A control method for box-type high and low voltage complete switchgear

Through comprehensive testing and evaluation of the mechanical properties, insulation performance and protective functions of box-type high and low voltage complete sets of switchgear, the problem of failure to effectively assess the health of the equipment in the existing technology is solved, and a safer and more reliable power supply is achieved. Breakdown and repair costs are reduced.

CN118523502BActive Publication Date: 2024-10-01QUANZHOU ZHENWEI ELECTRICAL EQUIP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410977358.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-22
Publication Date
2024-10-01
Estimated Expiration
2044-07-22

AI Technical Summary

Technical Problem

The existing monitoring and control methods of box-type high and low voltage complete sets of switchgear fail to comprehensively evaluate the mechanical performance and protection functions, resulting in the inability to effectively predict potential faults, which may cause power supply interruption and safety risks, and fail to initially determine the fault type during automatic reclosing. , which may cause secondary damage to the equipment or personal injury.

Method used

A control method is proposed, including the steps of mechanical performance detection, insulation performance detection, protection function detection, comprehensive performance evaluation, fault analysis and reclosing processing. By obtaining mechanical performance, insulation performance and protection function indicators, the health status of the equipment is analyzed. And decide whether to automatically reclose according to the fault type.

Benefits of technology

It improves the mechanical performance and insulation performance evaluation of equipment, ensures the accuracy of protection functions, reduces mechanical failures and insulation failures, avoids unnecessary reclosing, enhances the continuity and safety of power supply, and reduces maintenance costs and system downtime.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118523502B_ABST
    Figure CN118523502B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of control of box-type high and low voltage complete switchgear, and specifically discloses a control method for box-type high and low voltage complete switchgear. The present invention analyzes the mechanical properties of the switchgear from the action accuracy, mechanical stability and durability of the operating mechanism; analyzes the insulation performance of the switchgear from the insulation resistance, withstand voltage performance and partial discharge; analyzes the protection function of the switchgear from the action thresholds and response time of short-circuit protection, overload protection and ground fault protection, further comprehensively evaluates the performance of the switchgear, and detects the health status of the switchgear from multiple indicators, which is beneficial to improving the operating efficiency of power equipment and enabling power transmission and distribution systems to operate continuously, stably and safely; analyzes the tripping fault type after the switchgear trips, and then performs corresponding reclosing processing, thereby avoiding rash reclosing to cause secondary damage to the equipment or cause personal injury.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of control of box-type high- and low-voltage complete switchgear, and in particular to a control method for box-type high- and low-voltage complete switchgear. Background Art

[0002] With the continuous improvement of my country's economic level, the power industry has developed rapidly. At the same time, the demand for the power industry has gradually increased, which has led to higher requirements for the quality of electrical switches. Among them, the development of high and low voltage complete switchgear towards intelligence is the result of adapting to the development of the times, which can ensure the safe and stable operation of the switch cabinet.

[0003] Box-type high and low voltage switchgear is an electrical equipment that integrates high and low voltage electrical components and control equipment. It is used for power distribution, transmission and control in the power distribution system. It usually includes components such as circuit breakers, contactors, fuses, relays, etc., which can realize remote control and protection of electrical equipment and play a vital role in the power system.

[0004] It is of great significance to reasonably control the box-type high and low voltage switchgear to ensure the normal operation of the power supply equipment.

[0005] There are some shortcomings in the existing monitoring and control methods of box-type high and low voltage complete switchgear: on the one hand, when evaluating the performance of box-type high and low voltage complete switchgear, the existing methods mostly focus on conventional indicators such as electrical performance indicators, temperature indicators, energy consumption indicators, environmental and physical state indicators of the switchgear, and pay less attention to other indicators related to the performance of the switchgear, such as mechanical performance indicators, insulation performance indicators and protection function indicators, etc., which makes the monitoring of the switchgear have loopholes and cannot comprehensively and effectively evaluate the health status of the box-type high and low voltage complete switchgear and predict potential faults, which is not conducive to taking maintenance measures in advance, avoiding power supply interruptions and ensuring the safe and stable operation of the power grid.

[0006] On the other hand, in the existing method, when the box-type high and low voltage complete switch equipment trips, the automatic reclosing device will automatically try to close the switch to restore power supply after a set delay, and then perform fault troubleshooting if the closing is unsuccessful. There is no preliminary judgment of the fault type, such as transient fault and permanent fault, before trying to close the switch, and then decide whether to automatically reclose the switch. If the box-type high and low voltage complete switch equipment trips due to a permanent fault, directly reclosing the switch after tripping may cause secondary damage to the equipment or cause personal injury. Summary of the invention

[0007] In view of the above problems, the present invention proposes a control method for a box-type high and low voltage complete switch equipment. The specific technical scheme is as follows: A control method for a box-type high and low voltage complete switch equipment, comprising the following steps: Step 1, detection and analysis of mechanical properties of the switch equipment: Obtain the mechanical performance indicators of the box-type high and low voltage complete switch equipment, and record them as the mechanical performance indicators of the switch equipment, wherein the mechanical performance indicators include the action accuracy coefficient, mechanical stability coefficient and durability coefficient of the operating mechanism, and analyze the mechanical performance evaluation index of the switch equipment.

[0008] Step 2: Insulation performance test and analysis of switchgear: Obtain insulation performance indicators of switchgear, where insulation performance indicators include insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient, and analyze insulation performance evaluation index of switchgear.

[0009] Step 3: Switchgear protection function detection and analysis: Obtain the switchgear protection function index, where the protection function index includes short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient, and analyze the switchgear protection function evaluation index.

[0010] Step 4: Comprehensive evaluation of switchgear performance: Analyze the comprehensive performance evaluation index of the switchgear based on the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear.

[0011] Step 5. Switchgear tripping fault analysis and reclosing processing: Obtain the electrical parameters of the switchgear when it trips and after the set tripping time, analyze the fault type of the switchgear tripping, where the fault type includes transient fault and permanent fault, and perform corresponding reclosing processing according to the fault type of the switchgear tripping.

[0012] Step 6: Feedback of switchgear monitoring information: Feedback the comprehensive performance evaluation index of the switchgear and the fault type of the switchgear tripping to the remote monitoring center of the switchgear.

[0013] On the basis of the above-mentioned embodiment, the specific analysis process of the step 1 includes: setting the duration of the monitoring period, collecting images of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, obtaining the contact position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, and comparing them with the contact set positions corresponding to the opening and closing actions and closing and opening actions of each operating mechanism of the switch device stored in the database, obtaining the distance between the contact position and the set position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, recording it as the contact position deviation of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, and expressing them as , Indicates The number of the operating mechanism, , Indicates The number of the opening and closing action. , Indicates The number of the closing and opening action. .

[0014] By analyzing the formula Get the action accuracy coefficient of the switchgear operating mechanism ,in Indicates the correction factor of the preset action accuracy coefficient, Respectively represent the number of opening and closing actions and closing and opening and closing actions, Indicates the preset The threshold value of the contact position deviation of an operating mechanism.

[0015] On the basis of the above embodiment, the specific analysis process of step 1 further includes: obtaining the maximum vibration velocity and maximum vibration displacement of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period by means of a micro vibration tester, and recording them as and .

[0016] By analyzing the formula Obtain the mechanical stability factor of the switchgear operating mechanism ,in Indicates the preset mechanical stability coefficient correction factor, Respectively represent the preset The thresholds of vibration velocity and vibration displacement when an operating mechanism is in action.

[0017] Based on the above embodiment, the specific analysis process of step 1 further includes: F1: collecting images of each operating mechanism of the switch device, obtaining the rust area of ​​each operating mechanism of the switch device, and recording it as .

[0018] According to the images of the operating mechanisms of the switchgear, the spatial models of the operating mechanisms of the switchgear are constructed and compared with the standard spatial models of the operating mechanisms of the switchgear stored in the database to obtain the degree of coincidence between the spatial models of the operating mechanisms of the switchgear and their standard spatial models, which is recorded as the shape coincidence of the operating mechanisms of the switchgear and expressed as .

[0019] By analyzing the formula Obtain the degree of wear of each operating mechanism of the switchgear ,in represents a natural constant, Indicates the influence factor of the preset unit corrosion area, Indicates the preset shape matching threshold.

[0020] F2: Obtain the sound waveform of each operating mechanism of the switch device during the monitoring period, and compare it with the ideal sound waveform of each operating mechanism of the switch device stored in the database, and obtain the coincidence degree between the sound waveform of each operating mechanism of the switch device during the monitoring period and the ideal sound waveform, which is recorded as the sound coincidence degree of each operation of each operating mechanism of the switch device during the monitoring period, and calculate the average value to obtain the sound coincidence degree of each operating mechanism of the switch device during the monitoring period, which is recorded as .

[0021] F3: Extract the historical operation log of the switchgear stored in the database, obtain the historical operation cycle number of each operating mechanism of the switchgear, and record it as .

[0022] F4: By analyzing the formula Obtain the durability factor of the switchgear operating mechanism ,in Indicates the preset durability coefficient correction factor, Indicates the preset threshold of action-sound matching. Indicates the preset threshold of the number of historical operation cycles.

[0023] Based on the above embodiment, the specific analysis process of step 1 further includes: calculating the action accuracy coefficient of the switch device operating mechanism , Mechanical stability coefficient and durability coefficient Substitute into the analysis formula Get the mechanical performance evaluation index of the switchgear ,in They represent the weights of the preset action accuracy coefficient, mechanical stability coefficient and durability coefficient respectively. .

[0024] Based on the above embodiment, the specific analysis process of step 2 includes: recording each circuit of the switch device that needs to be tested for insulation as each circuit to be tested, obtaining the insulation resistance between phases and relative to the ground of each circuit to be tested of the switch device through an insulation resistance tester, and recording them as , Indicates The number of the line to be tested, .

[0025] By analyzing the formula Get the insulation resistance compliance coefficient of the switchgear ,in Indicates the preset insulation resistance compliance coefficient correction factor, Respectively represent the switchgear The threshold values ​​of the phase-to-phase insulation resistance and the phase-to-ground insulation resistance of the circuit to be tested.

[0026] On the basis of the above embodiment, the specific analysis process of step 2 also includes: obtaining the voltage level and insulation strength of the switch device at each overvoltage during the monitoring period, extracting the insulation strength corresponding to each overvoltage level of the switch device stored in the database, screening and obtaining the reference insulation strength corresponding to each overvoltage of the switch device during the monitoring period, and recording it as , Indicates The number of overvoltages, .

[0027] By analyzing the formula Get the withstand voltage compliance coefficient of the switchgear ,in Indicates the preset withstand voltage compliance coefficient correction factor, Indicates the number of overvoltages. Indicates the number of switchgears in the monitoring cycle. Dielectric strength during overvoltage.

[0028] Obtain the maximum partial discharge of the switchgear during the monitoring period, substitute it into the preset relationship function between the partial discharge and the partial discharge coefficient, and obtain the partial discharge coefficient of the switchgear, which is recorded as .

[0029] The insulation resistance of the switchgear meets the coefficient , Withstand voltage compliance coefficient and partial discharge coefficient Substitute into the analysis formula Get the insulation performance evaluation index of the switchgear ,in They represent the weights of the preset insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient respectively. .

[0030] Based on the above embodiment, the specific analysis process of step three is: H1: Through the relay protection action records of the switching device stored in the database, the short-circuit current and the time required to disconnect the circuit of each short-circuit protection of the switching device during the monitoring period, the overload current and the time required to disconnect the circuit of each overload protection, and the grounding fault current and the time required to disconnect the circuit of each grounding fault protection are obtained.

[0031] H2: The short-circuit current and the time required to disconnect the circuit of each short-circuit protection of the switchgear during the monitoring period are recorded as , Indicates Secondary short circuit protection number, .

[0032] Extract the action threshold and response time of the short-circuit protection setting of the switch device stored in the database and record them as .

[0033] By analyzing the formula Get the short-circuit protection compliance coefficient of the switching device ,in Indicates the number of short-circuit protection. Indicates the deviation threshold of the preset short-circuit protection action threshold.

[0034] H3: Similarly, according to the analysis method of H2, the overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear are obtained.

[0035] H4: Calculate the weighted average of the short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear to obtain the protection function evaluation index of the switchgear.

[0036] Based on the above embodiment, the specific analysis process of step 4 is: calculating the weighted average value of the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear to obtain the comprehensive performance evaluation index of the switchgear.

[0037] Based on the above embodiment, the specific analysis process of step five is as follows: T1: obtaining electrical parameters when the switch device trips through a fault recorder, and obtaining electrical parameters after the switch device trips for a set time.

[0038] The electrical parameters at the time of tripping and the electrical parameters after the tripping delay corresponding to each transient fault in the history of the switchgear stored in the database are extracted to train the recognition model of transient fault tripping of the switchgear.

[0039] Substitute the electrical parameters of the switch device when it trips and after the set tripping time into the identification model of the switch device's transient fault tripping. If they match, the fault type of the switch device tripping is a transient fault, and T2 is executed. Otherwise, the fault type of the switch device tripping is a permanent fault, and T3 is executed.

[0040] T2: Remote control of automatic reclosing of switchgear.

[0041] T3: Issue an early warning and notify relevant personnel to handle the situation.

[0042] Compared with the prior art, the control method of a box-type high and low voltage complete switchgear described in the present invention has the following beneficial effects: 1. The present invention evaluates the mechanical properties of the switchgear from mechanical performance indicators such as the action accuracy, mechanical stability and durability of the switchgear operating mechanism, which can improve the flexibility and durability of the switchgear operating mechanism, reduce power outages caused by mechanical failures and avoid electrical accidents, ensure the safety of personnel and equipment, and thus improve the continuity and reliability of power supply.

[0043] 2. The present invention evaluates the insulation performance of the switchgear based on insulation performance indicators such as insulation resistance, withstand voltage performance and partial discharge, which can effectively prevent leakage and short circuit between electrical equipment, avoid sudden insulation failures and power outages, reduce maintenance costs and system downtime, and thus maintain high-quality operation of the power grid and ensure users' electricity experience.

[0044] 3. The present invention detects the action thresholds and response times of the short-circuit protection, overload protection and ground fault protection of the switchgear and evaluates the protection function of the switchgear, thereby ensuring that the protection device works accurately, effectively avoiding unnecessary tripping, reducing system disturbances, and maintaining the continuity and stability of the power supply. At the same time, it provides a scientific basis for adjusting protection parameters and optimizing protection configuration, thereby achieving more refined operation and maintenance management.

[0045] 4. The present invention analyzes the fault type of the switch device tripping after the switch device trips, determines whether it is a transient fault or a permanent fault, and performs corresponding reclosing processing according to the fault type of the switch device tripping, thereby avoiding rash reclosing to cause secondary damage to the equipment or personal injury. BRIEF DESCRIPTION OF THE DRAWINGS

[0046] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the accompanying drawings required for describing the embodiments will be briefly introduced below. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other accompanying drawings can be obtained based on these accompanying drawings without paying creative work.

[0047] Figure 1 It is a schematic diagram of the method flow of the present invention. DETAILED DESCRIPTION

[0048] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0049] See also Figure 1 As shown, a control method for a box-type high and low voltage complete switch equipment provided by the present invention includes the following steps: Step 1, detection and analysis of the mechanical performance of the switch equipment: obtaining the mechanical performance indicators of the box-type high and low voltage complete switch equipment, and recording them as the mechanical performance indicators of the switch equipment, wherein the mechanical performance indicators include the action accuracy coefficient, mechanical stability coefficient and durability coefficient of the operating mechanism, and analyzing the mechanical performance evaluation index of the switch equipment.

[0050] As a preferred solution, the specific analysis process of step 1 includes: setting the duration of the monitoring period, collecting images of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, obtaining the contact position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, and comparing with the contact set positions corresponding to the opening and closing actions and closing and opening actions of each operating mechanism of the switch device stored in the database, obtaining the distance between the contact position and the set position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, recording it as the contact position deviation of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period, and expressing it as , Indicates The number of the operating mechanism, , Indicates The number of the opening and closing action. , Indicates The number of the closing and opening action. .

[0051] By analyzing the formula Get the action accuracy coefficient of the switchgear operating mechanism ,in Indicates the correction factor of the preset action accuracy coefficient, Respectively represent the number of opening and closing actions and closing and opening and closing actions, Indicates the preset The threshold value of the contact position deviation of an operating mechanism.

[0052] It should be noted that the operating mechanism of the switchgear includes but is not limited to: circuit breakers, disconnectors, etc.

[0053] As a preferred solution, the specific analysis process of step 1 further includes: obtaining the maximum vibration velocity and maximum vibration displacement of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring period by a micro vibration tester, and recording them as and .

[0054] By analyzing the formula Obtain the mechanical stability factor of the switchgear operating mechanism ,in Indicates the preset mechanical stability coefficient correction factor, Respectively represent the preset The thresholds of vibration velocity and vibration displacement when an operating mechanism is in action.

[0055] As a preferred solution, the specific analysis process of step 1 further includes: F1: collecting images of each operating mechanism of the switch device, obtaining the rust area of ​​each operating mechanism of the switch device, and recording it as .

[0056] According to the images of the operating mechanisms of the switchgear, the spatial models of the operating mechanisms of the switchgear are constructed and compared with the standard spatial models of the operating mechanisms of the switchgear stored in the database to obtain the degree of coincidence between the spatial models of the operating mechanisms of the switchgear and their standard spatial models, which is recorded as the shape coincidence of the operating mechanisms of the switchgear and expressed as .

[0057] By analyzing the formula Obtain the degree of wear of each operating mechanism of the switchgear ,in represents a natural constant, Indicates the influence factor of the preset unit corrosion area, Indicates the preset shape matching threshold.

[0058] F2: Obtain the sound waveform of each operating mechanism of the switch device during the monitoring period, and compare it with the ideal sound waveform of each operating mechanism of the switch device stored in the database, and obtain the coincidence degree between the sound waveform of each operating mechanism of the switch device during the monitoring period and the ideal sound waveform, which is recorded as the sound coincidence degree of each operation of each operating mechanism of the switch device during the monitoring period, and calculate the average value to obtain the sound coincidence degree of each operating mechanism of the switch device during the monitoring period, which is recorded as .

[0059] It should be noted that each action of the operating mechanism includes each opening and closing action and each closing and opening action.

[0060] F3: Extract the historical operation log of the switchgear stored in the database, obtain the historical operation cycle number of each operating mechanism of the switchgear, and record it as .

[0061] F4: By analyzing the formula Obtain the durability factor of the switchgear operating mechanism ,in Indicates the preset durability coefficient correction factor, Indicates the preset threshold of action-sound matching. Indicates the preset threshold of the number of historical operation cycles.

[0062] As a preferred solution, the specific analysis process of step 1 further includes: calculating the action accuracy coefficient of the switch device operating mechanism , Mechanical stability coefficient and durability coefficient Substitute into the analysis formula Get the mechanical performance evaluation index of the switchgear ,in They represent the weights of the preset action accuracy coefficient, mechanical stability coefficient and durability coefficient respectively. .

[0063] In this embodiment, the present invention evaluates the mechanical performance of the switch device from mechanical performance indicators such as the action accuracy, mechanical stability and durability of the switch device operating mechanism, which can improve the flexibility and durability of the switch device operating mechanism, reduce power outages caused by mechanical failures and avoid electrical accidents, ensure the safety of personnel and equipment, and thus improve the continuity and reliability of power supply.

[0064] Step 2: Insulation performance test and analysis of switchgear: Obtain insulation performance indicators of switchgear, where insulation performance indicators include insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient, and analyze insulation performance evaluation index of switchgear.

[0065] As a preferred solution, the specific analysis process of step 2 includes: recording each circuit of the switch device that needs to be tested for insulation as each circuit to be tested, obtaining the insulation resistance between phases and relative to the ground of each circuit to be tested of the switch device through an insulation resistance tester, and recording them as , Indicates The number of the line to be tested, .

[0066] By analyzing the formula Get the insulation resistance compliance coefficient of the switchgear ,in Indicates the preset insulation resistance compliance coefficient correction factor, Respectively represent the switchgear The threshold values ​​of the phase-to-phase insulation resistance and the phase-to-ground insulation resistance of the circuit to be tested.

[0067] It should be noted that the insulation resistance of each circuit to be tested of the switchgear should be measured when the switchgear is powered off and safety is ensured.

[0068] As a preferred solution, the specific analysis process of step 2 further includes: obtaining the voltage level and insulation strength of the switch device at each overvoltage during the monitoring period, extracting the insulation strength corresponding to each overvoltage level of the switch device stored in the database, screening and obtaining the reference insulation strength corresponding to each overvoltage of the switch device during the monitoring period, and recording it as , Indicates The number of overvoltages, .

[0069] By analyzing the formula Get the withstand voltage compliance coefficient of the switchgear ,in Indicates the preset withstand voltage compliance coefficient correction factor, Indicates the number of overvoltages. Indicates the number of switchgears in the monitoring cycle. Dielectric strength during overvoltage.

[0070] Obtain the maximum partial discharge of the switchgear during the monitoring period, substitute it into the preset relationship function between the partial discharge and the partial discharge coefficient, and obtain the partial discharge coefficient of the switchgear, which is recorded as .

[0071] It should be noted that the partial discharge of the switchgear should be within an acceptable range.

[0072] The insulation resistance of the switchgear meets the coefficient , Withstand voltage compliance coefficient and partial discharge coefficient Substitute into the analysis formula Get the insulation performance evaluation index of the switchgear ,in They represent the weights of the preset insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient respectively. .

[0073] In this embodiment, the present invention evaluates the insulation performance of the switchgear from insulation performance indicators such as insulation resistance, withstand voltage performance and partial discharge, which can effectively prevent leakage and short circuit between electrical equipment, avoid sudden insulation failures and power outages, reduce maintenance costs and system downtime, and thus maintain high-quality operation of the power grid and ensure users' electricity experience.

[0074] Step 3: Switchgear protection function detection and analysis: Obtain the switchgear protection function index, where the protection function index includes short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient, and analyze the switchgear protection function evaluation index.

[0075] As a preferred solution, the specific analysis process of step three is: H1: Through the relay protection action records of the switching device stored in the database, obtain the short-circuit current and the time required to disconnect the circuit for each short-circuit protection of the switching device during the monitoring period, the overload current and the time required to disconnect the circuit for each overload protection, and the grounding fault current and the time required to disconnect the circuit for each grounding fault protection.

[0076] H2: The short-circuit current and the time required to disconnect the circuit of each short-circuit protection of the switchgear during the monitoring period are recorded as , Indicates Secondary short circuit protection number, .

[0077] Extract the action threshold and response time of the short-circuit protection setting of the switch device stored in the database and record them as .

[0078] By analyzing the formula Get the short-circuit protection compliance coefficient of the switching device ,in Indicates the number of short-circuit protection. Indicates the deviation threshold of the preset short-circuit protection action threshold.

[0079] H3: Similarly, according to the analysis method of H2, the overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear are obtained.

[0080] H4: Calculate the weighted average of the short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear to obtain the protection function evaluation index of the switchgear.

[0081] It should be noted that the weights of the short-circuit protection compliance coefficient, the overload protection compliance coefficient and the ground fault protection compliance coefficient are set values, and the cumulative sum is 1.

[0082] In this embodiment, the present invention evaluates the protection function of the switching device by detecting the action thresholds and response times of the short-circuit protection, overload protection and ground fault protection of the switching device, thereby ensuring that the protection device works accurately and correctly, effectively avoiding unnecessary tripping, reducing system disturbances, and maintaining the continuity and stability of the power supply. At the same time, it provides a scientific basis for adjusting protection parameters and optimizing protection configuration, thereby achieving more refined operation and maintenance management.

[0083] Step 4: Comprehensive evaluation of switchgear performance: Analyze the comprehensive performance evaluation index of the switchgear based on the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear.

[0084] As a preferred solution, the specific analysis process of step four is: calculating the weighted average of the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear to obtain the comprehensive performance evaluation index of the switchgear.

[0085] It should be noted that the weights of the mechanical property evaluation index, the insulation performance evaluation index and the protection function evaluation index are set values, and the cumulative sum is 1.

[0086] Step 5. Switchgear tripping fault analysis and reclosing processing: Obtain the electrical parameters of the switchgear when it trips and after the set tripping time, analyze the fault type of the switchgear tripping, where the fault type includes transient fault and permanent fault, and perform corresponding reclosing processing according to the fault type of the switchgear tripping.

[0087] As a preferred solution, the specific analysis process of step five is as follows: T1: obtaining electrical parameters of the switch device when it trips through a fault recorder, and obtaining electrical parameters of the switch device after it trips for a set time.

[0088] It should be noted that electrical parameters include but are not limited to voltage and current.

[0089] The electrical parameters at the time of tripping and the electrical parameters after the tripping delay corresponding to each transient fault in the history of the switchgear stored in the database are extracted to train the recognition model of transient fault tripping of the switchgear.

[0090] Substitute the electrical parameters of the switch device when it trips and after the set tripping time into the identification model of the switch device's transient fault tripping. If they match, the fault type of the switch device tripping is a transient fault, and T2 is executed. Otherwise, the fault type of the switch device tripping is a permanent fault, and T3 is executed.

[0091] T2: Remote control of automatic reclosing of switchgear.

[0092] T3: Issue an early warning and notify relevant personnel to handle the situation.

[0093] In this embodiment, the present invention analyzes the fault type of the switch device tripping after the switch device trips, determines whether it is a transient fault or a permanent fault, and performs corresponding reclosing processing according to the fault type of the switch device tripping, thereby avoiding rash reclosing to cause secondary damage to the equipment or personal injury.

[0094] Step 6: Feedback of switchgear monitoring information: Feedback the comprehensive performance evaluation index of the switchgear and the fault type of the switchgear tripping to the remote monitoring center of the switchgear.

[0095] The above contents are merely examples and explanations of the concept of the present invention. Those skilled in the art may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the concept of the invention or exceed the scope defined by the present invention, they shall all fall within the protection scope of the present invention.

Claims

1. A control method for a box-type high and low voltage complete switchgear, characterized in that: The steps include: Step 1: Mechanical performance test and analysis of switchgear: Obtain the mechanical performance index of box-type high and low voltage complete switchgear, record it as the mechanical performance index of the switchgear, where the mechanical performance index includes the action accuracy coefficient, mechanical stability coefficient and durability coefficient of the operating mechanism, and analyze the mechanical performance evaluation index of the switchgear; Step 2: Insulation performance test and analysis of switchgear: Obtain insulation performance indicators of switchgear, where insulation performance indicators include insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient, and analyze insulation performance evaluation index of switchgear; Step 3: Switchgear protection function detection and analysis: Obtain the switchgear protection function index, where the protection function index includes short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient, and analyze the switchgear protection function evaluation index; Step 4: Comprehensive evaluation of switchgear performance: Analyze the comprehensive performance evaluation index of the switchgear based on the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear; Step 5: Switchgear tripping fault analysis and reclosing processing: obtain electrical parameters when the switchgear trips and after the tripping set time, analyze the fault type of the switchgear tripping, where the fault type includes transient fault and permanent fault, and perform corresponding reclosing processing according to the fault type of the switchgear tripping; Step 6: Feedback of switchgear monitoring information: Feedback the comprehensive performance evaluation index of the switchgear and the fault type of the switchgear tripping to the remote monitoring center of the switchgear; The specific analysis process of step 1 includes: The duration of the monitoring cycle is set, and images of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring cycle are collected, and the contact position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring cycle is obtained, and compared with the contact setting position corresponding to the opening and closing action and closing and opening action of each operating mechanism of the switch device stored in the database, and the distance between the contact position and the set position of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring cycle is obtained, which is recorded as the contact position deviation of each opening and closing action and each closing and opening action of each operating mechanism of the switch device during the monitoring cycle, and is expressed as , Indicates The number of the operating mechanism, , Indicates The number of the opening and closing action. , Indicates The number of the closing and opening action. ; By analyzing the formula Get the action accuracy coefficient of the switchgear operating mechanism ,in Indicates the correction factor of the preset action accuracy coefficient, Respectively represent the number of opening and closing actions and closing and opening and closing actions, Indicates the preset The threshold value of the contact position deviation of each operating mechanism; The specific analysis process of step 1 also includes: The maximum vibration velocity and maximum vibration displacement of each opening and closing action and each closing and opening action of each operating mechanism of the switchgear during the monitoring period are obtained by a micro vibration tester, and are recorded as and ; By analyzing the formula Obtain the mechanical stability factor of the switchgear operating mechanism ,in Indicates the preset mechanical stability coefficient correction factor, Respectively represent the preset The thresholds of vibration velocity and vibration displacement when each operating mechanism is in action; The specific analysis process of step 1 also includes: F1: Collect images of each operating mechanism of the switchgear and obtain the corrosion area of ​​each operating mechanism of the switchgear, which is recorded as ; According to the images of the operating mechanisms of the switchgear, the spatial models of the operating mechanisms of the switchgear are constructed and compared with the standard spatial models of the operating mechanisms of the switchgear stored in the database to obtain the degree of coincidence between the spatial models of the operating mechanisms of the switchgear and their standard spatial models, which is recorded as the shape coincidence of the operating mechanisms of the switchgear and expressed as ; By analyzing the formula Obtain the degree of wear of each operating mechanism of the switchgear ,in represents a natural constant, Indicates the influence factor of the preset unit corrosion area, Indicates the preset shape matching threshold; F2: Obtain the sound waveform of each operating mechanism of the switch device during the monitoring period, and compare it with the ideal sound waveform of each operating mechanism of the switch device stored in the database, and obtain the coincidence degree between the sound waveform of each operating mechanism of the switch device during the monitoring period and the ideal sound waveform, which is recorded as the sound coincidence degree of each operation of each operating mechanism of the switch device during the monitoring period, and calculate the average value to obtain the sound coincidence degree of each operating mechanism of the switch device during the monitoring period, which is recorded as ; F3: Extract the historical operation log of the switchgear stored in the database, obtain the historical operation cycle number of each operating mechanism of the switchgear, and record it as ; F4: By analyzing the formula Obtain the durability factor of the switchgear operating mechanism ,in Indicates the preset durability coefficient correction factor, Indicates the preset threshold of action-sound matching. Indicates the threshold value of the preset number of historical operation cycles; The specific analysis process of step 2 includes: Each circuit of the switchgear that needs to be tested for insulation is recorded as each circuit to be tested. The insulation resistance between phases and relative to the ground of each circuit to be tested of the switchgear is obtained by an insulation resistance tester and recorded as , Indicates The number of the line to be tested, ; By analyzing the formula Get the insulation resistance compliance coefficient of the switchgear ,in Indicates the preset insulation resistance compliance coefficient correction factor, Respectively represent the switchgear The threshold values ​​of the phase-to-phase insulation resistance and the phase-to-ground insulation resistance of the circuit to be tested; The specific analysis process of step 2 also includes: Obtain the voltage level and insulation strength of each overvoltage of the switchgear during the monitoring period, extract the insulation strength corresponding to each overvoltage level of the switchgear stored in the database, and screen out the reference insulation strength corresponding to each overvoltage of the switchgear during the monitoring period, which is recorded as , Indicates The number of overvoltages, ; By analyzing the formula Get the withstand voltage compliance coefficient of the switchgear ,in Indicates the preset withstand voltage compliance coefficient correction factor, Indicates the number of overvoltages. Indicates the number of switchgears in the monitoring cycle. Dielectric strength at the first overvoltage; Obtain the maximum partial discharge of the switchgear during the monitoring period, substitute it into the preset relationship function between the partial discharge and the partial discharge coefficient, and obtain the partial discharge coefficient of the switchgear, which is recorded as ; The insulation resistance of the switchgear meets the coefficient , Withstand voltage compliance coefficient and partial discharge coefficient Substitute into the analysis formula Get the insulation performance evaluation index of the switchgear ,in They represent the weights of the preset insulation resistance compliance coefficient, withstand voltage compliance coefficient and partial discharge coefficient respectively. ; The specific analysis process of step three is as follows: H1: Through the relay protection action records of the switchgear stored in the database, the short-circuit current and the time required to disconnect the circuit of each short-circuit protection of the switchgear within the monitoring period, the overload current and the time required to disconnect the circuit of each overload protection, and the grounding fault current and the time required to disconnect the circuit of each grounding fault protection are obtained; H2: The short-circuit current and the time required to disconnect the circuit of each short-circuit protection of the switchgear during the monitoring period are recorded as , Indicates Secondary short circuit protection number, ; Extract the action threshold and response time of the short-circuit protection setting of the switch device stored in the database and record them as ; By analyzing the formula Get the short-circuit protection compliance coefficient of the switching device ,in Indicates the number of short circuit protection times. Indicates the deviation threshold of the preset short-circuit protection action threshold; H3: Similarly, according to the analysis method of H2, the overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear are obtained; H4: Calculate the weighted average of the short-circuit protection compliance coefficient, overload protection compliance coefficient and ground fault protection compliance coefficient of the switchgear to obtain the protection function evaluation index of the switchgear.

2. A control method for a box-type high and low voltage complete switchgear according to claim 1, characterized in that: The specific analysis process of step 1 also includes: The action accuracy coefficient of the switchgear operating mechanism , Mechanical stability coefficient and durability coefficient Substitute into the analysis formula Get the mechanical performance evaluation index of the switchgear ,in They represent the weights of the preset action accuracy coefficient, mechanical stability coefficient and durability coefficient respectively. .

3. The control method of a box-type high and low voltage complete switchgear according to claim 1 is characterized in that: The specific analysis process of step 4 is as follows: The weighted average value of the mechanical performance evaluation index, insulation performance evaluation index and protection function evaluation index of the switchgear is calculated to obtain the comprehensive performance evaluation index of the switchgear.

4. The control method of a box-type high and low voltage complete switchgear according to claim 1 is characterized in that: The specific analysis process of step 5 is as follows: T1: Obtain the electrical parameters of the switch device when it trips through the fault recorder, and obtain the electrical parameters of the switch device after the set time of tripping; Extracting the electrical parameters at the time of tripping and the electrical parameters after the tripping delay corresponding to each transient fault in the history of the switchgear stored in the database, and training the recognition model of the transient fault tripping of the switchgear; Substitute the electrical parameters of the switch device when it trips and after the set tripping time into the identification model of the instantaneous fault tripping of the switch device. If they match, the fault type of the switch device tripping is an instantaneous fault, and T2 is executed. Otherwise, the fault type of the switch device tripping is a permanent fault, and T3 is executed. T2: remote control switchgear automatic reclosing; T3: Issue an early warning and notify relevant personnel to handle the situation.