A method for economic dispatch of power system integrating wind power
By establishing a wind power integration model in the power system, setting stability constraints and using the cross-over algorithm to optimize the dispatch plan, the power system stability problems caused by the uncertainty of wind power are solved and the economic and stable dispatch of the power system after wind power is achieved.
Patent Information
- Application Number
- CN202410963055.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-18
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2044-07-18
AI Technical Summary
The uncertainty of wind power makes it difficult for the power system to maintain stable operation after integrating wind power, and increases the cost of power system dispatching.
A power system economic dispatch method that integrates wind power is adopted. By establishing a wind power integrated power system model, setting stability constraints, dividing strongly stable and non-strongly stable areas, and using a crisscross algorithm based on guidance factors to optimize the dispatch plan to ensure power After integrating wind power, the system can operate stably and reduce dispatch costs.
It achieves stable economic dispatch of the power system after wind power, overcomes the randomness of traditional algorithms, improves calculation efficiency, and ensures that the power system can effectively perform economic and stable control after integrating wind power.
Smart Images

Figure CN118508529B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of economic dispatch of power systems, and more specifically, to an economic dispatch method for a power system integrating wind power. Background Art
[0002] As the world begins to transform its energy system towards a carbon-neutral future, the installed capacity of renewable energy has increased significantly in recent years, becoming an indispensable part of the modern power system. In order to achieve sustainable development and mitigate climate change, new energy technologies have been fully incorporated into the economic dispatch process of the power system. However, intermittent renewable energy is unstable, and when intermittent renewable energy is integrated into the power system, it will affect the stability of the system. Therefore, when integrating intermittent renewable energy into the power system, it is necessary to ensure that the power system can operate reliably.
[0003] As a representative of intermittent renewable energy, wind resources show obvious uncertainty due to the volatility and intermittency of wind speed, which makes wind power unable to be regarded as a constant power source. Due to the uncertainty of wind power, after the integration of wind power in the power system under conventional static constraints, the dynamic interaction brought by the access of wind power will affect the stability of the power system, which will not only make it difficult to ensure the stable operation of the power system, but also increase the cost of power system scheduling. Therefore, how to stably and economically schedule the power system after integrating wind power is an urgent problem that technicians in this field need to solve. Summary of the invention
[0004] In order to overcome the problem in the above-mentioned prior art that directly integrating wind power into the power system not only makes it difficult to ensure the stable operation of the power system, but also increases the dispatching cost of the power system, the present invention provides an economic dispatching method for a power system integrating wind power, thereby improving and optimizing the economic dispatching plan of the power system, so that the power system can be dispatched and operated stably and economically after integrating wind power.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a method for economic dispatching of a power system integrating wind power, comprising the following steps:
[0006] S1: Establishing a wind power integrated power system model:
[0007]
[0008] in, represents the objective function of the conventional scheduling model; Indicates the number of unit scheduling periods; Indicates the total number of units involved in dispatching; Indicates The effective power of each unit; , , Represents the fuel cost factor.
[0009] S2: Input general constraints for the power system model:
[0010] Common constraints include:
[0011] Generator output constraints:
[0012]
[0013] in, Indicates The minimum active power of each unit; Indicates The maximum active power of each unit; Indicates The effective power of each unit;
[0014] Output climbing constraints:
[0015]
[0016]
[0017] in Indicates Output climbing limit of each unit; Indicates Output reduction limit of each unit; Indicates Unit in The effective power at the moment;
[0018] Load balancing constraints:
[0019]
[0020] in, represents the number of load nodes, Indicates The input power of the load.
[0021] S3: Based on the damping ratio function, set stability constraints for the power system model:
[0022] According to the eigenvalues of the state matrix of the closed-loop power system of the wind turbine dynamics, the main modes are selected to calculate the damping ratio.
[0023] The state matrix of the closed-loop power system of wind turbine dynamics is:
[0024]
[0025] in, , , , represents the state space matrix of the power grid; , , represents the state space matrix obtained by integrating all linearized differential equations of the power system; , , , , , , , , represents an element in the admittance matrix of a transmission network including wind turbines;
[0026] The damping ratio greater than 0.03 is used as the threshold for judging whether the system has reached strong stability. The formula for calculating the damping ratio based on the main modes in the eigenvalue of the matrix is:
[0027]
[0028] in, represents the damping ratio; , represents the real and imaginary parts of the main modal eigenvalues.
[0029] S4: Based on the stability constraints, the stability partition strategy of the power system model is obtained, and the multi-objective function under the stability operation conditions of the power system model is constructed based on the stability partition strategy:
[0030] According to the damping ratio, the results of the dispatching scheme are divided into strong stability areas and non-strong stability areas, where the non-strong stability areas include weak stability areas and unstable areas. After determining the strong stability area, the objective function will be constructed in the strong stability area to keep the power system cycle in the strong stability area. The objective function is:
[0031]
[0032] in, represents a non-zero constant used to divide the region; represents the objective function of the conventional scheduling model; Represents the damping ratio.
[0033] S5: Calculate the system stability margin of the original scheduling plan.
[0034] S6: Determine the algorithm exploration scope based on the constraints of the multi-objective function and the system stability margin of the original scheduling solution:
[0035] The particles in the algorithm correspond to the generators in the unit. The exploration range of the algorithm is the power generation range of the generator after constraints. In the subsequent iteration process, the optimal solution will be found within the power generation range of the generator.
[0036] The calculation formula of the algorithm exploration range is as follows:
[0037]
[0038] in, Indicates the unit output of the original dispatch plan; Indicates the specific size of the guide; Indicates The effective power of each unit; Indicates the minimum power of the unit; Indicates the maximum power of the unit; Indicates the unit climb limit; Indicates the unit descent limit.
[0039] S7: Based on power sensitivity, a cross-cutting algorithm based on guidance factor optimization is constructed.
[0040] S8: Use the vertical and horizontal cross algorithm to obtain the multi-objective scheduling results within the algorithm exploration range.
[0041] S9: Update the system stability margin and unit output of the original dispatch plan.
[0042] Modify the power system of the original dispatch plan according to the dispatch results.
[0043] S10: Use the updated dispatching plan to arrange the power generation plan and obtain the corresponding calculated power generation cost.
[0044] Preferably, in step S7, based on the power sensitivity, a cross-cutting algorithm based on the optimization of the guiding factor is constructed, which specifically includes the following steps:
[0045] S71: Initialize the particle swarm number, dimension, horizontal crossing probability, vertical crossing probability, guidance factor and number of iterations.
[0046] S72: Generate a random number between 0 and 1, and confirm the generation method of the offspring particle group according to the frequency of horizontal crossover and vertical crossover. If the random number is greater than the probability of vertical crossover, execute S73 to perform horizontal crossover; if the random number is less than the probability of vertical crossover, execute S76 to perform vertical crossover.
[0047] S73: If crossover is performed, the offspring particle group is generated by the following formula:
[0048]
[0049] in, Represents dimension; , Represents two parent individuals; , Indicates the two sub-individuals produced by horizontal crossover; and Randomly generated from the range 0 to 1; and Randomly generated from the range -1 to 1.
[0050] The power sensitivity is calculated based on the particles and is defined as:
[0051]
[0052] in, For the period Damping coefficients of key modes; For the Unit in The effective power at the moment; , are the real and imaginary parts of the main modal characteristic roots;
[0053] To perform sensitivity guidance:
[0054]
[0055] in, represents the particle before the boot; represents the guided particle; Represents the guiding factor.
[0056] S74: If vertical crossover is performed, the offspring particle group is generated by the following formula:
[0057]
[0058] in, , Representation Dimension and The parent individual; Indicates that the vertical cross is in dimension The sub-individuals produced on Randomly generated from the range 0 to 1.
[0059] S75: Perform the next iteration and determine whether the number of iterations is greater than the maximum number of iterations. If yes, execute S76; if not, execute S72.
[0060] S76: Output the global optimal particle after iteration.
[0061] Compared with the prior art, the beneficial effects of the present invention are as follows: the present scheme provides an economic dispatch method for a power system integrating wind power. The present method proposes a stable partitioning strategy, and obtains a multi-objective function based on the stability partitioning strategy, so that the power system model after integrating wind power can operate stably. After obtaining the algorithm exploration range according to the multi-objective function and the system stability margin of the original dispatching scheme, a vertical and horizontal cross algorithm based on guidance factor optimization is used to obtain the multi-objective dispatch result and update the original dispatching scheme. After introducing the guidance factor, the randomness of the traditional artificial intelligence algorithm can be overcome, the calculation efficiency can be improved, and the multi-objective dispatch result can be the optimal economic dispatching scheme. The dispatching method of the present scheme can effectively realize the economic dispatch and stable control of the power system when dispatching the power system integrating wind power. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] Figure 1 It is a flow chart of a method for economic dispatching of a power system integrating wind power according to the present invention;
[0063] Figure 2 It is a flow chart of a vertical and horizontal cross algorithm in a method for economic dispatching of a power system integrating wind power according to the present invention;
[0064] Figure 3 It is a comparison diagram of the damping ratio before and after the power system of the present invention adopts the stable regulation economic dispatch scheme;
[0065] Figure 4 is a cost comparison diagram of the power system of the present invention before and after adopting the stable regulation economic dispatch scheme;
[0066] Figure 5 It is an iterative effect diagram of the optimization algorithm based on the guiding factor and the stable partitioning strategy of the present invention. DETAILED DESCRIPTION
[0067] The drawings are only for illustrative purposes and cannot be construed as limiting the present invention. To better illustrate the present embodiment, some parts of the drawings may be omitted, enlarged, or reduced, and do not represent the size of the actual product. For those skilled in the art, it is understandable that some well-known structures and their descriptions may be omitted in the drawings. The positional relationships described in the drawings are only for illustrative purposes and cannot be construed as limiting the present invention.
[0068] The same or similar numbers in the drawings of the embodiments of the present invention correspond to the same or similar parts; in the description of the present invention, it should be understood that if the terms "upper", "lower", "left", "right", "long", "short" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, they are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation. Therefore, the terms describing the positional relationship in the drawings are only used for illustrative purposes and cannot be understood as limitations on this patent. For ordinary technicians in this field, the specific meanings of the above terms can be understood according to specific circumstances.
[0069] The technical solution of the present invention is further described in detail below through specific embodiments and in conjunction with the accompanying drawings:
[0070] Example 1
[0071] like Figure 1 An embodiment of a method for economic dispatching of a power system integrating wind power is shown, comprising the following steps:
[0072] S1: Establish a wind power integrated power system model;
[0073] S2: Input conventional constraints to the power system model;
[0074] S3: Setting stability constraints on the power system model based on the damping ratio function;
[0075] S4: Based on the stability constraints, a stability partitioning strategy for the power system model is obtained, and a multi-objective function under the stability operation conditions of the power system model is constructed based on the stability partitioning strategy;
[0076] S5: Calculate the system stability margin of the original scheduling plan;
[0077] S6: Determine the algorithm exploration scope based on the constraints of the multi-objective function and the system stability margin of the original scheduling solution;
[0078] S7: Based on power sensitivity, a cross-cutting algorithm based on guidance factor optimization is constructed;
[0079] S8: Use the vertical and horizontal cross algorithm to obtain the multi-objective scheduling results within the algorithm exploration range;
[0080] S9: Update the system stability margin and unit output of the original dispatch plan;
[0081] S10: Use the updated dispatching plan to arrange the power generation plan and obtain the corresponding calculated power generation cost.
[0082] Beneficial effects of this embodiment: This solution provides an economic dispatch method for a power system that integrates wind power. This method proposes a stability partitioning strategy. Based on the stability partitioning strategy, a multi-objective function is obtained so that the power system model after integrating wind power can operate stably. After the algorithm exploration range is obtained according to the multi-objective function and the system stability margin of the original dispatching scheme, a vertical and horizontal cross algorithm based on guidance factor optimization is used to obtain the multi-objective dispatch result and update the original dispatching scheme. After the guidance factor is introduced, the randomness of the traditional artificial intelligence algorithm can be overcome, the calculation efficiency can be improved, and the multi-objective dispatch result can be the optimal economic dispatching scheme. The dispatching method of this scheme can effectively realize the economic dispatch and stable control of the power system when dispatching the power system that integrates wind power.
[0083] Example 2
[0084] Embodiment 2 of a method for economic dispatch of a power system integrating wind power, based on Embodiment 1, further defines the steps in Embodiment 1.
[0085] Specifically, in S1, the power system model is:
[0086]
[0087] in, represents the objective function of the conventional scheduling model; Indicates the number of unit scheduling periods; Indicates the total number of units participating in the dispatch; Indicates The effective power of each unit; , , Represents the fuel cost factor.
[0088] Specifically, in S2, conventional constraint adjustments include:
[0089] Generator output constraints:
[0090]
[0091] in, Indicates The minimum active power of each unit; Indicates The maximum active power of each unit; Indicates The effective power of each unit;
[0092] Output climbing constraints:
[0093]
[0094]
[0095] in Indicates Output climbing limit of each unit; Indicates Output reduction limit of each unit; Indicates Unit in The effective power at the moment;
[0096] Load balancing constraints:
[0097]
[0098] in, represents the number of load nodes, Indicates The input power of the load.
[0099] Specifically, in S3, the main modes are selected according to the eigenvalues of the state matrix of the closed-loop power system of the wind turbine dynamics to calculate the damping ratio.
[0100] The state matrix of the closed-loop power system of wind turbine dynamics is:
[0101]
[0102] in, , , , represents the state space matrix of the power grid; , , represents the state space matrix obtained by integrating all linearized differential equations of the power system; , , , , , , , , represents an element in the admittance matrix of a transmission network including wind turbines;
[0103] The damping ratio greater than 0.03 is used as the threshold for judging whether the system has reached strong stability. The formula for calculating the damping ratio based on the main modes in the eigenvalue of the matrix is:
[0104]
[0105] in, represents the damping ratio; , represents the real and imaginary parts of the main modal characteristic roots.
[0106] Specifically, in S4, the stability zoning strategy is to divide the results caused by the scheduling scheme into strong stability areas and non-strong stability areas according to the size of the damping ratio. After determining the strong stability area, the objective function will be constructed in the strong stability area to keep the power system period within the strong stability area.
[0107] The objective function is:
[0108]
[0109] in, represents a non-zero constant used to divide the region; represents the objective function of the conventional scheduling model; Represents the damping ratio.
[0110] Specifically, in S6, the particles in the algorithm correspond to the generators in the unit, and the exploration range of the algorithm is the power generation range of the generator after being constrained. In the subsequent iteration process, the optimal solution will be found within the power generation range of the generator. The calculation formula of the algorithm exploration range is as follows:
[0111]
[0112] in, Indicates the unit output of the original dispatch plan; Indicates the specific size of the guide; Indicates The effective power of each unit; Indicates the minimum power of the unit; Indicates the maximum power of the unit; Indicates the unit climb limit; Indicates the unit descent limit.
[0113] Specifically, Figure 2 As shown, in S7, a cross-cutting algorithm based on guidance factor optimization is constructed, including the following steps:
[0114] S71: Initialize the particle swarm number, dimension, horizontal crossing probability, vertical crossing probability, guidance factor and number of iterations;
[0115] S72: Generate a random number between 0 and 1, and determine the generation method of the offspring particle group according to the frequency of horizontal and vertical crossovers.
[0116] If the random number is greater than the probability of vertical crossing, execute S73; if the random number is less than the probability of vertical crossing, execute S74;
[0117] S73: Perform crossover, output the obtained offspring particle swarm, and execute S75:
[0118] The steps for crossover are as follows:
[0119] S731: Generate a descendant particle swarm. The formula for generating a descendant particle swarm is:
[0120]
[0121] in, Represents dimension; , Represents two parent individuals; , Indicates the two sub-individuals produced by horizontal crossover; and Randomly generated from the range 0 to 1; and Randomly generated from the range -1 to 1;
[0122] S732: Calculate power sensitivity. The calculation formula for power sensitivity is:
[0123]
[0124] in, For the period Damping coefficients of key modes; For the Unit in The effective power at the moment; , are the real and imaginary parts of the main modal characteristic roots;
[0125] S733: Sensitivity Guide:
[0126]
[0127] in, represents the particle before the boot; represents the guided particle; Represents the guiding factor.
[0128] S74: Perform vertical crossover, output the obtained offspring particle swarm, and execute S75:
[0129] The formula for generating offspring particle swarm by vertical crossover is as follows:
[0130]
[0131] in, , Representation Dimension and The parent individual; Indicates that the vertical cross is in dimension The sub-individuals produced on Randomly generated from the range 0 to 1.
[0132] S75: perform the next iteration and determine whether the number of iterations is greater than the maximum number of iterations. If yes, execute S76; if not, execute S72;
[0133] S76: End the iteration and output the global optimal particle after the iteration.
[0134] Example 3
[0135] An embodiment of an economic dispatch method for a wind power integrated power system. In this embodiment, the cost and damping ratio before adjustment by the scheme are compared with the cost and damping ratio after adjustment by the scheme based on cases.
[0136] Specifically, Figure 3 As shown in the figure, before the scheme was used for dispatching, the power system had exceeded the stability boundary and was in an unstable state during the three peak hours of electricity consumption in the morning, afternoon and evening. After the scheme was used for dispatching the power system, the power system was in a stable state at any time of the day, and Figure 4 It can be seen that after the dispatching method in this scheme is used to dispatch electricity, only a very small economic cost is sacrificed, but the stability of the power system is maintained throughout the dispatching cycle. Figure 5 It can be seen that when the dispatching method of this scheme is used to dispatch the power system, as the number of iterations increases, the dispatching cost becomes lower and the power system operation tends to be more stable.
[0137] Obviously, the above embodiments of the present invention are merely examples for clearly illustrating the present invention, and are not intended to limit the embodiments of the present invention. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the embodiments here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the claims of the present invention.
Claims
1. A method for economic dispatch of power systems integrating wind power, It is characterized in that The steps include: S1: Establish a wind power integrated power system model; S2: Input general constraints to the power system model; S3: Based on the damping ratio function, stability constraints are set for the power system model; S4: Based on the stability constraints, a stability partitioning strategy for the power system model is obtained, and a multi-objective function under the stability operation conditions of the power system model is constructed based on the stability partitioning strategy; S5: Calculate the system stability margin of the original scheduling plan; S6: Determine the algorithm exploration scope based on the constraints of the multi-objective function and the system stability margin of the original scheduling solution; S7: Based on power sensitivity, a cross-cutting algorithm based on guidance factor optimization is constructed; S8: Use the vertical and horizontal cross algorithm to obtain the multi-objective scheduling results within the algorithm exploration range; S9: Update the system stability margin and unit output of the original dispatch plan; S10: using the updated dispatching scheme to arrange the power generation plan and obtain the corresponding calculated power generation cost; In S3, the main modes are selected according to the eigenvalues of the state matrix of the closed-loop power system of the wind turbine dynamics to calculate the damping ratio. The state matrix of the closed-loop power system of wind turbine dynamics is: in, , , , represents the state space matrix of the power grid; , , represents the state space matrix obtained by integrating all linearized differential equations of the power system; , , , , , , , , represents an element in the admittance matrix of a transmission network including wind turbines; The formula for calculating the damping ratio based on the main modes in the eigenvalue of the matrix is: in, represents the damping ratio; , represents the real and imaginary parts of the main modal characteristic roots; In S3, the damping ratio greater than 0.03 is used as the threshold for judging whether the system has reached strong stability, that is, in, represents the damping ratio; , represents the real and imaginary parts of the main modal characteristic roots; In said S4, the stability partitioning strategy is to divide the results caused by the scheduling scheme into a strong stability region and a non-strong stability region according to the damping ratio; The multi-objective function is: in, represents a non-zero constant used to divide the region; represents the objective function of the conventional scheduling model; Represents the damping ratio.
2. According to the method for economic dispatch of a power system integrating wind power according to claim 1, It is characterized in that In S1, the power system model is: in, represents the objective function of the conventional scheduling model; Indicates the number of unit scheduling periods; Indicates the total number of units participating in the dispatch; Indicates The effective power of each unit; , , Represents the fuel cost factor.
3. According to the method for economic dispatch of a power system integrating wind power as claimed in claim 1, It is characterized in that In said S2, conventional constraint adjustment includes: Generator output constraints: in, Indicates The minimum active power of each unit; Indicates The maximum active power of the unit, Indicates The effective power of each unit; Output climbing constraints: in Indicates Output climbing limit of each unit; Indicates Output reduction limit of each unit; Indicates Unit in The effective power at the moment; Load balancing constraints: in, represents the number of load nodes, Indicates The input power of a load.
4. According to the method for economic dispatch of a power system integrating wind power as claimed in claim 1, It is characterized in that In S6, the calculation formula of the algorithm exploration range is as follows: in, Indicates the unit output of the original dispatch plan; Indicates the specific size of the guide; Indicates The effective power of each unit; Indicates the minimum power of the unit; Indicates the maximum power of the unit; Indicates the unit climb limit; Indicates the unit descent limit.
5. According to the method for economic dispatch of a power system integrating wind power as claimed in claim 1, It is characterized in that In S7, a cross-cutting algorithm based on guidance factor optimization is constructed, including the following steps: S71: Initialize the particle swarm number, dimension, horizontal crossing probability, vertical crossing probability, guidance factor and number of iterations; S72: Generate a random number between 0 and 1, and determine the generation method of the offspring particle group according to the frequency of horizontal and vertical crossovers. If the random number is greater than the probability of vertical crossing, execute S73; if the random number is less than the probability of vertical crossing, execute S74; S73: Perform crossover, output the obtained offspring particle swarm, and execute S75; S74: Perform vertical crossover, output the obtained offspring particle swarm, and execute S75; S75: perform the next iteration and determine whether the number of iterations is greater than the maximum number of iterations. If yes, execute S76; if not, execute S72; S76: End the iteration and output the global optimal particle after the iteration.
6. According to the method for economic dispatch of a power system integrating wind power according to claim 5, It is characterized in that In the above S73, the steps of horizontal crossing are as follows: S731: Generate a descendant particle swarm. The formula for generating a descendant particle swarm is: in, Represents dimension; , Represents two parent individuals; , Indicates the two sub-individuals produced by horizontal crossover; and Randomly generated from the range 0 to 1; and Randomly generated from the range -1 to 1; S732: Calculate power sensitivity. The calculation formula for power sensitivity is: in, For the period Damping coefficients of key modes; For the Unit in The effective power at the moment; , are the real and imaginary parts of the main modal characteristic roots; S733: Sensitivity Guide: in, represents the particle before the boot; represents the guided particle; Represents the guiding factor.
7. According to claim 5, a method for economic dispatching of a power system integrating wind power, It is characterized in that In S4, the formula for generating a descendant particle group by vertical crossover is as follows: in, , Representation Dimension and The parent individual; Indicates that the vertical cross is in dimension The sub-individuals produced on Randomly generated from the range 0 to 1.
Citation Information
Patent Citations
Wind-power-containing electric power system active dispatching method considering small interference stability risk
CN108063461A
Unit combination method considering converter driving stability constraint