A photovoltaic building integrated system for zero-carbon campuses

CN118611545BActive Publication Date: 2024-11-19JIANGSU LONG LEAPING ENG DESIGN
-1 Cites 0 Cited by

Patent Information

Application Number
CN202410730814.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-06-06
Publication Date
2024-11-19
Estimated Expiration
2044-06-06

AI Technical Summary

Technical Problem

In the existing integrated photovoltaic building system, the glue may lose its viscosity in severe weather conditions, resulting in the photovoltaic panels falling off or damaged, posing safety hazards.

Method used

The design of the side-open transparent cover and the extraction box is used to fix the solar photovoltaic module on the color steel plate through the positioning mechanism and sealing mechanism to avoid corrosion or damage from external factors such as sand and wind and rain, reduce the probability of failure, and simplify the installation and maintenance process. .

Benefits of technology

It improves the safety factor and service life of photovoltaic modules, reduces the safety hazards of maintenance personnel, extends the maintenance cycle, simplifies the installation and maintenance process, and enhances the protection effect of photovoltaic modules.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118611545B_ABST
    Figure CN118611545B_ABST
Patent Text Reader

Abstract

The present invention relates to a photovoltaic building integration system for a zero-carbon campus, and belongs to the field of photovoltaic building technology. The photovoltaic building integration system for a zero-carbon campus includes a color steel plate and a solar photovoltaic module, the color steel plate is installed with a mounting assembly, and the solar photovoltaic module is installed inside the mounting assembly; the staff can install the solar photovoltaic module and the color steel plate on the ground for fixing the solar photovoltaic module respectively. When the staff installs on site, the staff only needs to perform two steps of plugging the positioning block and installing the stainless steel sealing strip by adjusting the bolts to fix all the positioning blocks under the solar photovoltaic module inside the circular cavity, and no adjustment is required one by one. This not only effectively reduces the difficulty of the existing glue coating installation, but also improves the safety factor of the solar photovoltaic module used in the campus.
Need to check novelty before this filing date? Find Prior Art