A full-process engineering consulting management method and management system based on BIM
By collecting and preprocessing various types of data from BIM engineering projects and adjusting the conversion nodes using the Dragonfly optimization algorithm, the problem of low data conversion efficiency in different majors is solved, and the overall efficiency and refined management of BIM engineering consulting management are improved.
Patent Information
- Application Number
- CN202411114246.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-08-14
AI Technical Summary
In BIM engineering consulting management, engineering implementers of different professions have low data conversion efficiency due to differences in data recording and model construction methods and formats, which affects the implementation efficiency of overall engineering consulting management.
By collecting various types of project professional numerical data and model data, preprocessing and distributed system node optimization, adjusting the number of conversion nodes, improving the conversion efficiency of data and model data, and using the Dragonfly optimization algorithm to optimize the conversion nodes to meet the efficiency requirements.
It improves the overall implementation efficiency of BIM engineering projects, ensures the optimal conversion efficiency of data and model data, and achieves more refined engineering project management and analysis.
Smart Images

Figure CN118643432B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the field of engineering consulting management, and in particular, relates to a full-process engineering consulting management method and a management system thereof based on BIM. Background Art
[0002] A Chinese patent with announcement number CN117094472B discloses a BIM-based full-process engineering consulting integrated management method and system, which collects project task data; obtains project categories and delay categories based on task data; obtains matching groups and co-extended task groups based on delay values and tasks; obtains the best embedded graph based on the embedded graph structure and the co-extended task group; obtains key tasks based on the best embedded graph; and performs integrated management based on key tasks to solve the problem of task delays affecting the integrated management of BIM full-process engineering consulting.
[0003] At present, in BIM's engineering consulting management, engineering implementation personnel of different professions are often required to communicate and cooperate. In the process of communication and cooperation, the sharing of their respective professional data is involved. There are generally differences in the way and format of engineering implementation personnel of different professions to record data and build models. Therefore, the data of engineering implementation personnel of different professions need to be converted for mutual analysis; however, the efficiency of converting different types of data is low, which affects and reduces the implementation efficiency of the entire engineering consulting management. Summary of the invention
[0004] In response to the problems in the related technology, the present invention proposes a full-process engineering consulting management method and management system based on BIM to overcome the above-mentioned technical problems existing in the existing related technology.
[0005] To solve the above technical problems, the present invention is achieved through the following technical solutions:
[0006] The present invention is a full-process engineering consulting management method based on BIM, comprising the following steps:
[0007] S1, a first numerical data collection module collects various types of project professional numerical data of multiple BIM engineering projects to obtain a project professional numerical data set matrix;
[0008] The preprocessing module performs preprocessing operations on the project professional numerical data set matrix;
[0009] S2, the first model data collection module collects various types of project professional model data of multiple BIM engineering projects to obtain a project professional model data set matrix;
[0010] S3, the second numerical data collection module collects various types of project professional numerical data to obtain a second project professional numerical data matrix;
[0011] The second model data collection module collects various types of project professional model data to obtain a second project professional model data matrix;
[0012] S4, the distributed system node number optimization module uses the second project professional numerical data matrix and the second project professional model data matrix to optimize the first node number matrix and the second node number matrix respectively, to obtain the first optimal node number matrix and the second optimal node number matrix;
[0013] S5. The data conversion module obtains a final numerical data conversion distributed system and a final model data conversion distributed system according to the first optimal node number matrix and the second optimal node number matrix, and respectively performs data conversion on the preprocessed project professional numerical data set matrix and the project professional model data set matrix through the final numerical data conversion distributed system and the final model data conversion distributed system;
[0014] Data in existing BIM project engineering is generally divided into two categories: numerical data and model data; numerical data refers to data obtained through measurement and other methods in engineering projects; model data refers to model data obtained by professionals in engineering projects by modeling some models in the project; based on the above reasons, the scheme of the present invention collects various types of project professional numerical data and various types of project professional model data of multiple BIM engineering projects, making the collected data more complete and comprehensive, and improving the versatility; then pre-processing operations are performed on the collected various types of project professional numerical data of multiple BIM engineering projects, making the quality of project professional numerical data higher, and facilitating the subsequent correct conversion operations; by collecting various types of project professional numerical data again Professional numerical data and project professional model data provide data support for the subsequent adjustment and optimization of the number of each conversion node in the initial numerical data conversion distributed system and the initial model data conversion distributed system; for the distributed system, selecting an appropriate number of conversion nodes will greatly improve the computing efficiency; therefore, in this scheme, the number of conversion nodes of the initial numerical data conversion distributed system and the initial model data conversion distributed system is continuously optimized and adjusted until the time consumed by the initial numerical data conversion distributed system and the initial model data conversion distributed system for converting numerical data and model data meets the requirements; the numerical data conversion distributed system and the model data conversion distributed system that meet the requirements are then used in actual BIM engineering projects, which is conducive to improving the efficiency of the overall project implementation.
[0015] Preferably, the S1 comprises the following steps:
[0016] S11. Set multiple BIM project types and obtain a set of project types , Indicates the setting BIM project types, Indicates the total number of BIM project engineering types set;
[0017] According to the project type set Set the corresponding engineering project for each type in the project list to get the engineering project set , Indicates the setting Project engineering of project engineering type;
[0018] For the project set Divide each engineering project in the project into stages to obtain the engineering project stage matrix ;as follows,
[0019] ;
[0020] in, Expressing the The project engineering of the project engineering type is divided into stage, Expressing the The total number of phases divided into project projects of the project engineering type;
[0021] S12, the engineering type set Each engineering type in the numerical data professional type is set to obtain the numerical data professional type matrix ;as follows,
[0022] ;
[0023] in, Indicates the setting Project Engineering Type Numeric data professional types, Indicates the setting The total number of project engineering types, numerical data, and professional types;
[0024] According to the numerical data professional type matrix Collection Project Phase Matrix The project professional numerical data of each stage in the project professional numerical data set matrix is obtained ;as follows,
[0025] ;
[0026] in, Indicates The first project of the project type Professional numerical data sets for projects in different stages, , Indicates The first project of the project type The first of the Types of project professional numerical data, Indicates The first project of the project type The total number of project professional numeric data types in each stage;
[0027] S13, performing a preprocessing operation on each project professional numerical data in the project professional numerical data set matrix to obtain a preprocessed project professional numerical data set matrix;
[0028] S14, calculating the data volume of each project professional numerical data in the preprocessed project professional numerical data set matrix to obtain a first project professional numerical data volume matrix;
[0029] The engineering types include industrial project types, agricultural project types, infrastructure project types, social welfare project types, etc.; the engineering project stage matrix includes planning and decision-making stage, survey and design stage, construction stage, use stage, project commissioning stage, project post-evaluation stage, etc.; because the types and amounts of numerical data and model data involved in each type of engineering project and different engineering project stages are different, the analysis and management of various engineering project types and project stages are separated, making the analysis and management more refined, thereby improving the efficiency of engineering projects.
[0030] Preferably, the S13 comprises the following steps:
[0031] S131, setting the data precision corresponding to each numerical data professional type in the numerical data professional type matrix to obtain a data precision threshold matrix;
[0032] S132, perform precision check on each project professional numerical data in the project professional numerical data set matrix according to the data precision threshold matrix; when the precision of the project professional numerical data in the project professional numerical data set matrix is greater than or equal to the data precision threshold in the corresponding data precision threshold matrix, the project professional numerical data is not processed; otherwise, the digits of the project professional numerical data that do not reach the data precision threshold in the corresponding data precision threshold matrix are filled with 0;
[0033] After the accuracy test is completed, the project professional numerical data set matrix after accuracy verification is obtained;
[0034] S133, setting the data range corresponding to each numerical data professional type in the numerical data professional type matrix to obtain a data range interval matrix;
[0035] S134, performing a value range check on the corresponding project professional numerical data in the project professional numerical data set matrix after the accuracy check according to the data range interval matrix; when the project professional numerical data in the project professional numerical data set matrix after the accuracy check is within the data range interval in the corresponding data range interval matrix, the project professional numerical data is processed; otherwise, the project professional numerical data is set as invalid data, the project professional numerical data is collected again, and an accuracy check and a value range check are performed until the accuracy requirements and the interval range requirements are met; the preprocessed project professional numerical data set matrix is obtained;
[0036] Since each type of numerical data in an engineering project has its own accuracy standard and range standard, each project professional numerical data in the project professional numerical data set matrix is verified for accuracy and range, making each project professional numerical data in the project professional numerical data set matrix more accurate, thereby ensuring the accuracy of subsequent conversion of numerical data.
[0037] Preferably, S2 comprises the following steps:
[0038] S21, setting a corresponding model data professional type for each engineering type in the engineering type set to obtain a model data professional type matrix;
[0039] S22, collecting the project professional model data of each stage in the engineering project stage matrix according to the model data professional type matrix to obtain a project professional model data set matrix;
[0040] S23, calculating the data volume of each project professional model data in the project professional model data set matrix to obtain a first project professional model data volume matrix;
[0041] By collecting various types of project professional model data for each engineering project, the model data of the engineering project is also taken into consideration, and the conversion efficiency of the model data is also optimized, thereby further improving the efficiency of the entire engineering project.
[0042] Preferably, S3 comprises the following steps:
[0043] S31, integrating the numerical data professional type of each project engineering in the numerical data professional type matrix to obtain a numerical data professional type set; collecting a plurality of different types of project professional numerical data with different data volumes according to the numerical data professional type set to obtain a second project professional numerical data matrix;
[0044] S32, integrating the model data professional type of each project engineering in the model data professional type matrix to obtain a model data professional type set; collecting a plurality of different types of project professional model data with different data volumes according to the model data professional type set to obtain a second project professional model data matrix;
[0045] Since the size of the data has a direct impact on the efficiency of the conversion, by additionally collecting multiple types of project professional numerical data and project professional model data with different data volumes, data support is provided for the subsequent determination of the optimal number of nodes for various types of project professional numerical data and project professional model data with different data volumes for the initial numerical data conversion distributed system and the initial model data conversion distributed system.
[0046] Preferably, the S4 comprises the following steps:
[0047] S41, constructing an initial numerical data conversion distributed system and an initial model data conversion distributed system; setting the number of nodes for each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system to obtain a first node number matrix and a second node number matrix;
[0048] S42, setting the upper limit and lower limit of the number of nodes of each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system to obtain a first node number value interval matrix and a second node number value interval matrix;
[0049] S43, setting a first time threshold matrix and a second time threshold matrix;
[0050] S44, inputting each column of project professional numerical data in the second project professional numerical data matrix into the initial numerical data conversion distributed system for numerical data conversion; then inputting each column of project professional model data in the second project professional model data matrix into the initial model data conversion distributed system for model data conversion; after the conversion is completed, obtaining a first conversion time matrix and a second conversion time matrix;
[0051] S45. Setting a first probability threshold and the second probability threshold ; Then set the probability that the conversion time in the first conversion time matrix is less than the corresponding time threshold in the first time threshold matrix to The probability that the conversion time in the second conversion time matrix is less than the corresponding time threshold in the second time threshold matrix is ;when When , the first node number matrix is used as the first optimal node number matrix; otherwise, the number of nodes in the first node number matrix is adjusted to obtain the first optimal node number matrix; when , taking the second node number matrix as the second optimal node number matrix; otherwise, adjusting the number of nodes in the second node number matrix to obtain the second optimal node number matrix;
[0052] By testing, the time consumed for data conversion by inputting the second project professional numerical data matrix and the second project professional model data matrix into the initial numerical data conversion distributed system and the initial model data conversion distributed system respectively, when the consumed time exceeds the set time threshold, it means that the conversion efficiency is low, and it is necessary to adjust and optimize the number of conversion nodes in the initial numerical data conversion distributed system and the initial model data conversion distributed system so that the consumed time meets the requirements; thereby determining the basis for optimizing the nodes of the initial numerical data conversion distributed system and the initial model data conversion distributed system, and obtaining the numerical data conversion distributed system and the model data conversion distributed system that can meet the requirements.
[0053] Preferably, in S45, adjusting the number of nodes in the first node number matrix to obtain a first optimal node number matrix comprises the following steps:
[0054] S4511, construct a first dragonfly population; set the maximum number of iterations of the first dragonfly population to , the current number of iterations is ; respectively recorded as the first maximum number of iterations and the first current number of iterations;
[0055] S4512: According to the first node number matrix Randomly generate the initial position of each dragonfly in the first dragonfly population to obtain a first initial position matrix set;
[0056] S4513: Based on the first probability threshold and Set the fitness function of the first dragonfly population;
[0057] S4514, start iteration, and set the first current iteration number is set to 1; in each round of iteration, the fitness value of each dragonfly is calculated according to the fitness function of the first dragonfly population to obtain a first fitness value set; the maximum value in the first fitness value set is selected as the first optimal fitness value, and the dragonfly individual corresponding to the first optimal fitness value is selected as the global optimal dragonfly individual; and the position of each dragonfly in the first dragonfly population is updated according to the first optimal fitness value; after the update is completed, the first current iteration number is plus one;
[0058] S4515, when When , stop iteration; output the first optimal position matrix;
[0059] S4516, using each data in the first optimal position matrix in the initial numerical data conversion distributed system to obtain an optimized numerical data conversion distributed system; inputting each column of project professional numerical data in the second project professional numerical data matrix in S44 into the optimized numerical data conversion distributed system respectively, and using the methods of S44 and S45 to calculate the probability of the conversion time being less than the corresponding time threshold in the first time threshold matrix: ;
[0060] when , the first optimal position matrix is used as the first optimal node number matrix; otherwise, the iterative operation of S4514 is continued until So far, the first optimal node number matrix is obtained;
[0061] Preferably, adjusting the number of nodes in the second node number matrix in S45 to obtain a second optimal node number matrix comprises the following steps:
[0062] S4521, construct a second dragonfly population; set the maximum number of iterations of the second dragonfly population to , the current number of iterations is ; Recorded as the second maximum number of iterations and the second current number of iterations respectively;
[0063] S4522. Randomly generate an initial position of each dragonfly in the second dragonfly population according to the second node number matrix to obtain a second initial position matrix set;
[0064] S4523: According to the second probability threshold and Set the fitness function of the second dragonfly population;
[0065] S4524, start iterating, and set the second current iteration number Set to 1; in each round of iteration, calculate the fitness value of each dragonfly according to the fitness function of the second dragonfly population to obtain a second fitness value set; select the maximum value in the second fitness value set as the second optimal fitness value, and take the dragonfly individual corresponding to the second optimal fitness value as the global optimal dragonfly individual; and update the position of each dragonfly in the second dragonfly population according to the second optimal fitness value; after the update is completed, set the second current iteration number plus one;
[0066] S4525, when When , stop iteration; output the second optimal position matrix;
[0067] S4526, using each data in the second optimal position matrix in the initial model data conversion distributed system to obtain an optimized model data conversion distributed system; inputting each column of project professional model data in the second project professional model data matrix in S44 into the optimized model data conversion distributed system respectively, and using the methods of S44 and S45 to calculate the probability of the conversion time being less than the corresponding time threshold in the second time threshold matrix: ;
[0068] when , the second optimal position matrix is used as the second optimal node number matrix; otherwise, the iterative operation of S4524 is continued until So far, the second optimal node number matrix is obtained;
[0069] By using the dragonfly optimization algorithm to iteratively optimize the node data of the initial numerical data conversion distributed system and the initial model data conversion distributed system, the dragonfly optimization algorithm has fewer parameters and can avoid falling into the local optimal situation. The probability of the number of tests where the time consumed by the conversion is less than the set time threshold is used as the fitness. Therefore, through a certain number of iterative operations, the optimal number of nodes can be obtained, making the conversion efficiency of numerical data and model data the highest.
[0070] Preferably, the S5 comprises the following steps:
[0071] S51, according to the data volume of each project professional numerical data in the first project professional numerical data volume matrix and in conjunction with the first optimal node number matrix, select the number of nodes to form a plurality of final numerical data conversion distributed systems; use the plurality of final numerical data conversion distributed systems for each engineering project in the engineering project set respectively, and input the preprocessed project professional numerical data set matrix into the final numerical data conversion distributed system for numerical data conversion;
[0072] S52, selecting the number of nodes according to the data volume of each project professional model data in the first project professional model data volume matrix and in conjunction with the second optimal node number matrix to form multiple final model data conversion distributed systems; using the multiple final model data conversion distributed systems for each engineering project in the engineering project set, and inputting the project professional model data set matrix into the final model data conversion distributed system for model data conversion;
[0073] After multiple iterations, the optimal number of nodes for different data volumes is obtained, and then the corresponding optimal number of nodes is selected according to the size of each data volume in the first project professional numerical data volume matrix and the first project professional model data volume matrix, so that the conversion efficiency of numerical data and model data in multiple project projects is optimized, thereby improving the implementation efficiency of each project.
[0074] A full-process engineering consulting management system based on BIM includes a first numerical data acquisition module, a preprocessing module, a first model data acquisition module, a second numerical data acquisition module, a second model data acquisition module, a distributed system node number optimization module and a data conversion module.
[0075] The present invention has the following beneficial effects:
[0076] 1. In the present invention, various types of project professional numerical data and various types of project professional model data of multiple BIM engineering projects are collected, so that the collected data are more complete and comprehensive, and the versatility is improved; then the collected various types of project professional numerical data of multiple BIM engineering projects are preprocessed to make the quality of the project professional numerical data higher, which is convenient for subsequent correct conversion operations; the number of conversion nodes of the initial numerical data conversion distributed system and the initial model data conversion distributed system are continuously optimized and adjusted until the time consumed by the two distributed systems for the conversion of numerical data and model data meets the requirements; then the two distributed systems that meet the requirements are used in actual BIM engineering projects, which is beneficial to improving the efficiency of the overall project implementation.
[0077] 2. The present invention analyzes and manages various types of engineering projects and project stages separately, making the analysis and management more refined, thereby better improving the efficiency of engineering projects.
[0078] 3. In the present invention, the dragonfly optimization algorithm is used to iteratively optimize the node data of the initial numerical data conversion distributed system and the initial model data conversion distributed system, and the probability of the number of tests where the time consumed by the conversion is less than the set time threshold is used as the fitness. Through a certain number of iterative operations, the optimal number of nodes can be obtained, so that the conversion efficiency of the numerical data and the model data is optimized.
[0079] Of course, any product implementing the present invention does not necessarily need to achieve all of the advantages described above at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0080] In order to more clearly illustrate the technical solutions of the embodiments of the invention, the drawings required for describing the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the invention. For ordinary technicians in this field, they can also obtain drawings based on these drawings without paying creative work.
[0081] Figure 1 A schematic diagram of a process of converting numerical data in a project by a full-process engineering consulting management system based on BIM according to the present invention;
[0082] Figure 2 The present invention is a flow chart of a BIM-based full-process engineering consulting management system for converting model data in a project. DETAILED DESCRIPTION
[0083] The following will be combined with the drawings in the embodiments of the invention to clearly and completely describe the technical solutions in the embodiments of the invention. Obviously, the described embodiments are only part of the embodiments of the invention, not all of the embodiments. Based on the embodiments in the invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the invention.
[0084] In the description of the present invention, it is necessary to understand that the terms "opening", "upper", "lower", "top", "middle", "inside" and the like indicating orientation or positional relationship are only for the convenience of describing the invention and simplifying the description, and do not indicate or imply that the components or elements referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore cannot be understood as limiting the invention.
[0085] Embodiment 1
[0086] This embodiment is a full-process engineering consulting management method based on BIM, comprising the following steps:
[0087] S1, a first numerical data collection module collects various types of project professional numerical data of multiple BIM engineering projects to obtain a project professional numerical data set matrix;
[0088] The preprocessing module performs preprocessing operations on the project professional numerical data set matrix;
[0089] The S1 comprises the following steps:
[0090] S11. Set multiple BIM project types and obtain a set of project types , Indicates the setting BIM project types, Indicates the total number of BIM project engineering types set;
[0091] According to the project type set Set the corresponding engineering project for each type in the project list to get the engineering project set , Indicates the setting Project engineering of project engineering type;
[0092] For the project set Divide each engineering project in the project into stages to obtain the engineering project stage matrix ;as follows,
[0093] ;
[0094] in, Expressing the The project engineering of the project engineering type is divided into stage, Expressing the The total number of phases divided into project projects of the project engineering type;
[0095] S12, the engineering type set Each engineering type in the numerical data professional type is set to obtain the numerical data professional type matrix ;as follows,
[0096] ;
[0097] in, Indicates the setting Project Engineering Type Numeric data professional types, Indicates the setting The total number of project engineering types, numerical data, and professional types;
[0098] According to the numerical data professional type matrix Collection Project Phase Matrix The project professional numerical data of each stage in the project professional numerical data set matrix is obtained ;as follows,
[0099] ;
[0100] in, Indicates The first project of the project type Professional numerical data sets for projects in different stages, , Indicates The first project of the project type The first of the Types of project professional numerical data, Indicates The first project of the project type The total number of project professional numeric data types in each stage;
[0101] S13, the professional numerical data set matrix of the project Each project professional numerical data in is preprocessed to obtain the preprocessed project professional numerical data set matrix ;as follows,
[0102] ;
[0103] in, Express The project professional numerical data is obtained by preprocessing each project professional numerical data; , Express Project professional numerical data obtained after preprocessing;
[0104] The S13 comprises the following steps:
[0105] S131, setting the numerical data professional type matrix The data accuracy corresponding to each type of numerical data professional is obtained to obtain the data accuracy threshold matrix ;as follows,
[0106] ;
[0107] in, Indicates Project type Data accuracy thresholds for professional types of numerical data;
[0108] S132: According to the data accuracy threshold matrix Matrix of professional numerical datasets for the project Each project professional numerical data is checked for accuracy; when the project professional numerical data set matrix The precision of the project professional numerical data is greater than or equal to the corresponding data precision threshold matrix If the data accuracy threshold in the matrix is reached, the professional numerical data of the project will not be processed; otherwise, if the professional numerical data of the project does not reach the corresponding data accuracy threshold matrix The digits of the data precision threshold in are filled with 0;
[0109] After the accuracy test is completed, the project professional numerical data set matrix after accuracy verification is obtained;
[0110] S133, setting the professional type matrix of the numerical data The data range corresponding to each type of numerical data professional is obtained to obtain the data range interval matrix ;as follows,
[0111] ;
[0112] in, and Respectively represent Project type The lower and upper limits of the numerical data of the project professional type;
[0113] S134, according to the data range interval matrix Perform value range check on the corresponding project professional numerical data in the project professional numerical data set matrix after precision check; when the project professional numerical data in the project professional numerical data set matrix after precision check is within the corresponding data range interval matrix If the data is within the range of the data, the project professional numerical data is processed; otherwise, the project professional numerical data is set to invalid data, the project professional numerical data is collected again, and the accuracy check and value range check are performed until the accuracy requirements and the interval range requirements are met; the preprocessed project professional numerical data set matrix is obtained. ;
[0114] S14, calculating the preprocessed project professional numerical data set matrix The amount of professional numerical data for each project in the first project professional numerical data matrix is obtained. ;as follows,
[0115] ;
[0116] in, express The data volume collection of each project professional numerical data, , express The amount of data;
[0117] S2, the first model data collection module collects various types of project professional model data of multiple BIM engineering projects to obtain a project professional model data set matrix;
[0118] The S2 comprises the following steps:
[0119] S21, the engineering type set Each engineering type in the model data professional type is set to obtain the model data professional type matrix ;as follows,
[0120] ;
[0121] in, Indicates the setting Project Engineering Type Model data professional type, Indicates the setting The total number of model data professional types of project engineering types;
[0122] S22, according to the professional type matrix of the model data Collection Project Phase Matrix The project professional model data of each stage in the project professional model data set matrix is obtained ;as follows,
[0123] ;
[0124] in, Indicates The first project of the project type Project professional model datasets for each stage, , Indicates The first project of the project type The first of the Types of project professional model data, Indicates The first project of the project type The total number of project professional model data types in each phase;
[0125] S23, calculating the project professional model data set matrix The amount of professional model data for each project in the first project professional model data matrix is obtained ;as follows,
[0126] ;
[0127] in, express The data volume of each project professional model data is collected, , express The amount of data;
[0128] S3, the second numerical data collection module collects various types of project professional numerical data to obtain a second project professional numerical data matrix;
[0129] The second model data collection module collects various types of project professional model data to obtain a second project professional model data matrix;
[0130] The S3 comprises the following steps:
[0131] S31, the professional type matrix of the numerical data The numerical data professional type of each project engineering is integrated to obtain the numerical data professional type set , Indicates the integrated Numeric data professional types, Indicates the total number of professional types of numerical data obtained through integration;
[0132] According to the numerical data professional type set Collect different types of project professional numerical data with different data volumes to obtain the second project professional numerical data matrix ;as follows,
[0133] ;
[0134] in, Indicates Of the numerical data professional types Project professional numerical data of various data volumes, Indicates the total number of project professional numerical data with different data volumes in each numerical data professional type;
[0135] S32: the model data professional type matrix The model data professional type of each project engineering is integrated to obtain the model data professional type set , Indicates the integrated Model data professional type, Indicates the total number of professional types of model data obtained through integration;
[0136] According to the model data professional type set Collect different types of project professional model data with different data volumes to obtain the second project professional model data matrix ;as follows,
[0137] ;
[0138] in, Indicates Model data professional type Project professional model data of various data volumes, Indicates the total number of project professional model data with different data volumes in each model data professional type;
[0139] S4, the distributed system node number optimization module uses the second project professional numerical data matrix and the second project professional model data matrix to optimize the first node number matrix and the second node number matrix respectively, to obtain the first optimal node number matrix and the second optimal node number matrix;
[0140] The S4 comprises the following steps:
[0141] S41, constructing an initial numerical data conversion distributed system and an initial model data conversion distributed system; setting the number of nodes for each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system, and obtaining a first node number matrix and the second node number matrix ; They are as follows,
[0142] ; ;
[0143] in, Represents the initial numerical data conversion distributed system for the The first step of professional numerical data conversion for medium-volume projects The number of nodes for the conversion task, Represents the initial numerical data conversion distributed system for the The total number of transformation tasks for medium data volume; Represents the initial model data conversion distributed system for the first The first step of project professional model data conversion with medium data volume The number of nodes for a conversion task; The calculation formula is as follows,
[0144] ;
[0145] S42: Set the upper and lower limits of the number of nodes for each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system to obtain a first node number value interval matrix and the second node number value interval matrix ; They are as follows,
[0146] ;
[0147] ;
[0148] in, and They represent the initial numerical data conversion distributed system for the The first step of professional numerical data conversion for medium-volume projects The lower and upper limits of the number of nodes for a conversion task; and They represent the initial model data conversion distributed system for the The first step of project professional model data conversion with medium data volume The lower and upper limits of the number of nodes for a conversion task;
[0149] S43, setting the first time threshold matrix and the second time threshold matrix , respectively as follows,
[0150] ; ;
[0151] in, Indicates the initial numerical data conversion in the distributed system for the first The first step of professional numerical data conversion for medium-volume projects The threshold for setting the time consumption of each conversion task; Indicates the initial model data conversion distributed system for the first The first step of project professional model data conversion with medium data volume The threshold of the time consumption of a conversion task;
[0152] S44, the second project professional numerical data matrix Each column of project professional numerical data in the initial numerical data conversion distributed system is input into the initial numerical data conversion distributed system for numerical data conversion; then the second project professional model data matrix Each column of project professional model data in is input into the initial model data conversion distributed system for model data conversion; after the conversion is completed, the first conversion time matrix is obtained and the second conversion time matrix ; They are as follows,
[0153] ; ;
[0154] in, Represents the initial numerical data conversion distributed system for the The first step of professional numerical data conversion for medium-volume projects The time it takes to complete a conversion task; Represents the initial model data conversion distributed system for the first The first step of project professional model data conversion with medium data volume The time it takes to complete a conversion task;
[0155] S45. Setting a first probability threshold and the second probability threshold ; Then set the first conversion time matrix The transition time in the matrix is less than the first time threshold The probability of the corresponding time threshold occurring is , the second conversion time matrix The transition time in the matrix is less than the second time threshold The probability of the corresponding time threshold occurring is ;
[0156] when When the first node number matrix As the first optimal node number matrix; otherwise, the first node number matrix The number of nodes is adjusted to obtain the first optimal node number matrix;
[0157] when When the second node number matrix As the second optimal node number matrix; otherwise, the second node number matrix The number of nodes is adjusted to obtain the second optimal node number matrix;
[0158] In S45, the first node number matrix The number of nodes in each matrix is adjusted to obtain the first optimal node number matrix, which includes the following steps:
[0159] S4511. Establishing the first dragonfly population , Indicates the first dragonfly population A dragonfly, represents the size of the first dragonfly population; sets the maximum number of iterations of the first dragonfly population to , the current number of iterations is ; respectively recorded as the first maximum number of iterations and the first current number of iterations; and then the search space dimension of the first dragonfly population is set to ;
[0160] S4512: According to the first node number matrix Randomly generate the initial position of each dragonfly in the first dragonfly population and obtain the first initial position matrix set , Indicates the first dragonfly population The initial position matrix of a dragonfly is as follows:
[0161] ;
[0162] in, express The initial numerical data conversion in the distributed system is The first step of professional numerical data conversion for medium-volume projects The dimension component of the number of nodes of a conversion task; the calculation formula is as follows,
[0163] ;
[0164] In the formula, represents the rounding function, Indicates for Generated random numbers;
[0165] S4513: Based on the first probability threshold and Set the fitness function of the first dragonfly population ;as follows,
[0166] ;
[0167] In the formula, is a positive number, indicating the first correction parameter;
[0168] S4514, start iteration, and set the first current iteration number Set to 1; in each iteration, according to the fitness function of the first dragonfly population Calculate the fitness value of each dragonfly to obtain a first fitness value set; select the maximum value in the first fitness value set as the first optimal fitness value, and use the dragonfly individual corresponding to the first optimal fitness value as the global optimal dragonfly individual; and update the position of each dragonfly in the first dragonfly population according to the first optimal fitness value; after the update is completed, update the first current iteration number plus one;
[0169] S4515, when When , stop the iteration; output the first optimal position matrix ;as follows,
[0170] ;
[0171] in, The first optimal position matrix represents the initial numerical data conversion distributed system for the first The first step of professional numerical data conversion for medium-volume projects The dimension component of the number of nodes of a transformation task;
[0172] S4516: The first optimal position matrix The various data in the initial numerical data conversion distributed system are used to obtain an optimized numerical data conversion distributed system;
[0173] The second project professional numerical data matrix in S44 Each column of project professional numerical data in is respectively input into the optimized numerical data conversion distributed system, and the conversion time is less than the first time threshold matrix calculated by S44 and S45. The probability of the corresponding time threshold occurring is ;
[0174] when When the first optimal position matrix As the first optimal node number matrix; otherwise, continue the iterative operation of S4514 until So far, the first optimal node number matrix is obtained;
[0175] In S45, the second node number matrix The number of nodes is adjusted to obtain the second optimal node number matrix, which includes the following steps:
[0176] S4521. Construct the second dragonfly population , Indicates the second dragonfly population A dragonfly, represents the size of the second dragonfly population; sets the maximum number of iterations of the second dragonfly population to , the current number of iterations is ; respectively recorded as the second maximum number of iterations and the second current number of iterations; and then set the search space dimension of the second dragonfly population to ;
[0177] S4522: According to the second node number matrix Randomly generate the initial position of each dragonfly in the second dragonfly population and obtain the second initial position matrix set , Indicates the second dragonfly population The initial position matrix of the dragonfly is as follows:
[0178] ;
[0179] in, express The initial model data conversion distributed system is represented by The first step of project professional model data conversion with medium data volume The dimension component of the number of nodes of a conversion task; the calculation formula is as follows,
[0180] ;
[0181] In the formula, Indicates for Generated random numbers;
[0182] S4523: According to the second probability threshold and Set the fitness function of the second dragonfly population ;as follows,
[0183] ;
[0184] In the formula, is a positive number, indicating the second correction parameter;
[0185] S4524, start iterating, and set the second current iteration number Set to 1; in each iteration, the fitness function of the second dragonfly population is used. Calculate the fitness value of each dragonfly to obtain a second fitness value set; select the maximum value in the second fitness value set as the second optimal fitness value, and use the dragonfly individual corresponding to the second optimal fitness value as the global optimal dragonfly individual; and update the position of each dragonfly in the second dragonfly population according to the second optimal fitness value; after the update is completed, the second current iteration number plus one;
[0186] S4525, when When , stop the iteration; output the second optimal position matrix ;as follows,
[0187] ;
[0188] in, The second optimal position matrix represents the initial model data conversion distributed system for the first The first step of project professional model data conversion with medium data volume The dimension component of the number of nodes of a transformation task;
[0189] S4526: The second optimal position matrix The various data in the initial model data conversion distributed system are used to obtain an optimized model data conversion distributed system;
[0190] The second project professional model data matrix in S44 Each column of project professional model data in is respectively input into the optimized model data conversion distributed system, and the conversion time is calculated to be less than the second time threshold matrix by using S44 and S45. The probability of the corresponding time threshold occurring is ;
[0191] when When the second optimal position matrix As the second optimal node number matrix; otherwise, continue the iterative operation of S4524 until So far, the second optimal node number matrix is obtained;
[0192] S5. The data conversion module obtains a final numerical data conversion distributed system and a final model data conversion distributed system according to the first optimal node number matrix and the second optimal node number matrix, and respectively performs data conversion on the preprocessed project professional numerical data set matrix and the project professional model data set matrix through the final numerical data conversion distributed system and the final model data conversion distributed system;
[0193] The S5 comprises the following steps:
[0194] S51, according to the professional numerical data quantity matrix of the first project The amount of professional numerical data of each project in the data set and the number of nodes selected in conjunction with the first optimal node number matrix constitute multiple final numerical data conversion distributed systems;
[0195] The plurality of final numerical data conversion distributed systems are respectively used for engineering project sets In each engineering project, the preprocessed project professional numerical data set matrix Input final numerical data conversion to perform numerical data conversion in distributed system;
[0196] S52: Based on the professional model data matrix of the first project The amount of professional model data of each project in the data set and the number of nodes selected in conjunction with the second optimal node number matrix constitute multiple final model data conversion distributed systems;
[0197] The plurality of final model data conversion distributed systems are respectively used for engineering project sets In each engineering project, the project professional model dataset matrix The final model data is input into the distributed system for model data conversion.
[0198] Embodiment 2
[0199] This embodiment discloses a full-process engineering consulting management system based on BIM, which can implement the method of the above embodiment, including a first numerical data acquisition module, a preprocessing module, a first model data acquisition module, a second numerical data acquisition module, a second model data acquisition module, a distributed system node number optimization module and a data conversion module;
[0200] The first numerical data collection module is used to collect various types of project professional numerical data of multiple BIM engineering projects to obtain a project professional numerical data set matrix;
[0201] The preprocessing module is used to perform a preprocessing operation on the project professional numerical data set matrix to obtain a preprocessed project professional numerical data set matrix;
[0202] The first model data acquisition module is used to collect various types of project professional model data of multiple BIM engineering projects to obtain a project professional model data set matrix;
[0203] The second numerical data collection module is used to collect various types of project professional numerical data to obtain a second project professional numerical data matrix;
[0204] The second model data collection module is used to collect various types of project professional model data to obtain a second project professional model data matrix;
[0205] The distributed system node number optimization module is used to optimize the first node number matrix and the second node number matrix respectively by using the second project professional numerical data matrix and the second project professional model data matrix to obtain the first optimal node number matrix and the second optimal node number matrix;
[0206] The data conversion module is used to obtain a final numerical data conversion distributed system and a final model data conversion distributed system according to the first optimal node number matrix and the second optimal node number matrix, and to perform data conversion on the preprocessed project professional numerical data set matrix and the project professional model data set matrix respectively through the final numerical data conversion distributed system and the final model data conversion distributed system.
[0207] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.
[0208] The preferred embodiments of the invention disclosed above are only used to help explain the invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to the specific implementation methods described. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the invention, so that those skilled in the art can understand and use the invention well.
Claims
1. A full-process engineering consulting management method based on BIM, It is characterized in that The following steps are involved: S1, a first numerical data collection module collects various types of project professional numerical data of multiple BIM engineering projects to obtain a project professional numerical data set matrix; The preprocessing module performs preprocessing operations on the project professional numerical data set matrix; S2, the first model data collection module collects various types of project professional model data of multiple BIM engineering projects to obtain a project professional model data set matrix; S3, the second numerical data collection module collects various types of project professional numerical data to obtain a second project professional numerical data matrix; The second model data collection module collects various types of project professional model data to obtain a second project professional model data matrix; S4, the distributed system node number optimization module uses the second project professional numerical data matrix and the second project professional model data matrix to optimize the first node number matrix and the second node number matrix respectively; The S4 comprises the following steps: S41, constructing an initial numerical data conversion distributed system and an initial model data conversion distributed system; setting the number of nodes for each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system to obtain a first node number matrix and a second node number matrix; S42, setting the upper limit and lower limit of the number of nodes of each conversion task of the initial numerical data conversion distributed system and the initial model data conversion distributed system to obtain a first node number value interval matrix and a second node number value interval matrix; S43, setting a first time threshold matrix and a second time threshold matrix; S44, inputting each column of project professional numerical data in the second project professional numerical data matrix into the initial numerical data conversion distributed system for numerical data conversion; then inputting each column of project professional model data in the second project professional model data matrix into the initial model data conversion distributed system for model data conversion; after the conversion is completed, obtaining a first conversion time matrix and a second conversion time matrix; S45. Setting a first probability threshold and the second probability threshold Then, the probability that the conversion time in the first conversion time matrix is less than the corresponding time threshold in the first time threshold matrix is set to The probability that the conversion time in the second conversion time matrix is less than the corresponding time threshold in the second time threshold matrix is: when When , the first node number matrix is used as the first optimal node number matrix; otherwise, the number of nodes in the first node number matrix is adjusted to obtain the first optimal node number matrix; when , taking the second node number matrix as the second optimal node number matrix; otherwise, adjusting the number of nodes in the second node number matrix to obtain the second optimal node number matrix; In S45, the number of nodes in each of the first node number matrix is adjusted to obtain a first optimal node number matrix, which includes the following steps: S4511, construct a first dragonfly population; set the maximum number of iterations of the first dragonfly population to The current number of iterations is They are respectively recorded as the first maximum number of iterations and the first current number of iterations; S4512. Randomly generate an initial position of each dragonfly in the first dragonfly population according to the first node number matrix to obtain a first initial position matrix set; S4513: Based on the first probability threshold and Set the fitness function of the first dragonfly population; S4514, start iteration, and set the first current iteration number Set to 1; in each iteration, the position of each dragonfly in the first dragonfly population is updated according to the fitness function of the first dragonfly population; S4515, when When , stop iteration; output the first optimal position matrix; S4516, using each data in the first optimal position matrix in the initial numerical data conversion distributed system to obtain an optimized numerical data conversion distributed system; inputting each column of project professional numerical data in the second project professional numerical data matrix in S44 into the optimized numerical data conversion distributed system respectively, and using the method of S44 and S45 to calculate the probability of the conversion time being less than the corresponding time threshold in the first time threshold matrix as h~ 5 ; When h~ 5 ≥h~ 1 , the first optimal position matrix is used as the first optimal node number matrix; otherwise, the iterative operation of S4514 is continued until h~ 5 ≥h~ 1 So far, the first optimal node number matrix is obtained; S5. The data conversion module performs data conversion on the preprocessed project professional numerical data set matrix and project professional model data set matrix.
2. According to the BIM-based full-process engineering consulting management method of claim 1, It is characterized in that The S1 comprises the following steps: S11. Set multiple BIM project engineering types to obtain an engineering type set; According to each type in the engineering type set, a corresponding engineering project is set to obtain an engineering project set; each engineering project in the engineering project set is divided into stages to obtain an engineering project stage matrix; S12, setting a corresponding numerical data professional type for each engineering type in the engineering type set to obtain a numerical data professional type matrix; collecting project professional numerical data of each stage in the engineering project stage matrix according to the numerical data professional type matrix to obtain a project professional numerical data set matrix; S13, performing a preprocessing operation on each project professional numerical data in the project professional numerical data set matrix to obtain a preprocessed project professional numerical data set matrix; S14, calculating the data volume of each project professional numerical data in the preprocessed project professional numerical data set matrix to obtain a first project professional numerical data volume matrix.
3. According to the BIM-based full-process engineering consulting management method of claim 2, It is characterized in that The S13 comprises the following steps: S131, setting the data precision corresponding to each numerical data professional type in the numerical data professional type matrix to obtain a data precision threshold matrix; S132, performing accuracy check on each project professional numerical data in the project professional numerical data set matrix according to the data accuracy threshold matrix; after the accuracy check is completed, obtaining the project professional numerical data set matrix after accuracy check; S133, setting the data range corresponding to each numerical data professional type in the numerical data professional type matrix to obtain a data range interval matrix; S134, performing a value range check on the corresponding project professional numerical data in the project professional numerical data set matrix after the accuracy check according to the data range interval matrix; after the value range check is completed, a preprocessed project professional numerical data set matrix is obtained.
4. According to the BIM-based full-process engineering consulting management method of claim 3, It is characterized in that The S2 comprises the following steps: S21, setting a corresponding model data professional type for each engineering type in the engineering type set to obtain a model data professional type matrix; S22, collecting the project professional model data of each stage in the engineering project stage matrix according to the model data professional type matrix to obtain a project professional model data set matrix; S23. Calculate the data volume of each project professional model data in the project professional model data set matrix to obtain a first project professional model data volume matrix.
5. According to the BIM-based full-process engineering consulting management method of claim 4, It is characterized in that The S3 comprises the following steps: S31, integrating the numerical data professional type of each project engineering in the numerical data professional type matrix to obtain a numerical data professional type set; collecting a plurality of different types of project professional numerical data with different data volumes according to the numerical data professional type set to obtain a second project professional numerical data matrix; S32. Integrate the model data professional type of each project engineering in the model data professional type matrix to obtain a model data professional type set; collect different types of project professional model data with different data volumes according to the model data professional type set to obtain a second project professional model data matrix.
6. According to the BIM-based full-process engineering consulting management method of claim 5, It is characterized in that In S45, the number of nodes in the second node number matrix is adjusted to obtain a second optimal node number matrix, which includes the following steps: S4521, construct a second dragonfly population; set the maximum number of iterations of the second dragonfly population to The current number of iterations is Denoted as the second maximum number of iterations and the second current number of iterations respectively; S4522. Randomly generate an initial position of each dragonfly in the second dragonfly population according to the second node number matrix to obtain a second initial position matrix set; S4523: According to the second probability threshold and Set the fitness function of the second dragonfly population; S4524, start iteration, and in each round of iteration, update the position of each dragonfly in the second dragonfly population according to the fitness function of the second dragonfly population; S4525, when When , stop iteration; output the second optimal position matrix; S4526, using each data in the second optimal position matrix in the initial model data conversion distributed system to obtain an optimized model data conversion distributed system; inputting each column of project professional model data in the second project professional model data matrix in S44 into the optimized model data conversion distributed system respectively, and using the methods of S44 and S45 to calculate the probability of the conversion time being less than the corresponding time threshold in the second time threshold matrix: when , the second optimal position matrix is used as the second optimal node number matrix; otherwise, the iterative operation of S4524 is continued until So far, the second optimal node number matrix is obtained.
7. According to the BIM-based full-process engineering consulting management method of claim 6, It is characterized in that The S5 comprises the following steps: S51, according to the data volume of each project professional numerical data in the first project professional numerical data volume matrix and in conjunction with the first optimal node number matrix, select the number of nodes to form a plurality of final numerical data conversion distributed systems; use the plurality of final numerical data conversion distributed systems for each engineering project in the engineering project set respectively, and input the preprocessed project professional numerical data set matrix into the final numerical data conversion distributed system for numerical data conversion; S52. According to the data volume of each project professional model data in the first project professional model data volume matrix and in conjunction with the second optimal node number matrix, the number of nodes is selected to form multiple final model data conversion distributed systems; the multiple final model data conversion distributed systems are respectively used for each engineering project in the engineering project set, and the project professional model data set matrix is input into the final model data conversion distributed system for model data conversion.
8. A system for implementing the BIM-based full-process engineering consulting management method as described in any one of claims 1 to 7, Features: It includes a first numerical data acquisition module, a preprocessing module, a first model data acquisition module, a second numerical data acquisition module, a second model data acquisition module, a distributed system node number optimization module and a data conversion module; The first numerical data collection module is used to collect various types of project professional numerical data of multiple BIM engineering projects to obtain a project professional numerical data set matrix; The preprocessing module is used to perform a preprocessing operation on the project professional numerical data set matrix to obtain a preprocessed project professional numerical data set matrix; The first model data acquisition module is used to collect various types of project professional model data of multiple BIM engineering projects to obtain a project professional model data set matrix; The second numerical data collection module is used to collect various types of project professional numerical data to obtain a second project professional numerical data matrix; The second model data collection module is used to collect various types of project professional model data to obtain a second project professional model data matrix; The distributed system node number optimization module is used to optimize the first node number matrix and the second node number matrix respectively by using the second project professional numerical data matrix and the second project professional model data matrix to obtain the first optimal node number matrix and the second optimal node number matrix; The data conversion module is used to obtain a final numerical data conversion distributed system and a final model data conversion distributed system according to the first optimal node number matrix and the second optimal node number matrix, and to perform data conversion on the preprocessed project professional numerical data set matrix and the project professional model data set matrix respectively through the final numerical data conversion distributed system and the final model data conversion distributed system.