A safe feeding device based on primidone reduction reaction
By using screens and scrapers to disperse zinc powder in the primidone reduction reaction equipment, and combining hot water circulation and drying measures with electric actuators, the problem of reduced reaction efficiency and increased by-products caused by agglomeration of zinc powder was solved. Enables more efficient responses and simplified processing.
Patent Information
- Application Number
- CN202410820100.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-24
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-06-24
AI Technical Summary
The agglomeration of zinc powder in a humid environment reduces the efficiency of the reduction reaction, produces more by-products, and increases the difficulty and cost of subsequent processing.
Design a safe feeding equipment that uses a combination of screen and scraper to mechanically break up the agglomerated zinc powder and dry it through hot water circulation to prevent the zinc powder from re-agglomerating. It combines an electric actuator and a limit column to realize the screen Shake up and down to ensure the zinc powder is fully dry and evenly discharged.
It effectively avoids zinc powder agglomeration affecting the reduction reaction efficiency, reduces the production of by-products, simplifies subsequent processing, and improves the efficiency and safety of primidone preparation.
Smart Images

Figure CN118371192B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of primidone production, and in particular to a safe feeding device based on primidone reduction reaction. Background Art
[0002] Existing Chinese patent: (CN212092171U) A safety control device for feeding solid zinc powder of primidone, by setting a material temporary storage chamber between the zinc powder conveying pipe and the reduction reactor, and then controlling the opening and closing of the first discharge valve and the second discharge valve, and designing the material temporary storage chamber into a diamond shape, to achieve control of the unpowered feeding of zinc powder, and then control the feeding speed of zinc powder to avoid the generation of a large amount of hydrogen, but it is necessary to control multiple switches in sequence to control the input of zinc powder, which limits the efficiency of primidone preparation, and when the zinc powder is in a humid environment, the moisture makes the zinc powder particles adhere to form lumps, and the lumpy zinc powder causes the total surface area of the zinc powder to decrease, thereby reducing the chance of contact with the reactants. Zinc powder, as a catalyst, is bound to reduce the efficiency of the reduction reaction, and the agglomerated zinc powder will also cause local overheating in the reactor, or the reduction reaction is insufficient, or more by-products are produced. At this time, additional steps are required to remove it, which increases the difficulty and cost of subsequent processing. Summary of the invention
[0003] The technical problems of the present invention are:
[0004] In order to overcome the disadvantages that zinc powder agglomeration affects the efficiency of the reduction reaction, and also causes local overheating, resulting in an insufficient reduction reaction and more by-products, the present invention provides a safe feeding device based on the primidone reduction reaction.
[0005] The technical implementation scheme adopted by the present invention is:
[0006] A safe feeding device based on the reduction reaction of primidone comprises a reduction reaction kettle and a feeding pipe; the reduction reaction kettle is connected to the feeding pipe; the feeding pipe is equipped with a solenoid valve; it also comprises a material temporary storage chamber, a feeding pipe, a main shaft, a central column, a scraper and a screen; the feeding pipe is connected to the material temporary storage chamber, and a temperature sensor is arranged in the material temporary storage chamber; the material temporary storage chamber is connected to the feeding pipe; the material temporary storage chamber is rotatably connected to the main shaft; the main shaft is fixedly connected to the central column; a plurality of scrapers are fixedly connected to the central column; a screen is connected to the lower part of the material temporary storage chamber, and the pores of the screen are much larger than the particle size of zinc powder; the screen is in contact with the scraper to mechanically break up the agglomerated zinc powder; the screen is connected to the central column.
[0007] More preferably, the upper portion of the central column is configured to be conical to reduce the accumulation of powder on the central column.
[0008] More preferably, the scraper and the plane of the screen are inclined at an angle, and the scraper rotates counterclockwise when viewed from top to bottom.
[0009] More preferably, it also includes a support rod I, a reflux chamber, a water inlet chamber, a water pipe I, a confluence chamber and a branch pipe; the material temporary storage chamber is connected to a plurality of support rods I; all the support rods I are commonly connected to the reflux chamber; the reflux chamber is fixedly connected to the water inlet chamber; the water inlet chamber is rotatably connected to the main shaft; the water inlet chamber is connected to the water pipe I; the main shaft is a hollow rod, and a plurality of water inlets are opened on the upper part of the main shaft; a diversion chamber is provided in the water inlet chamber; the diversion chamber is connected to all the water inlets; the support rod I is a hollow rod; an annular chamber is provided in the reflux chamber; the annular chamber is connected to all the support rods I; the reflux chamber is fixedly connected to the confluence chamber; a collecting chamber is opened in the confluence chamber; the annular chamber is connected to the collecting chamber through a connecting hole; a plurality of branch pipes are connected to the lower part of the collecting chamber; all the branch pipes are connected to the main shaft; the central column is fixedly connected to all the branch pipes; the lower part of the branch pipe extends into the feeding pipe.
[0010] More preferably, it also includes a partition; a plurality of water outlets are opened at the lower part of the main shaft; the main shaft is connected to a plurality of partitions; a cooling chamber is opened in each partition; each cooling chamber is connected to a water outlet; each partition is connected to a branch pipe.
[0011] More preferably, it also includes a water pipe II; a heat preservation chamber is opened in the material temporary storage room; the heat preservation chamber is connected with all the hollow support rods I; the heat preservation chamber is connected with a water pipe II, and a solenoid valve is arranged in the water pipe II.
[0012] More preferably, it also includes an electric actuator, a connecting plate, a support rod II, an annular plate and a spring rod; a central column is installed with multiple electric actuators; each telescopic part of the electric actuator is fixedly connected to a connecting plate; each connecting plate is slidably connected to an adjacent branch pipe; each connecting plate is fixedly connected to a support rod II; all the support rods II are commonly fixedly connected to an annular plate; the annular plate is slidably connected to the central column; the annular plate is located below the screen; the screen is slidably connected to the central column; the screen is fixedly connected to multiple spring rods; all the telescopic parts of the spring rods are fixedly connected to the material temporary storage chamber.
[0013] More preferably, it also includes a limiting column; a plurality of limiting columns are fixedly connected to the screen; each scraper is fixedly connected to a contact block on the side away from the center column; the contact block is arranged at an angle and is parallel to the scraper; each contact block is in contact with a limiting column; the limiting column is a deformable metal rod, and the elastic coefficient of the limiting column is greater than the elastic coefficient of the spring rod.
[0014] More preferably, a spherical contact head is provided on the upper portion of the limiting column.
[0015] More preferably, the number of the limiting posts is in multiple relation with the number of the scrapers, so that each contact block can contact with one limiting post at the same time.
[0016] Compared with the prior art, the present invention has the following advantages: 1. The present invention can intercept the agglomerated zinc powder by setting a screen, and then use an inclined scraper to drive the agglomerated zinc powder to scrape on the screen, so that the agglomerate structure of the zinc powder is gradually destroyed, and the zinc powder is broken up, effectively preventing the agglomerated zinc powder from entering the reactor and affecting the efficiency of the reduction reaction, reducing the generation of by-products, and reducing the difficulty of subsequent treatment of the by-products.
[0017] 2. The zinc powder in the temporary material storage room and the feeding pipe is heated through a branch pipe with hot water circulating, and the main shaft with hot water circulating heats the screen to fully dry the zinc powder to prevent the zinc powder from re-agglomerating under the adhesion of water after being dispersed.
[0018] 3. Move the limit column through the contact block. After the elastic limit column is restored, the limit column vibrates, and the screen is also driven to vibrate, so that the zinc powder adhering to the screen can be shaken off during the zinc powder breaking process. Then, in conjunction with the spring rod, the contact block presses the limit column down and drives the screen downward at the same time. After the contact block passes over the limit column, the spring rod is restored, driving the screen upward, thereby realizing the up and down reciprocating motion of the screen, shaking off the zinc powder accumulated on the screen, and avoiding the screen being blocked. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a schematic diagram of the three-dimensional structure of the safe feeding equipment based on the primidone reduction reaction of the present invention;
[0020] Figure 2 It is a cross-sectional view of the safe feeding equipment based on the primidone reduction reaction of the present invention;
[0021] Figure 3 This is a schematic diagram of the internal structure of the material temporary storage chamber of the present invention;
[0022] Figure 4 A schematic diagram of the location of the water inlet of the present invention;
[0023] Figure 5 It is a schematic diagram of the installation position of the screen of the present invention;
[0024] Figure 6 A schematic diagram of the location of the water outlet of the present invention;
[0025] Figure 7 It is a schematic diagram of the installation position of the electric actuator of the present invention;
[0026] Figure 8 It is a schematic diagram of the installation position of the limit column of the present invention;
[0027] Fig. 9 It is a schematic diagram of the matching state of the limit column and the contact block of the present invention.
[0028] Among them, the above-mentioned drawings include the following drawing marks: 1-reduction reactor, 2-feeding pipe, 3-material temporary storage chamber, 4-feeding pipe, 5-main shaft, 6-center column, 7-scraper, 8-screen, 101-support rod I, 102-reflux chamber, 103-water inlet chamber, 104-water pipe I, 105-convergence chamber, 106-branch pipe, 3001-insulation chamber, 5001-water inlet, 10201-annular chamber, 10301-diversion chamber, 10501-collecting chamber, 107-partition, 108-water pipe II, 5002-water outlet, 10701-cooling chamber, 201-electric actuator, 202-connecting plate, 203-support rod II, 204-annular plate, 205-spring rod, 206-limiting column, 7001-contact block. DETAILED DESCRIPTION
[0029] First of all, it should be pointed out that in the different described embodiments, the same parts are provided with the same reference numerals or the same component names, wherein the disclosure contained in the entire description can be transferred to the same parts with the same reference numerals or the same component names. Selected positional descriptions in the description, such as top, bottom, lateral, etc., also refer to the directly described and shown figures and are transferred to the new positions in the case of a change in position.
[0030] Embodiment 1
[0031] A safe feeding device based on primidone reduction reaction, according to Figure 1-5 As shown, it includes a reduction reactor 1 and a feeding pipe 2; the upper part of the reduction reactor 1 is connected to the feeding pipe 2; the lower part of the feeding pipe 2 is equipped with a solenoid valve;
[0032] It also includes a material storage chamber 3, a feeding pipe 4, a main shaft 5, a central column 6, a scraper 7 and a screen 8; the upper part of the feeding pipe 2 is connected to the material storage chamber 3, and a temperature sensor is arranged in the material storage chamber 3; the upper part of the material storage chamber 3 is connected to the feeding pipe 4; the middle part of the material storage chamber 3 is rotatably connected to the main shaft 5; the lower part of the main shaft 5 is fixedly connected to the central column 6; three annular array-type scrapers 7 are welded to the central column 6; the lower part of the material storage chamber 3 is connected to the screen 8, and the pores of the screen 8 are much larger than the particle size of the zinc powder; the screen 8 is in contact with the scraper 7 and is used to mechanically break up the agglomerated zinc powder; the screen 8 is connected to the central column 6.
[0033] The upper portion of the central column 6 is configured to be conical, so as to reduce the accumulation of powder on the central column 6 .
[0034] The scraper 7 and the screen 8 have an inclined angle of 45°, and the scraper 7 rotates counterclockwise when viewed from top to bottom.
[0035] It also includes a support rod Ⅰ101, a reflux chamber 102, a water inlet chamber 103, a water pipe Ⅰ104, a confluence chamber 105 and a branch pipe 106; three annular array support rods Ⅰ101 are connected to the upper part of the material temporary storage chamber 3; all the support rods Ⅰ101 are commonly connected to the reflux chamber 102; the upper part of the reflux chamber 102 is fixedly connected to the water inlet chamber 103; the water inlet chamber 103 is rotatably connected to the main shaft 5; the water inlet chamber 103 is connected to the water pipe Ⅰ104; the main shaft 5 is a hollow rod, and a plurality of water inlets 5001 are opened on the upper part of the main shaft 5; a diversion chamber 10301 is provided in the water inlet chamber 103; the diversion chamber 10301 is connected to all the inlets The water inlet 5001 is connected; the support rod I101 is a hollow rod; an annular cavity 10201 is provided in the reflux chamber 102; the annular cavity 10201 is connected with all the support rods I101; a confluence chamber 105 is fixedly connected to the lower part of the reflux chamber 102; a collecting chamber 10501 is provided in the confluence chamber 105; the annular cavity 10201 is connected with the collecting chamber 10501 through a connecting hole; at least six annular array-type branch pipes 106 are connected to the lower part of the collecting chamber 10501; all the branch pipes 106 are connected with the main shaft 5; the central column 6 is fixedly connected to all the branch pipes 106; the lower part of the branch pipe 106 extends into the feeding pipe 2.
[0036] See the attached figure, Figures 1 to 5 The working process shown is:
[0037] Connect the solenoid valve in the feeding pipe 2 to the power supply;
[0038] Connect the feed pipe 4 to the zinc powder delivery pipe;
[0039] Connect the spindle 5 to the external motor;
[0040] Connect water pipe Ⅰ104 to the water circulation equipment;
[0041] First, before adding zinc powder to the feed pipe 4, the solenoid valve in the feed pipe 2 is controlled to be closed, and then zinc powder is added to the material temporary storage chamber 3 through the feed pipe 4. The zinc powder falls on the screen 8. The pores of the screen 8 are much larger than the particle size of the zinc powder, and the zinc powder has strong fluidity. The zinc powder can continue to fall through the screen 8 and fall on the solenoid valve of the feed pipe 2, and then wait for program control. When the reaction in the reduction reactor 1 needs to use zinc powder as a catalyst, the solenoid valve of the feed pipe 2 is controlled to open, and the zinc powder can enter the reduction reactor 1 to participate in the reaction. The time interval of opening and closing the solenoid valve of the feed pipe 2 is controlled, so that the zinc powder is added to the reduction reactor 1 in small amounts and multiple times, so that the chemical reaction in the reduction reactor 1 is carried out smoothly and efficiently, and a large amount of zinc powder is effectively avoided. After the zinc powder reacts with the reduction reactor 1, it also reacts with other chemical agents, so that a large amount of by-products, such as hydrogen, are generated in the reduction reactor 1, which has a large safety hazard and is prone to safety accidents, and the utilization rate of raw materials is not high.
[0042] It should be noted that zinc powder is used as a catalyst for the reduction reaction of primidone. The state of zinc powder will affect the rate of the reduction reaction. For example, if zinc powder agglomerates, its surface area will be reduced, reducing the chance of contact between zinc powder and reactants, thereby reducing the reaction efficiency. In addition, agglomerated zinc powder will also cause the reduction reaction to produce more by-products due to local overproduction or incomplete reaction. These by-products require additional steps to remove, increasing the difficulty and cost of subsequent treatment.
[0043] At this time, a screen 8 is set in the material temporary storage chamber 3 to intercept the agglomerated zinc powder, and the external motor is controlled to drive the main shaft 5 to rotate, and the main shaft 5 drives the central column 6 and the corresponding parts thereon to rotate together, and the scraper 7 scrapes on the screen 8. If there is agglomerated zinc powder on the screen 8, the scraper 7 will drive the agglomerated zinc powder to slide on the screen 8. Through the friction between the zinc powder and the screen 8, the agglomerated structure of the zinc powder is gradually destroyed, and the ground zinc powder falls through the pores of the screen 8. The scraper 7 can be arranged in an inclined shape so that the scraper 7 and the screen 8 form an angle of 45°, and the scraper 7 rotates counterclockwise when viewed from the top, so that the scraper 7 at the angle can not only drive the agglomerated zinc powder to slide on the screen 8, but also exert an oblique downward force on the agglomerated zinc powder, so that the agglomerated zinc powder squeezes the screen 8, which is convenient for the agglomerated zinc powder to be ground more quickly, and effectively prevents the agglomerated zinc powder from blocking the screen 8 and affecting the normal feeding of the zinc powder;
[0044] In the above steps, since the agglomerated zinc powder needs to be scraped to slide on the screen 8, if the zinc powder is agglomerated only due to moisture, when the agglomerated zinc powder is ground, the residual moisture causes the zinc powder to adhere to the pores of the screen 8, so that the screen 8 is blocked. At this time, the external water circulation equipment pumps water with a temperature below 80°C into the water inlet tank 103 through the water pipe I 104, as shown in FIG. Figures 4 to 5As shown, water then enters the hollow main shaft 5 through the water inlet 5001, flows downward, and flows into each branch pipe 106 through the lower part of the main shaft 5. As the liquid level in the main shaft 5 rises, the liquid level in each branch pipe 106 also rises, and the water enters the confluence chamber 105 and then enters the annular cavity 10201 through the connecting port. Then the water is discharged through each hollow support rod Ⅰ101, and then the water flowing out of each support rod Ⅰ101 is collected and put back into the water circulation device, and the water flows in the main shaft 5 and each branch pipe 106. At the same time, the center column 6 and the screen 8 are also heated up to evaporate the moisture in the zinc powder, prevent the zinc powder from adhering to the screen 8 all the time, block the pores of the screen 8, and at the same time, the zinc powder in the feeding pipe 2 is lowered in small amounts for multiple times, so that some zinc powder is still retained in the feeding pipe 2. When the main shaft 5 rotates, it also drives each branch pipe 106 to rotate. The lower part of the branch pipe 106 also extends into the feeding pipe 2. The branch pipe 106 stirs the zinc powder that is about to be lowered in the feeding pipe 2, so that the moisture on the zinc powder in the feeding pipe 2 is fully dried to prevent the zinc powder in the feeding pipe 2 from agglomerating again.
[0045] Second embodiment
[0046] On the basis of the first embodiment, according to Figure 1-6 As shown, it also includes a partition 107; at least six circular array-type water outlets 5002 are opened at the lower part of the main shaft 5; the main shaft 5 is connected to at least six circular array-type partitions 107; each partition 107 has a cooling chamber 10701 opened in it; each cooling chamber 10701 is connected to a water outlet 5002; each partition 107 is connected to a branch pipe 106.
[0047] It also includes a water pipe II 108; a heat preservation chamber 3001 is opened in the material temporary storage chamber 3; the heat preservation chamber 3001 is connected to all the hollow support rods I 101; the lower part of the heat preservation chamber 3001 is connected to the water pipe II 108, and the water pipe II 108 is provided with a solenoid valve.
[0048] Connect water pipe II 108 to the water circulation equipment;
[0049] Connect the solenoid valve in water pipe II 108 to the power supply;
[0050] like Figures 4 to 6As shown, on the basis of the above embodiments, it is described that the zinc powder to be lowered in the feeding pipe 2 is stirred by the branch pipe 106, the zinc powder in the feeding pipe 2 is fully dried, and the zinc powder in the feeding pipe 2 is prevented from agglomerating again. At this time, a hollow partition 107 is added between the branch pipe 106 and the main shaft 5, and the water in the main shaft 5 flows into the cooling chamber 10701 through the water outlet 5002. The water flows in the cooling chamber 10701 to heat the partition 107, and then the water in the cooling chamber 10701 is transmitted upward through the branch pipe 106 and flows back to the collecting chamber 10501. By replacing part of the branch pipe 106 with the partition 107, the partition 107 contacts with the broken zinc powder, and the contact area is increased, which effectively makes the water in the zinc powder evaporate quickly and fully, thereby avoiding the re-agglomeration of the zinc powder. The re-agglomerated zinc powder needs to be broken up before the solenoid valve of the feeding pipe 2 can be opened, resulting in the frequency of opening and closing of the solenoid valve of the feeding pipe 2 being affected.
[0051] In the above embodiment, it is also noted that the water flowing back into the annular cavity 10201 is finally led outward through the hollow support rod Ⅰ101. Figure 4 As shown, a heat preservation chamber 3001 is opened in the material temporary storage chamber 3, and after the hollow support rod Ⅰ101 is connected to the heat preservation chamber 3001, the water flowing back into the annular chamber 10201 can flow into the heat preservation chamber 3001 through the hollow support rod Ⅰ101. At this time, the water with a certain temperature in the heat preservation chamber 3001 acts as the heat preservation layer of the material temporary storage chamber 3, so as to avoid the environment temperature being too high, causing the temperature of the zinc powder in the material temporary storage chamber 3 to exceed 80°C, so that the zinc powder combines with other substances, which makes the zinc powder a safety hazard. Through the temperature sensor in the material temporary storage chamber 3, Monitor the temperature of the zinc powder in real time. If the temperature of the zinc powder is too high, the temperature of the water input into the feed pipe 4 can be controlled, and the solenoid valve in the water pipe II 108 can be fully opened to allow the water in the insulation chamber 3001 to be discharged through the water pipe II 108 as quickly as possible, thereby accelerating the water circulation in the material storage chamber 3. The water in the insulation chamber 3001 also heats the zinc powder in contact with the material storage chamber 3, or when the temperature of the zinc powder is too high, absorbs the temperature of the zinc powder, thereby effectively controlling the temperature in the material storage chamber 3 and avoiding the problem of excessive temperature in the material storage chamber 3 and the zinc powder.
[0052] The third embodiment
[0053] On the basis of the first embodiment, according to Figure 1-3 and Figure 7-9As shown, it also includes an electric actuator 201, a connecting plate 202, a support rod II 203, an annular plate 204 and a spring rod 205; four annular array electric actuators 201 are installed at the bottom of the central column 6; the electric actuator 201 is an electric push rod; each electric actuator 201 telescopic part is fixedly connected to a connecting plate 202; each connecting plate 202 is slidably connected to an adjacent branch pipe 106; each connecting plate 202 is fixedly connected to a support rod II 203; all the support rods II 203 are commonly fixedly connected to the upper part with an annular plate 204; the annular plate 204 is slidably connected to the annular surface of the central column 6; the annular plate 204 is located below the screen 8; the screen 8 is slidably connected to the central column 6; the screen 8 is fixedly connected to at least six annular array spring rods 205; all the telescopic parts of the spring rods 205 are fixedly connected to the material temporary storage chamber 3.
[0054] It also includes a limiting column 206; at least six circular array-type limiting columns 206 are fixedly connected to the screen 8; each scraper 7 is fixedly connected to a contact block 7001 on the side away from the central column 6; the contact block 7001 is inclined and parallel to the scraper 7; each contact block 7001 is in contact with a limiting column 206; the limiting column 206 is a deformable metal rod, and the elastic coefficient of the limiting column 206 is greater than the elastic coefficient of the spring rod 205.
[0055] A spherical contact head is disposed on the upper portion of the limiting column 206 .
[0056] The number of the limiting posts 206 is in multiple relation with the number of the scrapers 7 , so that each contact block 7001 can contact with one limiting post 206 at the same time.
[0057] Connect the electric actuator 201 to a power source;
[0058] On the basis of the above embodiment, after the screen 8 is heated, the zinc powder adhered to the pores of the screen 8 can be dried to a certain extent. However, the zinc powder will not recover its fluidity until the moisture in the zinc powder is fully dried, thereby separating from the screen 8. The zinc powder adheres to the screen 8, which will also affect the full drying rate of the zinc powder. At this time, a plurality of limit posts 206 are set on the screen 8. When the screen 8 and the scraper 7 need to cooperate to break up the agglomerated zinc powder, all the electric actuators 201 are controlled to contract, and the connecting plate 202 and the corresponding parts thereon are synchronously driven to move upward. The annular plate 204 is against the lower part of the screen 8, and the electric actuator 201 is controlled to be closed. At this time, when the scraper 7 drives the agglomerated zinc powder to scrape on the screen 8, the contact blocks 7001 on each scraper 7 also contact with each limit post 206 in turn. Fig. 9As shown, the contact block 7001 is in close contact with the spherical contact head of the limiting column 206, and then with the rotation of the scraper 7, the contact block 7001 is synchronously driven to rotate, the metal limiting column 206 is deformed and bent, the contact block 7001 is in close contact with the limiting column 206, and then the contact block 7001 is separated from the limiting column 206, and the bent metal limiting column 206 is deformed and restored, so that the upper part of the limiting column 206 begins to swing back and forth, and the swing of the limiting column 206 also makes the screen 8 vibrate, effectively shaking off the adhered zinc powder, and the shaken zinc powder is finally dried when it contacts the partition 107 at the feeding pipe 2, thereby effectively preventing the scattered zinc powder from adhering to the screen 8 under the bonding effect of moisture, so that the pores on the screen 8 are blocked, and the vibration of the screen 8 can also assist in the rapid discharge of zinc powder;
[0059] Among them, the unstable zinc powder can be shaken off to a certain extent by vibration. If the feed pipe 4 puts a large amount of zinc powder into the material storage chamber 3 at one time, the large amount of zinc powder will still block the screen 8. At this time, all the electric actuators 201 are controlled to extend, so that the annular plate 204 moves downward, and the annular plate 204 is separated from the screen 8. At this time, the screen 8 is fully supported by the spring rod 205, and the elastic coefficient of the spring rod 205 is smaller than the elastic coefficient of the limiting column 206. Therefore, when the contact block 7001 contacts the limiting column 206, since the contact block 7001 is parallel to the scraper 7, the inclined contact block 7001 presses the limiting column 206 downward, and the corresponding limiting column 206 presses the screen 8 downward, and the screen 8 slides downward on the center column 6. The spring rods 205 are all compressed, and the screen 8 is separated from the scraper 7. Then, after the contact block 7001 passes over the limit column 206, all the spring rods 205 are restored, and the screen 8 is synchronously driven to move upward. Therefore, when the scraper 7 rotates, the limit column 206 can be frequently pressed down, thereby controlling the screen 8 to frequently shake up and down. The shaking of the screen 8 is conducive to the zinc powder on the screen 8 to quickly pass through the pores on the screen 8, thereby realizing rapid discharge of the zinc powder and avoiding the zinc powder from blocking the screen 8. In addition, by setting the number of limit columns 206 to be a multiple of the number of scrapers 7, each contact block 7001 can contact one limit column 206 at the same time, and synchronously press down the screen 8 to avoid the screen 8 and the 5-spindle and 3-material temporary storage chamber from getting stuck.
[0060] It should be understood that the above description is only for exemplary purposes and is not meant to limit the present invention. Those skilled in the art will appreciate that variations of the present invention will be included within the scope of the claims herein.
Claims
1. A safe feeding device based on primidone reduction reaction, comprising a reduction reaction kettle (1) and a feeding pipe (2); the reduction reaction kettle (1) is connected to the feeding pipe (2); the feeding pipe (2) is equipped with a solenoid valve; wherein: The machine also comprises a temporary material storage chamber (3), a feed pipe (4), a main shaft (5), a central column (6), a scraper (7) and a screen (8); the feed pipe (2) is connected to the temporary material storage chamber (3), and a temperature sensor is arranged in the temporary material storage chamber (3); the temporary material storage chamber (3) is connected to the feed pipe (4); the temporary material storage chamber (3) is rotatably connected to the main shaft (5); the main shaft (5) is fixedly connected to the central column (6); the central column (6) is fixedly connected to a plurality of scrapers (7); the lower part of the temporary material storage chamber (3) is connected to a screen (8), and the pores of the screen (8) are much larger than the particle size of the zinc powder; the screen (8) is in contact with and cooperates with the scraper (7) to mechanically break up the agglomerated zinc powder; the screen (8) is connected to the central column (6); The material storage chamber (3) further comprises a support rod I (101), a return chamber (102), a water intake chamber (103), a water pipe I (104), a confluence chamber (105) and a branch pipe (106); the material temporary storage chamber (3) is connected to a plurality of support rods I (101); all the support rods I (101) are commonly connected to the return chamber (102); the return chamber (102) is fixedly connected to the water intake chamber (103); the water intake chamber (103) is rotatably connected to the main shaft (5); the water intake chamber (103) is connected to the water pipe I (104); the main shaft (5) is a hollow rod, and a plurality of water inlets (5001) are opened on the upper part of the main shaft (5); a diversion chamber (10301) is provided in the water intake chamber (103); the diversion chamber (10301) is connected to all the water intake chambers (10301); The water inlet (5001) is connected to the water inlet (5001); the support rod I (101) is a hollow rod; an annular cavity (10201) is provided in the reflux chamber (102); the annular cavity (10201) is connected to all the support rods I (101); the reflux chamber (102) is fixedly connected to a confluence chamber (105); a collecting chamber (10501) is provided in the confluence chamber (105); the annular cavity (10201) is connected to the collecting chamber (10501) through a connecting hole; a plurality of branch pipes (106) are connected to the lower part of the collecting chamber (10501); all the branch pipes (106) are connected to the main shaft (5); the central column (6) is fixedly connected to all the branch pipes (106); the lower part of the branch pipe (106) extends into the feeding pipe (2); It also includes a partition (107); a plurality of water outlets (5002) are opened at the lower part of the main shaft (5); the main shaft (5) is connected to the plurality of partitions (107); a cooling chamber (10701) is opened in each partition (107); each cooling chamber (10701) is connected to a water outlet (5002); each partition (107) is connected to a branch pipe (106); The invention also comprises a water pipe II (108); a heat preservation chamber (3001) is provided in the material temporary storage chamber (3); the heat preservation chamber (3001) is connected with all the hollow support rods I (101); the heat preservation chamber (3001) is connected with the water pipe II (108), and a solenoid valve is provided in the water pipe II (108).
2. A safe feeding device based on primidone reduction reaction according to claim 1, characterized in that: The upper portion of the central column (6) is configured to be conical, so as to reduce the accumulation of powder on the central column (6).
3. A safe feeding device based on primidone reduction reaction according to claim 1, characterized in that: The scraper (7) and the plane of the screen (8) form an inclined angle, and when viewed from top to bottom, the rotation direction of the scraper (7) is counterclockwise.
4. A safe feeding device based on primidone reduction reaction according to claim 1, characterized in that: The invention also comprises an electric actuator (201), a connecting plate (202), a support rod II (203), an annular plate (204) and a spring rod (205); the central column (6) is provided with a plurality of electric actuators (201); the telescopic portion of each electric actuator (201) is fixedly connected to a connecting plate (202); each connecting plate (202) is slidably connected to an adjacent branch pipe (106); each connecting plate (202) is fixedly connected to a support rod II (203); all the support rods II (203) are commonly fixedly connected to an annular plate (204); the annular plate (204) is slidably connected to the central column (6); the annular plate (204) is located below the screen (8); the screen (8) is slidably connected to the central column (6); the screen (8) is fixedly connected to a plurality of spring rods (205); and the telescopic portions of all the spring rods (205) are fixedly connected to the material temporary storage chamber (3).
5. A safe feeding device based on primidone reduction reaction according to claim 4, characterized in that: It also includes a limiting column (206); a plurality of limiting columns (206) are fixedly connected to the screen (8); each scraper (7) is fixedly connected to a contact block (7001) on a side away from the central column (6); the contact block (7001) is arranged obliquely, and the contact block (7001) is parallel to the scraper (7); each contact block (7001) is in contact with a limiting column (206); the limiting column (206) is a deformable metal rod, and the elastic coefficient of the limiting column (206) is greater than the elastic coefficient of the spring rod (205).
6. A safe feeding device based on primidone reduction reaction according to claim 5, characterized in that: A spherical contact head is provided on the upper part of the limiting column (206).
7. A safe feeding device based on primidone reduction reaction according to claim 6, characterized in that: The number of the limiting posts (206) is in multiple relation with the number of the scrapers (7), so that each contact block (7001) can contact one limiting post (206) at the same time.
Citation Information
Patent Citations
Safety control device for feeding of solid zinc powder containing prometryn
CN212092171U
Deck covering producing and processing machine
CN115350639A
Solvent-free polyester synthesis system and synthesis method thereof
CN116408024A