A large-span hyperbolic skylight building roof structure and construction method thereof

Through the mobile component system, the sliding shoes and support blocks driven by channel steel rails and hydraulic telescopic cylinders are used to achieve stable installation of large-span roofs, solve the problem of insufficient stability of the construction frame, and improve construction efficiency and safety.

CN118461824BActive Publication Date: 2024-10-11CHINA RAILWAY CONSTR GRP SOUTHERN ENG CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410943117.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-15
Publication Date
2024-10-11
Estimated Expiration
2044-07-15

AI Technical Summary

Technical Problem

In long-span roof construction, the stability of the construction frame is weak, making it inconvenient to install the steel structure and difficult to put it in place at one time, causing repeated operations and affecting the construction progress.

Method used

A mobile component system is adopted, including channel steel rails, sliding shoes, support blocks and hydraulic telescopic cylinders. The support unit is driven by the movement of the I-shaped steel to achieve stable installation and adjustment of large-span special-shaped double-sided curved roofs.

Benefits of technology

It improves the controllability of erection of steel structure nodes, reduces repeated operations, improves construction efficiency and safety, and ensures stable installation of large-span roofs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118461824B_ABST
    Figure CN118461824B_ABST
Patent Text Reader

Abstract

The invention relates to the technical field of engineering construction, and specifically discloses a large-span hyperbolic daylighting building roof structure and a construction method thereof, comprising a large-span roof assembly and a building wall: a moving assembly arranged on the building wall; the large-span roof assembly comprises a large-span special-shaped double-sided curved roof and a supporting unit; the moving assembly comprises a channel steel track; the channel steel track is provided with two groups; a sliding shoe and a supporting block are slidably connected in the channel steel track; the sliding shoe and the top of the supporting block are fixedly connected with an I-shaped steel; the supporting unit is installed on the I-shaped steel; the supporting block is driven to move by a driving force; the large-span roof assembly comprises a large-span special-shaped double-sided curved roof, the large-span special-shaped double-sided curved roof is an integrated structure, and a plurality of groups of daylighting grooves are respectively opened on two curved surfaces on the large-span special-shaped double-sided curved roof, and daylighting panels and other materials can be placed in the daylighting grooves.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of engineering construction, and in particular to a large-span hyperbolic daylighting building roof structure and a construction method thereof. Background Art

[0002] At present, architectural forms are no longer confined to traditional forms, but are gradually showing a diversified development trend. Among them, large-span special-shaped roofs are a common structural form in architectural design. Its characteristics are that the roof has a large span and an irregular shape or a special geometric shape. This design is becoming more and more popular in modern architecture because it not only provides a unique visual effect, but also meets specific functional requirements.

[0003] During the construction of a large-span roof, the steel structure must first be inspected. After the inspection, the construction scaffolding is erected. After the erection is completed, the workers take the scaffolding to the construction site, and then use the coordinated crane to install the steel structure to the roof. After the steel structure is installed, the trusses are welded, and finally waterproofing construction and laying of lighting materials are carried out.

[0004] In the prior art, when constructing a large-span roof, scaffolding is often used as a construction and operation platform. However, the height of some construction roofs is relatively high, and there are safety hazards when workers stand on the scaffolding to carry out construction. In addition, the stability of the overall frame is relatively weak. During installation, high node stiffness requirements are required, which is difficult to control during the specific construction process. As a result, it is difficult to install the steel structure in place at one time during the erection process, resulting in repeated operations and affecting the overall construction progress. Summary of the invention

[0005] The purpose of the present invention is to provide a large-span hyperbolic daylighting building roof structure and a construction method thereof, so as to solve the following technical problems:

[0006] (1) How to control the framework to make it easier for workers to set up steel structure nodes;

[0007] (2) How to avoid duplication of operations and improve the overall construction progress.

[0008] The purpose of the present invention can be achieved through the following technical solutions:

[0009] A large-span hyperbolic skylight building roof structure, comprising a large-span roof assembly and a building wall:

[0010] A mobile assembly mounted on a building wall;

[0011] The long-span roof assembly comprises a long-span special-shaped double-sided curved roof and a supporting unit;

[0012] The moving component includes a channel steel track; the channel steel track is provided with two groups; a sliding shoe and a support block are slidably connected in the channel steel track; the sliding shoe and the top of the support block are fixedly connected with an I-shaped steel; the support unit is installed on the I-shaped steel; the support block is driven to move by a driving force.

[0013] Further, the support unit includes a first support frame; the first support frame is provided with two groups; the side wall of the first support frame is fixedly connected to the second connecting frame; the middle part of the second connecting frame is fixedly connected to the third support frame; the end of the third support frame away from the second connecting frame is fixedly connected to the first connecting frame; the side walls on both sides of the first connecting frame are fixedly connected to the inclined support frames; the end of the inclined support frame away from the first connecting frame is fixedly connected to the first support frame; the large-span special-shaped double-sided curved roof is fixedly connected to both ends of the first support frame; and a lighting groove is provided on the large-span special-shaped double-sided curved roof.

[0014] Furthermore, a slider is slidably connected in the channel steel track between the sliding shoe and the support block; a hydraulic telescopic cylinder is fixedly connected to the side wall of the slider; and one end of the hydraulic telescopic cylinder away from the slider is fixedly connected to the side wall of the support block.

[0015] Furthermore, a block is fixedly connected to the side wall of the channel steel track; a telescopic column is fixedly connected to the top of the slider; a baffle is fixedly connected to the end of the telescopic column away from the slider; the baffle is U-shaped; the bottom of the baffle is an inclined surface; a telescopic spring is fixedly connected to the top of the slider; and the end of the telescopic spring away from the slider is fixedly connected to the bottom of the baffle.

[0016] Furthermore, the telescopic columns are provided in four groups; and the telescopic springs are provided in two groups.

[0017] Furthermore, the blocks are provided in a plurality of groups; and the spacing between the blocks in each group is consistent.

[0018] Furthermore, the side wall of the building wall is fixedly connected to a concrete casting base; the bottom of the channel steel track is fixedly connected to the concrete casting base.

[0019] Furthermore, two groups of the oblique support frames are provided; the oblique support frames are supported in a triangular shape.

[0020] Furthermore, the lighting troughs are provided in multiple groups and are arranged at equal intervals.

[0021] A method for constructing a large-span hyperbolic skylight building roof comprises the following steps:

[0022] S1, construction preparation: first prepare materials, including materials and components (accessories), and then start labor organization preparation. First, determine the work flow of each team, measurement team: responsible for on-site measurement and layout; keel team: responsible for keel processing and installation; glass team: responsible for glass gluing and installation; profile making team: responsible for profile installation; electrician team: responsible for temporary power supply maintenance on the construction site; fitter team: responsible for keel installation processing and assembly; welder team: responsible for welding steel keels and connectors; decoration team: responsible for the installation of panels and scattered panels, as well as sealing and weather-resistant glue caulking; after confirmation, start construction and evaluate and analyze the construction. During the evaluation process, review the drawings and design documents, and then carry out the construction of the steel structure project. Before construction, prepare the process and installation construction organization design according to the requirements of the construction drawings, and prepare a complete and correct construction process flow before construction;

[0023] S2, track pre-setting: after the preparation work is completed, the building wall area to be constructed is primed, and then concrete is laid to facilitate the subsequent laying of tracks;

[0024] S3, initial installation: after the concrete is laid, it is poured into a concrete casting base. After the pouring is completed, the channel steel track is installed on the surface of the concrete casting base;

[0025] S4, adjustment: install the moving assembly into the channel steel track to facilitate the sliding of the moving assembly, thereby driving the support unit to move, facilitating the installation of large-span special-shaped roofs;

[0026] S5, connection: construction workers use cranes and other equipment to place the support unit on the I-shaped steel and connect it;

[0027] S6, skylight installation: install the large-span special-shaped double-sided curved ceiling onto the support unit, and then start installing the glass panel components. The glass panels need to be inspected and accepted before construction, and then the glass panels are stacked in layers. During construction, the initial installation is carried out first, and then they are adjusted and fixed after installation. Finally, the installation results are checked, and then the glass panel installation is accepted. After the installation is completed, the skylight is tested, and the project can be delivered after the test is qualified.

[0028] Beneficial effects of the present invention:

[0029] The mobile assembly in the present invention can facilitate the erection of the steel structure. After the support unit is built, the bottom of the support unit is installed on the I-shaped steel in the mobile assembly, and then supported by the I-shaped steel, and the movement of the I-shaped steel is used to drive the support unit to move. Through the movement of the I-shaped steel, the support unit can be driven to reach each installation node. Through the setting of the mobile assembly, the installation of large-span special-shaped double-sided curved roofs can be better controlled to avoid the situation where the large-span special-shaped double-sided curved roof is not installed in place and then repeatedly installed.

[0030] The large-span special-shaped double-sided curved roof in the present invention can be applied to large-span roof buildings. The large-span roof assembly includes the large-span special-shaped double-sided curved roof. The large-span special-shaped double-sided curved roof is an integrated structure. Multiple groups of skylights are respectively opened on the two curved surfaces of the large-span special-shaped double-sided curved roof, and skylight panels and other materials can be placed in the skylights.

[0031] The present invention can support a large-span special-shaped double-sided curved roof through the support unit. The specific number of support units to be built can be determined according to the size of the building roof, so that it is used to support the large-span special-shaped double-sided curved roof. The support unit includes a first support frame and other components. The first support frame is assembled with the second connecting frame. After the assembly is completed, the third support frame is installed to the middle of the second connecting frame, and the first connecting frame is fixedly connected to the end of the third support frame. After the first support frame, the first connecting frame, the second connecting frame, and the third support frame are connected, a triangle is formed, which has a stable structure, and the side wall of the first connecting frame is fixedly connected to the oblique support frame, and the other end of the oblique support frame is fixedly connected to the first support frame to form a triangular structure again, wherein the support units are fixed by bolts and nuts to ensure that the support units provide stable support for the large-span special-shaped double-sided curved roof, so that the large-span special-shaped double-sided curved roof can be installed smoothly.

[0032] The large-span special-shaped double-sided curved roof in the present invention needs to be subjected to a wind-uplift resistance test before construction. First, the test purpose and wind speed range are determined according to the purpose of the building and the wind speed conditions in the area where it is located. Then, a suitable test method is selected according to the type of building, such as a wind tunnel test, a digital simulation test, etc., and then a test model is built according to the actual situation of the building to ensure that the size, proportion and structure of the test model are consistent with the actual building to ensure the accuracy of the test results. The wind-uplift resistance test provides a basis for the wind resistance performance of the building, helps to evaluate the stability and safety of the building in a strong wind environment, thereby ensuring that the large-span special-shaped double-sided curved roof after installation achieves a wind-resistant effect in windy weather. BRIEF DESCRIPTION OF THE DRAWINGS

[0033] The present invention will be further described below in conjunction with the accompanying drawings.

[0034] Figure 1 It is a schematic diagram of the overall structure of the large-span special-shaped double-sided curved roof in the present invention;

[0035] Figure 2 It is a schematic diagram of the structure in which the mobile assembly and the building wall are installed together in the present invention;

[0036] Figure 3 It is a top view of the large-span special-shaped double-sided curved roof in the present invention;

[0037] Figure 4 It is a structural schematic diagram of the support unit in the present invention;

[0038] Figure 5 It is a schematic diagram of the overall structure of the mobile assembly in the present invention;

[0039] Figure 6 It is a schematic diagram of the overall structure of the slider in the present invention;

[0040] Figure 7 is a cross-sectional view of the overall structure of the slider in the present invention;

[0041] Figure 8 It is a schematic diagram of the overall structure of the mobile assembly and the supporting unit in the present invention.

[0042] Description of the drawings: 1. Building wall; 2. Concrete pouring base; 3. Channel steel track; 4. Block; 5. Moving assembly; 51. Slide shoe; 52. I-shaped steel; 53. Sliding block; 54. Baffle; 55. Telescopic column; 56. Telescopic spring; 57. Hydraulic telescopic cylinder; 58. Support block; 6. Large-span roof assembly; 61. Large-span special-shaped double-sided curved roof; 62. Lighting trough; 7. Support unit; 71. First support frame; 72. Oblique support frame; 73. First connecting frame; 75. Third support frame; 76. Second connecting frame. DETAILED DESCRIPTION

[0043] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0044] See also Figure 1-Figure 8 As shown, the present invention provides a large-span hyperbolic daylighting building roof structure, comprising a large-span roof assembly 6 and a building wall 1: a moving assembly 5 arranged on the building wall 1; the large-span roof assembly 6 comprises a large-span special-shaped double-sided curved roof 61 and a support unit 7; the moving assembly 5 comprises a channel steel track 3; the channel steel track 3 is provided with two groups; a sliding shoe 51 and a support block 58 are slidably connected in the channel steel track 3; the sliding shoe 51 and the top of the support block 58 are fixedly connected with an I-shaped steel 52; the support unit 7 is installed on the I-shaped steel 52; the support block 58 is driven to move by a driving force;

[0045] During work, in the prior art, when constructing a large-span roof, scaffolding is often used as a construction and operation platform. However, the height of some construction roofs is relatively high, and there will be safety hazards when workers stand on the scaffolding to carry out construction. In addition, the stability of the overall frame is relatively weak. During installation, high node stiffness requirements are required, and it is difficult to control the specific construction process, resulting in the steel structure being difficult to install in place at one time during the erection process, causing repeated operations and affecting the overall construction progress. In order to prevent such incidents from occurring, the installation of the large-span roof assembly 6 can be achieved through the mobile assembly 5 on the building wall 1. The large-span roof assembly 6 includes a large-span special-shaped double-sided curved roof 61. The large-span special-shaped double-sided curved roof 61 is an integrated structure. A plurality of groups of light grooves 62 are respectively provided on the two curved surfaces of the large-span special-shaped double-sided curved roof 61. The light grooves 62 Materials such as skylights can be placed inside. First, the staff needs to build the support unit 7. The specific number of support units 7 to be built can be determined according to the size of the building roof, so as to be used to support the large-span special-shaped double-sided curved roof 61. The support units 7 are fixed by bolts and nuts. After the support unit 7 is built, the support unit 7 is installed on the I-shaped steel 52 on the sliding shoe 51 and the I-shaped steel 52 on the support block 58 respectively. After the installation is completed, the support unit 7 is supported by the I-shaped steel 52, and then the support block 58 is driven to move. When the support block 58 moves, it will drag the sliding shoe 51 behind it to slide in the channel steel track 3. The channel steel track 3 is provided with two groups, which respectively carry two groups of moving components 5, which are used to support the two ends of the support unit 7. During the sliding process, the support unit 7 can be transported to a suitable position and installed on the building wall 1.

[0046] like Figure 4 As shown, the support unit 7 includes a first support frame 71; the first support frame 71 is provided with two groups; the side wall of the first support frame 71 is fixedly connected to the second connecting frame 76; the middle of the second connecting frame 76 is fixedly connected to the third support frame 75; the end of the third support frame 75 away from the second connecting frame 76 is fixedly connected to the first connecting frame 73; the side walls of both sides of the first connecting frame 73 are fixedly connected to the oblique support frames 72; the end of the oblique support frame 72 away from the first connecting frame 73 is fixedly connected to the first support frame 71; the large-span special-shaped double-sided curved roof 61 is fixedly connected to both ends of the first support frame 71; the large-span special-shaped double-sided curved roof 61 is provided with a lighting groove 62;

[0047] When working, the support unit 7 includes components such as the first support frame 71. The first support frame 71 is assembled with the second connecting frame 76. After the assembly is completed, the third support frame 75 is installed to the middle of the second connecting frame 76. The first connecting frame 73 is fixed to the end of the third support frame 75. After the first support frame 71, the first connecting frame 73, the second connecting frame 76, and the third support frame 75 are connected, a triangle is formed with a stable structure, and the side wall of the first connecting frame 73 is fixed to the inclined support frame 72, and the other end of the inclined support frame 72 is fixed to the first support frame 71 to form a triangular structure again. After the assembly is completed, the support unit 7 is moved to the moving component 5. After the moving component 5 moves the support units 7 in groups to the appropriate positions, the large-span special-shaped double-sided curved top 61 is installed on the support unit 7 and supported by the support unit 7.

[0048] like Figure 6 As shown, a slider 53 is slidably connected in the channel steel track 3 between the sliding shoe 51 and the support block 58; a hydraulic telescopic cylinder 57 is fixedly connected to the side wall of the slider 53; and one end of the hydraulic telescopic cylinder 57 away from the slider 53 is fixedly connected to the side wall of the support block 58;

[0049] During operation, the two ends of the hydraulic telescopic cylinder 57 are fixedly connected to the side walls of the slider 53 and the support block 58 respectively. The hydraulic telescopic cylinder 57 is driven by a computer numerical control. After the support unit 7 is installed on the I-shaped steel 52, the hydraulic telescopic cylinder 57 can drive the support block 58 to move, thereby driving the slider 53 and the sliding shoe 51 to move, and then moving the support unit 7.

[0050] like Figure 6 As shown, the side wall of the channel steel track 3 is fixedly connected with a block 4; the top of the slider 53 is fixedly connected with a telescopic column 55; the end of the telescopic column 55 away from the slider 53 is fixedly connected with a baffle 54; the baffle 54 is U-shaped; the bottom of the baffle 54 is inclined; the top of the slider 53 is fixedly connected with a telescopic spring 56; the end of the telescopic spring 56 away from the slider 53 is fixedly connected to the bottom of the baffle 54;

[0051] During operation, the block 4 is arranged on both sides of the channel steel track 3, and multiple groups of block 4 are arranged. The slider 53 is arranged between the support block 58 and the sliding shoe 51. A baffle 54 is arranged on the top of the slider 53. The size of the baffle 54 is consistent with the spacing between the two groups of block 4, and the bottom of the baffle 54 is arranged as an inclined surface, and a telescopic spring 56 and a telescopic column 55 are arranged on the top of the slider 53. When the support unit 7 is moved, the baffle 54 on the slider 53 is pressed by the block 4, thereby driving the hydraulic telescopic cylinder 57 to extend and push the support block 58 in front to move. After moving a certain distance, the hydraulic telescopic cylinder 57 contracts, and when contracting, it will drive the slider 53 to the support block 58 The baffle 54 moves at the place where the slider 53 moves. During the movement, the bottom inclined surface of the baffle 54 contacts the block 4, and the block 4 holds up the baffle 54 after the contact. During the holding up process, the baffle 54 is in a vertical rising state, and while rising, it drives the telescopic spring 56 and the telescopic column 55 to rise vertically. Then, the baffle 54 passes over the block 4 while the slider 53 continues to move until the hydraulic telescopic cylinder 57 is completely retracted. After the retraction is complete, the baffle 54 reaches between the two groups of blocks 4 again. At this time, the baffle 54 is again held by the block 4, and then the hydraulic telescopic cylinder 57 is driven to extend, which can push the support block 58 and the support unit 7 forward again, and repeat this step until the support unit 7 is moved to a suitable position.

[0052] like Figure 6 and Figure 7 As shown, four groups of telescopic columns 55 are provided; two groups of telescopic springs 56 are provided; when working, the baffle 54 can be supported and connected at the same time through the provision of multiple groups of telescopic columns 55 and telescopic springs 56.

[0053] like Figure 5 As shown, the blocks 4 are provided in multiple groups; the spacing between the blocks 4 in each group is consistent; when working, the spacing between the blocks 4 on the side walls of the two groups of channel rails 3 needs to be set consistent to avoid malfunctions caused by inconsistent progress during the sliding process.

[0054] like Figure 2 As shown, the side wall of the building wall 1 is fixedly connected to the concrete casting base 2; the bottom of the channel steel track 3 is fixedly connected to the concrete casting base 2; when working, the concrete casting base 2 is arranged on both sides of the building wall 1, for supporting the channel steel track 3, so that the support unit 7 is installed to the roof.

[0055] like Figure 4 As shown, two groups of the oblique support frames 72 are provided; the oblique support frames 72 are supported in a triangular shape; when working, the first connecting frame 73 is supported by the oblique support frames 72, and the oblique support frames 72 are triangular structures, which can play a better supporting role.

[0056] like Figure 1 As shown, the lighting grooves 62 are provided in multiple groups and are arranged at equal intervals; when working, the lighting effect can be achieved by installing the lighting materials into the lighting grooves 62.

[0057] See also Figure 1-Figure 8 As shown, the present invention provides a large-span hyperbolic skylight building roof construction method, comprising the following steps:

[0058] S1, construction preparation: first prepare materials, including materials and components (accessories), and then start labor organization preparation. First, determine the work flow of each team, measurement team: responsible for on-site measurement and layout; keel team: responsible for keel processing and installation; glass team: responsible for glass gluing and installation; profile making team: responsible for profile installation; electrician team: responsible for temporary power supply maintenance on the construction site; fitter team: responsible for keel installation processing and assembly; welder team: responsible for welding steel keels and connectors; decoration team: responsible for the installation of panels and scattered panels, as well as sealing and weather-resistant glue caulking; after confirmation, start construction and evaluate and analyze the construction. During the evaluation process, review the drawings and design documents, and then carry out the construction of the steel structure project. Before construction, prepare the process and installation construction organization design according to the requirements of the construction drawings, and prepare a complete and correct construction process flow before construction;

[0059] S2, track pre-setting: after the preparation work is completed, the building wall area to be constructed is primed, and then concrete is laid to facilitate the subsequent laying of tracks;

[0060] S3, initial installation: after the concrete is laid, it is poured into a concrete pouring base 2, and after the pouring is completed, the channel steel track 3 is installed on the surface of the concrete pouring base 2;

[0061] S4, adjustment: install the moving assembly 5 into the channel steel track 3 to facilitate the sliding of the moving assembly 5, thereby driving the support unit 7 to move, facilitating the installation of a large-span special-shaped roof;

[0062] S5, connection: the construction personnel use a crane or other equipment to place the support unit 7 on the I-shaped steel 52 and connect it;

[0063] S6, installation of skylight: install the large-span special-shaped double-sided curved roof 61 onto the support unit 7, and then start installing the glass panel assembly. Before construction, the glass panels need to be inspected and accepted, and then the glass panels are stacked in layers. During construction, the initial installation is first performed, and then they are adjusted and fixed after installation. Finally, the installation results are checked, and then the glass panel installation is accepted. After the installation is completed, the skylight is tested, and the project can be delivered after the test is qualified;

[0064] When working, first of all, prepare the materials. Materials, components (accessories), machinery and equipment are the material basis to ensure smooth construction. The preparation of these materials must be completed before the project starts. According to the demand plan of various materials, the supply, installation, transportation and preparation are respectively implemented to meet the requirements of continuous construction, and then the labor organization preparation begins. The preparation should be determined according to the labor demand plan formulated in the construction organization design. When organizing the installation team to enter the site, education on safety, fire prevention and civilized construction should be carried out, and various management systems of the construction site should be established and improved. According to the various guarantee measures formulated by the organization design, the personnel in each position should be assessed, and then the drawings should be reviewed to check whether the design documents are complete. The design documents include design drawings, construction drawings, drawing instructions and design change notices, etc. Then check whether the geometric dimensions of the components are fully marked, whether the dimensions of the relevant components are correct, whether the nodes are clear, and whether they meet the national standards. Use MIDAS Gen and ANSYS respectively established the finite element model of the structure, and carried out static performance analysis, dynamic performance analysis, eigenvalue buckling analysis, and dual nonlinear buckling analysis of geometric nonlinearity and material nonlinearity coupling. Combined with the test data, the stress level and node displacement of the rods were studied, the weak points were found, the design was optimized, the connection performance of the nodes was guaranteed, and the stability and bearing capacity of the entire structure were ensured to meet the requirements. Then, a detailed wind resistance study was conducted on the ultra-high altitude large-volume complex steel structure system by combining CFD simulation and experimental research in combination with local climatic conditions, revealing the working mechanism of wind field and structural coupling and optimizing the structural form. A thermal calculation and analysis of the glass skylight was conducted by combining CFD simulation and experimental research and on-site investigation in combination with local climatic conditions, and its energy-saving performance was evaluated. Its anti-seepage and anti-leakage performance was evaluated and optimized. After a series of preparations and evaluations were completed, during construction, The two sides of the building wall are primed, and then concrete is laid to cast it into a concrete base, and then the channel steel track 3 is installed on the concrete casting base 2, and it is ensured that the two sets of channel steel tracks 3 are in a parallel position. After the installation is completed, the stopper 4 is equidistantly installed on both sides of the channel steel track 3 after on-site testing. The distance between the stoppers 4 on the two sets of channel steel tracks 3 needs to be set to be consistent. Then the staff installs the sliding shoe 51, the support block 58 and the I-shaped steel 52, and places them in the channel steel track 3 after installation. Then the slider 53 is connected to the hydraulic telescopic cylinder 57 and the support block 58, and then the CNC system is connected after connection to drive the hydraulic telescopic cylinder 57 to work. Then the staff builds the support unit 7. After the construction is completed, the support unit 7 is hoisted onto the I-shaped steel 52 using a small crane and other equipment and fixed. After the fixation is completed, the moving component 5 is driven to move, and the support unit 7 is moved to a suitable position, and then the large-span special-shaped double-sided curved top 61 is installed on the support unit 7.

[0065] Working principle of the present invention: In the prior art, when constructing a large-span roof, scaffolding is often used as a construction and operation platform. However, the height of some construction roofs is relatively high, and there will be safety hazards when workers stand on the scaffolding for construction. In addition, the stability of the overall frame is relatively weak. During installation, the node stiffness requirements are relatively high, and it is difficult to control the specific construction process, which makes it difficult to install the steel structure in place at one time during the erection process, resulting in repeated operations and affecting the overall construction progress. In order to prevent such incidents from happening, the large-span roof component 6 can be realized by the mobile component 5 on the building wall 1. The large-span roof assembly 6 includes a large-span special-shaped double-sided curved roof 61. The large-span special-shaped double-sided curved roof 61 is an integrated structure. Two curved surfaces on the large-span special-shaped double-sided curved roof 61 are respectively provided with multiple groups of light-collecting grooves 62. Light-collecting panels and other materials can be placed in the light-collecting grooves 62. First, the staff needs to build a support unit 7. The specific number of support units 7 to be built can be determined according to the size of the building roof, so as to support the large-span special-shaped double-sided curved roof 61. The support unit 7 includes a first support frame 71 and other components. The first support frame 71 is assembled with the second connecting frame 76. After the assembly is completed, the third support frame 7 is assembled. 5 is installed to the middle of the second connecting frame 76, and the first connecting frame 73 is fixed to the end of the third supporting frame 75. After the first supporting frame 71, the first connecting frame 73, the second connecting frame 76, and the third supporting frame 75 are connected, a triangle is formed, which has a stable structure, and the side wall of the first connecting frame 73 is fixed to the oblique supporting frame 72, and the other end of the oblique supporting frame 72 is fixed to the first supporting frame 71, forming a triangular structure again, wherein the supporting units 7 are fixed by bolts and nuts. After the supporting unit 7 is built, the two groups of first supporting frames 71 in the supporting unit 7 are respectively installed on the two groups of I-shaped steel 52, and each group of supporting units There are two groups of first support frames 71 in element 7, and the two groups of first support frames 71 are respectively installed on the I-shaped steel 52 on the sliding shoe 51 and the I-shaped steel 52 on the support block 58. After the installation is completed, the first support frame 71 is supported by the I-shaped steel 52, and then the support block 58 is driven to move. When the support block 58 moves, it will drag the sliding shoe 51 behind to slide in the channel steel track 3. The channel steel track 3 is provided with two groups, which respectively carry two groups of moving components 5, which are used to support the two ends of the first support frame 71. During the sliding process, the support unit 7 can be transported to a suitable position and installed on the building wall 1.

[0066] Among them, the structural design performance of this skylight is reliable, and its airtightness and watertightness meet the requirements. It has been widely used in many projects and has received a good response. In addition to meeting the three requirements of the skylight, this design system fully considers the on-site installation and construction period requirements, and realizes the disorderly installation of glass panels and the free replacement of any glass panels, which greatly simplifies the installation procedure and shortens the construction period. The glass panel is fixed on the steel frame with a hidden frame. The skylight glass is TP8+12A+TP8+1.52pvb+TP8 double silver (Low-E) laminated hollow tempered glazed glass, and the glass at the door is TP8+12A+TP8 single silver (Low-E) hollow tempered glass. The edges and edges are made of 3mm thick aluminum veneer (fluorocarbon spraying). When installing the glass panel, lift the glass When it reaches the installation position, a series of work such as grooving, slotting, and seaming is carried out. After the initial installation of the glass panels, the panels are adjusted according to the standards of horizontal, vertical, and surface flatness. Horizontal flatness means that the horizontal beams are horizontal; verticality means that the vertical beams are vertical and the gaps are vertical; surface flatness means that all glasses are in the same plane or on the curved surface. After the outdoor adjustment, it is also necessary to check whether the indoor areas that should be flat are flat, and whether the dimensions of each location meet the design requirements. After the adjustment of the glass panels, they must be fixed immediately, mainly with rubber heat blocks. The pads must be pressed positively and tightly to prevent the glass panels from loosening. After the glass panels are installed, the aluminum panels are installed. After all the installation is completed, the glue injection process is started on the skylight, and then the data test is carried out on the skylight. The tests include the skylight hanging test and the skylight water test. After passing the test, it can be delivered.

[0067] At the same time, before construction, the large-span special-shaped double-sided curved roof 61 needs to be subjected to a wind-uplift resistance test. First, the test purpose and wind speed range are determined according to the purpose of the building and the wind speed conditions in the area. Then, a suitable test method is selected according to the type of building, such as a wind tunnel test, a digital simulation test, etc. Then, according to the actual situation of the building, a test model is built to ensure that the size, proportion and structure of the test model are consistent with the actual building to ensure the accuracy of the test results. The wind-uplift resistance test provides a basis for the wind resistance performance of the building and helps evaluate the stability and safety of the building in a strong wind environment.

[0068] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A large-span hyperbolic daylighting building roof structure, characterized in that: It includes a long-span roof assembly (6) and a building wall (1): A moving component (5) arranged on a building wall (1); The large-span roof assembly (6) comprises a large-span special-shaped double-sided curved roof (61) and a supporting unit (7); The moving assembly (5) comprises a channel steel track (3); the channel steel track (3) is provided with two groups; a sliding shoe (51) and a support block (58) are slidably connected inside the channel steel track (3); an I-shaped steel (52) is fixedly connected to the top of the sliding shoe (51) and the support block (58); the support unit (7) is mounted on the I-shaped steel (52); the support block (58) is driven to move by a driving force; The support unit (7) comprises a first support frame (71); the first support frame (71) is provided with two groups; the side wall of the first support frame (71) is fixedly connected to the second connection frame (76); the middle part of the second connection frame (76) is fixedly connected to the third support frame (75); one end of the third support frame (75) away from the second connection frame (76) is fixedly connected to the first connection frame (73); the side walls of both sides of the first connection frame (73) are fixedly connected to the oblique support frames (72); one end of the oblique support frame (72) away from the first connection frame (73) is fixedly connected to the first support frame (71); the large-span special-shaped double-sided curved roof (61) is fixedly connected to both ends of the first support frame (71); a lighting groove (62) is provided on the large-span special-shaped double-sided curved roof (61); A sliding block (53) is slidably connected in the channel steel track (3) between the sliding shoe (51) and the support block (58); a hydraulic telescopic cylinder (57) is fixedly connected to the side wall of the sliding block (53); an end of the hydraulic telescopic cylinder (57) away from the sliding block (53) is fixedly connected to the side wall of the support block (58); The side wall of the channel steel track (3) is fixedly connected with a stopper (4); the top of the slider (53) is fixedly connected with a telescopic column (55); the end of the telescopic column (55) away from the slider (53) is fixedly connected with a baffle (54); the baffle (54) is U-shaped; the bottom of the baffle (54) is inclined; the top of the slider (53) is fixedly connected with a telescopic spring (56); the end of the telescopic spring (56) away from the slider (53) is fixedly connected to the bottom of the baffle (54); The telescopic columns (55) are provided in four groups; the telescopic springs (56) are provided in two groups; The stoppers (4) are provided in a plurality of groups; the spacing between the stoppers (4) in each group is consistent; Two groups of the oblique support frames (72) are provided; the oblique support frames (72) are supported in a triangular shape.

2. A large-span hyperbolic daylighting building roof structure according to claim 1, characterized in that: The side wall of the building wall (1) is fixedly connected to a concrete casting base (2); and the bottom of the channel steel track (3) is fixedly connected to the concrete casting base (2).

3. The large-span hyperbolic daylighting building roof structure according to claim 1, characterized in that: The light-collecting grooves (62) are arranged in multiple groups and are arranged at equal intervals.

4. A method for constructing a large-span hyperbolic daylighting building roof, characterized in that: The following steps are involved: S1, construction preparation: first prepare materials, including materials and components, and then start labor organization preparation. First, determine the work flow of each team, measurement team: responsible for on-site measurement and layout; keel team: responsible for keel processing and installation; glass team: responsible for glass gluing and installation; profile making team: responsible for profile installation; electrician team: responsible for temporary power supply maintenance on site; fitter team: responsible for keel installation processing and assembly; welder team: responsible for welding steel keel and connectors; decoration team: responsible for panel and sporadic plate closing installation and sealing and weather-resistant glue caulking; after confirmation, start construction and evaluate and analyze the construction, review the drawings and design documents during the evaluation process, and then carry out the construction of steel structure engineering. Before construction, prepare the process and installation construction organization design according to the requirements of the construction drawings, and prepare a complete and correct construction process flow before construction; S2, track pre-setting: after the preparation work is completed, the building wall area to be constructed is primed, and then concrete is laid to facilitate the subsequent laying of tracks; S3, initial installation: after the concrete is laid, it is poured into a concrete pouring base (2), and after the pouring is completed, the channel steel track (3) is installed on the surface of the concrete pouring base (2); S4, adjustment: installing the moving assembly (5) into the channel steel track (3) to facilitate the sliding of the moving assembly (5), thereby driving the support unit (7) to move, and facilitating the installation of a large-span special-shaped roof; S5, connection: the construction personnel use a crane to place the support unit (7) on the I-shaped steel (52) and connect it; S6, installation of the skylight: install the large-span special-shaped double-sided curved roof (61) onto the support unit (7), and then start installing the glass panel assembly. Before construction, the glass panels need to be inspected and accepted, and then the glass panels are stacked in layers. During construction, the initial installation is first carried out, and after installation, they are adjusted and fixed. Finally, the installation results are checked, and then the glass panel installation is accepted. After the installation is completed, the skylight is tested, and the project is delivered after the test is qualified.