A remote monitoring method for high and low voltage switch cabinets

By analyzing the history and real-time data of high and low voltage switch cabinets and calculating the parameter curve similarity, the problem that high and low voltage switch cabinets cannot monitor parameters in real time is solved, and the accurate judgment and output of high and low voltage conversion abnormal parameters are achieved, and the stability of the equipment is improved Sex and safety.

CN118646160BActive Publication Date: 2024-11-01HUNAN HUANENG ELECTRICAL MFG COMPANY
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411088431.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-09
Publication Date
2024-11-01
Estimated Expiration
2044-08-09

AI Technical Summary

Technical Problem

The high and low voltage switch cabinet cannot monitor various parameters in real time during the high and low voltage conversion process, resulting in an increase in the failure rate and the abnormal parameter types cannot be identified in time.

Method used

By obtaining and preprocessing the historical data of high and low voltage switch cabinets, analyzing the parameter curves during high and low voltage conversion, obtaining real-time values ​​in real-time, calculating the similarity of the parameter curve, determining the abnormal parameter type, and outputting it to the remote display terminal.

Benefits of technology

Real-time monitoring of various parameters by high and low voltage switch cabinets during high and low voltage conversion, accurately judge abnormal parameter types, improve operational stability and safety, and reduce failure rate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118646160B_ABST
    Figure CN118646160B_ABST
Patent Text Reader

Abstract

The invention discloses a remote monitoring method for high and low voltage switch cabinets, which relates to the technical field of high and low voltage switch cabinet monitoring, and comprises the following steps: in a high voltage conversion process, real-time values ​​of various parameters are acquired in real time and real-time parameter curves of various parameters are obtained, the stage similarity between the real-time parameter curves of various parameters and the high voltage conversion transformation curve is calculated, the type of abnormal high voltage conversion parameter is determined according to the stage similarity of various parameters, and the abnormal high voltage conversion parameter type is output to a remote display terminal; when the high and low voltage switch cabinet performs high and low voltage conversion, the type of abnormal high voltage conversion parameter and the type of abnormal low voltage conversion parameter are determined according to the stage similarity of various parameters, and the abnormal low voltage conversion parameter is output to a remote display terminal, so as to realize the problem of monitoring various parameters when the high and low voltage switch cabinet performs high and low voltage conversion, improve the operation stability and safety of the high and low voltage switch cabinet, and reduce the failure rate of the high and low voltage switch cabinet when performing high and low voltage conversion.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of high and low voltage switch cabinet monitoring, and in particular to a remote monitoring method for high and low voltage switch cabinets. Background Art

[0002] With the development of technology, intelligent and digital technologies have been widely used in high and low voltage switchgear, improving the reliability and efficiency of the system. The core function of high and low voltage switchgear is to convert high voltage into low voltage for end users, or vice versa, to increase low voltage to high voltage for long-distance transmission. For example, the power supply bureau will use high-voltage cabinets, which will be transferred to low-voltage cabinets after voltage reduction through transformers, and then further distributed to various power consumption points; the reduction in voltage not only facilitates the utilization of electric energy, but is also an important means to reduce transmission losses and improve energy efficiency. Accordingly, this affects the cabinet design and the selection of technical parameters, ensuring the safety of operators and equipment.

[0003] However, when the high and low voltage switchgear is performing high and low voltage conversion, it is impossible to monitor the various parameters of the high and low voltage switchgear in real time, and it is impossible to monitor the abnormal parameter types of the high and low voltage conversion in time, resulting in an increase in the failure rate of the high and low voltage switchgear during high and low voltage conversion; based on this, a remote monitoring method for high and low voltage switchgear is proposed. Summary of the invention

[0004] The purpose of the present invention is to provide a remote monitoring method for high and low voltage switch cabinets, which solves the technical problem that when the high and low voltage switch cabinets are performing high and low voltage conversion, the various parameters of the high and low voltage switch cabinets cannot be monitored in real time, and the abnormal parameter types of the high and low voltage conversion cannot be monitored in time.

[0005] The purpose of the present invention can be achieved through the following technical solutions:

[0006] A remote monitoring method for high and low voltage switch cabinets comprises the following steps:

[0007] Step 1: Obtain historical data of various parameters of the high and low voltage switchgear when performing high and low voltage conversion, including input voltage, output voltage, input current, output current, input pressure and output pressure;

[0008] Step 2: Preprocess the historical data of various parameters obtained;

[0009] Step 3: According to the duration of high-voltage conversion in the preset number of times z of the high-voltage and low-voltage switchgear, determine the high-voltage conversion duration interval, set multiple conversion time points in the high-voltage conversion duration interval, analyze the historical data of various parameters of the high-voltage and low-voltage switchgear at various conversion time points when performing high-voltage conversion, and obtain the high-voltage conversion transformation curves corresponding to various parameters when performing high-voltage conversion and the high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear, z is the preset number, z is a positive integer, and the specific value range is: 90≥z≥2;

[0010] Step 4: During the high-voltage conversion process, the real-time values ​​of various parameters are obtained in real time and the real-time parameter curves of various parameters are obtained, the stage similarity between the real-time parameter curves of various parameters and the high-voltage conversion transformation curve is calculated, and the type of abnormal high-voltage conversion parameters is determined according to the stage similarity of various parameters, and the abnormal parameters are output to the remote display terminal;

[0011] Step 5: Use the same method as steps 3 and 4 to analyze the historical data of various parameters at each conversion time point during low voltage conversion, determine the type of abnormal low voltage conversion parameters, and output them to the remote display terminal.

[0012] As a further solution of the present invention: the specific method of determining the high speed duration interval is:

[0013] Get the maximum value GT of the high-voltage conversion time GTz corresponding to the high-voltage conversion of the high-voltage and low-voltage switch cabinets when performing the preset number of z high-voltage conversions. max and minimum GT min , through the maximum value GT max and minimum GT min Combined generation of high-speed time zone [GT min , GT max ].

[0014] As a further solution of the present invention: the specific method of setting multiple switching time points within the high speed duration interval is:

[0015] In [GT min , GT max ]A few transition time points ZTa are randomly set within the frame, and the interval between each transition time point ZTa is JT, where a is the number of transition time points, a is a positive integer, and the specific duration of JT is 10 minutes.

[0016] As a further solution of the present invention: the specific method of obtaining the high-voltage conversion transformation curves corresponding to various parameters during high-voltage conversion and the high-voltage conversion parameter curve comparison table corresponding to the high- and low-voltage switch cabinets is:

[0017] S1: arbitrarily obtain one type of parameter from various types of parameters as analysis parameters;

[0018] S2: randomly select one of the conversion time points ZTa as the target time point;

[0019] Obtain the historical data value Az of the analysis parameter at the target time point each time when the high-voltage and low-voltage switchgear performs the preset number of high-voltage conversions z times, obtain the number b of values ​​in Az that meet the preset screening condition X1, and analyze them, and obtain the benchmark parameter value of the analysis parameter at the target time point according to the analysis result, where the preset condition X1 is specifically: |Az-Ap|≥Y2, where Y2 is the preset value, and Ap is the mean value of Az;

[0020] S3: Repeat steps S1-S2 to obtain the reference parameter values ​​Ba corresponding to the analysis parameters at each conversion time point;

[0021] According to each conversion time point and the reference parameter value corresponding to each conversion time point of the analysis parameter, multiple conversion data points of the analysis parameter are generated, and they are arranged in ascending order according to each conversion time point ZTa, and each conversion time point ZTa is used as the horizontal coordinate, and the reference parameter value corresponding to each conversion time point of the analysis parameter is used as the vertical coordinate, so as to obtain the coordinates Ha (ZTa, Ba) of each conversion data point of the analysis parameter, and each conversion data point is connected in sequence, so as to generate a high-voltage conversion transformation curve corresponding to the analysis parameter when the high-voltage and low-voltage switchgear is performing high-voltage conversion;

[0022] S4: Repeat steps S1-S3 to obtain the transformation curves corresponding to various parameters of the high and low voltage switchgear when performing high voltage conversion, and bind the transformation curves corresponding to various parameters to generate a high voltage conversion parameter curve comparison table corresponding to the high and low voltage switchgear.

[0023] As a further solution of the present invention: the specific method of obtaining the reference parameter value of the analysis parameter at the target time point is:

[0024] When the quantity b is greater than the preset threshold Y1, the mean Ap of Az is defined as the baseline parameter value of the analysis parameter at the target time point. When the quantity b is less than or equal to the preset threshold Y1, the mean of the maximum and minimum values ​​in Az is defined as the baseline parameter value of the analysis parameter at the target time point.

[0025] As a further solution of the present invention: the specific method of obtaining the real-time parameter curve of various parameters is:

[0026] S01: Select the same type of parameters as step S1 as analysis parameters;

[0027] When the high-voltage and low-voltage switchgear performs high-voltage conversion, the real-time values ​​of the analysis parameters at each conversion time point are obtained in real time according to each conversion time point, and after each acquisition, the corresponding implementation parameter points ZKn (ZTn, Kn) of the analysis parameters are obtained according to the real-time value Kn of the analysis parameter and the corresponding conversion time point ZTn, and the real-time parameter points of the analysis parameters are connected to obtain the real-time parameter curve corresponding to the analysis parameters, where n is the number of times the real-time values ​​of the analysis parameters are obtained, n is a positive integer, and a≥n≥2;

[0028] S02: Repeat step S01 to obtain real-time parameter curves of various parameters.

[0029] As a further solution of the present invention: the specific method of calculating the stage similarity between the real-time parameter curve of each parameter and the high-voltage conversion transformation curve is:

[0030] S101: Select the same type of parameters as in step S01 as analysis parameters;

[0031] The high-voltage conversion transformation curve GA1 corresponding to the analysis parameters is obtained from the high-voltage conversion parameter curve comparison table. The coordinates of each conversion data point at the conversion time point corresponding to each real-time parameter point of the analysis parameters are obtained from the high-voltage conversion transformation curve GA1 corresponding to the analysis parameters, and marked as the comparison data point coordinates Mn (MAn, MBn). The similarity calculation formula is: The stage similarity JD1 between the real-time parameter curve of the analysis parameter and its high-pressure conversion transformation curve is calculated, where MBp and Kp are the means of MBr and Kr respectively, Kr is the real-time value of the analysis parameter at each conversion time point, MBr is the ordinate corresponding to the conversion data point of the analysis parameter at each conversion time point in the high-pressure conversion transformation curve GA1, a≥n≥r≥1;

[0032] S102: Repeat step S101 to obtain the stage similarity between the real-time parameter curves of various parameters and the high-voltage conversion curve.

[0033] As a further solution of the present invention: the specific method for determining the type of abnormal high-voltage conversion parameters according to the stage similarity of various parameters is:

[0034] The parameter type whose stage similarity is less than or equal to the preset value Y3 is marked as a high-voltage conversion abnormal parameter type, otherwise no processing is performed.

[0035] Beneficial effects of the present invention:

[0036] The present invention analyzes the historical data of various parameters at various conversion time points at several conversion time points set within the high-voltage conversion time interval, obtains the corresponding conversion curves of various parameters of high- and low-voltage switch cabinets when performing high- and low-voltage conversion and the corresponding high- and low-voltage conversion parameter curve comparison table according to the analysis results, obtains the real-time values ​​of various parameters at various conversion time points in real time when the high- and low-voltage switch cabinets perform high- and low-voltage conversion, and calculates the stage similarity between the real-time parameter curves of various parameters and the corresponding high- and low-voltage conversion conversion curves, determines the high-voltage conversion abnormal parameter type and the low-voltage conversion abnormal parameter type according to the stage similarity of various parameters, and outputs them to the remote display terminal, realizes the problem of monitoring various parameters when the high- and low-voltage switch cabinets perform high- and low-voltage conversion, and accurately determines the high-voltage conversion abnormal parameter type through the analysis of historical data and the monitoring of real-time data, and outputs it to the remote display terminal, which is beneficial for relevant personnel to conduct targeted analysis and adjustment of corresponding type parameter data according to the high- and low-voltage conversion abnormal parameter type, improves the operation stability and safety of the high- and low-voltage switch cabinets, and reduces the failure rate of the high- and low-voltage switch cabinets when performing high- and low-voltage conversion. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] The present invention will be further described below in conjunction with the accompanying drawings.

[0038] Figure 1 It is a schematic diagram of the framework structure of a remote monitoring method for high and low voltage switch cabinets of the present invention. DETAILED DESCRIPTION

[0039] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention. Example

[0040] See also Figure 1 As shown, the present invention is a remote monitoring method for high and low voltage switch cabinets, comprising the following steps:

[0041] Step 1: Obtain historical data of various parameters of high and low voltage switchgear during high and low voltage conversion. The high and low voltage conversion of high and low voltage switchgear refers to the conversion of high voltage to low voltage (hereinafter referred to as high voltage conversion), and the high and low voltage when converting low voltage to high voltage (hereinafter referred to as low voltage conversion). The various parameters of high and low voltage switchgear include input voltage, current, power factor, temperature, pressure and output voltage, current, power factor, temperature, pressure and other parameters. It should be noted that the acquired data should cover multiple conversion cycles to ensure the comprehensiveness and accuracy of the analysis;

[0042] Step 2: Preprocess the acquired historical data of various parameters. The specific operations of preprocessing are to clean the historical data of various parameters, remove noise and outliers, etc., to ensure the quality of the historical data of various parameters for subsequent analysis. The above operations are existing and mature technologies, so the specific operations are not described here.

[0043] Step 3: According to the high-voltage conversion time of the high-voltage and low-voltage switchgear when performing a preset number of z high-voltage conversions, obtain the high-voltage conversion time interval of the high-voltage and low-voltage switchgear, set several conversion time points within the high-voltage conversion time interval, analyze the historical data of various parameters of the high-voltage and low-voltage switchgear at various conversion time points when performing high-voltage conversion, and obtain the high-voltage conversion transformation curves corresponding to various parameters of the high-voltage and low-voltage switchgear when performing high-voltage conversion according to the analysis results, and the high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear, the specific method is as follows;

[0044] Obtain the high-voltage conversion time GTz corresponding to the high-voltage and low-voltage switchgear when performing the preset number of z high-voltage conversions, where z is the preset number of times, z is a positive integer, and the specific value range is: 90≥z≥2;

[0045] Get the maximum value GT in the high voltage conversion time GTz max and minimum GT min , the maximum value GT max As the upper limit of the high speed time interval, the minimum value GT min As the lower limit of the high speed duration range, the maximum value GT max and minimum GT min , combined into a high-speed time zone [GT min , GT max ];

[0046] In [GT min , GT max ]A few conversion time points ZTa are randomly set in the system, and the interval between each conversion time point ZTa is JT, a is the number of conversion time points, a is a positive integer, and the specific value range is: 20≥a≥2, JT is the interval of the preset value, and the specific duration is 10 minutes;

[0047] S1: arbitrarily obtain one type of parameter from various types of parameters as analysis parameters;

[0048] S2: randomly select one of the conversion time points ZTa as the target time point;

[0049] Obtain the historical data value of the analysis parameter at each target time point when the high-voltage and low-voltage switchgear performs a preset number of z high-voltage conversions, and mark it as Az;

[0050] Get the value Ab in Az that meets the preset screening condition X1, where b is the number of values ​​in Az that meet the preset screening condition A1, z≥b≥1, and compare the number b with the preset threshold value Y1. When the number b is greater than the preset threshold value Y1, it means that the number of values ​​in Az that meet the preset screening condition Az is large, and the mean Ap of Az is representative. Then the mean Ap of Az is defined as the benchmark parameter value B1 of the analysis parameter at the target time point. When the number b is less than or equal to the preset threshold value Y1, it means that the number of values ​​in Az that meet the preset screening condition Az is small, and the mean Ap of Az is not representative. Then the mean of the maximum and minimum values ​​in Az is defined as the benchmark parameter value B1 of the analysis parameter at the target time point, that is, B1=(A min +A max ) / 2, where A max and A min are the maximum and minimum values ​​in Az respectively;

[0051] Here, the preset condition X1 is specifically: |Az-Ap|≥Y2, where Y2 is a preset value, and the specific values ​​of Y1 and Y2 are formulated by relevant personnel according to actual needs;

[0052] S3: Repeat steps S1-S2 to obtain the reference parameter values ​​Ba corresponding to the analysis parameters at each conversion time point;

[0053] According to each conversion time point and the reference parameter value Ba corresponding to the analysis parameter at each conversion time point, the high-voltage conversion transformation curve corresponding to the analysis parameter when the high-voltage and low-voltage switchgear is performing high-voltage conversion is drawn. The specific method is as follows:

[0054] According to each conversion time point and the reference parameter value corresponding to each conversion time point of the analysis parameter, a plurality of conversion data points of the analysis parameter are generated, and they are arranged in ascending order according to each conversion time point ZTa, and each conversion time point ZTa is used as the horizontal coordinate, and the reference parameter value corresponding to each conversion time point of the analysis parameter is used as the vertical coordinate, so as to obtain the coordinates Ha (ZTa, Ba) of each conversion data point of the analysis parameter, and each conversion data point is connected in sequence, so as to generate a high-voltage conversion transformation curve GA1 corresponding to the analysis parameter when the high-voltage and low-voltage switchgear is performing high-voltage conversion;

[0055] S4: Repeat steps S1-S3 to obtain the conversion curves GAe corresponding to various parameters of the high-voltage and low-voltage switchgear when performing high-voltage conversion, and bind the conversion curves corresponding to various parameters to generate a high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear, where e is the corresponding number of various parameters of the high-voltage and low-voltage switchgear, e is a positive integer, and e≥1;

[0056] Step 4: When the high-voltage and low-voltage switchgear performs high-voltage conversion, the real-time values ​​of various parameters at various conversion time points are obtained in real time according to each conversion time point ZTa, and after each acquisition, the implementation parameter points corresponding to various parameters are obtained according to the real-time values ​​of various parameters and the corresponding conversion time points. At the same time, the real-time parameter curves corresponding to various parameters are drawn according to the implementation parameter points corresponding to various parameters. According to the coordinates of the implementation parameter points corresponding to various parameters, the stage similarity between the real-time parameter curves of various parameters and the corresponding high-voltage conversion transformation curves is calculated. When the high-voltage and low-voltage switchgear performs high-voltage conversion, according to the stage similarity between the real-time parameter curves of various parameters and the corresponding high-voltage conversion transformation curves, the type of abnormal high-voltage conversion parameters is determined and output according to the stage similarity between the real-time parameter curves of various parameters and the corresponding high-voltage conversion transformation curves. The specific method is as follows:

[0057] S01: Select the same type of parameters as step S1 as analysis parameters;

[0058] S02: When the high-voltage and low-voltage switchgear performs high-voltage conversion, the real-time values ​​of the analysis parameters at the various conversion time points are obtained in real time according to the various conversion time points, and after each acquisition, the real-time parameter points ZKn (ZTn, Kn) corresponding to each analysis parameter are obtained according to the real-time value Kn of the analysis parameter and the corresponding conversion time point ZTn, and the various real-time parameter points of the analysis parameter are connected to obtain the real-time parameter curve corresponding to the analysis parameter, where n is the number of times the real-time value of the analysis parameter is obtained, n is a positive integer, and a≥n≥2;

[0059] Obtain the high-voltage conversion transformation curve GA1 corresponding to the analysis parameter from the high-voltage conversion parameter curve comparison table, obtain the coordinates of each conversion data point at the conversion time point corresponding to each real-time parameter point of the analysis parameter from the high-voltage conversion transformation curve GA1 corresponding to the analysis parameter, and mark it as the comparison data point coordinate Mn (MAn, MBn);

[0060] The similarity calculation formula is: The stage similarity JD1 between the real-time parameter curve of the analysis parameter and its high-pressure conversion transformation curve is calculated, where Kr is the real-time value of the analysis parameter at each conversion time point, MBr is the ordinate corresponding to the conversion data point of the analysis parameter at each conversion time point in the high-pressure conversion transformation curve GA1, MBp and Kp are the means of MBr and Kr respectively, and a≥n≥r≥1;

[0061] When the stage similarity JD1>Y3, no processing is done. When the stage similarity JD1≤Y3, the analysis parameter is marked as a high-voltage conversion abnormal parameter type. Y3 is a preset value, and the specific value is formulated by relevant personnel according to actual needs.

[0062] S03: Repeat steps S01-S02 to monitor and determine various parameters when the high-voltage and low-voltage switchgear performs high-voltage conversion, mark the abnormal parameter types of high-voltage conversion in various parameters, and output them to the remote display terminal, which includes computers, operation display screens, and mobile devices such as mobile phones and tablet computers;

[0063] Analyze the historical data of various parameters of high and low voltage switchgear when converting high voltage to low voltage, obtain the high voltage conversion transformation curves corresponding to various parameters of high and low voltage switchgear when performing high voltage conversion, and the high voltage conversion parameter curve comparison table corresponding to the high and low voltage switchgear; when the high and low voltage switchgear performs high voltage conversion, obtain the real-time values ​​of various parameters at various conversion time points in real time, and after each acquisition, draw the real-time parameter curves corresponding to various parameters according to the real-time values ​​of various parameters and the corresponding conversion time points; at the same time, calculate the stage similarity between the real-time parameter curves of various parameters and the corresponding high voltage conversion transformation curves; mark the abnormal high voltage conversion parameter types in various parameters according to the stage similarity of various parameters, and output them to the remote display terminal, so as to realize the monitoring of various parameters by high and low voltage switchgear when performing high voltage conversion, which is conducive to the relevant personnel to conduct targeted analysis and adjustment of the corresponding type of parameter data according to the abnormal high voltage conversion parameter type; Example

[0064] As the second embodiment of the present invention, when the present application is implemented, compared with the first embodiment, the technical solution of the present embodiment is different from the first embodiment only in that the present embodiment further includes step five;

[0065] Step 5: adopt the same method as step 3 to analyze the historical data of various parameters of the high and low voltage switchgear when performing low voltage conversion, and then obtain the low voltage conversion conversion curves corresponding to various parameters of the high and low voltage switchgear when performing low voltage conversion, and the low voltage conversion parameter curve comparison table corresponding to the high and low voltage switchgear, and then adopt the same method as step 4 to analyze the real-time values ​​of various parameters of the high and low voltage switchgear when performing low voltage conversion, and then obtain the low voltage conversion abnormal parameter type corresponding to the high and low voltage switchgear when performing low voltage conversion, and output it to the remote display terminal;

[0066] The historical data of various parameters of the high and low voltage switchgear when performing low voltage conversion are analyzed, and the low voltage conversion transformation curves corresponding to the various parameters of the high and low voltage switchgear when performing low voltage conversion and the low voltage conversion parameter curve comparison table corresponding to the high and low voltage switchgear are obtained. When the high and low voltage switchgear performs low voltage conversion, the real-time values ​​of various parameters at various conversion time points are obtained in real time, and after each acquisition, the real-time parameter curves corresponding to various parameters are drawn according to the real-time values ​​of various parameters and the corresponding conversion time points. At the same time, the stage similarity between the real-time parameter curves of various parameters and the corresponding low voltage conversion transformation curves is calculated. According to the stage similarity of various parameters, the low voltage conversion abnormal parameter type in each parameter is marked and output to the remote display terminal, so as to realize the monitoring of various parameters by the high and low voltage switchgear when performing low voltage conversion, which is conducive to the relevant personnel to conduct targeted analysis and adjustment of the corresponding type of parameter data according to the low voltage conversion abnormal parameter type. Example

[0067] As the third embodiment of the present invention, when the present application is specifically implemented, compared with the first and second embodiments, the technical solution of this embodiment is to combine the solutions of the first and second embodiments mentioned above for implementation.

[0068] The above formulas are all dimensionless and numerical calculations. The formula is a formula for the most recent real situation obtained by collecting a large amount of data and performing software simulation. The preset parameters and thresholds in the formula are set by technicians in this field according to actual conditions.

[0069] The above is only a specific implementation of the present application, but the protection scope of the present application is not limited thereto. Any person skilled in the art who is familiar with the present technical field can easily think of changes or substitutions within the technical scope disclosed in the present application, which should be included in the protection scope of the present application. Therefore, the protection scope of the present application should be based on the protection scope of the claims.

Claims

1. A remote monitoring method for high and low voltage switch cabinets, characterized in that: The following steps are involved: Step 1: Obtain historical data of various parameters of the high and low voltage switchgear when performing high and low voltage conversion, including input voltage, output voltage, input current, output current, input pressure and output pressure; Step 2: Preprocess the historical data of various parameters obtained; Step 3: According to the duration of high-voltage conversion in the preset number of times z of the high-voltage and low-voltage switchgear, determine the high-voltage conversion duration interval, set multiple conversion time points in the high-voltage conversion duration interval, analyze the historical data of various parameters of the high-voltage and low-voltage switchgear at various conversion time points when performing high-voltage conversion, and obtain the high-voltage conversion transformation curves corresponding to various parameters when performing high-voltage conversion and the high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear, z is the preset number, z is a positive integer, and the specific value range is: 90≥z≥2; Step 4: During the high-voltage conversion process, the real-time values ​​of various parameters are obtained in real time and the real-time parameter curves of various parameters are obtained, the stage similarity between the real-time parameter curves of various parameters and the high-voltage conversion transformation curve is calculated, and the type of abnormal high-voltage conversion parameters is determined according to the stage similarity of various parameters, and the abnormal parameters are output to the remote display terminal; Step 5: Analyze the historical data of various parameters at various conversion time points during low voltage conversion by the same method as steps 3 and 4, determine the type of abnormal low voltage conversion parameters, and output them to the remote display terminal; The specific method for determining the high-speed rotation time interval is: Get the maximum value GT of the high-voltage conversion time GTz corresponding to the high-voltage conversion of the high-voltage and low-voltage switch cabinets when performing the preset number of z high-voltage conversions. max and minimum GT min , through the maximum value GT max and minimum GT min Combined generation of high-speed time zone [GT min , GT max ]; The specific method of setting multiple conversion time points within the high-speed duration interval is as follows: In [GT min , GT max ]A few transition time points ZTa are randomly set in the space, and the interval between each transition time point ZTa is JT, where a is the number of transition time points, a is a positive integer, and the specific duration of JT is 10 minutes; The specific method of obtaining the high-voltage conversion transformation curves corresponding to various parameters during high-voltage conversion and the high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear is as follows: S1: arbitrarily obtain one type of parameter from various types of parameters as analysis parameters; S2: randomly select one of the conversion time points ZTa as the target time point; Obtain the historical data value Az of the analysis parameter at the target time point each time when the high-voltage and low-voltage switchgear performs the preset number of high-voltage conversions z times, obtain the number b of values ​​in Az that meet the preset screening condition X1, and analyze them, and obtain the benchmark parameter value of the analysis parameter at the target time point according to the analysis result, where the preset condition X1 is specifically: |Az-Ap|≥Y2, where Y2 is the preset value and Ap is the mean value of Az; S3: Repeat steps S1-S2 to obtain the reference parameter values ​​Ba corresponding to the analysis parameters at each conversion time point; According to each conversion time point and the reference parameter value corresponding to each conversion time point of the analysis parameter, multiple conversion data points of the analysis parameter are generated, and they are arranged in ascending order according to each conversion time point ZTa, and each conversion time point ZTa is used as the horizontal coordinate, and the reference parameter value corresponding to each conversion time point of the analysis parameter is used as the vertical coordinate, so as to obtain the coordinates Ha (ZTa, Ba) of each conversion data point of the analysis parameter, and each conversion data point is connected in sequence, so as to generate a high-voltage conversion transformation curve corresponding to the analysis parameter when the high-voltage and low-voltage switchgear is performing high-voltage conversion; S4: Repeat steps S1-S3 to obtain the conversion curves corresponding to various parameters of the high-voltage and low-voltage switchgear when performing high-voltage conversion, and bind the conversion curves corresponding to various parameters to generate a high-voltage conversion parameter curve comparison table corresponding to the high-voltage and low-voltage switchgear; The specific method of obtaining the real-time parameter curves of various parameters is: S01: Select the same type of parameters as step S1 as analysis parameters; When the high-voltage and low-voltage switchgear performs high-voltage conversion, the real-time values ​​of the analysis parameters at each conversion time point are obtained in real time according to each conversion time point, and after each acquisition, the corresponding implementation parameter points ZKn (ZTn, Kn) of the analysis parameters are obtained according to the real-time value Kn of the analysis parameter and the corresponding conversion time point ZTn, and the real-time parameter points of the analysis parameters are connected to obtain the real-time parameter curve corresponding to the analysis parameters, where n is the number of times the real-time values ​​of the analysis parameters are obtained, n is a positive integer, and a≥n≥2; S02: Repeat step S01 to obtain real-time parameter curves of various parameters; The specific method for calculating the stage similarity between the real-time parameter curves of various parameters and the high-voltage conversion transformation curve is as follows: S101: Select the same type of parameters as in step S01 as analysis parameters; The high-voltage conversion transformation curve GA1 corresponding to the analysis parameters is obtained from the high-voltage conversion parameter curve comparison table. The coordinates of each conversion data point at the conversion time point corresponding to each real-time parameter point of the analysis parameters are obtained from the high-voltage conversion transformation curve GA1 corresponding to the analysis parameters, and marked as the comparison data point coordinates Mn (MAn, MBn). The similarity calculation formula is: The stage similarity JD1 between the real-time parameter curve of the analysis parameter and its high-pressure conversion transformation curve is calculated, where MBp and Kp are the means of MBr and Kr respectively, Kr is the real-time value of the analysis parameter at each conversion time point, MBr is the ordinate corresponding to the conversion data point of the analysis parameter at each conversion time point in the high-pressure conversion transformation curve GA1, a≥n≥r≥1; S102: Repeat step S101 to obtain the stage similarity between the real-time parameter curves of various parameters and the high-voltage conversion curve.

2. A remote monitoring method for high and low voltage switch cabinets according to claim 1, characterized in that: The specific method of obtaining the baseline parameter value of the analysis parameter at the target time point is: When the quantity b is greater than the preset threshold Y1, the mean Ap of Az is defined as the baseline parameter value of the analysis parameter at the target time point. When the quantity b is less than or equal to the preset threshold Y1, the mean of the maximum and minimum values ​​in Az is defined as the baseline parameter value of the analysis parameter at the target time point.

3. A remote monitoring method for high and low voltage switch cabinets according to claim 1, characterized in that: The specific method for determining the type of abnormal high-voltage conversion parameters based on the stage similarity of various parameters is as follows: The parameter type whose stage similarity is less than or equal to the preset value Y3 is marked as a high-voltage conversion abnormal parameter type, otherwise no processing is performed.

Citation Information

Cited By

  • Remote monitoring method and system for high-low voltage switch cabinet

    CN121933818A