Method and system for detecting and processing karst caves at the bottom of prefabricated piles

Through three-dimensional laser scanning equipment, the cave and silt area are identified, and the amount and pressure of clean water injection is accurately controlled, which solves the problems of waste and low efficiency of water resources in the construction of prefabricated piles, and achieves efficient dredging and stability guarantees.

CN118259302BActive Publication Date: 2024-11-19广东永和建设集团有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410406643.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-07
Publication Date
2024-11-19
Estimated Expiration
2044-04-07

AI Technical Summary

Technical Problem

During the construction of prefabricated piles, it is difficult to accurately control the clean water when injected into the cave, resulting in waste of water resources and increased sludge and reducing work efficiency.

Method used

Three-dimensional laser scanning equipment is used to obtain laser point cloud data, identify sludge and cave areas, determine the water injection volume and pressure based on characteristic information, and accurately control the injection of clean water to avoid excessive water injection.

Benefits of technology

It has achieved water resource conservation and improved dredging efficiency, ensured the stability of the cave, and reduced the amount of silt and workload.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118259302B_ABST
    Figure CN118259302B_ABST
Patent Text Reader

Abstract

The present application provides a method and system for detecting and processing karst caves at the bottom of prefabricated piles, wherein the method steps include: obtaining first laser point cloud data, wherein the first laser point cloud data is laser point cloud data obtained by scanning the karst cave using a three-dimensional laser scanning device; identifying a first silt area and a karst cave area according to the first laser point cloud data; determining corresponding first water injection information according to characteristic information of the first silt area and the karst cave area, wherein the first water injection information includes a first water injection amount that can cover all silt in the karst cave; sending the first water injection information to a water injection device, so that the water injection device performs quantitative injection according to the first water injection information to realize karst cave desilting control, which not only saves water resources, but also facilitates the rapid suction of all silt in the karst cave. The present application provides a method and system for detecting and processing karst caves at the bottom of prefabricated piles, which can be widely used in the field of building construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application belongs to the technical field of detection and processing of building construction, and in particular, relates to a method and system for detecting and processing karst caves at the bottom of prefabricated piles. Background Art

[0002] In pile foundation engineering, precast piles are one of the commonly used construction structures. The full name is precast cement soil piles. They are used to reinforce the bearing capacity of land or buildings. They are suitable for foundations such as silt, silty soil, clay, silt, sand and artificial fill. Sometimes, during the construction of precast piles, there will be caves in the area where the pile bottom is located. Since the caves at the bottom of the pile have a great influence on the bearing capacity and stability of the pile, it is very necessary and important to strengthen the caves.

[0003] The process of strengthening the cave generally includes the following steps: injecting clean water into the bottom of the cave to extract the silt in the cave, then filling the bottom of the cave with materials, and then injecting grout on the filling material to consolidate it. However, in the process of dredging, it is found that since the current amount of clean water injection is basically controlled based on the experience of the staff, excessive clean water injection often occurs, which not only wastes water, but also easily washes the mud and sand around the cave into the bottom of the cave, thereby increasing the amount of silt, increasing the workload of dredging, and reducing work efficiency. Summary of the invention

[0004] In view of this, an embodiment of the present application provides a method and system for detecting and processing karst caves at the bottom of prefabricated piles, so as to accurately control the amount of clean water injected, thereby reducing water resource waste and improving work efficiency while ensuring the dredging effect.

[0005] A first aspect of an embodiment of the present application provides a method for detecting and processing a karst cave at the bottom of a prefabricated pile, the method comprising the following steps:

[0006] Acquire first laser point cloud data, wherein the first laser point cloud data is laser point cloud data obtained by scanning the cave using a three-dimensional laser scanning device;

[0007] Identifying a first silt area and a cave area according to the first laser point cloud data;

[0008] Determine corresponding first water injection information according to the characteristic information of the first sludge area and the cave area, wherein the first water injection information includes a first water injection volume;

[0009] The first water injection information is sent to a water injection device, so that the water injection device performs a water injection control operation according to the first water injection information.

[0010] Furthermore, the characteristic information includes spatial characteristics, and the step of determining the corresponding first water injection information according to the characteristic information of the first sludge area and the cave area includes:

[0011] Acquire the highest position point of the first sludge area according to the spatial characteristics of the first sludge area;

[0012] Determining a first spatial volume between a horizontal plane obtained when the first water level is at the highest point and the silt in the first silt area according to the spatial characteristics of the first silt area and the karst cave area;

[0013] When the first spatial volume is greater than or equal to a first volume threshold, the water volume corresponding to the first spatial volume is used as the first water injection volume.

[0014] Furthermore, the step of obtaining the highest position point of the first sludge area according to the spatial characteristics of the first sludge area includes:

[0015] Determine the highest coordinate point of the outline of the first sludge area according to the spatial characteristics of the first sludge area;

[0016] The highest position point is obtained by moving the highest coordinate point of the contour upward by a first distance.

[0017] Furthermore, the first water injection information further includes a first water injection pressure, and the corresponding first water injection information is determined according to the characteristic information of the first sludge area and the cave area, which may also include:

[0018] obtaining a first humidity of a first sludge area;

[0019] A corresponding first water injection pressure is determined according to the first humidity, wherein the first humidity and the first water injection pressure are in inverse proportion.

[0020] Furthermore, the step of determining the corresponding first water injection pressure according to the first humidity is specifically as follows:

[0021] Obtain the stability of the cave;

[0022] A corresponding first water injection pressure is determined according to the first humidity and the stability of the cave, wherein the stability of the cave is in direct proportion to the first water injection pressure.

[0023] Furthermore, the step of obtaining the first humidity of the first sludge area includes:

[0024] dividing the first silt area into a plurality of silt sub-areas;

[0025] Performing humidity detection on a plurality of sludge sub-areas, thereby obtaining a second humidity of the plurality of sludge sub-areas;

[0026] The average humidity is obtained by calculating the average value of the plurality of second humidities;

[0027] The average humidity value is taken as the first humidity.

[0028] Furthermore, the method further comprises the step of confirming the stability of the cave, and the step of confirming the stability of the cave comprises:

[0029] Selecting a first sub-land area from a first preset area, wherein the first preset area refers to an area centered on the location of the cave, and the first sub-land area refers to a sub-land area with a water content lower than a first threshold;

[0030] The stability of the cave is determined according to the water content of the first sub-soil area and the distance between the first sub-soil area and the cave.

[0031] Furthermore, the first water injection information further includes the residence time after the water injection is completed, and the corresponding first water injection information is determined according to the characteristic information of the first sludge area and the cave area, which also includes:

[0032] obtaining a second humidity of the first sludge area;

[0033] The residence time after the water injection is completed is determined according to the second humidity, wherein the second humidity and the residence time after the water injection are in inverse proportion.

[0034] Furthermore, the method comprises the following steps:

[0035] Acquire second laser point cloud data, wherein the second laser point cloud data is laser point cloud data obtained by scanning the cave using a three-dimensional laser scanning device;

[0036] When it is identified according to the second laser point cloud data that there is no silt area in the cave, reinforcement information is sent to the material feeding and grouting device, so that the material feeding and grouting device performs the material feeding and grouting control operation according to the reinforcement information.

[0037] A second aspect of the embodiment of the present application provides a detection and processing system for karst caves at the bottom of piles, including:

[0038] A detection device, used to detect a plurality of target objects in a construction site, the detection device at least comprising a three-dimensional laser scanning device;

[0039] A control device, comprising at least one processor, for executing the steps of the above-mentioned method for detecting and processing karst cavities at the bottom of prefabricated piles;

[0040] A water injection device, used to perform water injection control operations;

[0041] A material discharging and grouting device, used for performing material discharging and grouting control operations;

[0042] The control device is respectively connected to the detection device, the water injection device and the material feeding and grouting device for communication.

[0043] Compared with the prior art, the beneficial effect of the embodiment of the present application is as follows: the present application obtains corresponding laser point cloud data after scanning and detecting the cave using a three-dimensional laser scanning device, and then obtains a first silt area and a cave area after identifying and processing the first laser point cloud data. Combining the characteristic information of the two areas, the water injection volume that can cover all the silt in the cave can be determined, so that the water injection device can perform quantitative injection according to the determined water injection volume, which can not only facilitate the rapid suction of all the silt in the cave, but also will not cause excessive injection of clean water, thereby avoiding waste of water resources. BRIEF DESCRIPTION OF THE DRAWINGS

[0044] In order to more clearly illustrate the technical solutions in the embodiments of the present application, the drawings required for use in the embodiments or related technical descriptions will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying any creative work.

[0045] Figure 1 A schematic flow chart of a first embodiment of a method for detecting and processing karst caves at the bottom of a prefabricated pile provided by the present application is shown;

[0046] Figure 2 A schematic flow chart of a second embodiment of a method for detecting and processing karst caves at the bottom of a prefabricated pile provided by the present application is shown;

[0047] Figure 3 The schematic diagram of the construction of water injection and dredging of the cave is shown;

[0048] Figure 4 A schematic diagram of the system structure of a detection and processing system for karst caves at the bottom of a prefabricated pile provided in the present application is shown. DETAILED DESCRIPTION

[0049] In order to make the purpose, technical solution and advantages of the present application clearer, the technical solution of the present application will be clearly and completely described through the implementation method with reference to the drawings in the embodiments of the present application. Obviously, the described embodiments are part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present application.

[0050] In the process of strengthening and reinforcing the cave, the staff will inject clean water into the cave, and then use the high suction force of the pump to suck out the silt while sucking water, so as to achieve the cleaning of the cave. At present, since this step is basically a manual operation, the staff will basically choose to directly fill the cave with clean water and then suck it for convenience. However, this not only causes a waste of water resources, but also excessive water injection easily washes the mud and sand around the cave into the bottom of the cave, thereby increasing the amount of silt, increasing the workload of dredging, and reducing work efficiency. In addition, excessive water injection will cause a large impact force on the wall of the cave, which is easy to make the cave unstable and increase the potential risk of collapse. In view of this, the present application proposes a method that can accurately control the amount of clean water injection, reduce water resource waste and improve work efficiency while ensuring the dredging effect.

[0051] Reference Figure 1 A method for detecting and processing karst caves at the bottom of a prefabricated pile comprises the following steps:

[0052] S1. Acquire first laser point cloud data, wherein the first laser point cloud data is laser point cloud data obtained by scanning a cave using a three-dimensional laser scanning device.

[0053] Specifically, the above-mentioned 3D laser scanning equipment utilizes the principle of laser ranging. It can quickly reconstruct the 3D model of the object being measured and various drawing data such as lines, surfaces and bodies by scanning and collecting the 3D coordinates, reflection intensity and texture information of a large number of densely packed points on the surface of the object being measured. Therefore, the laser point cloud data obtained after scanning the cave with the 3D laser scanning equipment can construct a 3D model of the cave. That is to say, the laser point cloud data obtained by the scan can be used to determine the spatial characteristics corresponding to the cave, such as characteristic information including contour shape, contour area, contour coordinates, contour surface texture, contour surface density, etc.

[0054] S2. Identify a first silt area and a cave area according to the first laser point cloud data.

[0055] Specifically, in this embodiment, in order to accurately calculate the required water injection volume, it is necessary to identify the spatial area belonging to the silt part and the spatial area belonging to the cave. In the study, it was found that the silt part can be identified and distinguished by the attribute characteristics of the reflection intensity and point cloud density corresponding to the point cloud. That is to say, for step S2, it can be specifically as follows: according to a number of silt attribute characteristics, the first silt area is determined from the first laser point cloud data, and then the karst cave area is determined according to the three-dimensional model constructed based on the first laser point cloud data and the determined first silt area.

[0056] Furthermore, the above step S2 may include the following steps:

[0057] S201. According to the first reflection intensity threshold, a threshold judgment is performed on the reflection intensity contained in each first laser point cloud data, so as to obtain third laser point cloud data, wherein the third laser point cloud data is laser point cloud data having a reflection intensity less than the first reflection intensity threshold; then, a corresponding first sludge sub-area is constructed according to the third laser point cloud data.

[0058] S202, according to the first density threshold, threshold judgment is performed on the point cloud density of the first laser point cloud data, so as to obtain fourth laser point cloud data, wherein the fourth laser point cloud data is laser point cloud data with a point cloud density greater than the first density threshold; and then a corresponding second sludge sub-area is constructed according to the fourth laser point cloud data. The point cloud density refers to the number of point clouds contained in the first preset space.

[0059] Specifically, the following results were found: ① Since the wall of the cave is basically made of hard rock, it has a strong ability to reflect laser signals. However, since the surface of the silt is relatively delicate and soft, its ability to reflect laser signals is relatively weak. In view of this, the corresponding first reflection intensity threshold (this threshold is an empirical value) can be obtained by testing and analyzing the historical point cloud data. When the reflection intensity of the scanned point cloud data is less than the first reflection intensity threshold, the point cloud can be judged as a point cloud belonging to the silt part. Then, the closed area of ​​these point clouds is calculated, so as to construct the corresponding first silt sub-area. ② Similarly, since the wall of the cave is basically made of hard rock, the The point cloud corresponding to the area will be relatively sparse, that is, the density of the point cloud corresponding to the area will be relatively small, and because the surface of the silt is relatively delicate, soft and sticky, the point cloud in this area will be relatively dense, that is, the density of the point cloud corresponding to the area will be relatively large. In view of this, the corresponding first density threshold (this threshold is an empirical value) can be obtained after testing and analyzing the historical point cloud data. When the density of the point cloud actually scanned is greater than the first density threshold, the point cloud contained in the first preset space corresponding to the point cloud density can be identified as a point cloud belonging to the silt part, and then the closed area of ​​the point clouds in these preset spaces is calculated, so that the corresponding second silt sub-area can be constructed.

[0060] S203, merging the first sludge sub-region and the second sludge sub-region to obtain a first sludge region.

[0061] S204: Determine the karst cave area based on the boundary between the three-dimensional model constructed based on the first laser point cloud data and the first silt area.

[0062] Specifically, in this embodiment, the contour area except the silt area in the karst cave three-dimensional model constructed based on the first laser point cloud data is classified as the karst cave area.

[0063] It can be seen that the above method is used to realize the identification and division between the silt area and the cave area in the three-dimensional cave model with high accuracy.

[0064] S3. Determine corresponding first water injection information according to the characteristic information of the first silt area and the cave area, wherein the first water injection information includes a first water injection volume, which mainly refers to the water injection volume that can cover all the silt in the cave.

[0065] Furthermore, the feature information includes spatial features, and step S3 may specifically include:

[0066] S301. Acquire the highest point of the first sludge area according to the spatial characteristics of the first sludge area.

[0067] Specifically, for the highest position point of the first silt area, it can be the coordinate point at the highest position in the first silt area. However, if the coordinate point at the highest position in the first silt area is directly used as the highest position point, then after water injection according to the water injection amount calculated in the subsequent steps, the horizontal plane just covers the highest point of the first silt area. In view of the fact that there are generally errors between theoretical calculations and actual conditions, in order to further ensure that the horizontal plane after water injection can completely cover the silt in the first silt area, the coordinate point at the highest position in the first silt area can be moved upward by a small distance, and a distance value is added to the z coordinate value of the coordinate point to obtain the final required highest position point.

[0068] Therefore, if Figure 3 As shown, the step S301 may further include the following steps:

[0069] S3011. Determine the highest coordinate point of the contour of the first sludge area according to the spatial characteristics of the first sludge area. The highest coordinate point of the contour of the first sludge area is Figure 3 The point a shown in the figure, and the spatial feature includes the point cloud coordinate data corresponding to the outline of the area, so the coordinate data of the point a can be obtained according to the data in the constructed three-dimensional model.

[0070] S3012, moving the highest coordinate point a of the contour upward by a first distance to obtain the highest position point.

[0071] Specifically, the first distance is generally selected within the range of 10 cm to 30 cm. Of course, the value of the distance is not limited here and can be preset according to actual needs.

[0072] S302. Determine, based on the spatial characteristics of the first silt area and the cave area, a first spatial volume V1 between a horizontal plane h1 obtained when the first water level is at the highest point and the silt in the first silt area.

[0073] Specifically, if Figure 3 As shown, a horizontal plane h1 is set with the coordinates of the highest position point. Since this horizontal plane h1 represents the horizontal plane obtained when a certain amount of clean water is injected into the cave, a space is formed by the wall of the cave, the surface of the silt area and the horizontal plane. After the known cave contour coordinates, silt contour coordinates and horizontal plane contour coordinates (according to the intersection of the plane constructed with the highest position point and the surface between the cave contour, the intersection coordinate points can be obtained, and the contour coordinates of the horizontal plane can be confirmed based on these coordinate points), the first spatial volume V1 between the horizontal plane h1 and the silt in the first silt area can be calculated. Since the calculation method of the first spatial volume V1 is only obtained by using commonly used mathematical methods, it will not be elaborated here.

[0074] S303 . When the first spatial volume V1 is greater than or equal to a first volume threshold, use the water volume corresponding to the first spatial volume V1 as a first water injection volume.

[0075] Specifically, in the process of using clean water to inject and thus suck out the sludge, it was found that the amount of clean water required varies depending on the thickness and volume of the first sludge area. For example, the larger the volume, the greater the amount of water required to be injected, and under the same volume, the greater the thickness, the greater the amount of water required to be injected. In other words, for the first volume threshold, it is the volume value corresponding to the benchmark amount of clean water required corresponding to different thicknesses and volumes.

[0076] There are two ways to obtain the first volume threshold:

[0077] 1. Through the previous multiple tests, the historical benchmark water injection volume corresponding to different historical silt thicknesses and historical volumes is obtained, and then the historical benchmark water injection volume is converted into a corresponding volume value for data storage, so that the data of this database can be retrieved later to query the historical silt thickness and volume size closest to the actual detected silt thickness and volume size (that is, the silt volume V2 contained in the first silt area), so as to obtain the matching historical volume value according to the mapping relationship between the queried historical silt thickness and historical volume size and the historical volume value, and then use it as the first volume threshold;

[0078] 2. Through multiple tests in the early stage, the historical benchmark water injection volume corresponding to different historical silt thicknesses and historical volumes is obtained, and then the different historical silt thicknesses and historical volumes are used as training input data, and the volume value corresponding to the historical benchmark water injection volume is used as training output data to train the deep learning model. In this way, in the future, only the actual detected silt thickness and volume size (i.e., the silt volume V2 contained in the first silt area) need to be input into the trained deep learning model for data processing, and the volume value corresponding to the corresponding benchmark water injection volume can be obtained, and then it is used as the first volume threshold.

[0079] In actual construction scenarios, it is found that there are many combinations of silt thickness and volume size. Therefore, in order to ensure accuracy and processing efficiency, the above method 2 will be used to obtain the first volume threshold.

[0080] As for the volume of the first silt area, it can be calculated by the contour coordinates of the first silt area and the corresponding thickness. Further, the contour of the first silt area can be divided into several sub-area contours, and then the vertical thickness of the sub-area can be detected to calculate the volume of several sub-areas, and finally the final volume of the first silt area (i.e. the silt volume V2 contained in the first silt area) can be determined according to the volume of several sub-areas. Further, for the thickness of the first silt area, it can be detected in the following two ways: the first is to use an ultrasonic detection device to detect the thickness. The detection signal of ultrasonic waves penetrating silt and penetrating other media (such as the rock layer below the silt) is different, so the detected ultrasonic signal is used to determine the first silt area and the complete shape of the first silt area; the second is to use a core drilling machine and a vibration sensor and a displacement sensor arranged thereon, and analyze the displacement data obtained by the displacement sensor and the spectrum change of the vibration signal during the downward movement of the core drilling machine, so as to determine the thickness of the first silt area. In order to save costs and facilitate the operation and use of the staff, the above-mentioned first method is preferably implemented.

[0081] S304: When the first spatial volume V1 is smaller than a first volume threshold, use the water volume corresponding to the first volume threshold as a first water injection volume.

[0082] It can be seen that through the above-mentioned water injection volume confirmation steps, the water injection volume can be accurately controlled to not only cover the silt in the cave, but also ensure that the water injection volume meets the silt suction requirements.

[0083] In some embodiments, for silt, when its humidity is higher, the silt will have higher fluidity. At this time, if the water injection pressure is too high, the silt will be easily splashed onto the side wall and / or upper wall of the cave, which is not only not conducive to cleaning the silt in the cave, but also the impact of the silt on the cave may reduce the stability and safety of the cave; on the contrary, when its humidity is lower, the silt is not easy to be dispersed. At this time, the water injection pressure is high, and the water injection completion time can be increased while ensuring that the silt does not splash (because the higher the water injection pressure, the greater the water injection flow rate). It can be seen that there is an inverse proportional relationship between the water injection pressure and the humidity of the silt.

[0084] It can be seen that the first water injection information may also include a first water injection pressure, and the step S3 may also include:

[0085] S305: Obtain the first humidity of the first sludge area.

[0086] Specifically, the first humidity can be directly detected using a commonly used humidity sensor. However, if the humidity sensor is used to detect the humidity at any position in the first sludge area, and the humidity value obtained is used as the final humidity value required, this will be relatively local, resulting in insufficient accuracy when confirming the water injection pressure later. Therefore, in order to improve the detection accuracy of the first humidity, multiple positions in the first sludge area will be detected, and then the average value will be taken as the final required humidity value.

[0087] Therefore, in some embodiments, the step S305 may specifically include:

[0088] S3051. Divide the first sludge area into a plurality of sludge sub-areas.

[0089] S3052. Detect humidity of the plurality of sludge sub-areas to obtain second humidity of the plurality of sludge sub-areas.

[0090] S3053. Calculate the average value of the plurality of second humidities to obtain an average humidity value.

[0091] S3054. Use the average humidity as the first humidity.

[0092] S306. Determine a corresponding first water injection pressure according to the first humidity, wherein the first humidity and the first water injection pressure are in inverse proportion.

[0093] Specifically, the confirmation formula of the first water injection pressure P1 may be: P1=K1*(W0 / W1)*P0, wherein W0 is the reference humidity, P0 is the reference water injection pressure corresponding to W0, W1 is the first humidity detected in the first sludge interval, and K1 is an empirical constant.

[0094] In some embodiments, water injection will cause a certain impact on the cave, and the greater the water injection pressure, the greater the impact on the cave. That is to say, the greater the stability of the cave, the greater the water injection pressure can be. In this way, under the premise of ensuring that the stability of the cave is still within a controllable range during injection, increasing the water injection pressure (equivalent to increasing the water injection speed) can improve the water injection efficiency. Therefore, for the step S306, it also includes the following steps:

[0095] S3060. Confirm the stability of the cave.

[0096] Specifically, the step S3060 may include:

[0097] S30601. Select a first sub-land area from a first preset area, wherein the first preset area refers to an area centered on a karst cave, and the first sub-land area refers to a sub-land area having a water content lower than a first threshold.

[0098] S30602. Determine the stability of the cave according to the water content of the first sub-soil area and the distance between the first sub-soil area and the cave.

[0099] Specifically, if the water content of the rock and soil near the cave is too low, it means that the rock and soil near the cave is dry and cracked, that is, it is easy to cause the rock and soil in the area to break when it is subjected to strong vibration. It can be seen that the more sub-land areas with low water content there are around the cave, and the closer the sub-land area is to the cave, the lower the stability of the cave will be. This means that the impact pressure generated by water injection that the cave can withstand should be lower, so as to ensure that the cave will not be subjected to strong vibration due to excessive water injection pressure, resulting in rock and soil fragmentation in the area. In view of this, the stability of the cave can be determined by the water content of the first sub-land area and the distance between the first sub-land area and the cave, and the smaller the stability, the smaller the water injection pressure that the cave can withstand.

[0100] As for step S30602, it can be specifically as follows: the water content of a plurality of first sub-soil regions and the distance between the first sub-soil regions and the karst caves constitute an input data matrix [C i ,D i ], C i represents the water content of the ith sub-land area, D i It represents the distance between the i-th sub-land area and the cave, i=1,2,3...n, n is the total number of the first sub-land area; then it is input into the corresponding deep learning training model, and the corresponding stability coefficient of the cave is output. Among them, for the deep learning training model, it can be obtained by corresponding training using the corresponding historical data, which will not be elaborated here.

[0101] S3061. Obtain the stability of the cave, that is, obtain the stability coefficient obtained in step S30602.

[0102] S3062. Determine a corresponding first water injection pressure according to the first humidity and the stability of the cave, wherein the stability of the cave is directly proportional to the first water injection pressure.

[0103] Specifically, in this embodiment, the confirmation formula of the first water injection pressure can be further optimized as: P1 = K2*(W0 / W1)*(S1 / S0)*P0. Wherein, W0 is the reference humidity, SO is the reference stability coefficient, P0 is the reference water injection pressure corresponding to the state of W0 and SO, W1 is the first humidity detected in the first silt interval, S1 is the stability coefficient of the cave obtained, and K2 is an empirical constant. K2 and K1 in this embodiment can be the same or different, and the empirical value obtained by actual testing shall prevail.

[0104] In some embodiments, the first water injection information further includes the residence time after the water injection is completed, and the step S3 further includes:

[0105] S307, obtaining the second humidity of the first sludge area. The second humidity mentioned here is the same as the first humidity, and the method of obtaining the second humidity is the same, so it will not be elaborated here.

[0106] S308. Determine the residence time after the water injection is completed according to the second humidity, wherein the second humidity and the residence time after the water injection are in inverse proportion.

[0107] Specifically, in order to avoid the problem of caking due to insufficient water content of the sludge, which makes it difficult to be pumped out later, a certain amount of water can be injected into the cave, and then the sludge can be soaked for a period of time before being pumped out. The water content of the sludge can be directly expressed by its humidity, and the lower the humidity, the longer the soaking time, that is, the residence time, should be. Therefore, the second humidity is inversely proportional to the residence time after the water injection is completed.

[0108] Furthermore, the formula for determining the residence time T1 after water injection is completed can be: T1 = K3*(M0 / M1)*T0, where M0 is the reference humidity, T0 is the reference residence time corresponding to MO, M1 is the second humidity of the first sludge area, and K3 is an empirical constant.

[0109] Alternatively, a historical database may be constructed using a mapping relationship between historical humidity values ​​and historical residence times, so that when actual humidity data is collected, the historical database may be used to search for a residence time that matches the humidity data. In other words, the above step S308 may also be specifically as follows: searching for a corresponding residence time from the historical database based on the acquired second humidity.

[0110] S4. Send the first water injection information to a water injection device, so that the water injection device performs a water injection control operation according to the first water injection information.

[0111] Specifically, according to the above steps, the first water injection information includes the water injection volume, water injection pressure and residence time, and the water injection device can perform corresponding control of the water injection operation according to these three information.

[0112] In some embodiments, Figure 2 As shown, the method of the present application scheme may also include the following steps:

[0113] S5. Acquire second laser point cloud data, wherein the second laser point cloud data is laser point cloud data obtained by scanning the cave using a three-dimensional laser scanning device.

[0114] Specifically, after the injection and dredging steps, the cave can be scanned and modeled again using a three-dimensional laser scanning device to confirm whether there are still silt areas. If so, the above steps S2-S4 can be repeated. Otherwise, grouting can be carried out to reinforce the cave.

[0115] S6. When it is identified according to the second laser point cloud data that there is no silt area in the cave, reinforcement information is sent to the material feeding and grouting device, so that the material feeding and grouting device performs the material feeding and grouting control operation according to the reinforcement information.

[0116] Specifically, the material unloading and grouting control operation is as follows: the initial filling of the filler is carried out using filling aggregates, wherein the filling aggregates are packed in carbon fiber mesh bags, and the pipes are lifted and shaken while unloading to facilitate the diffusion and filling of the filler. When the height of the filler pile reaches a preset height, the filling is suspended; then, grouting is injected onto the filler pile with a grouting pump, and the pipes are lifted while grouting to facilitate the diffusion and filling of the slurry; then, the above-mentioned material unloading and grouting steps are repeated until the filler pile is against the upper wall of the cave.

[0117] In some embodiments, the slurry used for grouting is composed of sludge and a curing agent. The sludge here can be realized by using the sludge sucked out in the above step S4, that is, the sludge sucked out in step S4 is reused, which can not only reduce the purchase of the material for the dumping and landfill, but also reduce the transportation cost of the discarded sludge.

[0118] In some embodiments, based on the above description, it can be known that the volume of the silt can be calculated, that is, the amount of silt in the cave is known, and therefore, this data can be sent to the backend server center, so that when the backend allocates resources, the amount of silt material required for the construction site can be confirmed. That is, the method of the present application also includes the steps of: sending the volume data of the first silt area to the backend server.

[0119] In summary, it can be seen that by using the method of the present application, water injection control operations can be performed accurately, which can not only save water resources, but also improve treatment efficiency while ensuring dredging effects and cave safety.

[0120] Reference Figure 4 The present application also provides a detection and processing system for karst caves at the bottom of prefabricated piles, comprising:

[0121] A detection device, used to detect a plurality of target objects in a construction site, the detection device at least comprising a three-dimensional laser scanning device;

[0122] A control device, comprising at least one processor, configured to execute the steps of implementing the above method embodiment;

[0123] A water injection device, used to perform water injection control operations;

[0124] A material discharging and grouting device, used for performing material discharging and grouting control operations;

[0125] The control device is respectively connected to the detection device, the water injection device and the material feeding and grouting device for communication.

[0126] The number of the processors can be at least 2, and at least any step in the above method embodiment can be executed, and at least two processors can be connected to each other by communication, not limited to wired or wireless communication connection, and the at least one processor can be connected to the central server of the construction contractor by remote wireless communication to realize remote wireless transmission of data. In addition, the processor can be a central processing unit (CPU), or other general-purpose processors, digital signal processors (DSP), application-specific integrated circuits (ASIC), field-programmable gate arrays (FPGA) or other programmable logic devices, discrete gates or transistor logic devices, discrete hardware components, etc. The general-purpose processor can be a microprocessor or the processor can also be any conventional processor, etc.

[0127] In addition, the present application also provides a computer-readable storage medium, which stores a computer program, and the computer program is executed by a processor to implement the steps of the above method embodiment.

[0128] It should be understood that the size of the serial numbers of the steps in the above embodiments does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiments of the present application.

[0129] If the integrated unit is implemented in the form of a software functional unit and sold or used as an independent product, it can be stored in a computer-readable storage medium. Based on this understanding, the present application implements all or part of the processes in the above-mentioned embodiment method, which can be completed by instructing the relevant hardware through a computer program. The computer program can be stored in a computer-readable storage medium, and the computer program can implement the steps of the above-mentioned various method embodiments when executed by the processor. Among them, the computer program includes computer program code, and the computer program code can be in source code form, object code form, executable file or some intermediate form. The computer-readable medium may at least include: any entity or device that can carry the computer program code to the camera / terminal device, recording medium, computer memory, read-only memory (ROM), random access memory (RAM), electric carrier signal, telecommunication signal and software distribution medium. For example, a USB flash drive, a mobile hard disk, a magnetic disk or an optical disk. In some jurisdictions, according to legislation and patent practice, computer-readable media cannot be electric carrier signals and telecommunication signals.

[0130] The embodiments described above are only used to illustrate the technical solutions of the present application, rather than to limit them. Although the present application has been described in detail with reference to the aforementioned embodiments, a person skilled in the art should understand that the technical solutions described in the aforementioned embodiments may still be modified, or some of the technical features may be replaced by equivalents. Such modifications or replacements do not deviate the essence of the corresponding technical solutions from the spirit and scope of the technical solutions of the embodiments of the present application, and should all be included in the protection scope of the present application.

Claims

1. A method for detecting and treating karst caves at the bottom of prefabricated piles, characterized in that: The method comprises the following steps: Acquire first laser point cloud data, wherein the first laser point cloud data is laser point cloud data obtained by scanning the cave using a three-dimensional laser scanning device; Identifying a first silt area and a cave area according to the first laser point cloud data; Determine corresponding first water injection information according to the characteristic information of the first sludge area and the cave area, wherein the first water injection information includes a first water injection volume; sending the first water injection information to a water injection device, so that the water injection device performs a water injection control operation according to the first water injection information; The characteristic information includes spatial characteristics, and the step of determining the corresponding first water injection information according to the characteristic information of the first sludge area and the cave area includes: Acquire the highest position point of the first sludge area according to the spatial characteristics of the first sludge area; Determining a first spatial volume between a horizontal plane obtained when the first water level is at the highest point and the silt in the first silt area according to the spatial characteristics of the first silt area and the karst cave area; When the first spatial volume is greater than or equal to a first volume threshold, the water volume corresponding to the first spatial volume is used as the first water injection volume.

2. The method according to claim 1, characterized in that The step of obtaining the highest position point of the first sludge area according to the spatial characteristics of the first sludge area comprises: Determine the highest coordinate point of the outline of the first sludge area according to the spatial characteristics of the first sludge area; The highest position point is obtained by moving the highest coordinate point of the contour upward by a first distance.

3. The method according to claim 1, characterized in that The first water injection information further includes a first water injection pressure, and the first water injection information corresponding to the first water injection information is determined according to the characteristic information of the first sludge area and the cave area, and further includes: obtaining a first humidity of a first sludge area; A corresponding first water injection pressure is determined according to the first humidity, wherein the first humidity and the first water injection pressure are in inverse proportion.

4. The method according to claim 3, characterized in that The step of determining the corresponding first water injection pressure according to the first humidity is specifically as follows: Obtain the stability of the cave; A corresponding first water injection pressure is determined according to the first humidity and the stability of the cave, wherein the stability of the cave is in direct proportion to the first water injection pressure.

5. The method according to claim 3 or 4, characterized in that The step of obtaining the first humidity of the first sludge area comprises: dividing the first silt area into a plurality of silt sub-areas; Performing humidity detection on a plurality of sludge sub-areas, thereby obtaining a second humidity of the plurality of sludge sub-areas; The average humidity is obtained by calculating the average value of the plurality of second humidities; The average humidity value is taken as the first humidity.

6. The method according to claim 4, characterized in that The method further comprises the step of confirming the stability of the cave, wherein the step of confirming the stability of the cave comprises: Selecting a first sub-land area from a first preset area, wherein the first preset area refers to an area centered on the location of the cave, and the first sub-land area refers to a sub-land area with a water content lower than a first threshold; The stability of the cave is determined according to the water content of the first sub-soil area and the distance between the first sub-soil area and the cave.

7. The method according to claim 1, characterized in that The first water injection information further includes the residence time after the water injection is completed. The first water injection information corresponding to the first water injection information is determined according to the characteristic information of the first sludge area and the cave area, and further includes: obtaining a second humidity of the first sludge area; The residence time after the water injection is completed is determined according to the second humidity, wherein the second humidity and the residence time after the water injection are in inverse proportion.

8. The method according to claim 1, characterized in that The method comprises the following steps: Acquire second laser point cloud data, wherein the second laser point cloud data is laser point cloud data obtained by scanning the cave using a three-dimensional laser scanning device; When it is identified according to the second laser point cloud data that there is no silt area in the cave, reinforcement information is sent to the material feeding and grouting device, so that the material feeding and grouting device performs the material feeding and grouting control operation according to the reinforcement information.

9. The detection and processing system of the karst cave at the bottom of the prefabricated pile is characterized by: include: A detection device, used to detect a plurality of target objects in a construction site, the detection device at least comprising a three-dimensional laser scanning device; A control device, comprising at least one processor, for executing the steps of implementing the method according to any one of claims 1 to 8; A water injection device, used to perform water injection control operations; A material discharging and grouting device, used for performing material discharging and grouting control operations; The control device is respectively connected to the detection device, the water injection device and the material feeding and grouting device for communication.