A method and system for monitoring long-distance power transmission status

By calculating the influencing factors of wire sag and identifying the status of wire sag, we solve the problem of fault monitoring of long-distance power transmission lines, achieve accurate monitoring and early warning of power transmission lines, and ensure the stability and safety of power transmission.

CN118554644BActive Publication Date: 2024-10-22ZHANGYE POWER SUPPLY COMPANY OF STATE GRID GANSU ELECTRIC POWER
View PDF 7 Cites 0 Cited by

Patent Information

Application Number
CN202411019824.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-07-29
Publication Date
2024-10-22
Estimated Expiration
2044-07-29

AI Technical Summary

Technical Problem

In the existing technology, due to the long distance of power transmission, if a certain transmission node fails, it cannot be monitored in time, resulting in a decline in power quality, and may even cause a failure of the entire transmission line.

Method used

By obtaining the dynamic parameters of the monitoring sub-unit, calculating the influencing factors of wire sag, identifying the wire sag status, generating normal operation or verification signals, identifying the wire sag status of adjacent monitoring sub-units, and forming an overall power transmission line status monitoring. Generate warning signals to warn of abnormalities.

Benefits of technology

It achieves accurate status monitoring of long-distance power transmission lines, improves monitoring reliability, promptly identifies and warns potential faults, and ensures the stability and safety of power transmission.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118554644B_ABST
    Figure CN118554644B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of power transmission status monitoring, and in particular to a method and system for monitoring the status of long-distance power transmission. The method processes the temperature, wind speed and wire gravity of the environment in which a monitoring subunit is located, obtains the influence factor of the wire sag of the monitoring subunit, combines the influence factor of the wire sag of the monitoring subunit with the wire arc length of the monitoring subunit and the wire radius of the monitoring subunit, thereby obtaining the actual wire sag of the monitoring subunit. The actual wire sag of the monitoring subunit is then compared with the preset wire sag of the monitoring subunit to complete the monitoring of the wire sag status of the monitoring subunit. Combined with the influence factor of the wire sag, the management terminal can more accurately monitor the wire sag status of the monitoring subunit.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of power transmission status monitoring, and in particular to a method and system for monitoring the status of long-distance power transmission. Background Art

[0002] During the power transmission process, the electric energy generated by the power station needs to be stepped up by the transformer, then sent to the nearby substation through the transmission line, and then transformed again before being transmitted to the user end. During this process, the dispatching center will dispatch and control the power according to the operation of the power grid to ensure efficient, safe and stable power transmission.

[0003] Since the distance of power transmission is long, if a transmission node fails and cannot be monitored in time, the quality of the entire power will be reduced. In serious cases, it may even cause the failure of the entire transmission line. Therefore, it is very important to monitor the status of wires during long-distance power transmission. Based on this, the present invention proposes a method and system for monitoring the status of long-distance power transmission. Summary of the invention

[0004] In order to make up for the shortcomings of the existing technology and solve the problem that due to the long distance of power transmission, if a transmission node fails and cannot be monitored in time, it will lead to the decline of the overall power quality. In serious cases, it may even cause the failure of the entire transmission line.

[0005] The technical solution adopted by the present invention to solve its technical problem is:

[0006] A method for monitoring the state of long-distance power transmission comprises the following steps:

[0007] Step 1: obtaining dynamic parameters of the monitoring subunit, and monitoring the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit;

[0008] During the power transmission process, adjacent power towers and the wires between adjacent power towers together constitute a monitoring subunit;

[0009] Step 2: Identify the wire sag of the monitoring subunit obtained by monitoring, and obtain a normal operation signal of the monitoring subunit and a monitoring subunit operation verification signal;

[0010] If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0011] If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated;

[0012] Step three: record the monitoring subunit corresponding to the monitoring subunit operation verification signal as the verification subunit, identify the sag of the wires of the monitoring subunits adjacent to the verification subunit, and complete the monitoring and identification of the overall power transmission line status based on the sag status of the wires of the monitoring subunits adjacent to the verification subunit.

[0013] As a further solution of the present invention: in step 1, the acquisition process of the wire sag of the monitoring subunit is:

[0014] By formula The wire sag LR of the monitoring subunit is calculated, where L represents the span between two pillars, that is, the distance between two suspension points of adjacent wire towers; w represents the unit length weight of the line, that is, the weight per meter of wire between adjacent wire towers; T represents the tension of the line, that is, the tension on the wire between adjacent wire towers; and k is the influencing factor of wire sag.

[0015] As a further solution of the present invention: the process of obtaining the influence factor of wire sag is:

[0016] Get the temperature value in the monitoring subunit, and record the temperature value of the monitoring subunit as Jwt;

[0017] Obtain the weight of the wires in the monitoring subunit, and record the weight of the wires in the monitoring subunit as Jzt;

[0018] Obtain the wind speed of the wires in the monitoring subunit, and mark the wind speed in the monitoring subunit as Jft;

[0019] That is, through the formula Calculate the influence factor of wire sag , where f1 and f2 are preset proportional coefficients, and wt is the minimum impact temperature on the thermal expansion and contraction of the wire caused by temperature changes.

[0020] As a further solution of the present invention: In step 2, the process of acquiring the running status signal of the monitoring subunit is:

[0021] If the wire sag LR of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0022] If the wire sag LR of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated.

[0023] As a further solution of the present invention: in step 3, the sag of the electric wires of the monitoring subunits adjacent to the verification subunit is obtained;

[0024] If the wire sags of two adjacent monitoring sub-units are both within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as an independent abnormal unit;

[0025] The status of the wires in the independent abnormal unit is identified to check whether foreign objects are hanging on the wires or the status of the anti-vibration devices connecting the wires on the two wire towers in the independent abnormal unit is identified.

[0026] As a further solution of the present invention: in step 3, the sag of the electric wires of the monitoring subunits adjacent to the verification subunit is obtained;

[0027] If the wire sags of two adjacent monitoring sub-units are not within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as a continuous abnormal unit, and the monitoring sub-units on both sides are recorded as abnormal edge units;

[0028] The continuous abnormal unit and the abnormal adjacent units on both sides are recorded as a continuous abnormal unit group;

[0029] The deviation value of the electric wire sag of the continuous abnormal unit compared with the preset range requirement of the electric wire sag of the monitoring subunit is marked as the measured difference value of the continuous abnormal unit;

[0030] The deviation value of the wire sag of the abnormal adjacent units on both sides compared with the preset range requirement of the wire sag of the monitoring subunit is marked as the measured difference value of the abnormal adjacent unit;

[0031] The measured difference of the continuous abnormal unit is multiplied by the preset warning coefficient to obtain the warning value of the continuous abnormal unit;

[0032] The measured difference value of the abnormal edge unit is multiplied by the preset warning coefficient to obtain the warning value of the abnormal edge unit;

[0033] The warning value of the continuous abnormal unit is summed with the warning values ​​of the abnormal adjacent units on both sides to obtain the warning value of the continuous abnormal unit group.

[0034] As a further solution of the present invention: the warning value of the continuous abnormal unit group is marked as YJ, and a first limit value YJ1 of the warning value threshold of the continuous abnormal unit group and a second limit value YJ2 of the warning value threshold of the continuous abnormal unit group are preset, wherein YJ1 <YJ2;

[0035] If YJ<YJ1, the sag deviation of the wires in the continuous abnormal unit group is low, and a first-level warning signal is generated;

[0036] If YJ1≤YJ<YJ2, the sag deviation of the wires in the continuous abnormal unit group is moderate, and a secondary warning signal is generated;

[0037] If YJ ≥ YJ2, the sag deviation of the wires in the continuous abnormal unit group is high, and a third-level warning signal is generated.

[0038] As a further solution of the present invention: the warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal in the power transmission line are obtained and marked as Yti;

[0039] Obtain the warning values ​​of all continuous abnormal unit groups belonging to the second-level warning signal in the power transmission line and mark them as Rtm;

[0040] The warning values ​​of all continuous abnormal unit groups belonging to the third-level warning signal in the power transmission line are obtained and marked as Stn;

[0041] Quantify and calculate the obtained warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal, the warning values ​​of the continuous abnormal unit groups belonging to the second-level warning signal, and the warning values ​​of the continuous abnormal unit groups belonging to the third-level warning signal;

[0042] That is, through the formula The power transmission line bus state warning value XZ is calculated, where: is the linear anomaly factor;

[0043] If the bus state warning value of the power transmission line exceeds the maximum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is extremely poor and the power transmission risk is high;

[0044] If the bus state warning value of the power transmission line is within the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is poor and the power transmission risk is moderate;

[0045] If the bus state warning value of the power transmission line is less than the minimum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is general and the power transmission risk is small.

[0046] As a further solution of the present invention: all continuous abnormal unit groups in the power transmission line are processed, the wire length of each continuous abnormal unit group is obtained respectively, the wire length of all continuous abnormal unit groups is summed up, and the total abnormal value of the wire length of all continuous abnormal unit groups is obtained;

[0047] The line length anomaly factor is obtained by calculating the ratio of the total value of the abnormal length of the electric wire to the total length of the power transmission line.

[0048] As another embodiment of the present invention: a long-distance power transmission status monitoring system includes:

[0049] A wire sag monitoring module, the wire sag monitoring module is used to obtain dynamic parameters of the monitoring subunit, and monitor the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit;

[0050] And transmit the wire sag of the monitoring sub-unit to the cloud management and control platform;

[0051] A status analysis module, which is used to obtain the wire sag of the monitoring subunit of the cloud management and control platform, identify the wire sag of the monitoring subunit obtained by monitoring, and obtain a normal operation signal of the monitoring subunit and a monitoring subunit operation verification signal;

[0052] If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0053] If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated;

[0054] And transmit the status signal of the monitoring subunit to the cloud management and control platform;

[0055] A decision-making monitoring module is used to obtain the operating status signal of the monitoring subunit of the cloud management and control platform, record the monitoring subunit corresponding to the operating verification signal of the monitoring subunit as the verification subunit, identify the sag of the wires of the monitoring subunits adjacent to the verification subunit, and complete the monitoring of the overall power transmission line status based on the sag status of the wires of the monitoring subunits adjacent to the verification subunit.

[0056] Beneficial effects of the present invention:

[0057] The present invention processes the temperature, wind speed and wire gravity of the environment in which the monitoring subunit is located to obtain the influence factor of the wire sag of the monitoring subunit, and based on the influence factor of the wire sag of the monitoring subunit, obtains the actual wire sag of the monitoring subunit, and then compares the actual wire sag of the monitoring subunit with the preset wire sag of the monitoring subunit to complete the monitoring of the wire sag state of the monitoring subunit. Combined with the influence factor of the wire sag, the management terminal can more accurately monitor the wire sag state of the monitoring subunit.

[0058] The present invention identifies the sag of the electric wires of the adjacent monitoring subunits of the verification subunit. If the sag of the electric wires of the two adjacent monitoring subunits is not within the preset range of the sag of the electric wires of the monitoring subunits, the verification subunit is recorded as a continuous abnormal unit, the monitoring subunits on both sides are recorded as abnormal adjacent units, the continuous abnormal unit and the abnormal adjacent units on both sides are recorded together as a continuous abnormal unit group, based on the early warning value of the continuous abnormal unit group, the warning level of the continuous abnormal unit group is identified, and the early warning value of the continuous abnormal unit group corresponding to different warning level signals and the abnormal factor of the power transmission line are combined to monitor the overall operation state of the power transmission line, thereby completing the monitoring of the power transmission line from the monitoring subunit to the overall power transmission line, with high reliability. BRIEF DESCRIPTION OF THE DRAWINGS

[0059] The present invention will be further described below in conjunction with the accompanying drawings.

[0060] Figure 1 This is a flow chart of a method for monitoring long-distance transmission of renewable energy power generation according to an embodiment of the present invention;

[0061] Figure 2 It is a flowchart of a new energy power generation long-distance transmission monitoring system according to an embodiment of the present invention. DETAILED DESCRIPTION

[0062] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0063] In the prior art, due to the long distance of power transmission, if a certain transmission node fails and cannot be monitored in time, the quality of the entire power will be reduced. In severe cases, it may even cause the failure of the entire transmission line. Therefore, it is very important to monitor the status of the wires during the transmission of long-distance power. The present invention proposes a method and system for monitoring the status of long-distance power transmission. By processing the temperature, wind speed and wire gravity of the environment in which the monitoring subunit is located, the influence factor of the wire sag of the monitoring subunit is obtained, and the influence factor of the wire sag of the monitoring subunit is combined with the wire arc length of the monitoring subunit and the wire radius of the monitoring subunit to obtain the actual wire sag of the monitoring subunit. The actual wire sag of the monitoring subunit is compared with the preset wire sag of the monitoring subunit to complete the monitoring of the wire sag status of the monitoring subunit. Combined with the influence factor of the wire sag, the management terminal can more accurately monitor the wire sag status of the monitoring subunit. The specific implementation plan is as follows: Example 1

[0064] See also Figure 1 As shown, the present invention is a method and system for monitoring the state of long-distance power transmission, comprising the following steps:

[0065] Step 1: obtaining dynamic parameters of the monitoring subunit, and monitoring the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit;

[0066] Step 2: Identify the wire sag of the monitoring subunit obtained by monitoring, and obtain a normal operation signal of the monitoring subunit and a monitoring subunit operation verification signal;

[0067] If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0068] If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated;

[0069] Step three: record the monitoring subunit corresponding to the monitoring subunit operation verification signal as the verification subunit, identify the sag of the wires of the monitoring subunits adjacent to the verification subunit, and complete the monitoring of the overall power transmission line status based on the sag status of the wires of the monitoring subunits adjacent to the verification subunit.

[0070] During the power transmission process, adjacent power towers and the wires between adjacent power towers together constitute a monitoring subunit;

[0071] The acquisition process of the wire sag of the monitoring subunit is as follows:

[0072] By formula The wire sag LR of the monitoring subunit is calculated, where L represents the span between two pillars, that is, the distance between two suspension points of adjacent wire towers, w represents the unit length weight of the line, that is, the weight of each meter of wire between adjacent wire towers, T represents the tension of the line, that is, the tension on the wire between adjacent wire towers, and k is the influencing factor of wire sag;

[0073] Among them, the process of obtaining the influencing factor of wire sag is:

[0074] Get the temperature value in the monitoring subunit, and record the temperature value of the monitoring subunit as Jwt;

[0075] Obtain the weight of the wires in the monitoring subunit, and record the weight of the wires in the monitoring subunit as Jzt;

[0076] Obtain the wind speed of the wires in the monitoring subunit, and mark the wind speed in the monitoring subunit as Jft;

[0077] That is, through the formula Calculate the influence factor of wire sag , where f1 and f2 are both preset proportional coefficients, and wt is the minimum impact temperature on the thermal expansion and contraction of the wire caused by temperature changes, that is, when the temperature is wt, the change of thermal expansion and contraction of the wire at this temperature is the smallest;

[0078] Among them, the temperature wt is a preset value, which is obtained by the staff based on factors such as the material, cross-sectional area, and tension of the wire.

[0079] If the wire sag LR of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0080] If the wire sag LR of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated.

[0081] Based on the monitoring sub-unit operation verification signal

[0082] The monitoring subunit corresponding to the monitoring subunit operation verification signal is recorded as the verification subunit;

[0083] Obtaining the sag of the electric wires of the monitoring subunits adjacent to the verification subunit;

[0084] If the wire sags of two adjacent monitoring sub-units are both within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as an independent abnormal unit;

[0085] The state of the wires in the independent abnormal unit is identified to check whether foreign objects are hanging on the wires or the state of the anti-vibration devices connecting the wires on the two wire towers in the independent abnormal unit is identified;

[0086] If the wire sags of two adjacent monitoring sub-units are not within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as a continuous abnormal unit, and the monitoring sub-units on both sides are recorded as abnormal edge units;

[0087] The continuous abnormal unit and the abnormal adjacent units on both sides are recorded as a continuous abnormal unit group;

[0088] The deviation value of the electric wire sag of the continuous abnormal unit compared with the preset range requirement of the electric wire sag of the monitoring subunit is marked as the measured difference value of the continuous abnormal unit;

[0089] The deviation value of the wire sag of the abnormal adjacent units on both sides compared with the preset range requirement of the wire sag of the monitoring subunit is marked as the measured difference value of the abnormal adjacent unit;

[0090] Retrieve the preset warning coefficient of the corresponding monitoring subunit. It should be noted that the value of the preset warning coefficient is greater than zero and is preset by the management personnel. The larger the value of the preset risk coefficient is, the greater the adverse impact of the deviation of the sag of the corresponding monitoring subunit's wire on the operating safety of the monitoring subunit is.

[0091] The measured difference of the continuous abnormal unit is multiplied by the preset warning coefficient to obtain the warning value of the continuous abnormal unit;

[0092] The measured difference value of the abnormal edge unit is multiplied by the preset warning coefficient to obtain the warning value of the abnormal edge unit;

[0093] The warning value of the continuous abnormal unit is summed with the warning values ​​of the abnormal adjacent units on both sides to obtain the warning value of the continuous abnormal unit group, which is recorded as YJ;

[0094] The first limit value YJ1 of the warning value threshold of the continuous abnormal unit group and the first and second limit values ​​YJ2 of the warning value threshold of the continuous abnormal unit group are preset, wherein YJ1 <YJ2;

[0095] If YJ<YJ1, the sag deviation of the wires in the continuous abnormal unit group is low, and a first-level warning signal is generated;

[0096] If YJ1≤YJ<YJ2, the sag deviation of the wires in the continuous abnormal unit group is moderate, and a secondary warning signal is generated;

[0097] If YJ ≥ YJ2, the sag deviation of the wires in the continuous abnormal unit group is high, and a third-level warning signal is generated;

[0098] Among them, the warning level of the third-level warning signal is higher than the warning level of the second-level warning signal, and the warning level of the second-level warning signal is higher than the warning level of the first-level warning signal. The higher the level of the warning signal, the greater the safety hazard of the continuous abnormal unit group, and the local visual management of the power transmission line is realized;

[0099] Acquire all continuous abnormal unit groups in the power transmission line, respectively acquire the wire length of each continuous abnormal unit group, sum up the wire lengths of all continuous abnormal unit groups, and obtain the abnormal total value of the wire lengths of all continuous abnormal unit groups;

[0100] The ratio of the total value of the abnormal length of the electric wire to the total length of the power transmission line is calculated to obtain the line abnormality factor, which is marked as Xy;

[0101] The warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal in the power transmission line are obtained and marked as Yti;

[0102] Obtain the warning values ​​of all continuous abnormal unit groups belonging to the second-level warning signal in the power transmission line and mark them as Rtm;

[0103] The warning values ​​of all continuous abnormal unit groups belonging to the third-level warning signal in the power transmission line are obtained and marked as Stn;

[0104] Quantify and calculate the obtained warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal, the warning values ​​of the continuous abnormal unit groups belonging to the second-level warning signal, and the warning values ​​of the continuous abnormal unit groups belonging to the third-level warning signal;

[0105] That is, through the formula The power transmission line bus state warning value XZ is calculated, where t is the time of data collection;

[0106] =1,2,……, ;in is the number of all consecutive abnormal unit groups belonging to the first-level warning signal in the power transmission line;

[0107] =1,2,……, ;in is the number of all consecutive abnormal unit groups belonging to the second-level warning signal in the power transmission line;

[0108] =1,2,……, ;in is the number of all continuous abnormal unit groups belonging to the third-level warning signal in the power transmission line;

[0109] Compare the power transmission line bus state warning value XZ with the corresponding power transmission line bus state warning value preset range:

[0110] If the bus state warning value of the power transmission line exceeds the maximum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is extremely poor and the power transmission risk is high;

[0111] If the bus state warning value of the power transmission line is within the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is poor and the power transmission risk is moderate;

[0112] If the bus state warning value of the power transmission line is less than the minimum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is general and the power transmission risk is small.

[0113] The degree of extremely poor stability of the power transmission line is higher than the degree of poor stability of the power transmission line, and the degree of poor stability of the power transmission line is higher than the degree of general stability of the power transmission line. Combined with the ratio of the length of the continuous abnormal unit group to the total length of the power transmission line and the early warning values ​​of the continuous abnormal unit groups of different levels in the power transmission line, the monitoring and identification of the entire transmission status of the power transmission line is completed.

[0114] If the wire sag of two adjacent monitoring sub-units is one within the preset range of the wire sag of the monitoring sub-unit, and the other is not within the preset range of the wire sag of the monitoring sub-unit;

[0115] The monitoring subunit that is not within the preset range of the monitoring subunit wire sag is recorded as an abnormal side unit;

[0116] The adjacent monitoring subunit on the side of the abnormal side unit away from the validation subunit is recorded as a tracing subunit;

[0117] Identify the sag of the wires in the traceability subunit:

[0118] If the sag of the wire of the tracing subunit is not within the preset range of the sag of the wire of the monitoring subunit, the sag of the wires of multiple consecutive monitoring subunits on the power transmission line are monitored starting from the verification subunit along the monitoring sequence of the verification subunit-abnormal side unit-tracing subunit, and a monitoring subunit group and a monitoring subunit group wire sag value group are obtained;

[0119] Wherein, the number of the plurality of monitoring subunits includes but is not limited to 5, 10 or 20;

[0120] If the wire sag values ​​in the wire sag group of the monitoring sub-unit change linearly and decrease in sequence according to the monitoring order, it means that the verification sub-unit in the power transmission line is the main influencing unit, and the influence range of the main influencing unit on the power transmission line is controllable;

[0121] If the wire sag values ​​in the wire sag group of the monitoring subunit change linearly and increase in sequence according to the monitoring sequence, it means that the overall transmission stability of the power transmission line is poor within a certain transmission area, and there is a greater transmission risk;

[0122] If the wire sag value in the wire sag group of the monitoring subunit changes nonlinearly:

[0123] Establish a plane coordinate system, with the monitoring subunit as the X-axis and the wire sag value corresponding to the monitoring subunit as the Y-axis;

[0124] Draw a comparison line parallel to the X-axis using the sag value of the wire of the test subunit

[0125] The wire sag value corresponding to each monitoring sub-unit is plotted in the plane coordinate system according to the monitoring sequence, and the wire sag values ​​corresponding to all monitoring sub-units are connected with a smooth curve to obtain a wire sag line;

[0126] Make the end of the arc-sag line of the electric wire perpendicular to the contrast line to form a closed contrast image with the contrast line;

[0127] The closed areas above the contrast line in the contrast image are summed to obtain the upper closed value;

[0128] The closed area below the contrast line in the contrast image is summed to obtain the lower closed value;

[0129] If the upper closure value is greater than the lower closure value, it means that the operating status of the monitoring subunit group is gradually getting worse, and a first-level warning signal is obtained;

[0130] If the upper closure value is ≤ the lower closure value, it means that the fluctuation of the operating state of the monitoring subunit group tends to be stable, and a second-level reminder signal is obtained;

[0131] When a first-level reminder signal is received, the status of all monitoring subunits in the monitoring subunit group and monitoring subunits outside the monitoring subunit group needs to be identified;

[0132] When the secondary reminder signal is received, the status of all monitoring sub-units in the monitoring sub-unit group is identified.

[0133] If the sag of the wire of the tracing subunit is within the preset range of the sag of the wire of the monitoring subunit, the status of the wire tower shared by the abnormal side unit and the verification subunit is monitored;

[0134] Monitor whether there is any subsidence in the area where the power towers are erected and whether the power towers are tilted. Example 2

[0135] See also Figure 2 As shown, the present invention is a new energy power generation long-distance transmission monitoring system, including a wire sag monitoring module, a state analysis module, a decision monitoring module and a cloud management and control platform;

[0136] The wire sag monitoring module, the state analysis module and the decision monitoring module are electrically connected to the cloud management and control platform;

[0137] The wire sag monitoring module is used to obtain the dynamic parameters of the monitoring subunit, and monitor the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit;

[0138] And transmit the wire sag of the monitoring sub-unit to the cloud management and control platform;

[0139] The status analysis module obtains the wire sag of the monitoring subunit of the cloud management and control platform, identifies the wire sag of the monitoring subunit obtained by monitoring, and obtains the normal operation signal of the monitoring subunit and the operation verification signal of the monitoring subunit;

[0140] If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated;

[0141] If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated;

[0142] And transmit the status signal (operation verification signal or normal operation signal) of the monitoring sub-unit to the cloud management and control platform;

[0143] The decision-making monitoring module obtains the status signal of the monitoring sub-unit of the cloud management and control platform, records the monitoring sub-unit corresponding to the monitoring sub-unit operation verification signal as the verification sub-unit, identifies the sag of the wires of the monitoring sub-units adjacent to the verification sub-unit, and completes the monitoring of the overall power transmission line status based on the sag status of the wires of the monitoring sub-units adjacent to the verification sub-unit.

[0144] One of the core points of the present invention is that the influence factor of the wire sag of the monitoring subunit is obtained by processing the temperature, wind speed and wire gravity of the environment in which the monitoring subunit is located, and the actual wire sag of the monitoring subunit is obtained based on the influence factor of the wire sag of the monitoring subunit. Then, the actual wire sag of the monitoring subunit is compared with the preset wire sag of the monitoring subunit to complete the monitoring of the wire sag state of the monitoring subunit. Combined with the influence factor of the wire sag, the management terminal can more accurately monitor the wire sag state of the monitoring subunit.

[0145] One of the core points of the present invention is to identify the sag of the wires of the adjacent monitoring subunits of the verification subunit. If the sag of the wires of the two adjacent monitoring subunits is not within the preset range of the sag of the wires of the monitoring subunits, the verification subunit is recorded as a continuous abnormal unit, the monitoring subunits on both sides are recorded as abnormal adjacent units, and the continuous abnormal unit and the abnormal adjacent units on both sides are collectively recorded as a continuous abnormal unit group. Based on the early warning value of the continuous abnormal unit group, the warning level of the continuous abnormal unit group is identified, and the early warning value of the continuous abnormal unit group corresponding to different warning level signals and the abnormal factor of the power transmission line are combined to monitor the overall operation status of the power transmission line, thereby completing the monitoring of the power transmission line from the monitoring subunit to the overall power transmission line.

[0146] The above is a detailed description of an embodiment of the present invention, but the content is only a preferred embodiment of the present invention and cannot be considered to limit the scope of implementation of the present invention. All equivalent changes and improvements made within the scope of the present invention should still fall within the scope of the patent coverage of the present invention.

Claims

1. A method for monitoring the state of long-distance power transmission, characterized in that: The following steps are involved: Step 1: obtaining dynamic parameters of the monitoring subunit, and monitoring the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit; During the power transmission process, adjacent power towers and the wires between adjacent power towers together constitute a monitoring subunit; Step 2: Identify the wire sag of the monitoring subunit obtained by monitoring, and obtain a normal operation signal of the monitoring subunit and a monitoring subunit operation verification signal; If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated; If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated; Step 3: Record the monitoring subunit corresponding to the monitoring subunit operation verification signal as the verification subunit, identify the wire sag of the monitoring subunit adjacent to the verification subunit, and complete the monitoring and identification of the overall power transmission line status based on the wire sag status of the monitoring subunit adjacent to the verification subunit; In step 1, the process of obtaining the wire sag of the monitoring subunit is as follows: By formula Calculate the wire sag LR of the monitoring subunit; Among them, L represents the span between two pillars, that is, the distance between the two suspension points of adjacent power towers, w represents the unit length weight of the line, that is, the weight of the wire per meter between adjacent power towers, T represents the tension of the line, that is, the tension on the wire between adjacent power towers, and k is the influence factor of the wire sag; The process of obtaining the influencing factor of wire sag is as follows: Get the temperature value in the monitoring subunit, and record the temperature value of the monitoring subunit as Jwt; Obtain the weight of the wires in the monitoring subunit, and record the weight of the wires in the monitoring subunit as Jzt; Obtain the wind speed of the wires in the monitoring subunit, and mark the wind speed in the monitoring subunit as Jft; That is, through the formula Calculate the influence factor of wire sag , where f1 and f2 are preset proportional coefficients, and wt is the minimum impact temperature on the thermal expansion and contraction of the wire caused by temperature changes; In step 3, the sag of the electric wires of the monitoring subunits adjacent to the verification subunit is obtained; If the wire sags of two adjacent monitoring sub-units are both within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as an independent abnormal unit; The state of the wires in the independent abnormal unit is identified to check whether foreign objects are hanging on the wires or the state of the anti-vibration devices connecting the wires on the two wire towers in the independent abnormal unit is identified; In step 3, the method for identifying the sag of the wires of the adjacent monitoring subunits of the verification subunit is as follows: If the wire sags of two adjacent monitoring sub-units are not within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as a continuous abnormal unit, and the monitoring sub-units on both sides are recorded as abnormal edge units; The continuous abnormal unit and the abnormal adjacent units on both sides are recorded as a continuous abnormal unit group; The deviation value of the electric wire sag of the continuous abnormal unit compared with the preset range requirement of the electric wire sag of the monitoring subunit is marked as the measured difference value of the continuous abnormal unit; The deviation value of the wire sag of the abnormal adjacent units on both sides compared with the preset range requirement of the wire sag of the monitoring subunit is marked as the measured difference value of the abnormal adjacent unit; The measured difference of the continuous abnormal unit is multiplied by the preset warning coefficient to obtain the warning value of the continuous abnormal unit; The measured difference value of the abnormal edge unit is multiplied by the preset warning coefficient to obtain the warning value of the abnormal edge unit; The warning value of the continuous abnormal unit is summed with the warning values ​​of the abnormal adjacent units on both sides to obtain the warning value of the continuous abnormal unit group, and the sag of the wires of the adjacent monitoring sub-units of the validation sub-unit is identified according to the warning value of the continuous abnormal unit group; The warning value of the continuous abnormal unit group is marked as YJ, and the first limit value YJ1 of the warning value threshold of the continuous abnormal unit group and the second limit value YJ2 of the warning value threshold of the continuous abnormal unit group are preset, wherein YJ1 <YJ2; If YJ<YJ1, the sag deviation of the wires in the continuous abnormal unit group is low, and a first-level warning signal is generated; If YJ1≤YJ<YJ2, the sag deviation of the wires in the continuous abnormal unit group is moderate, and a secondary warning signal is generated; If YJ ≥ YJ2, the sag deviation of the wires in the continuous abnormal unit group is high, and a third-level warning signal is generated; The warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal in the power transmission line are obtained and marked as Yti; Obtain the warning values ​​of all continuous abnormal unit groups belonging to the second-level warning signal in the power transmission line and mark them as Rtm; The warning values ​​of all continuous abnormal unit groups belonging to the third-level warning signal in the power transmission line are obtained and marked as Stn; Quantify and calculate the obtained warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal, the warning values ​​of the continuous abnormal unit groups belonging to the second-level warning signal, and the warning values ​​of the continuous abnormal unit groups belonging to the third-level warning signal; That is, through the formula The power transmission line bus state warning value XZ is calculated, where: is the linear anomaly factor; If the bus state warning value of the power transmission line exceeds the maximum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is extremely poor and the power transmission risk is high; If the bus state warning value of the power transmission line is within the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is poor and the power transmission risk is moderate; If the bus state warning value of the power transmission line is less than the minimum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is general and the power transmission risk is small.

2. A method for monitoring the state of long-distance power transmission according to claim 1, characterized in that: All continuous abnormal unit groups in the power transmission line are processed, the wire length of each continuous abnormal unit group is obtained respectively, the wire lengths of all continuous abnormal unit groups are summed up, and the total abnormal value of the wire lengths of all continuous abnormal unit groups is obtained.

3. A method for monitoring the state of long-distance power transmission according to claim 2, characterized in that: The line length anomaly factor is obtained by calculating the ratio of the total value of the abnormal length of the electric wire to the total length of the power transmission line.

4. A long-distance power transmission status monitoring system, characterized in that: include: A wire sag monitoring module, the wire sag monitoring module is used to obtain dynamic parameters of the monitoring subunit, and monitor the wire sag of the monitoring subunit based on the dynamic parameters of the monitoring subunit; During the power transmission process, adjacent power towers and the wires between adjacent power towers together constitute a monitoring subunit; And transmit the wire sag of the monitoring sub-unit to the cloud management and control platform; A status analysis module, which is used to obtain the wire sag of the monitoring subunit of the cloud management and control platform, identify the wire sag of the monitoring subunit obtained by monitoring, and obtain a normal operation signal of the monitoring subunit and a monitoring subunit operation verification signal; If the wire sag of the monitoring subunit is within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the safe range, and a normal operation signal of the monitoring subunit is generated; If the wire sag of the monitoring subunit is not within the preset range of the wire sag of the monitoring subunit, it means that the wire sag of the monitoring subunit is within the out-of-bounds range, and a monitoring subunit operation verification signal is generated; And transmit the status signal of the monitoring sub-unit to the cloud management and control platform; A decision-making monitoring module, which is used to obtain the status signal of the monitoring subunit of the cloud management and control platform, record the monitoring subunit corresponding to the monitoring subunit operation verification signal as the verification subunit, identify the wire sag of the monitoring subunit adjacent to the verification subunit, and complete the monitoring of the overall power transmission line status based on the status of the wire sag of the monitoring subunit adjacent to the verification subunit; The acquisition process of the wire sag of the monitoring subunit is as follows: By formula Calculate the wire sag LR of the monitoring subunit; Among them, L represents the span between two pillars, that is, the distance between the two suspension points of adjacent power towers, w represents the unit length weight of the line, that is, the weight of the wire per meter between adjacent power towers, T represents the tension of the line, that is, the tension on the wire between adjacent power towers, and k is the influence factor of the wire sag; The process of obtaining the influencing factor of wire sag is as follows: Get the temperature value in the monitoring subunit, and record the temperature value of the monitoring subunit as Jwt; Obtain the weight of the wires in the monitoring subunit, and record the weight of the wires in the monitoring subunit as Jzt; Obtain the wind speed of the wires in the monitoring subunit, and mark the wind speed in the monitoring subunit as Jft; That is, through the formula Calculate the influence factor of wire sag , where f1 and f2 are preset proportional coefficients, and wt is the minimum impact temperature on the thermal expansion and contraction of the wire caused by temperature changes; Obtaining the sag of the electric wires of the monitoring subunits adjacent to the verification subunit; If the wire sags of two adjacent monitoring sub-units are both within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as an independent abnormal unit; The state of the wires in the independent abnormal unit is identified to check whether foreign objects are hanging on the wires or the state of the anti-vibration devices connecting the wires on the two wire towers in the independent abnormal unit is identified; The method for identifying the sag of the wires of the adjacent monitoring subunits of the verification subunit is as follows: If the wire sags of two adjacent monitoring sub-units are not within the preset range of the wire sags of the monitoring sub-units, the verification sub-unit is recorded as a continuous abnormal unit, and the monitoring sub-units on both sides are recorded as abnormal edge units; The continuous abnormal unit and the abnormal adjacent units on both sides are recorded as a continuous abnormal unit group; The deviation value of the electric wire sag of the continuous abnormal unit compared with the preset range requirement of the electric wire sag of the monitoring subunit is marked as the measured difference value of the continuous abnormal unit; The deviation value of the wire sag of the abnormal adjacent units on both sides compared with the preset range requirement of the wire sag of the monitoring subunit is marked as the measured difference value of the abnormal adjacent unit; The measured difference of the continuous abnormal unit is multiplied by the preset warning coefficient to obtain the warning value of the continuous abnormal unit; The measured difference value of the abnormal edge unit is multiplied by the preset warning coefficient to obtain the warning value of the abnormal edge unit; The warning value of the continuous abnormal unit is summed with the warning values ​​of the abnormal adjacent units on both sides to obtain the warning value of the continuous abnormal unit group, and the sag of the wires of the adjacent monitoring sub-units of the validation sub-unit is identified according to the warning value of the continuous abnormal unit group; The warning value of the continuous abnormal unit group is marked as YJ, and the first limit value YJ1 of the warning value threshold of the continuous abnormal unit group and the second limit value YJ2 of the warning value threshold of the continuous abnormal unit group are preset, wherein YJ1 <YJ2; If YJ<YJ1, the sag deviation of the wires in the continuous abnormal unit group is low, and a first-level warning signal is generated; If YJ1≤YJ<YJ2, the sag deviation of the wires in the continuous abnormal unit group is moderate, and a secondary warning signal is generated; If YJ ≥ YJ2, the sag deviation of the wires in the continuous abnormal unit group is high, and a third-level warning signal is generated; The warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal in the power transmission line are obtained and marked as Yti; Obtain the warning values ​​of all continuous abnormal unit groups belonging to the second-level warning signal in the power transmission line and mark them as Rtm; The warning values ​​of all continuous abnormal unit groups belonging to the third-level warning signal in the power transmission line are obtained and marked as Stn; Quantify and calculate the obtained warning values ​​of all continuous abnormal unit groups belonging to the first-level warning signal, the warning values ​​of the continuous abnormal unit groups belonging to the second-level warning signal, and the warning values ​​of the continuous abnormal unit groups belonging to the third-level warning signal; That is, through the formula The power transmission line bus state warning value XZ is calculated, where: is the linear anomaly factor; If the bus state warning value of the power transmission line exceeds the maximum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is extremely poor and the power transmission risk is high; If the bus state warning value of the power transmission line is within the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is poor and the power transmission risk is moderate; If the bus state warning value of the power transmission line is less than the minimum value of the preset range of the bus state warning value of the power transmission line, it means that the stability of the power transmission line is general and the power transmission risk is small.

Citation Information

Patent Citations

  • System and method for dynamically measuring and calculating transmission capacity of transmission line

    CN102340139A

  • Sag calculation method and system

    CN105243201A

  • Power transmission line sag monitoring method and system

    CN116358418A

  • Distributed fault positioning method and device for overhead transmission line

    CN117849525A

  • Power transmission line state monitoring method and device and storage medium

    CN118362162A