth to achieve the preparation of mud and mixed materials. In the specific implementation, a diverter rod can be engaged with the mixing rod 105, and the movement of the mixing rack 104 and the mixing rod drives the movement of the plurality of diverter rods to improve the mixing and stirring effect of the material mud (the diverter rod is not shown in the figure).
[0047] See also Figure 3 The stirring device 2 includes a stirring tank 201, the top of the stirring tank 201 is snap-connected with a top cover 202, the edge of the top cover 202 is fixedly connected with a sealing gasket, the middle of the top cover 202 is fixedly connected with an exhaust pipe 203, and one end of the exhaust pipe 203 is fixedly connected to the air inlet end of an external exhaust pump;
[0048] A stirring motor 204 is fixedly installed at the bottom of the stirring tank 201, and a transmission rod is fixedly connected to the output end of the stirring motor 204, and a plurality of stirring rods 205 are fixedly connected to the outer wall of the transmission rod, and one end of the plurality of stirring rods 205 is fixedly connected to a scraping rod 206, and the plurality of scraping rods 206 are all arranged in close contact with the inner wall of the stirring tank 201;
[0049] The outer wall of the mixing tank 201 is fixedly connected to a plurality of vibration components 210, see Figure 4 The vibration assembly 210 includes a sliding seat, one side of the sliding seat is slidably connected with a vibration plate 212, one side of the vibration plate 212 is fixedly installed with a vibration motor, the output end of the vibration motor is fixedly connected with an eccentric wheel 213, and the outer cover of the vibration assembly 210 is provided with an outer cover plate 211; the stirring device 2 separates the bubbles generated during the stirring process from the slurry through the vibration of the vibration assembly 210 on the side wall of the container, and then the vacuum exhaust assembly exhausts the air on the top surface of the container to generate a vacuum negative pressure and discharge the air; a discharge pipe 207 for discharging the slurry is provided on one side of the outer wall of the stirring tube;
[0050] A linear motor is fixedly installed in the middle of the outer wall of the stirring tank 201, and a push ring 215 is fixedly connected to the output end of the linear motor. A connecting plate 214 is fixedly connected to one side of several vibration plates 212, and several connecting plates 214 are fixedly connected to the push ring 215. The linear motor drives each vibration component 210 to move up and down, thereby achieving uniform vibration of the stirring device 2 as a whole and achieving sufficient discharge of bubbles.
[0051] When the preparation device 1 and the stirring device 2 of the present invention are used, the mud raw material is put into the preparation chamber of the preparation device, the mixing assembly is started, and the mixing frame 104 is driven by the push rail to reciprocate to stir the raw material. During this period, the swelling agent, the fluid loss agent and other solvents are added as needed to adjust the mud properties, and the mud is ready for use after the adjustment and preparation are completed;
[0052] Prepare a network hanging plugging agent. The preparation method is as described in step 2. During the preparation process, start the vibration component 210, that is, the vibration motor drives the eccentric cam to rotate, generate vibration, and then drive the side wall of the stirring tank 201 to vibrate, so that the air inside the slurry is discharged. At the same time, the rotation of the stirring motor 204 drives the stirring rod 205 to rotate to stir the slurry. At the same time, the rotation of the stirring rod 205 drives the scraping rod 206 to rotate, and the bubbles attached to the inner wall of the stirring tank 201 are scraped and removed, and then the external air pump is started to extract and discharge through the exhaust pipe 203. Embodiment 2
[0053] Taking Well B as an example, the diameter of the third wellbore is 215.9 mm. Loss due to loss of return occurred at 2810 m, and the lithology is limestone.
[0054] The difference between this embodiment and the first embodiment is that, according to different drilling leakage states, different preparation methods of network suspension plugging agent configurations are provided; that is, in step two, first, clean water is flushed into the stirring device 2, 10 parts of large-particle gel plugging agents are added to the stirring device according to the added amount and stirred for 1.5 hours, 10 parts of medium-particle gel plugging agents and 10 parts of small-particle gel plugging agents are added and stirred for 20 minutes, 25 parts of high-viscosity elastic plugging agents are added and stirred for 20 minutes, 25 parts of network plugging agents are added and stirred for 20 minutes, 20 parts of inert plugging agents are added and stirred for 20 minutes, and a network suspension plugging agent is prepared.
[0055] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any form. Although the present invention has been disclosed as a preferred embodiment as above, it is not used to limit the present invention. Any technical personnel in this field can make some changes or modify the technical contents disclosed above into equivalent embodiments without departing from the scope of the technical solution of the present invention. However, any simple modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention still fall within the scope of the technical solution of the present invention.
Claims
1. A network suspension plugging method for drilling construction, characterized in that: The following steps are involved: Step 1: preparing mud by a preparation device (1); Step 2: preparing a network hanging plugging agent; Step 3: Mixing the network suspension plugging agent with the mud by means of the stirring device (2) to obtain a slurry, and expelling air bubbles; Step 4: Injecting the mixed slurry into the leakage zone through drilling equipment; Step 5: Wait for the slurry to solidify; Step 6: Check the plugging effect; In step 2, preparing a network suspension plugging agent comprises the following steps: pouring clean water into a stirring device (2), adding 10-20 parts of a large-particle gel plugging agent according to the added amount into the stirring device (2) and stirring for 1-2 hours, adding 10-20 parts of a medium-particle gel plugging agent and stirring for 10-20 minutes, adding 10-20 parts of a small-particle gel plugging agent and stirring for 10-20 minutes, adding 20-30 parts of a network plugging agent and 10-20 parts of a high-viscosity plugging agent and stirring for 10-20 minutes, adding 20-30 parts of an inert plugging agent and stirring for 10-20 minutes, and preparing a network suspension plugging agent; In step five, after the plugging slurry is injected, it circulates to the leaking layer section and enters the leaking layer channel under the action of pressure difference to start plugging. The viscoelastic gel formed by the high-viscoelastic plugging agent is suspended on the three-dimensional network formed by the network plugging agent. The inert plugging agent fills the network space. The gel plugging agents of various particle sizes further fill the remaining gaps. The plugging agent is allowed to stand to adhere to the formation to achieve plugging. In step three, the stirring device (2) causes bubbles generated during the stirring process to separate from the slurry through the vibration of the container side wall vibration component (210), and then the vacuum exhaust component exhausts air from the top surface of the container to generate a vacuum negative pressure and discharge the air.
2. A network hanging plugging method for drilling construction according to claim 1, characterized in that: During the use of mud, check the performance of the mud regularly and add new mud to avoid dehydration or loss of viscosity of the mud.
3. A network hanging plugging method for drilling construction according to claim 1, characterized in that: During the injection process of step 4, the injection speed, pressure and injection volume are controlled to ensure that the plugging slurry can be evenly distributed in the leakage channel.
4. A network hanging plugging method for drilling construction according to claim 1, characterized in that: By driving each vibration component (210) to move up and down, uniform vibration of the entire stirring device (2) is achieved, thereby achieving full discharge of bubbles.
5. A network hanging plugging method for drilling construction according to claim 1, characterized in that: In step one, the preparation device (1) comprises a preparation tank (101), the preparation tank (101) is divided into a preparation chamber and a pump chamber by a partition plate (102), the input end of the slurry pump in the pump chamber is connected to the partition plate (102) via a connecting pipe (103), and the port position of the connecting pipe (103) is changed by sliding the partition plate (102) to adjust the slurry extraction position.
6. A network hanging plugging method for drilling construction according to claim 5, characterized in that: A mixing component is arranged in the preparation chamber, and the mixing component realizes the preparation of mud and mixed material by driving the mixing frame (104) to move back and forth.
Citation Information
Patent Citations
Method for high-temperature well plugging by using core-shell type high-temperature-resistant plugging agent
CN111255411A
Composition, preparation method and application of high-temperature and high-pressure expandable plugging agent
CN114479789A