A modular energy storage system grid-connected test and analysis method
Through the battery health test and power parameter adaptability test of the modular energy storage system, combined with the grid-connected operation quality analysis, the deficiencies in the grid-connected test analysis of the modular energy storage system in the existing technology are solved, and the system's performance in the event of grid fluctuations is improved. responsiveness and security.
Patent Information
- Application Number
- CN202410962806.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-07-18
AI Technical Summary
Existing grid-connected test and analysis methods for modular energy storage systems fail to effectively evaluate battery health and adaptability, resulting in potential problems after grid connection that cannot respond as expected when the grid fluctuates or fails, which may lead to a decrease in grid stability or accidents.
A grid-connected test and analysis method for modular energy storage systems is proposed, including battery health test (self-discharge test and capacity deviation test) and power parameter adaptability test. Combined with grid-connected operation quality test, the feasibility and feasibility of grid-connected operation are judged. Identify potential anomalies to ensure the system can respond dynamically when the grid fluctuates.
Through detailed test analysis, the safety and reliability of the grid-connected operation of the modular energy storage system are improved, ensuring that the system can respond accurately when the power grid fluctuates, reducing the risk of potential failures and accidents, and enhancing the accuracy and accuracy of test results. Comprehensiveness.
Smart Images

Figure CN118501604B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of grid-connected testing of energy storage systems, and relates to a modularized grid-connected testing and analysis method for energy storage systems. Background Art
[0002] The modular energy storage system achieves flexible configuration and efficient utilization of the energy storage system by dividing the energy storage system into multiple energy storage batteries that can work independently or be combined and expanded. In practice, the load demand in the power system fluctuates with time, weather and other factors, and the modular energy storage system can respond quickly to these changes, balancing the supply and demand of the power grid by storing and releasing electrical energy. Therefore, the modular energy storage system needs to be connected to the grid.
[0003] The grid connection of modular energy storage system refers to connecting the modular energy storage system to the grid to achieve interconnection and coordinated operation with the grid. In the process of grid connection of modular energy storage system, there may be incompatibility between the energy storage system and the grid or abnormality of the energy storage battery, which may lead to abnormal operation after grid connection. Therefore, grid connection test and analysis of modular energy storage system is of great significance.
[0004] The grid-connected test analysis of modular energy storage systems can be divided into pre-grid-connected analysis and post-grid-connected analysis.
[0005] The battery health and compatibility of the modular energy storage system with the grid before grid connection are important prerequisites for ensuring the stable operation of the system after grid connection. The battery health test of the traditional modular energy storage system usually monitors indicators such as battery capacity after grid connection, but does not associate the battery health test and adaptability test with the grid connection feasibility of the energy storage system before grid connection. This analysis method may cause potential battery problems to be discovered after grid connection, resulting in system performance degradation, and cannot ensure that the energy storage system can respond as expected when the grid fluctuates or fails, which may lead to a decrease in grid stability and even cause serious grid accidents.
[0006] The post-grid operation quality test analysis is a necessary step to ensure the normal operation of the modular energy storage system after grid connection. The traditional modular energy storage system grid connection test usually directly analyzes various monitoring indicators of the modular energy storage system after grid connection, without considering the impact of grid fluctuations on the operation status of the energy storage system. This analysis method reduces the effectiveness and accuracy of the test, and cannot fully evaluate the dynamic response capability and stability of the energy storage system in a complex grid environment, resulting in deviations between the test results and the actual situation, making it difficult to find potential faults, which may lead to safety hazards. Summary of the invention
[0007] In view of this, in order to solve the problems raised in the above background technology, a modular energy storage system grid-connected test and analysis method is now proposed.
[0008] The purpose of the present invention can be achieved through the following technical solutions: A modular energy storage system grid-connected test and analysis method, comprising: S1, performing a battery health test on each battery module constituting the modular energy storage system, the battery health test including a self-discharge test and a capacity deviation test, and at the same time performing a power parameter adaptability test on the modular energy storage system and the target power grid that needs to be connected to the grid.
[0009] S2. Based on the results of the battery health test and the power parameter adaptability test, determine whether the modular energy storage system is allowed to be connected to the grid.
[0010] S3. Connecting the modular energy storage systems that are determined to be allowed to be connected to the target power grid is carried out, and dividing a day into several monitoring periods based on equal intervals.
[0011] S4. Perform a grid-connected operation quality test on the modular energy storage system after grid connection in each monitoring period. The grid-connected operation quality test includes an operation stability quality test and an operation response quality test. Based on the results of the operation quality test, determine whether the modular energy storage system has grid-connected abnormalities in each monitoring period.
[0012] S5. Based on the judgment result of whether the modular energy storage system has grid-connected abnormality in each monitoring period, further identify the specific tendency abnormality direction, the abnormality direction includes operation stability abnormality and operation response abnormality, and identify the suitable grid-connected period at the same time.
[0013] In a preferred embodiment of the present invention, the specific analysis steps of the self-discharge test are as follows: Read the rated charging voltage of the corresponding battery module from the instruction manual of each battery module.
[0014] Each battery module is charged, and the actual voltage of each battery module is collected in real time using a battery tester. When the actual voltage of each battery module is equal to the rated charging voltage, the charging operation is stopped, and the initial capacity of each battery module is collected using the battery tester.
[0015] The self-discharge monitoring end time of each battery module is obtained based on the charging completion time of each battery module and the preset self-discharge monitoring duration, and then each battery module is tested using a battery tester at the end time of the self-discharge monitoring to obtain the corresponding end capacity of each battery module.
[0016] The initial capacity of each battery module , End Capacity And self-discharge monitoring time Substitute into the formula Get the self-discharge rate of each battery module ,in Indicates unit duration.
[0017] In a preferred embodiment of the present invention, the specific analysis process of the capacity deviation test is as follows: the rated charging voltage and rated capacity of the corresponding battery module are read from the instruction manual of each battery module.
[0018] Perform charging operation on each battery module, collect monitoring voltage of each battery module by using battery tester, stop charging when monitoring voltage of each battery module is equal to corresponding rated charging voltage, and collect monitoring capacity of each battery module by using battery tester.
[0019] The capacity deviation of each battery module is obtained based on the monitored capacity and rated capacity of each battery module.
[0020] In a preferred embodiment of the present invention, the specific steps of the power parameter adaptability test are as follows: extracting the operating voltage of the target power grid and the allowable fluctuation percentage range of the operating voltage from the operating instructions of the target power grid, and then analyzing to obtain the allowable voltage fluctuation range of the target power grid.
[0021] A number of collection time points are set based on a preset reference adaptability analysis duration, and at each collection time point, a battery tester is used to collect voltage of the modular energy storage system after the connection is completed to obtain the operating voltage of the modular energy storage system corresponding to each collection time point.
[0022] The operating voltage corresponding to each acquisition time point is compared with the allowable voltage fluctuation range to determine whether voltage anomalies occur.
[0023] The collection time point at which the voltage anomaly occurs is recorded as the abnormal collection time point, and the number of abnormal collection time points and the total number of collection times are statistically obtained, thereby analyzing and obtaining the power parameter adaptability.
[0024] In a preferred embodiment of the present invention, the determination of whether the modular energy storage system is allowed to be connected to the grid is specifically as follows: the self-discharge rate and capacity deviation of each battery module are compared with the preset allowable self-discharge rate and allowable capacity deviation, respectively, and the power parameter adaptability of the modular energy storage system and the target power grid is compared with the preset standard power parameter adaptability, thereby obtaining a determination result of whether the modular energy storage system is allowed to be connected to the grid.
[0025] In a preferred embodiment of the present invention, the specific analysis steps of the operation stability quality test are as follows: the operating frequency of the target power grid, the output voltage and output efficiency of the power output end of the modular energy storage system are collected in real time during each monitoring period.
[0026] The frequency change curve of the target power grid in each monitoring period is plotted with time as the horizontal axis and the operating frequency of the target power grid as the vertical axis. The output voltage change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output voltage of the power output end of the modular energy storage system as the vertical axis. The output efficiency change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output efficiency of the power output end of the modular energy storage system as the vertical axis.
[0027] The frequency change curve of the target power grid corresponding to each monitoring period is evenly distributed to obtain several monitoring points, and the absolute value of the slope of the monitoring point on the change curve is analyzed and compared with the preset allowable monitoring slope to determine whether the operating frequency of the target power grid corresponding to each monitoring point fluctuates.
[0028] The monitoring points where the target power grid operating frequency fluctuates are recorded as frequency fluctuation points, and the horizontal coordinates of each frequency fluctuation point are extracted. Then, based on the time of the horizontal coordinate, the absolute value of the slope of the corresponding point in the output voltage change curve and the output efficiency change curve is obtained, and recorded as the output voltage fluctuation degree and output efficiency fluctuation degree of each frequency fluctuation point.
[0029] The output voltage fluctuation and output efficiency fluctuation of each frequency fluctuation point in each monitoring period are compared, and the maximum output voltage fluctuation and the maximum output efficiency fluctuation are selected as the output voltage fluctuation and the output efficiency fluctuation of the monitoring period.
[0030] The output voltage fluctuation of each monitoring period and output efficiency fluctuation Substitute into the analysis formula Obtain the operational stability of the modular energy storage system in each monitoring period ,in Respectively represent the weights of output voltage fluctuation and output efficiency fluctuation, Represents a natural constant.
[0031] In a preferred embodiment of the present invention, the specific analysis steps of the operation response quality test are as follows: obtaining the actual operating power of the modular energy storage system in each monitoring period in real time, and extracting the operating frequency of the target power grid.
[0032] The operating power change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the operating power as the vertical axis. The operating power change curve of the modular energy storage system in each monitoring period is evenly distributed to obtain a number of collection points, and the absolute value of the slope of each collection point on the operating power change curve is obtained, and then compared with the preset allowable monitoring slope to determine whether power fluctuation occurs at each collection point. If so, it is recorded as a power fluctuation point.
[0033] The frequency fluctuation points are sorted and numbered in chronological order, and the power fluctuation points are sorted and numbered in chronological order, and the frequency fluctuation points are matched with the power fluctuation points according to the numbers.
[0034] The horizontal coordinates of each frequency fluctuation point and each power fluctuation point are extracted to obtain the time of each frequency fluctuation point. The time of each frequency fluctuation point and the time of the corresponding power fluctuation point are calculated to obtain the corresponding operation response time of each frequency fluctuation point.
[0035] The operation response time of each frequency fluctuation point in each monitoring period is compared with the preset ideal response time to obtain the operation response timeliness of the modular energy storage system at each frequency fluctuation point in each monitoring period, and then the average calculation is performed to obtain the operation response timeliness of the modular energy storage system in each monitoring period.
[0036] In a preferred embodiment of the present invention, the determination of whether there is a grid-connected abnormality in the modular energy storage system during each monitoring period is specifically as follows: the operation stability and operation response timeliness of the modular energy storage system during each monitoring period are summed up according to the weights to obtain the grid-connected quality index of the modular energy storage system during each monitoring period.
[0037] The grid-connected quality index of the modular energy storage system in each monitoring period is compared with the pre-set standard grid-connected quality index, and then a judgment result is obtained as to whether there is any grid-connected abnormality in the modular energy storage system in each monitoring period.
[0038] In a preferred embodiment of the present invention, the identification of specific abnormal tendency is as follows: the operation stability and operation response timeliness of the modular energy storage system in each monitoring period are compared with the preset standard operation stability and standard operation response timeliness, respectively, to obtain the abnormal direction in each monitoring period.
[0039] The number of monitoring periods corresponding to each type of abnormal direction is counted, and then the number of monitoring periods corresponding to each type of abnormal direction and the total number of monitoring periods are calculated to obtain the proportion of each type of abnormal direction, and then compared to obtain the specific tendency of abnormal direction.
[0040] In a preferred embodiment of the present invention, the identification of a suitable grid-connected period is specifically as follows: the modular energy storage system grid-connected quality indexes of each monitoring period are compared, and then the monitoring period corresponding to the maximum grid-connected quality index is selected as the suitable grid-connected period.
[0041] Compared with the prior art, the beneficial effects of the present invention are as follows: (1) The present invention performs a self-discharge deviation test and a capacity deviation test on the battery modules of the modular energy storage system before the grid-connected test, and performs a power parameter adaptability test on the system and the power grid. Based on the test results, the feasibility of the grid-connected operation of the modular energy storage system is analyzed. This analysis method can ensure that the modular energy storage system that needs to be connected to the grid meets the requirements, avoids the occurrence of grid-connected failures or accidents caused by abnormalities of the modular energy storage system, and improves the safety and reliability of the system's grid-connected operation.
[0042] (2) The present invention performs an operation stability quality test and an operation response quality test on the modular energy storage system when the power grid frequency fluctuates, and then determines whether there is a grid-connected abnormality based on the test results. This analysis method can more realistically simulate the actual situation of the energy storage system in grid-connected operation through dynamic environment testing, thereby obtaining more accurate and reliable test results. Testing under frequency fluctuations can more easily expose the performance problems and potential faults of the energy storage system in dynamic changes, thereby avoiding serious operating accidents.
[0043] (3) The present invention conducts post-grid connection operation quality tests in different monitoring periods, and then analyzes the grid connection quality index of different monitoring periods based on the test results, and identifies the appropriate grid connection period. This analysis method increases the comprehensiveness of the test results, and can comprehensively and accurately discover potential safety hazards, avoiding the one-sidedness of the test results caused by the test time. At the same time, the analysis of the appropriate grid connection period improves the success rate of the grid connection operation and avoids safety hazards to the power grid operation. BRIEF DESCRIPTION OF THE DRAWINGS
[0044] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.
[0045] Figure 1 It is a schematic diagram of the steps of the method of the present invention. DETAILED DESCRIPTION
[0046] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0047] See also Figure 1As shown, the present invention provides a modular energy storage system grid-connected test and analysis method, comprising the following steps: S1, performing a battery health test on each battery module constituting the modular energy storage system, wherein the battery health test includes a self-discharge test and a capacity deviation test, and at the same time performing a power parameter adaptability test on the modular energy storage system and a target power grid that needs to be grid-connected.
[0048] It should be noted that the reasons for choosing self-discharge test and capacity deviation test as battery health tests are: 1. Self-discharge is the natural loss of battery power due to internal chemical reactions during storage. Through self-discharge test, the remaining power of the battery after long-term storage can be evaluated, so as to understand the storage performance of the battery. This is especially important for modular energy storage battery systems, because energy storage batteries need to be stored at different times and conditions to ensure that they can provide sufficient power when needed. 2. In modular energy storage battery systems, the consistency between battery cells is crucial to the overall performance of the system. The capacity deviation test can evaluate the capacity differences between individual battery cells to ensure that the battery pack can maintain consistent performance output during the charging and discharging process, which helps to improve the efficiency and stability of the system.
[0049] It should be noted that the reason for conducting power parameter compatibility tests on the modular energy storage system and the target power grid to be connected to the grid is that when the modular energy storage system is connected to the grid, it must ensure that its output voltage is consistent with the grid to avoid causing shocks to the grid or affecting the stability of the grid. Through power parameter adaptability tests, it can be verified whether the energy storage system can maintain a voltage and frequency that matches the grid under different operating conditions.
[0050] Preferably, the specific analysis steps of the self-discharge test are as follows: reading the rated charging voltage of the corresponding battery module from the instruction manual of each battery module.
[0051] Each battery module is charged, and the actual voltage of each battery module is collected in real time using a battery tester. When the actual voltage of each battery module is equal to the rated charging voltage, the charging operation is stopped, and the initial capacity of each battery module is collected using the battery tester.
[0052] It should be noted that the purpose of performing the charging operation first when performing the self-discharge test is to ensure that the initial power of all battery modules is the same, and then perform the self-discharge test on different battery modules, which is more reference and comparative.
[0053] The self-discharge monitoring end time of each battery module is obtained based on the charging completion time of each battery module and the preset self-discharge monitoring duration, and then each battery module is tested using a battery tester at the end time of the self-discharge monitoring to obtain the corresponding end capacity of each battery module.
[0054] Exemplarily, the self-discharge monitoring time may be sky.
[0055] The initial capacity of each battery module , End Capacity And self-discharge monitoring time Substitute into the formula Get the self-discharge rate of each battery module ,in Indicates unit duration.
[0056] It should be noted that the self-discharge rate refers to the ability of the battery to maintain the amount of electricity stored in the battery under certain conditions when the battery is in an open circuit state (i.e. no current passes through the battery). The self-discharge rate is usually expressed as a percentage of the battery capacity decrease per unit time (such as month or year).
[0057] For example, for sky.
[0058] Preferably, the specific analysis process of the capacity deviation test is as follows: reading the rated charging voltage and rated capacity of the corresponding battery module from the instruction manual of each battery module.
[0059] Perform charging operation on each battery module, collect monitoring voltage of each battery module by using battery tester, stop charging when monitoring voltage of each battery module is equal to corresponding rated charging voltage, and collect monitoring capacity of each battery module by using battery tester.
[0060] The capacity deviation of each battery module is obtained based on the monitored capacity and rated capacity of each battery module.
[0061] It should be added that the rated capacity of each battery module is calculated by difference with the corresponding monitoring capacity to obtain the capacity deviation of each battery module, and then the capacity deviation of each battery module is calculated by ratio with the rated capacity to obtain the capacity deviation degree of each battery module.
[0062] Preferably, the specific steps of the power parameter adaptability test are as follows: extracting the operating voltage of the target power grid and the allowable fluctuation percentage range of the operating voltage from the operation manual of the target power grid, and then analyzing to obtain the allowable voltage fluctuation range of the target power grid.
[0063] For example, Taking the single-phase power supply voltage as an example, the allowable fluctuation percentage range is , the corresponding allowable voltage fluctuation range is .
[0064] A number of collection time points are set based on a preset reference adaptability analysis duration, and at each collection time point, a battery tester is used to collect voltage of the modular energy storage system after the connection is completed to obtain the operating voltage of the modular energy storage system corresponding to each collection time point.
[0065] Exemplarily, the reference suitability analysis duration is .
[0066] The operating voltage corresponding to each acquisition time point is compared with the allowable voltage fluctuation range to determine whether voltage anomalies occur.
[0067] It should be added that when the operating voltage at a certain collection time point is within the allowable voltage fluctuation range, it is judged that no voltage abnormality occurs; when the operating voltage at a certain collection time point is outside the allowable voltage fluctuation range, it is judged that a voltage abnormality occurs.
[0068] The collection time point at which the voltage anomaly occurs is recorded as the abnormal collection time point, and the number of abnormal collection time points and the total number of collection times are statistically obtained, thereby analyzing and obtaining the power parameter adaptability.
[0069] It should be added that the power parameter adaptability is obtained by performing a ratio calculation between the number of abnormal acquisition time points and the total number of acquisition times, and then performing a difference calculation between 1 and the result of the ratio calculation.
[0070] S2. Based on the results of the battery health test and the power parameter adaptability test, determine whether the modular energy storage system is allowed to be connected to the grid.
[0071] Preferably, the judgment of whether the modular energy storage system is allowed to be connected to the grid is specifically as follows: the self-discharge rate and capacity deviation of each battery module are compared with the preset allowable self-discharge rate and allowable capacity deviation, respectively, and the power parameter adaptability of the modular energy storage system and the target power grid is compared with the preset standard power parameter adaptability, thereby obtaining a judgment result of whether the modular energy storage system is allowed to be connected to the grid.
[0072] For example, the allowable self-discharge rate is , the allowable capacity deviation is , the adaptability of the standard power parameters is .
[0073] It should be added that the self-discharge rates of the battery modules are averaged to obtain the average self-discharge rate, and the capacity deviations of the battery modules are averaged to obtain the average capacity deviation.
[0074] It should be added that the criteria for allowing the modular energy storage system to be connected to the grid are: 1. The average self-discharge rate is less than or equal to the allowed self-discharge rate; 2. The average capacity deviation is less than or equal to the allowed capacity deviation; 3. The power parameter adaptability of the modular energy storage system and the target power grid is greater than or equal to the qualified power parameter adaptability; when the above three conditions are met at the same time, it is judged that the modular energy storage system is allowed to be connected to the grid.
[0075] It should be noted that the present invention performs a self-discharge deviation test and a capacity deviation test on the battery modules of the modular energy storage system before the grid-connected test, and performs a power parameter adaptability test on the system and the power grid. Based on the test results, the feasibility of the grid-connected operation of the modular energy storage system is analyzed. This analysis method can ensure that the modular energy storage system that needs to be grid-connected meets the requirements, avoids the occurrence of grid-connected failures or accidents due to abnormalities of the modular energy storage system, and improves the safety and reliability of the system's grid-connected operation.
[0076] S3. Connecting the modular energy storage systems that are determined to be allowed to be connected to the target power grid is carried out, and dividing a day into several monitoring periods based on equal intervals.
[0077] For example, the interval is The monitoring period can be , , , , , , .
[0078] S4. Perform a grid-connected operation quality test on the modular energy storage system after grid connection in each monitoring period. The grid-connected operation quality test includes an operation stability quality test and an operation response quality test. Based on the results of the operation quality test, determine whether the modular energy storage system has grid-connected abnormalities in each monitoring period.
[0079] It should be noted that the reasons for selecting the operation stability quality test and the operation response quality test as the grid-connected operation quality test are as follows: 1. The stability test mainly analyzes the test load of the system under test to observe whether there are potential problems in the system during operation. This is especially important for the grid-connected operation system, because the grid-connected system needs to interact with the large power grid continuously and stably, and any unstable factors may cause an impact on the power grid; 2. The response quality test mainly focuses on the response speed of the system when receiving grid instructions or grid status changes. For the grid-connected operation system, quickly responding to grid demand is the key to ensuring stable operation of the grid.
[0080] Preferably, the specific analysis steps of the operation stability quality test are as follows: collecting the operating frequency of the target power grid, the output voltage and output efficiency of the power output end of the modular energy storage system in real time during each monitoring period.
[0081] The frequency change curve of the target power grid in each monitoring period is plotted with time as the horizontal axis and the operating frequency of the target power grid as the vertical axis. The output voltage change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output voltage of the power output end of the modular energy storage system as the vertical axis. The output efficiency change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output efficiency of the power output end of the modular energy storage system as the vertical axis.
[0082] The frequency change curve of the target power grid corresponding to each monitoring period is evenly distributed to obtain several monitoring points, and the absolute value of the slope of the monitoring point on the change curve is analyzed and compared with the preset allowable monitoring slope to determine whether the operating frequency of the target power grid corresponding to each monitoring point fluctuates.
[0083] Exemplarily, the monitoring slope is allowed to be .
[0084] It should be added that when the absolute value of the slope of a monitoring point on the frequency change curve is greater than the allowable monitoring slope, it is judged that the target power grid operating frequency corresponding to the monitoring point fluctuates; when the absolute value of the slope of a monitoring point on the frequency change curve is less than or equal to the allowable monitoring slope, it is judged that the target power grid operating frequency corresponding to the monitoring point fluctuates.
[0085] It should be noted that the purpose of judging whether the target grid operating frequency corresponding to each monitoring point fluctuates is to select the monitoring points where frequency fluctuations occur as references for subsequent analysis, which can truly simulate the system operation when grid fluctuations occur.
[0086] The monitoring points where the target power grid operating frequency fluctuates are recorded as frequency fluctuation points, and the horizontal coordinates of each frequency fluctuation point are extracted. Then, based on the time of the horizontal coordinate, the absolute value of the slope of the corresponding point in the output voltage change curve and the output efficiency change curve is obtained, and recorded as the output voltage fluctuation degree and output efficiency fluctuation degree of each frequency fluctuation point.
[0087] The output voltage fluctuation and output efficiency fluctuation of each frequency fluctuation point in each monitoring period are compared, and the maximum output voltage fluctuation and the maximum output efficiency fluctuation are selected as the output voltage fluctuation and the output efficiency fluctuation of the monitoring period.
[0088] It should be noted that the reason for drawing the change curve and then conducting analysis is that the change curve diagram relies on the plane rectangular coordinate system, which can intuitively and continuously display the dynamic change process of data over time or other variables, and can intuitively discover the fluctuations of parameters such as operating frequency, operating voltage, and operating power.
[0089] The output voltage fluctuation of each monitoring period and output efficiency fluctuation Substitute into the analysis formula Obtain the operational stability of the modular energy storage system in each monitoring period ,in Respectively represent the weights of output voltage fluctuation and output efficiency fluctuation, Represents a natural constant.
[0090] For example, .
[0091] It should be noted that the reason for choosing the grid operating frequency for analysis is that the grid frequency often fluctuates. When the active power load of the grid changes and the input power of the generator prime mover cannot be adjusted closely, the generator speed will change, which will cause grid frequency fluctuations. The fluctuation of grid frequency will directly affect the operating efficiency and service life of electrical equipment such as motors and transformers. Analyzing the response and stability of the modular energy storage system based on the operating frequency fluctuation can better reflect the quality of the system's grid connection.
[0092] It should be noted that the reasons for selecting output voltage and output efficiency as factors affecting the operational stability of modular energy storage systems are as follows: 1. In the power system, voltage stability is directly related to the quality of power supply and the safe operation of equipment. As part of the power system, the stability of the output voltage of the modular energy storage system is equally important. A stable output voltage means that the system can continuously and reliably provide the required electrical energy to the load, avoiding equipment damage or performance degradation caused by voltage fluctuations. 2. Output efficiency refers to the ratio of useful work to total work in the process of outputting electrical energy of the energy storage system. High efficiency means that the system can make better use of the input energy and reduce energy loss during conversion and transmission, which not only helps to improve the economy of the system, but also reduces the operating cost of the system.
[0093] Preferably, the specific analysis steps of the operation response quality test are as follows: obtaining the actual operation power of the modular energy storage system in each monitoring period in real time, and extracting the operation frequency of the target power grid.
[0094] It should be noted that during the energy storage process, the energy storage system can provide grid frequency regulation support. When the grid frequency is unstable, the energy storage system can increase or decrease the output power as needed to maintain the stability of the grid frequency. When the grid frequency fluctuates, if the frequency drops, the energy storage system will start the discharge mode, increase the output power, and provide additional active power to the grid to help increase the grid frequency. If the grid frequency rises, the energy storage system will switch to charging mode, reduce the output power (or absorb excess power in the grid) to help reduce the grid frequency.
[0095] The operating power change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the operating power as the vertical axis. The operating power change curve of the modular energy storage system in each monitoring period is evenly distributed to obtain a number of collection points, and the absolute value of the slope of each collection point on the operating power change curve is obtained, and then compared with the preset allowable monitoring slope to determine whether power fluctuation occurs at each collection point. If so, it is recorded as a power fluctuation point.
[0096] It should be added that if the absolute value of the slope of a certain collection point on the operating power change curve is greater than the allowable monitoring slope, it is judged that power fluctuation occurs at the collection point; if the absolute value of the slope of a certain collection point on the operating power change curve is less than or equal to the allowable monitoring slope, it is judged that no power fluctuation occurs at the collection point.
[0097] The frequency fluctuation points are sorted and numbered in chronological order, and the power fluctuation points are sorted and numbered in chronological order, and the frequency fluctuation points are matched with the power fluctuation points according to the numbers.
[0098] The horizontal coordinates of each frequency fluctuation point and each power fluctuation point are extracted to obtain the time of each frequency fluctuation point. The time of each frequency fluctuation point and the time of the corresponding power fluctuation point are calculated to obtain the corresponding operation response time of each frequency fluctuation point.
[0099] The operation response time of each frequency fluctuation point in each monitoring period is compared with the preset ideal response time to obtain the operation response timeliness of the modular energy storage system at each frequency fluctuation point in each monitoring period, and then the average calculation is performed to obtain the operation response timeliness of the modular energy storage system in each monitoring period.
[0100] For example, the ideal response time is .
[0101] It should be added that the operating response time of each frequency fluctuation point Substitute into the analysis formula Obtain the operational response timeliness of the modular energy storage system at each frequency fluctuation point ,in Indicates the ideal response time.
[0102] It should be noted that the ideal response time refers to the fastest response time in actual operation. In practice, the actual response time is longer than the ideal response time.
[0103] Preferably, the determination of whether there is a grid-connected abnormality in the modular energy storage system in each monitoring period is specifically as follows: the operational stability and operational response timeliness of the modular energy storage system in each monitoring period are summed up by weight to obtain a grid-connected quality index of the modular energy storage system in each monitoring period.
[0104] For example, the weights of operation stability and operation response timeliness are .
[0105] It should be noted that the present invention performs operation stability quality tests and operation response quality tests on the modular energy storage system when the power grid frequency fluctuates, and then determines whether there is a grid-connected abnormality based on the test results. This analysis method can more realistically simulate the actual situation of the energy storage system in grid-connected operation through dynamic environment testing, thereby obtaining more accurate and reliable test results. Testing under frequency fluctuations can more easily expose performance problems and potential faults of the energy storage system in dynamic changes, thereby avoiding serious operating accidents.
[0106] The grid-connected quality index of the modular energy storage system in each monitoring period is compared with the pre-set standard grid-connected quality index, and then a judgment result is obtained as to whether there is any grid-connected abnormality in the modular energy storage system in each monitoring period.
[0107] For example, the grid quality index that meets the standards is .
[0108] It should be added that when the grid-connected quality index of the modular energy storage system during a certain monitoring period is greater than or equal to the standard grid-connected quality index, it is judged that there is no grid-connected abnormality in the modular energy storage system during the monitoring period; when the grid-connected quality index of the modular energy storage system during a certain monitoring period is less than the standard grid-connected quality index, it is judged that there is a grid-connected abnormality in the modular energy storage system during the monitoring period.
[0109] S5. Based on the judgment result of whether the modular energy storage system has grid-connected abnormality in each monitoring period, further identify the specific tendency abnormality direction, the abnormality direction includes operation stability abnormality and operation response abnormality, and identify the suitable grid-connected period at the same time.
[0110] Preferably, the identification of specific abnormal tendency is as follows: the operation stability and operation response timeliness of the modular energy storage system in each monitoring period are compared with the preset standard operation stability and standard operation response timeliness, respectively, to obtain the abnormal tendency in each monitoring period.
[0111] For example, the standard operation stability and standard operation response timeliness are respectively .
[0112] It should be added that if the operating stability of the modular energy storage system in a certain monitoring period is less than the standard operating stability, the abnormality of the monitoring period is judged to be an operation stability abnormality; if the operating response timeliness of the modular energy storage system in a certain monitoring period is less than the standard operating response timeliness, the abnormality of the monitoring period is judged to be an operation response abnormality.
[0113] The number of monitoring periods corresponding to each type of abnormal direction is counted, and then the number of monitoring periods corresponding to each type of abnormal direction and the total number of monitoring periods are calculated to obtain the proportion of each type of abnormal direction, and then compared to obtain the specific tendency of abnormal direction.
[0114] It should be noted that if the proportion of operation stability anomalies is greater than the proportion of operation response anomalies, the specific tendency of the anomaly is toward operation stability anomalies; if the proportion of operation stability anomalies is less than the proportion of operation response anomalies, the specific tendency of the anomaly is toward operation response anomalies.
[0115] Preferably, the identification of the suitable grid-connected time period is specifically as follows: the modular energy storage system grid-connected quality indexes of each monitoring period are compared, and then the monitoring period corresponding to the maximum grid-connected quality index is selected as the suitable grid-connected time period.
[0116] It should be noted that the present invention conducts post-grid operation quality tests in different monitoring time periods, and then analyzes the grid quality index of different monitoring time periods based on the test results, and identifies suitable grid-connected time periods. This analysis method increases the comprehensiveness of the test results, can comprehensively and accurately discover potential safety hazards, and avoid the one-sidedness of the test results caused by the test time. At the same time, the analysis of suitable grid-connected time periods improves the success rate of grid-connected operations and avoids safety hazards to power grid operations.
[0117] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined by the present invention, they shall all fall within the protection scope of the present invention.
Claims
1. A modular energy storage system grid-connected test and analysis method, characterized in that: include: S1. Perform a battery health test on each battery module constituting the modular energy storage system, wherein the battery health test includes a self-discharge test and a capacity deviation test, and at the same time, perform a power parameter compatibility test on the modular energy storage system and the target power grid to be connected to the grid; S2. Determine whether to allow the modular energy storage system to be connected to the grid based on the results of the battery health test and the power parameter adaptability test; S3, connecting the modular energy storage system that is determined to be allowed to be connected to the target power grid, and dividing a day into several monitoring periods based on equal intervals; S4. Performing a grid-connected operation quality test on the grid-connected modular energy storage system in each monitoring period, wherein the grid-connected operation quality test includes an operation stability quality test and an operation response quality test, and judging whether the modular energy storage system has grid-connected abnormalities in each monitoring period based on the results of the operation quality test; S5. Based on the judgment result of whether the modular energy storage system has grid-connected abnormality in each monitoring period, further identify the specific tendency abnormality direction, the abnormality direction includes operation stability abnormality and operation response abnormality, and identify the suitable grid-connected period; The specific analysis steps of the self-discharge test are as follows: Read the rated charging voltage of the corresponding battery module from the instruction manual of each battery module; Perform charging operation on each battery module, and use a battery tester to collect the actual voltage of each battery module in real time, stop charging operation when the actual voltage of each battery module is equal to the rated charging voltage, and use the battery tester to collect the initial capacity of each battery module; Obtaining the self-discharge monitoring end time of each battery module based on the charging completion time of each battery module and the preset self-discharge monitoring duration, and then using a battery tester to detect each battery module at the self-discharge monitoring end time to obtain the corresponding end capacity of each battery module; The initial capacity of each battery module , End Capacity And self-discharge monitoring time Substitute into the formula Get the self-discharge rate of each battery module ,in Indicates unit duration; The specific analysis process of the capacity deviation test is as follows: Read the rated charging voltage and rated capacity of the corresponding battery module from the instruction manual of each battery module; Perform charging operation on each battery module, collect monitoring voltage of each battery module by using a battery tester, stop charging when the monitoring voltage of each battery module is equal to the corresponding rated charging voltage, and collect monitoring capacity of each battery module by using the battery tester; Obtaining a capacity deviation of each battery module based on the monitored capacity and rated capacity of each battery module; The specific steps of the power parameter adaptability test are as follows: Extract the operating voltage and the allowable fluctuation percentage range of the operating voltage of the target power grid from the operation manual of the target power grid, and then analyze and obtain the allowable voltage fluctuation range of the target power grid; A number of collection time points are set based on a preset reference adaptability analysis duration, and at each collection time point, a battery tester is used to collect voltage of the connected modular energy storage system to obtain the operating voltage of the modular energy storage system corresponding to each collection time point; Compare the operating voltage corresponding to each acquisition time point with the allowable voltage fluctuation range to determine whether voltage abnormality occurs; The collection time point where the voltage abnormality occurs is recorded as the abnormal collection time point, and the number of abnormal collection time points and the total number of collection times are statistically obtained, thereby analyzing and obtaining the power parameter adaptability; The specific analysis steps of the running stability quality test are as follows: Collect the operating frequency of the target power grid, the output voltage and output efficiency of the modular energy storage system power output terminal in real time during each monitoring period; The frequency change curve of the target power grid in each monitoring period is plotted with time as the horizontal axis and the operating frequency of the target power grid as the vertical axis. The output voltage change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output voltage of the power output end of the modular energy storage system as the vertical axis. The output efficiency change curve of the modular energy storage system in each monitoring period is plotted with time as the horizontal axis and the output efficiency of the power output end of the modular energy storage system as the vertical axis. The frequency change curve of the target power grid corresponding to each monitoring period is evenly distributed to obtain a number of monitoring points, and the absolute value of the slope of the monitoring point on the change curve is analyzed and then compared with the preset allowable monitoring slope to determine whether the operating frequency of the target power grid corresponding to each monitoring point fluctuates; The monitoring points where the target power grid operating frequency is judged to fluctuate are recorded as frequency fluctuation points, the abscissas of the frequency fluctuation points are extracted, and then the absolute values of the slopes of the corresponding points in the output voltage change curve and the output efficiency change curve are obtained based on the time of the abscissas, and recorded as the output voltage fluctuation degree and the output efficiency fluctuation degree of each frequency fluctuation point; The output voltage fluctuation and output efficiency fluctuation of each frequency fluctuation point in each monitoring period are compared, and the maximum output voltage fluctuation and the maximum output efficiency fluctuation are selected as the output voltage fluctuation and the output efficiency fluctuation of the monitoring period; The output voltage fluctuation within each monitoring period and output efficiency fluctuation Substitute into the analysis formula Obtain the operational stability of the modular energy storage system in each monitoring period ,in Respectively represent the weights of output voltage fluctuation and output efficiency fluctuation, represents a natural constant; The specific analysis steps of the operation response quality test are as follows: Obtain the actual operating power of the modular energy storage system in each monitoring period in real time, and extract the operating frequency of the target power grid; The operating power change curve of the modular energy storage system in each monitoring period is drawn with time as the horizontal axis and the operating power as the vertical axis. The operating power change curve of the modular energy storage system in each monitoring period is evenly distributed to obtain a number of collection points, and the absolute value of the slope of each collection point on the operating power change curve is obtained, and then compared with the preset allowable monitoring slope to determine whether power fluctuation occurs at each collection point. If so, it is recorded as a power fluctuation point; The frequency fluctuation points are sorted and numbered in chronological order, and the power fluctuation points are sorted and numbered in chronological order, and the frequency fluctuation points are matched with the power fluctuation points according to the numbers; Extract the horizontal coordinates of each frequency fluctuation point and each power fluctuation point, and then obtain the time of each frequency fluctuation point, and calculate the difference between the time of each frequency fluctuation point and the time of the corresponding power fluctuation point to obtain the corresponding operation response time of each frequency fluctuation point; The operation response time of each frequency fluctuation point in each monitoring period is compared with the preset ideal response time to obtain the operation response timeliness of the modular energy storage system at each frequency fluctuation point in each monitoring period, and then the average calculation is performed to obtain the operation response timeliness of the modular energy storage system in each monitoring period.
2. A modular energy storage system grid-connected test and analysis method according to claim 1, characterized in that: The determination of whether to allow the modular energy storage system to be connected to the grid is specifically as follows: The self-discharge rate and capacity deviation of each battery module are compared with the preset allowable self-discharge rate and allowable capacity deviation, and the power parameter adaptability of the modular energy storage system and the target power grid is compared with the preset standard power parameter adaptability, so as to obtain a judgment result on whether the modular energy storage system is allowed to be connected to the grid.
3. A modular energy storage system grid-connected test and analysis method according to claim 1, characterized in that: The specific method of judging whether the modular energy storage system has a grid-connected anomaly in each monitoring period is as follows: The operational stability and operational response timeliness of the modular energy storage system in each monitoring period are summed up according to the weights to obtain the grid-connected quality index of the modular energy storage system in each monitoring period; The grid-connected quality index of the modular energy storage system in each monitoring period is compared with the pre-set standard grid-connected quality index, and then a judgment result is obtained as to whether there is any grid-connected abnormality in the modular energy storage system in each monitoring period.
4. A modular energy storage system grid-connected test and analysis method according to claim 1, characterized in that: The specific abnormal tendency points to be identified are as follows: Compare the operation stability and operation response timeliness of the modular energy storage system in each monitoring period with the preset standard operation stability and standard operation response timeliness, and then obtain the abnormal direction in each monitoring period; The number of monitoring periods corresponding to each type of abnormal direction is counted, and then the number of monitoring periods corresponding to each type of abnormal direction and the total number of monitoring periods are calculated to obtain the proportion of each type of abnormal direction, and then compared to obtain the specific tendency of abnormal direction.
5. A modular energy storage system grid-connected test and analysis method as claimed in claim 3, characterized in that: The identification of suitable grid connection time period is as follows: The grid-connected quality index of the modular energy storage system in each monitoring period is compared, and then the monitoring period corresponding to the maximum grid-connected quality index is selected as the appropriate grid-connected period.
Citation Information
Patent Citations
An operation maintenance system and method for photovoltaic power generator
KR1020110005368A
Grid-connected solar power generation control system with ESS
KR102436391B1