Intelligent construction management system and method using multi-dimensional data fusion analysis technology
By applying multi-dimensional data fusion analysis technology at the construction site, establishing a BIM model and correcting the feature points in the positioning trajectory, the problem of inaccurate positioning trajectories of safety equipment at the construction site in the existing technology is solved, and the safety management effect of the construction site is improved.
Patent Information
- Application Number
- CN202411098263.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-12
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2044-08-12
AI Technical Summary
Existing construction site safety management methods cannot accurately monitor and warn workers' activities in dangerous areas in real time, resulting in inaccurate location information and possible accidents.
Multi-dimensional data fusion analysis technology is used to build a BIM model at the construction site, mark feature points, and workers wear positioning safety equipment to obtain positioning trajectories in real time, judge and correct normal, deviated and abnormal feature points in the positioning trajectory to ensure the accuracy of positioning information sex.
It achieves timely and accurate monitoring of the location of construction workers, reduces early warning errors, and improves the safety of the construction site.
Smart Images

Figure CN118643113B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of intelligent construction management, and specifically to an intelligent construction management system and method using multi-dimensional data fusion analysis technology. Background Art
[0002] At construction sites, workers' safety is of vital importance. During construction, workers may accidentally enter dangerous areas where construction is ongoing without knowing it, and accidents that cause serious injuries to workers may occur in dangerous areas. However, existing safety management methods often have some limitations that cannot be ignored, and cannot monitor and warn workers' activities in dangerous areas in real time and accurately. Smart construction sites have emerged as the times require. By having workers wear positioning helmets, workers' activities can be monitored and warned in real time. Although positioning helmets can provide certain information, they are still insufficient in terms of real-time and accuracy. There are problems such as inaccurate position display, abnormal personnel positioning trajectory, and incorrect area judgment, which may lead to inaccurate grasp of workers' position information. They may not be able to obtain the specific location and dynamic behavior of workers in dangerous areas in a timely and accurate manner, resulting in untimely or inaccurate warnings, which may cause serious accidents. Therefore, it is necessary to correct the workers' positioning trajectory in a timely manner. Summary of the invention
[0003] The purpose of the present invention is to provide an intelligent construction management system and method using multi-dimensional data fusion analysis technology to solve the problems raised in the above-mentioned background technology.
[0004] In order to solve the above technical problems, the present invention provides the following technical solutions:
[0005] The intelligent construction management method using multi-dimensional data fusion analysis technology includes the following steps:
[0006] Step S100: Obtain the construction site drawings and establish a construction site BIM model, and mark the positions of various characteristic punctuation points in the construction site BIM model. The characteristic punctuation points are facilities or buildings with fixed positions that are not easily changed;
[0007] Step S200: The construction worker wears a safety device with a positioning function, obtains the positioning trajectory of the safety device in real time, and obtains a positioning point set and a direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point, and determines whether the positioning trajectory is a trajectory to be detected according to the direction vector set;
[0008] The positioning trajectory of the safety equipment here is to continuously record the position coordinates of the safety equipment at different time points through positioning technology (such as GPS, Beidou, etc.), and connect these position coordinates in sequence to form a trajectory line reflecting the activity path of the equipment carrier (i.e., construction worker). The positioning trajectory of the safety equipment here is not necessarily the same as the actual movement path of the construction worker. It may be due to low battery of the safety equipment, the presence of a magnetic field around it, etc., which may cause deviation between the positioning trajectory of the safety equipment and the actual movement path of the construction worker.
[0009] Step S300: if the positioning trajectory is a trajectory to be detected, a reference distance set in the trajectory to be detected is obtained according to the positioning point set, and normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked according to the reference distance set;
[0010] Step S400: correcting all deviated feature points and abnormal feature points in the trajectory to be detected according to the normal feature points marked in the trajectory to be detected.
[0011] Further, step S200 includes:
[0012] Step S210: Get the current time as the starting point and go forward The positioning trajectory of the safety device within seconds; set the time interval to g, and subtract the current time from The moment of seconds is taken as the starting moment, and a set of positioning points including all positioning points between the starting moment and the current moment is obtained. The number of positioning points in the set of positioning points is ;
[0013] The set of positioning points is: a set of all positioning points obtained from all positioning points between the start time and the current time, where the positioning points in the set of positioning points are sorted in the order from the start time to the current time. , the set of anchor points The positioning points in are ,in, They are No. 1, 2, , positioning points at n moments.
[0014] Step S220: Record the location of the safety device at the start time and the current time as and , get the distance and The nearest feature point, and get the direction vector set with the nearest feature point as the starting point and each positioning point in the positioning point set as the end point , direction vector set The number of direction vectors in is also ;
[0015] Step S230: If there is a direction vector set The direction vector in does not satisfy , then the positioning trajectory is judged to be the trajectory to be detected, where is the direction vector difference threshold, are the direction vector sets The direction vector, .
[0016] The trajectory to be detected does not necessarily mean that the positioning trajectory of the safety equipment is abnormal. It may also be caused by the worker's sudden walking or stopping. The moment of sudden walking or stopping will cause the formula The result exceeds the direction vector difference threshold , and the trajectory to be detected may only contain normal moving trajectories, so the following steps are needed to further judge the trajectory to be detected.
[0017] Furthermore, step S300 includes:
[0018] Step S310: Get the coordinates of all the positioning points in the positioning point set, and get the positioning distances between all the two adjacent positioning points at all times, and mark the positioning distances that are less than the distance threshold, and get the reference distance set according to the adjacent positioning distances with the largest number of marks. The corresponding coordinate points in the reference distance set are all normal feature points, and the coordinates of the initial and final positioning points in the reference distance set are taken as and ;The number of positioning distances is n-1;
[0019] Step S320: Using the coordinates of the final positioning point For example, the positioning point The direction is: based on the positioning point The last moment's positioning point The position is the starting point and the positioning point The position is the direction of the end point; The coordinates of the next moment's positioning point are , then the positioning point The positioning point deviation is ,in, To follow the positioning point A distance of a meters forward in the direction of To follow the positioning point A distance of b meters forward in the opposite direction, a>b>0;
[0020] Positioning point deviation This is the calculation formula for the ellipse. If a person suddenly accelerates during normal walking, he will appear at a farther position in the front in the next second. But if he suddenly stops or turns around, he will not appear at a farther position in the back in the next second, but can only appear at a closer position in the back, so a>b>0.
[0021] Step S330: According to the positioning point Positioning point deviation , for the positioning point Marking; if the positioning point For normal feature points, the positioning point Replace anchor point Otherwise, if the positioning point If it is not a normal feature point, then according to the positioning point Get a reservation location , the predetermined site Replace anchor point Repeat step S320 to step S330 until all normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked.
[0022] Further, in step S330, according to the positioning point Get a reservation location To: Set the positioning point The last moment’s positioning point is , get the predetermined site The coordinates are: .
[0023] Furthermore, step S400 includes:
[0024] It should be noted that the difference between abnormal feature points and deviated feature points is that abnormal feature points are positioning points with excessive deviations in the positioning trajectory. Such positioning points are too extreme or unrepresentative. The possible reasons for their occurrence are signal interference or being in a complex area, which seriously affects signal propagation and cannot produce effective and positive effects on trajectory correction. Any measurement system has inherent errors, and deviated feature points may only be some subtle but unavoidable changes in the environment that have a slight effect on positioning, or the performance of the positioning helmet itself may have certain instabilities, which leads to positioning deviations, not caused by signal interference, etc. In order to help make corrections more accurately and ensure that the corrected trajectory is more in line with the actual situation. The present invention needs to treat the data of deviated feature points with caution and make rational use of them, while the data of abnormal feature points that are too extreme or unrepresentative are not needed.
[0025] Step S410: According to the normal feature points in the trajectory to be detected, all adjacent normal feature points are sorted to obtain m normal movement trajectories; the positioning point of the i-th normal movement trajectory at the terminal position is recorded as , The direction is: The last moment positioning point is the starting point. is the direction of the end point; the positioning point of the i+1th normal moving trajectory at the starting position is recorded as , The direction is: As a starting point, The next moment, the positioning point is the direction of the end point; Direction and anchor point The angle between the directions is expressed as ;in, ;
[0026] Step S420: According to the direction angle , get the positioning point and According to the number of positioning points that need to be corrected in the virtual trajectory, the virtual trajectory is evenly divided into several virtual positioning points. and If there are abnormal feature points between them, the positioning points are divided into several virtual positioning points evenly. and Correct the abnormal feature points corresponding to each other;
[0027] Step S430: If the positioning point and There are deviation feature points between them. According to several virtual positioning points evenly distributed, the positioning points and All the deviated feature points between approach the corresponding virtual positioning point in the virtual trajectory; the speed at which each deviated feature point approaches is ,in, For the The moving speed when the deviating feature point approaches, For the The distance between the deviation feature point and the corresponding virtual positioning point in the virtual trajectory, is the set approach time;
[0028] Step S440: The direction of the deviation from the feature point is: the direction starting from the positioning point at the last moment of the current deviation from the feature point and ending at the current deviation from the feature point; if the directions of all the deviation from the feature points are within the direction angle If the distance between the two points is between 0 and 1, the approach is stopped, and the deviation from the feature point is corrected accordingly.
[0029] Further, in step S420, according to the direction angle , get the positioning point and The virtual tracks include:
[0030] Step S421: If the direction angle , the virtual trajectory is: connecting the positioning points and The straight line between is the direction angle threshold;
[0031] Step S422: If the direction angle , the virtual trajectory is: respectively based on the positioning point and As the starting point, and follow the and The two circles are extended in the direction of until they intersect, and the intersection point is taken as the center of the circle, and the extended length is taken as the radius. An arc is drawn according to the center of the circle and the radius, and the arc is taken as the virtual trajectory.
[0032] The intelligent construction management system using multi-dimensional data fusion analysis technology includes the following modules:
[0033] Model building module: used to obtain construction site drawings and build a BIM model of the site, marking the location of each feature point in the BIM model of the site. Feature points are facilities or buildings with fixed positions that are not easily changed.
[0034] Track to be detected module: It is used for construction workers to wear safety equipment with positioning function, obtain the positioning track of the safety equipment in real time, and obtain the positioning point set and direction vector set of the positioning track according to the positioning track and each characteristic punctuation point, and judge whether the positioning track is the track to be detected according to the direction vector set;
[0035] Marking feature point module: If the positioning trajectory is the trajectory to be detected, the marking feature point module is used to obtain the reference distance set in the trajectory to be detected according to the positioning point set, and mark the normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected according to the reference distance set;
[0036] Trajectory correction module: used to correct all deviated feature points and abnormal feature points in the trajectory to be detected according to the normal feature points marked in the trajectory to be detected.
[0037] Further, the trajectory module to be detected includes the following units: a positioning point set unit, a direction vector set unit and a trajectory unit to be detected;
[0038] Positioning point set unit: used to obtain the positioning trajectory of the safety equipment in real time and obtain the positioning point set of the positioning trajectory;
[0039] Direction vector set unit: used to obtain the direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point;
[0040] The trajectory unit to be detected is used to determine whether the positioning trajectory is a trajectory to be detected according to the direction vector set.
[0041] Furthermore, the marking feature point module includes the following units: a reference distance set unit, a positioning point deviation unit and a marking feature point unit:
[0042] Reference distance set unit: if the positioning trajectory is a trajectory to be detected, the reference distance set unit is used to obtain a reference distance set in the trajectory to be detected according to the positioning point set;
[0043] A positioning point deviation unit: used for obtaining the positioning point deviations of all positioning points not in the reference distance set according to the reference distance set;
[0044] Marking feature point unit: used to mark normal feature points, deviated feature points and abnormal feature points in the detection trajectory according to the positioning point deviations of all positioning points that are not in the reference distance set.
[0045] Compared with the prior art, the beneficial effects achieved by the present invention are as follows: the present invention provides an intelligent construction management system and method using multi-dimensional data fusion analysis technology, including: establishing a BIM model of a construction site, marking the position of each characteristic punctuation point in the BIM model of the construction site; obtaining the positioning trajectory of the safety equipment in real time, and obtaining the positioning point set and direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point, and judging whether the positioning trajectory is a trajectory to be detected; marking the normal characteristic points, deviated characteristic points and abnormal characteristic points in the trajectory to be detected; and correcting all deviated characteristic points and abnormal characteristic points in the trajectory to be detected. The present invention is based on a safety device with a positioning function, and solves the problem that the positioning trajectory of the safety equipment at the construction site cannot be corrected in time through the positioning trajectory of the construction workers at the construction site and the characteristic punctuation points at the construction site. The present invention has the advantages of simple algorithm and easy implementation. BRIEF DESCRIPTION OF THE DRAWINGS
[0046] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0047] Figure 1 It is a flow chart of the intelligent construction management method using multi-dimensional data fusion analysis technology of the present invention;
[0048] Figure 2 It is a structural diagram of the intelligent construction management system of the present invention using multi-dimensional data fusion analysis technology. DETAILED DESCRIPTION
[0049] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0050] See also Figure 1-Figure 2 The present invention provides an intelligent construction management system and method using multi-dimensional data fusion analysis technology. The corresponding flowchart of the intelligent construction management method using multi-dimensional data fusion analysis technology is as follows: Figure 1 As shown. The following steps are included:
[0051] Step S100: Obtain the construction site drawings and establish a construction site BIM model, and mark the positions of various characteristic punctuation points in the construction site BIM model. The characteristic punctuation points are facilities or buildings with fixed positions that are not easily changed.
[0052] Obtain construction site drawings, establish a BIM model of the site, and mark the positions of various feature points in the BIM model. Feature points are facilities or buildings with fixed positions that are not easily changed. In this embodiment, feature points include: office rooms, warehouses, lighting towers, water towers, guard rooms, etc.
[0053] Step S200: The construction worker wears safety equipment with a positioning function, obtains the positioning trajectory of the safety equipment in real time, and obtains a positioning point set and a direction vector set of the positioning trajectory based on the positioning trajectory and each characteristic punctuation point, and determines whether the positioning trajectory is a trajectory to be detected based on the direction vector set.
[0054] Construction workers on the construction site wear safety equipment with a positioning function and obtain the positioning trajectory of the safety equipment in real time; under normal circumstances, the positioning trajectory of the safety equipment should be the same as the actual movement trajectory of the worker, but if the safety equipment is too low in power, there is a magnetic field around it, etc., the positioning trajectory of the safety equipment will deviate from the movement trajectory of the construction worker, which will be manifested in the form of positioning point jumping or teleporting, trajectory confusion, etc., and then the abnormal positioning trajectory will be corrected. In this embodiment, the safety equipment with a positioning function is a positioning helmet. The process of determining whether the positioning trajectory is the trajectory to be detected is as follows:
[0055] Step S210: Get the current time as the starting point and go forward The positioning trajectory of the safety device within seconds; set the time interval to g, and subtract the current time from The moment of seconds is taken as the starting moment, and a set of positioning points including all positioning points between the starting moment and the current moment is obtained. The number of positioning points in the set of positioning points is .
[0056] The set of positioning points is: a set of all positioning points obtained based on all positioning points between the starting time and the current time, wherein the positioning points in the set of positioning points are sorted in the order from the starting time to the current time. In this embodiment, the set of positioning points is set to , the set of anchor points The number of anchor points in is . Anchor point set The positioning points in are ,in, They are No. 1, 2, , n positioning points at the moment. Among them, To locate the trajectory time range, in this embodiment =10, time interval Second.
[0057] Step S220: Record the location of the safety device at the start time and the current time as and , get the distance and The nearest feature point, and get the direction vector set with the nearest feature point as the starting point and each positioning point in the positioning point set as the end point , direction vector set The number of direction vectors in is also In this embodiment, the vector set The elements in are ,in, They are No. 1, 2, , the direction vector at n moments.
[0058] Step S230: If there is a direction vector set The direction vector in does not satisfy , then the positioning trajectory is judged to be the trajectory to be detected, where is the direction vector difference threshold, are the direction vector sets The direction vector, In this embodiment, the direction vector difference threshold .
[0059] It should be noted that the trajectory to be detected does not necessarily mean that the positioning trajectory of the safety equipment is abnormal. It may also be caused by the worker's sudden walking or stopping. The moment of sudden walking or stopping will cause the formula The result exceeds the direction vector difference threshold , and there may be only normal moving trajectories in the trajectory to be detected, so it is necessary to further judge the trajectory to be detected, and mark normal feature points, deviation feature points and abnormal feature points from the trajectory to be detected, as shown in the following step S300.
[0060] Step S300: If the positioning trajectory is a trajectory to be detected, a reference distance set in the trajectory to be detected is obtained according to the positioning point set, and normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked according to the reference distance set.
[0061] Step S310: Get the coordinates of all the positioning points in the positioning point set, and get the positioning distances between all the two adjacent positioning points at all times, and mark the positioning distances that are less than the distance threshold, and get the reference distance set according to the adjacent positioning distances with the largest number of marks. The corresponding coordinate points in the reference distance set are all normal feature points, and the coordinates of the initial and final positioning points in the reference distance set are taken as and The number of positioning distances is n-1, and the specific distance threshold should be determined according to actual conditions. In this embodiment, the distance threshold is 3 meters.
[0062] Step S320: Using the coordinates of the final positioning point For example, the positioning point The direction is: based on the positioning point The last moment's positioning point The position is the starting point and the positioning point The position is the direction of the end point; The coordinates of the next moment's positioning point are , then the positioning point The positioning point deviation is ,in, To follow the positioning point A distance of a meters forward in the direction of To follow the positioning point A distance of b meters in the opposite direction, a>b>0.
[0063] It should be noted that if a person is walking normally, the possible range of his position in the next second is an ellipse, because if he suddenly accelerates, he will appear at a farther position in the front in the next second, and if he suddenly stops or turns around, he will not appear at a farther position in the back in the next second, but only at a closer position in the back. The calculation formula for the positioning point deviation is is the calculation formula of the ellipse, so a>b>0. In this embodiment, , .
[0064] Step S330: According to the positioning point Positioning point deviation , for the positioning point Marking; if the positioning point For normal feature points, the positioning point Replace anchor point Otherwise, if the positioning point If it is not a normal feature point, then according to the positioning point Get a reservation location , the predetermined site Replace anchor point Repeat step S320 to step S330 until all normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked.
[0065] In this embodiment, according to the positioning point Positioning point deviation , for the positioning point Marking includes: If the positioning point deviation satisfy , determine the positioning point Within the normal range, the positioning point Perform normal feature point marking; if the positioning point deviates satisfy , determine the positioning point Within the acceptable deviation range, the positioning point Mark the deviation feature points; if the positioning point deviation satisfy , determine the positioning point Not within the acceptable deviation range, the positioning point Mark abnormal feature points.
[0066] Among them, according to the positioning point Get a reservation location To: Set the positioning point The positioning point at the previous moment is , get the predetermined site The coordinates are: It should be noted that the positioning point in the present invention and predetermined sites The center point is the positioning point ,so , ,and then , So the predetermined site The coordinates are: .
[0067] Step S400: correcting all deviated feature points and abnormal feature points in the trajectory to be detected according to the normal feature points marked in the trajectory to be detected.
[0068] It should be noted that the difference between abnormal feature points and deviated feature points is that abnormal feature points are positioning points with excessive deviations in the positioning trajectory. Such positioning points are too extreme or unrepresentative. The possible reasons for their occurrence are signal interference or being in a complex area, which seriously affects signal propagation and cannot produce effective and positive effects on trajectory correction. Any measurement system has inherent errors, and deviated feature points may only be some subtle but unavoidable changes in the environment that have a slight effect on positioning, or the performance of the positioning helmet itself may have certain instabilities, which leads to positioning deviations, not caused by signal interference, etc. In order to help make corrections more accurately and ensure that the corrected trajectory is more in line with the actual situation. The present invention needs to treat the data of deviated feature points with caution and make rational use of them, while the data of abnormal feature points that are too extreme or unrepresentative are not needed. The specific analysis steps are as follows:
[0069] Step S410: According to the normal feature points in the trajectory to be detected, all adjacent normal feature points are sorted to obtain m normal movement trajectories; the positioning point of the i-th normal movement trajectory at the terminal position is recorded as , The direction is: The last moment positioning point is the starting point. is the direction of the end point; the positioning point of the i+1th normal moving trajectory at the starting position is recorded as , The direction is: As a starting point, The next moment, the positioning point is the direction of the end point; Direction and anchor point The angle between the directions is expressed as ;in, .
[0070] Step S420: According to the direction angle , get the positioning point and According to the number of positioning points that need to be corrected in the virtual trajectory, the virtual trajectory is evenly divided into several virtual positioning points. and If there are abnormal feature points between them, the positioning points are divided into several virtual positioning points evenly. and The corresponding abnormal feature points are corrected.
[0071] Among them, according to the direction angle , get the positioning point and The virtual tracks include:
[0072] Step S421: If the direction angle , the virtual trajectory is: connecting the positioning points and The straight line between is the direction angle threshold.
[0073] Step S422: If the direction angle , the virtual trajectory is: respectively based on the positioning point and As the starting point, and follow the and The two circles are extended in the direction of until they intersect, and the intersection point is taken as the center of the circle, and the extended length is taken as the radius. An arc is drawn according to the center of the circle and the radius, and the arc is taken as the virtual trajectory.
[0074] Step S430: If the positioning point and There are deviation feature points between them. According to several virtual positioning points evenly distributed, the positioning points and All the deviated feature points between approach the corresponding virtual positioning point in the virtual trajectory; the speed at which each deviated feature point approaches is ,in, For the The moving speed when the deviating feature point approaches, For the The distance between the deviation feature point and the corresponding virtual positioning point in the virtual trajectory, is the set approach time.
[0075] Step S440: The direction of the deviation from the feature point is: the direction starting from the positioning point at the last moment of the current deviation from the feature point and ending at the current deviation from the feature point; if the directions of all the deviation from the feature points are within the direction angle If the distance between the two points is between 0 and 1, the approach is stopped, and the deviation from the feature point is corrected accordingly.
[0076] The present invention establishes a BIM model of a construction site, marks the position of each characteristic punctuation point in the BIM model of the construction site; obtains the positioning trajectory of the safety equipment in real time, and obtains the positioning point set and direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point, and determines whether the positioning trajectory is a trajectory to be detected; marks the normal characteristic points, deviated characteristic points and abnormal characteristic points in the trajectory to be detected; and corrects all the deviated characteristic points and abnormal characteristic points in the trajectory to be detected. The present invention is based on a safety device with a positioning function, and solves the problem that the positioning trajectory of the safety equipment at the construction site cannot be corrected in time through the positioning trajectory of the construction workers at the construction site and the characteristic punctuation points at the construction site. The present invention has the advantages of simple algorithm and easy implementation.
[0077] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0078] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. The intelligent construction management method using multi-dimensional data fusion analysis technology is characterized by: The following steps are involved: Step S100: Obtain the construction site drawings and establish a construction site BIM model, and mark the positions of various characteristic punctuation points in the construction site BIM model, wherein the characteristic punctuation points are facilities or buildings whose positions are fixed and not easily changed; Step S200: The construction worker wears a safety device with a positioning function, obtains the positioning trajectory of the safety device in real time, and obtains a positioning point set and a direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point, and determines whether the positioning trajectory is a trajectory to be detected according to the direction vector set; Step S210: Get the current time as the starting point and go forward The positioning trajectory of the safety device within seconds; set the time interval to g, and subtract the current time from The moment of seconds is taken as the starting moment, and a positioning point set including all positioning points between the starting moment and the current moment is obtained. The number of positioning points in the positioning point set is ; Step S220: Record the location of the safety device at the start time and the current time as and , get the distance and The nearest feature point, and obtain a set of direction vectors with the nearest feature point as the starting point and each positioning point in the positioning point set as the end point , the direction vector set The number of direction vectors in is also ; Step S230: If there is a direction vector set The direction vector in does not satisfy , then the positioning trajectory is determined to be a trajectory to be detected, where is the direction vector difference threshold, are the direction vector sets The direction vector, ; Step S300: if the positioning trajectory is a trajectory to be detected, a reference distance set in the trajectory to be detected is obtained according to the positioning point set, and normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked according to the reference distance set; Step S400: correcting all deviated feature points and abnormal feature points in the trajectory to be detected according to the normal feature points marked in the trajectory to be detected.
2. The intelligent construction management method using multi-dimensional data fusion analysis technology according to claim 1 is characterized in that: Step S300 includes: Step S310: Get the coordinates of all the positioning points in the positioning point set, and get the positioning distances between all the two adjacent positioning points at all times, and mark the positioning distances that are less than the distance threshold, and get the reference distance set according to the adjacent positioning distances with the largest number of marks. The corresponding coordinate points in the reference distance set are all normal feature points, and the coordinates of the initial and final positioning points in the reference distance set are taken as and ; Step S320: Using the coordinates of the final positioning point For example, the positioning point The direction is: based on the positioning point The last moment's positioning point The position is the starting point and the positioning point The position is the direction of the end point; The coordinates of the next moment's positioning point are , then the positioning point The positioning point deviation is ,in, To follow the positioning point A distance of a meters forward in the direction of To follow the positioning point A distance of b meters forward in the opposite direction, a>b>0; Step S330: According to the positioning point Positioning point deviation , for the positioning point Marking; if the positioning point For normal feature points, the positioning point Replace anchor point Otherwise, if the positioning point If it is not a normal feature point, then according to the positioning point Get a reservation location , the predetermined site Replace anchor point Repeat step S320 to step S330 until all normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected are marked.
3. The intelligent construction management method using multi-dimensional data fusion analysis technology according to claim 2 is characterized in that: In step S330, according to the positioning point Get a reservation location To: Set the positioning point The last moment’s positioning point is , get the predetermined site The coordinates are: .
4. The intelligent construction management method using multi-dimensional data fusion analysis technology according to claim 1 is characterized in that: Step S400 includes: Step S410: According to the normal feature points in the trajectory to be detected, all adjacent normal feature points are sorted to obtain m normal movement trajectories; the positioning point of the i-th normal movement trajectory at the terminal position is recorded as , The direction is: The last moment positioning point is the starting point. is the direction of the end point; the positioning point of the i+1th normal moving trajectory at the starting position is recorded as , The direction is: As a starting point, The next moment, the positioning point is the direction of the end point; Direction and positioning point The angle between the directions is expressed as ;in, ; Step S420: According to the direction angle , get the positioning point and According to the number of positioning points that need to be corrected in the virtual trajectory, the virtual trajectory is evenly divided into several virtual positioning points. If the positioning points and If there are abnormal feature points between them, the positioning points are divided into several virtual positioning points evenly. and Correct the abnormal feature points corresponding to each other; Step S430: If the positioning point and There are deviation feature points between them, and the positioning points are divided into several virtual positioning points according to the even distribution. and All the deviated feature points between approach the corresponding virtual positioning point in the virtual trajectory; the speed at which each deviated feature point approaches is ,in, For the The moving speed when the deviating feature point approaches, For the The distance between the deviation feature point and the corresponding virtual positioning point in the virtual trajectory, is the set approach time; Step S440: The direction of the deviation from the feature point is: the direction starting from the positioning point at the last moment of the current deviation from the feature point and ending at the current deviation from the feature point; if the directions of all the deviation from the feature points are within the direction angle in the process of approaching in step S430 If the distance between the two points is between 0 and 1, the approach is stopped, and the deviation from the feature point is corrected accordingly.
5. The intelligent construction management method using multi-dimensional data fusion analysis technology according to claim 4 is characterized in that: In step S420, according to the direction angle , get the positioning point and The virtual tracks include: Step S421: If the direction angle , the virtual track is: connecting the positioning points and The straight line between is the direction angle threshold; Step S422: If the direction angle , the virtual trajectory is: respectively based on the positioning point and As the starting point, and follow the and The two are extended in the direction until they intersect, the intersection point is taken as the center of the circle, the extended length is taken as the radius, an arc is drawn according to the center of the circle and the radius, and the arc is taken as the virtual trajectory.
6. A smart construction management system for executing the smart construction management method using multi-dimensional data fusion analysis technology as described in any one of claims 1 to 5, characterized in that: Includes the following modules: Model building module: used to obtain construction site drawings and build a BIM model of the site, marking the location of each characteristic punctuation in the BIM model of the site. The characteristic punctuation is a facility or building with a fixed position that is not easily changed; The module for the trajectory to be detected is used for construction workers to wear safety equipment with positioning function, obtain the positioning trajectory of the safety equipment in real time, and obtain the positioning point set and direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point, and judge whether the positioning trajectory is the trajectory to be detected according to the direction vector set; Marking feature point module: if the positioning trajectory is a trajectory to be detected, the marking feature point module is used to obtain a reference distance set in the trajectory to be detected according to the positioning point set, and mark the normal feature points, deviated feature points and abnormal feature points in the trajectory to be detected according to the reference distance set; The trajectory correction module is used to correct all the deviated feature points and abnormal feature points in the trajectory to be detected according to the normal feature points marked in the trajectory to be detected.
7. The intelligent construction management system according to claim 6, characterized in that: The to-be-detected trajectory module comprises the following units: a positioning point set unit, a direction vector set unit and a to-be-detected trajectory unit; The positioning point set unit is used to obtain the positioning track of the safety device in real time and obtain the positioning point set of the positioning track; The direction vector set unit is used to obtain the direction vector set of the positioning trajectory according to the positioning trajectory and each characteristic punctuation point; The to-be-detected trajectory unit is used to determine whether the positioning trajectory is a to-be-detected trajectory according to a direction vector set.
8. The intelligent construction management system according to claim 6, characterized in that: The marking feature point module includes the following units: a reference distance set unit, a positioning point deviation unit and a marking feature point unit: The reference distance set unit: if the positioning trajectory is a trajectory to be detected, the reference distance set unit is used to obtain a reference distance set in the trajectory to be detected according to the positioning point set; The positioning point deviation unit is used to obtain the positioning point deviations of all positioning points not in the reference distance set according to the reference distance set; The feature point marking unit is used to mark normal feature points, deviated feature points and abnormal feature points in the to-be-detected trajectory according to the positioning point deviations of all positioning points not in the reference distance set.
Citation Information
Patent Citations
Method and device for correcting driving track, storage medium and electronic equipment
CN111831768A
A system and method for vehicle travel trajectory prediction and trajectory deviation risk assessment
CN112733270A