A method for optimizing the heat consumption of a food waste production line through simulation modeling

Through simulation modeling, the calorie consumption of the kitchen waste treatment production line is optimized, which solves the problems of high energy consumption and complex system, and has achieved the reduction of heat consumption and the improvement of production line efficiency. It is suitable for the optimization design of the kitchen waste treatment production line.

CN118709451BActive Publication Date: 2024-11-01SICHUAN TONGYI ENVIRONMENTAL TECH GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411189580.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-08-28
Publication Date
2024-11-01
Estimated Expiration
2044-08-28

AI Technical Summary

Technical Problem

There are high energy consumption problems in the kitchen waste treatment production line, and changes in equipment connection relationships and operating time affect the efficiency of waste treatment, resulting in complex optimization of heat consumption, and a systematic method is needed to optimize heat consumption.

Method used

Optimize the calorie consumption of the kitchen waste treatment production line through simulation modeling. The steps include determining the equipment type and connection relationship, establishing a simulation model, performing heat direction graph simulation, adjusting the equipment connection and working timing, calculating the net difference in heat consumption and balance indicators, Perform weighted sorting to select the optimization plan.

Benefits of technology

It effectively reduces the heat consumption of the kitchen waste treatment production line, improves the overall efficiency of the production line, optimizes the working timing of the equipment, and improves the overall performance. The significant advantages are in terms of heat management and energy consumption optimization.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118709451B_ABST
    Figure CN118709451B_ABST
Patent Text Reader

Abstract

The present invention provides a method for optimizing the heat consumption of a kitchen waste production line through simulation modeling, and relates to the field of energy consumption management and control. The present invention first determines and marks the type of production line equipment, performs mathematical modeling on it, and generates an equipment simulation module library. Then, a production line model before optimization is established in a simulation environment, and its working sequence and heat trend are simulated. By changing the equipment and its connection method, multiple adjusted simulation models are generated and simulated. Finally, combined with data such as the net difference in heat consumption, production line balance indicators, and equipment power consumption, the model is weighted and sorted to select the optimal production line design scheme; it can effectively reduce the heat consumption of the kitchen waste treatment production line, while improving the overall efficiency of the production line; in addition, through the working sequence iteration controller, the working sequence of the production line equipment is optimized, thereby further reducing energy consumption.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of energy consumption management and control, and in particular to a method for optimizing the heat consumption of a kitchen waste production line through simulation modeling. Background Art

[0002] The production line equipment used in the food waste treatment production line has high energy consumption. If the heat consumption of the food waste treatment production line is not optimized, it will lead to increased energy consumption and affect the waste treatment capacity of the production line.

[0003] However, there are a large number of production line equipment in the food waste treatment production line, and these equipment need to be operated by operators when they are working. Changes in the structure of the food waste treatment production line will not only affect the connection relationship of the production line equipment, but also affect the operation time of the production line equipment, and thus affect the operator's duty work; this makes optimizing the heat consumption of the food waste treatment production line a complex systemic problem, which requires comprehensive consideration of the impact of multiple factors on each other.

[0004] Therefore, a method for optimizing the heat consumption of a food waste production line through simulation modeling is needed to solve the above technical problems. Summary of the invention

[0005] In order to solve the above technical problems, the present invention provides a method for optimizing the heat consumption of a food waste production line through simulation modeling, which optimizes the heat consumption of a food waste treatment production line through the following steps:

[0006] Step 1: Determine the production line equipment used in the food waste treatment production line and mark the type of production line equipment; the production line equipment type includes necessary production line equipment and adjustable production line equipment;

[0007] Step 2: Conduct mathematical modeling for each production line equipment, and encapsulate it into a production line equipment module through a program, retaining the equipment input interface and equipment output interface to the outside; add the production line equipment module of each production line equipment to the equipment simulation module library;

[0008] Step 3: Obtain the equipment connection relationship before the optimization of the food waste treatment production line and mark the equipment connection type; the equipment connection type includes necessary equipment connection and adjustable equipment connection;

[0009] Step 4: Set up the simulation environment and place the production line equipment modules of each production line equipment in the simulation environment, connect the module interfaces according to the equipment connection relationship before optimization, and obtain the simulation model of the food waste treatment production line before optimization;

[0010] Step 5: Obtain the equipment working sequence of each production line equipment before optimization, obtain the equipment working sequence set before optimization, and use it for the production line equipment module working control of the food waste treatment production line simulation model before optimization;

[0011] Step 6: Set the number of simulation iterations and boundary conditions, start the simulation and record the simulation process data to obtain the heat trend diagram of the production line before optimization, including the heat consumption curve of each production line equipment;

[0012] Step 7: Generate several adjusted food waste treatment production line simulation models by changing the adjustable production line equipment and the adjustable equipment connection of the food waste treatment production line simulation model;

[0013] Step 8: Set the working timing iteration controller in the simulation environment, start the simulation and perform working timing iteration and record the simulation process data, and obtain the adjusted production line equipment working timing set and the adjusted production line heat trend diagram;

[0014] Step 9: By optimizing the heat trend diagram of the production line before and the heat trend diagram of the production line after adjustment, the net difference of heat consumption of the adjusted production line corresponding to each adjusted kitchen waste treatment production line simulation model is calculated;

[0015] Step 10: Calculate the corresponding production line balance indexes respectively by optimizing the working timing set of the production line equipment before and after the adjustment;

[0016] Step 11: Perform weighted sorting based on the production line balance index and the adjusted net difference in heat consumption of the production line, select the adjusted food waste treatment production line simulation model with the highest ranking, and output it as the optimized food waste treatment production line.

[0017] As a further solution, the completion time of each production line equipment station is obtained through the production line equipment work sequence set. The production line balance index includes the production line balance rate and the production line smoothness index, which are calculated by the following formula:

[0018]

[0019]

[0020] In the formula, LBR represents the production line balance rate, SI Line smoothing index; T i Indicates i Completion time of each workstation, It represents the sum of the time taken to complete all workstations. T max Indicates the bottleneck station time, N Indicates the number of processes, i Indicates the workstation number.

[0021] As a further solution, the production line equipment modules include a dump silo module, a star screen module, a conveyor belt module, an auger module, an intelligent sorting machine module, a primary storage box module, a crusher module, an extruder module, a mixer module, an oil-water mixing box module, a heating tank module, a dryer module, a steam generator module, a condenser module, a dust removal tank module, a three-phase centrifuge module, an oil storage tank module, a sewage tank module, an oil press module, a granulator module, a storage hopper module and a deodorizing tower module.

[0022] As a further solution, the equipment connection relationship includes equipment hardware connection relationship, material flow connection relationship, liquid flow connection relationship and heat flow connection relationship.

[0023] As a further solution, corresponding equipment power consumption parameters are set for each production line equipment module, and when executing the simulation, the corresponding equipment power consumption data is recorded and summarized to obtain an equipment power consumption curve; the total daily power consumption of the production line is obtained through each equipment power consumption curve and added to the weighted sorting of step 11.

[0024] As a further solution, when executing the simulation, the maximum daily production capacity of the production line of each food waste treatment production line simulation model is also calculated and added to the weighted sorting of step 11.

[0025] As a further solution, the working timing iteration controller performs working timing iteration through the following steps:

[0026] Step A: Set the iteration timing step;

[0027] Step B: Set the equipment working sequence of all production line equipment modules in the food waste treatment production line simulation model to normally open;

[0028] Iterate the working sequence of production line equipment module X, and keep the working sequence of other equipment unchanged; X is the equipment number;

[0029] Step C: The device working sequence is divided into two parts according to the iterative timing step length, and the divided parts are set to be normally closed, so as to obtain the first device working sequence and the second device working sequence;

[0030] Step D: Through the working sequence of the first device and the working sequence of the second device, respectively, the simulation model of the kitchen waste treatment production line is simulated and the normal operation part of the simulation is retained to obtain the working sequence of the binary screening device;

[0031] Step E: In the working sequence of the binary screening equipment, the middle parts of the shutdown are respectively set from the front to the back according to the iteration sequence step, and the simulation model of the kitchen waste treatment production line is simulated;

[0032] Step F: If the simulation runs normally, the current shutdown middle part is retained and set to shutdown; if the simulation runs abnormally, the current shutdown middle part is removed and set to startup;

[0033] Step G: Repeat step E and step F to complete the simulation iteration of the working sequence of the binary screening device and obtain the working sequence of the X device;

[0034] Step H: Iteratively update the equipment number through X=X+1, and return to execute step B until all production line equipment modules complete the simulation iteration to obtain the production line equipment working timing set.

[0035] Compared with the related art, the method for optimizing the heat consumption of a kitchen waste production line through simulation modeling provided by the present invention has the following beneficial effects:

[0036] The present invention first determines and marks the type of production line equipment, performs mathematical modeling on it, and generates an equipment simulation module library. Then, a production line model before optimization is established in a simulation environment, and its working sequence and heat trend are simulated. By changing the equipment and its connection method, multiple adjusted simulation models are generated and simulated. Finally, the model is weighted and sorted to select the optimal production line design scheme based on the data such as the net difference in heat consumption, production line balance index and equipment power consumption; it can effectively reduce the heat consumption of the food waste treatment production line and improve the overall efficiency of the production line; in addition, the working sequence of the production line equipment is optimized through the working sequence iteration controller, thereby further reducing energy consumption, and according to factors such as the equipment power consumption curve and the maximum production line capacity, the comprehensive performance of the production line is improved. It is suitable for the optimized design of the food waste treatment production line, especially in terms of heat management and energy consumption optimization. BRIEF DESCRIPTION OF THE DRAWINGS

[0037] Figure 1 A schematic diagram of a method for optimizing the heat consumption of a food waste production line through simulation modeling provided by the present invention. DETAILED DESCRIPTION

[0038] The present invention will be further described below in conjunction with the accompanying drawings and implementation modes.

[0039] like Figure 1 As shown in FIG. 1 , a method for optimizing the heat consumption of a food waste production line through simulation modeling is shown. The heat consumption of a food waste treatment production line is optimized through the following steps:

[0040] Step 1: Determine the production line equipment used in the food waste treatment production line and mark the type of production line equipment; the production line equipment type includes necessary production line equipment and adjustable production line equipment;

[0041] Step 2: Conduct mathematical modeling for each production line equipment, and encapsulate it into a production line equipment module through a program, retaining the equipment input interface and equipment output interface to the outside; add the production line equipment module of each production line equipment to the equipment simulation module library;

[0042] Step 3: Obtain the equipment connection relationship before the optimization of the food waste treatment production line and mark the equipment connection type; the equipment connection type includes necessary equipment connection and adjustable equipment connection;

[0043] Step 4: Set up the simulation environment and place the production line equipment modules of each production line equipment in the simulation environment, connect the module interfaces according to the equipment connection relationship before optimization, and obtain the simulation model of the food waste treatment production line before optimization;

[0044] Step 5: Obtain the equipment working sequence of each production line equipment before optimization, obtain the equipment working sequence set before optimization, and use it for the production line equipment module working control of the food waste treatment production line simulation model before optimization;

[0045] Step 6: Set the number of simulation iterations and boundary conditions, start the simulation and record the simulation process data to obtain the heat trend diagram of the production line before optimization, including the heat consumption curve of each production line equipment;

[0046] Step 7: Generate several adjusted food waste treatment production line simulation models by changing the adjustable production line equipment and the adjustable equipment connection of the food waste treatment production line simulation model;

[0047] Step 8: Set the working timing iteration controller in the simulation environment, start the simulation and perform working timing iteration and record the simulation process data, and obtain the adjusted production line equipment working timing set and the adjusted production line heat trend diagram;

[0048] Step 9: By optimizing the heat trend diagram of the production line before and the heat trend diagram of the production line after adjustment, the net difference of heat consumption of the adjusted production line corresponding to each adjusted kitchen waste treatment production line simulation model is calculated;

[0049] Step 10: Calculate the corresponding production line balance indexes respectively by optimizing the working timing set of the production line equipment before and after the adjustment;

[0050] Step 11: Perform weighted sorting based on the production line balance index and the adjusted net difference in heat consumption of the production line, select the adjusted food waste treatment production line simulation model with the highest ranking, and output it as the optimized food waste treatment production line.

[0051] As a further solution, the completion time of each production line equipment station is obtained through the production line equipment work sequence set. The production line balance index includes the production line balance rate and the production line smoothness index, which are calculated by the following formula:

[0052]

[0053]

[0054] In the formula, LBR represents the production line balance rate, SI Line smoothing index; T i Indicates i Completion time of each workstation, It represents the sum of the time taken to complete all workstations. T max Indicates the bottleneck station time, N Indicates the number of processes, i Indicates the workstation number.

[0055] It should be noted that the bottleneck station refers to the station that takes the longest time. The existence of these bottleneck stations affects the output of the entire production line, and the operation time of each station is long or short, and the operation time is uneven, which will inevitably lead to idle time and waste of personnel. The problem of production line imbalance is obvious, and the production line needs to be improved and optimized; this embodiment is to perform weighted sorting through the production line balance rate and production line smoothing index, and select the highest-ranked adjusted food waste treatment production line simulation model, so as to ensure that the production line is balanced and the bottleneck station is not too large.

[0056] Based on the data collected on site, we calculated the balance rate and smoothing index according to the formula. N =18, bottleneck time T max =13h, the total time of all workstations is 88h, then the balance rate of the production line is:

[0057] ;

[0058] The production line smoothness index is:

[0059]

[0060] As a further solution, the production line equipment modules include a dump silo module, a star screen module, a conveyor belt module, an auger module, an intelligent sorting machine module, a primary storage box module, a crusher module, an extruder module, a mixer module, an oil-water mixing box module, a heating tank module, a dryer module, a steam generator module, a condenser module, a dust removal tank module, a three-phase centrifuge module, an oil storage tank module, a sewage tank module, an oil press module, a granulator module, a storage hopper module and a deodorizing tower module.

[0061] It should be noted that: we mathematically model the production line equipment, and then programmatically construct and encapsulate the mathematical modeling to obtain the corresponding production line equipment module; in a specific embodiment, the mathematical model of the mixer module is as follows:

[0062]

[0063]

[0064] Where: 固(入) is the mass of solid slag input from the extruder (kg); 油(入) is the waste oil flow rate input from the extruder (kg / s); 水(入) is the waste water flow rate input by the extruder (kg / s); 固(出) is the mass of solid residue entering the dryer from the mixer (kg); 油(出) is the mass of oil entering the dryer from the mixer (kg); 水(出) The mass of water entering the dryer from the mixer (kg); 𝑚 (存) is the remaining mass in the extruder (kg); (入) is the mass of garbage input by the extruder; 𝑚 (出) is the mass entering the dryer from the mixer (kg); 入 Input mixer waste handling flow rate for extruder (kg / s); l 固(出) is the mass proportion of solid residue entering the dryer from the mixer; l 油(出) The mass percentage of oil entering the dryer from the mixer; 水(出) The percentage of water mass entering the dryer from the mixer; 固(入) Input mixer waste solids ratio for extruder; l 油(入) Input the oil content of mixer waste to the extruder; l 水(入) Enter the mixer waste moisture content for the extruder.

[0065] We mathematically modeled each production line equipment, and programmatically constructed the mathematical model through modular programs to obtain the corresponding production line equipment module. When using it, you only need to call it directly, that is, to correlate the various calculation steps of the mathematical model, connect the internal relationships through modular programs, and encapsulate it externally to obtain the mixer module; the remaining equipment has been successfully modeled and will not be repeated here.

[0066] As a further solution, the equipment connection relationship includes equipment hardware connection relationship, material flow connection relationship, liquid flow connection relationship and heat flow connection relationship.

[0067] As a further solution, corresponding equipment power consumption parameters are set for each production line equipment module, and when executing the simulation, the corresponding equipment power consumption data is recorded and summarized to obtain an equipment power consumption curve; the total daily power consumption of the production line is obtained through each equipment power consumption curve and added to the weighted sorting of step 11.

[0068] As a further solution, when executing the simulation, the maximum daily production capacity of the production line of each food waste treatment production line simulation model is also calculated and added to the weighted sorting of step 11.

[0069] It should be noted that for environmental protection and manufacturing companies, production plans are the basis for corporate production planning. When making production plans, companies need to systematically take into account the number of production line operators, materials, machinery and equipment and other resources to ensure the smooth progress of production plans. Affected by bottleneck constraints, the production capacity of the food waste production line has been restricted, which may make it difficult to meet the increasing market demand. Therefore, it needs to be improved to achieve balanced production, increase output and increase corporate profits. The maximum daily production capacity (Q) of the production line refers to the maximum output efficiency of the production line within one day's working hours. The calculation formula is Q = unit time capacity × effective working time / p (bottleneck time).

[0070] In a specific embodiment, the company adopts a two-shift production system with a unit capacity of 20 tons, an effective time of 24 hours, and a bottleneck time of 13 hours. The maximum capacity of the production line is: .

[0071] As a further solution, the working timing iteration controller performs working timing iteration through the following steps:

[0072] Step A: Set the iteration timing step;

[0073] Step B: Set the equipment working sequence of all production line equipment modules in the food waste treatment production line simulation model to normally open;

[0074] Iterate the working sequence of production line equipment module X, and keep the working sequence of other equipment unchanged; X is the equipment number;

[0075] Step C: The device working sequence is divided into two parts according to the iterative timing step length, and the divided parts are set to be normally closed, so as to obtain the first device working sequence and the second device working sequence;

[0076] Step D: Through the working sequence of the first device and the working sequence of the second device, respectively, the simulation model of the kitchen waste treatment production line is simulated and the normal operation part of the simulation is retained to obtain the working sequence of the binary screening device;

[0077] Step E: In the working sequence of the binary screening equipment, the middle parts of the shutdown are respectively set from the front to the back according to the iteration sequence step, and the simulation model of the kitchen waste treatment production line is simulated;

[0078] Step F: If the simulation runs normally, the current shutdown middle part is retained and set to shutdown; if the simulation runs abnormally, the current shutdown middle part is removed and set to startup;

[0079] Step G: Repeat step E and step F to complete the simulation iteration of the working sequence of the binary screening device and obtain the working sequence of the X device;

[0080] Step H: Iteratively update the equipment number through X=X+1, and return to execute step B until all production line equipment modules complete the simulation iteration to obtain the production line equipment working timing set.

[0081] In a specific embodiment, the food waste treatment production line before optimization has the largest heat consumption ratio. The top six equipments with the highest heat consumption are the storage hopper, which consumes 53% of the total heat and dissipates 7.9×10 6 kJ; oil-water mixing tank 18%, daily dissipation 2.65×10 6 kJ; dust collector 10%, daily dissipation 1.48×10 6 kJ; condensation tank 9%, daily dissipation 1.41×10 6 kJ; sewage tank 8%, daily dissipation 1.19×10 6 kJ; deodorization tower 2%, daily dissipation 0.25×10 6 kJ; oil storage tank 1%, daily dissipation 0.04×10 6 kJ. The following is an analysis item by item: Combining the simulation results and the production line equipment working sequence set, the power consumption of the main working components of each device is calculated. When all devices are working normally at the current beat, the average daily power consumption of the entire production line is 5.6×10 6 kJ, which is approximately equal to 1557.3 kWh. The dryer consumes 2.43×10 6 kJ, which is approximately equal to 676 kWh, accounting for about 42% of the total power consumption. The top seven power consumption from high to low are dryer (power consumption 676 kWh), deodorization tower (power consumption 180 kWh), condenser (power consumption 97.5 kWh), granulator (power consumption 90 kWh), steam generator (power consumption 67.6 kWh), extruder (power consumption 60 kWh), three-phase centrifuge (power consumption 57 kWh).

[0082] Through the method provided by the present invention, we iterated the optimized food waste treatment production line and the corresponding optimized production line equipment working sequence set for the food waste treatment production line before optimization; the bottleneck factor of the improved food waste production line is the steamer, and the bottleneck time is 6h. If uninterrupted production is carried out throughout the day and the working time is 24h, the maximum production capacity of the production line is Compared with the maximum daily output of 36.9 tons before the improvement of the food waste production line, the maximum daily output after the improvement is 80 tons of food waste, an increase of nearly 116.8%.

[0083] From the simulation results, the heat transfer equipment involved in the production line mainly includes storage boxes, cooking machines, dryers, steam generators, condensers, dust removal tanks, three-phase centrifuges, plunger extruders, exhaust gas heat exchangers, sewage heat exchangers, steam recovery machines, oil storage tanks, sewage tanks, granulators, storage hoppers and deodorization towers. The steam heat produced by the steam generator eventually goes to the storage hopper, deodorization tower, sewage tank, oil storage tank, dust removal tank, exhaust gas heat exchanger, sewage heat exchanger, and the heat is dissipated in the environment over time.

[0084] Through the optimized heat consumption curve, we know that: the storage hopper consumes 1811176kJ of heat, accounting for about 28% of the total heat ratio; the deodorization tower consumes about 140760kJ of heat, accounting for about 2% of the total heat ratio; the exhaust gas recovery machine recovers about 65752.34kJ of heat, accounting for about 1% of the total heat ratio; the material pool consumes 185.4678kJ, accounting for about 0% of the total heat ratio; the sewage recovers heat 388182.6kJ, accounting for about 6% of the total heat ratio; the steam recovery machine recovers heat about 4080640kJ, accounting for about 62% of the total heat ratio; the dust collector consumes about 8365.815kJ of heat, accounting for about 0% of the total heat ratio; the oil storage tank consumes about 508 10.86kJ, accounting for about 1% of the total heat ratio; the heat consumption of the dumping bin is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the star screen is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the intelligent sorting machine is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the sewage tank is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the extruder is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the dryer is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the mixer is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the three-phase centrifuge is about 0kJ, accounting for about 0% of the total heat ratio; the heat consumption of the granulator is about 0kJ, accounting for about 0% of the total heat ratio.

[0085] After the improvement, the steam recovery machine recovers about 4080640 kJ of heat, accounting for about 62% of the total heat ratio, so the steam heat can be saved by 62%. Calculated based on 3.165×106 kJ per ton of steam, 1.29 tons of steam output can be saved. Taking the biomass calorific value of 4200 kJ / kg and the boiler thermal efficiency of 80%, 4200 kJ / kg×1000 kg×0.8=3360000 kJ, 1 ton of biomass can be put into the boiler to remove heat loss and obtain 14×106 kJ of heat, and 1.29 tons of steam requires 3.165×106 kJ of heat. It can be concluded that after the improvement of the food waste treatment production line, about 1214 kg of fuel can be saved.

[0086] From the production process point of view, when all equipment works normally according to the improved production line rhythm, the average daily power consumption of the entire production line is 3.04×106kW, which is approximately equal to 843.4 kWh. Among them, the dryer consumes 0.468×106kJ, which is approximately equal to 130 kWh, accounting for about 15% of the total power consumption. The top five power consumptions from high to low are three-phase centrifuge (power consumption 142.5 kWh), dryer (power consumption 130 kWh), granulator (power consumption 90 kWh), extruder (power consumption 75 kWh), steam recovery machine (power consumption 56.25 kWh), boiler (power consumption 39 kWh).

[0087] According to the simulation data analysis of the improved production line, the balance rate and smoothness index are calculated according to the formula. From the above statistical data, we can get N=14, bottleneck time=6h, total workstation time 67.5h, then the balance rate of the production line is: , production line smoothing index: .

[0088] Compared with the balance indicators of the food waste production line before improvement, it can be seen that the balance rate of the production line after improvement is 80.4%, which is 42.8% higher than the balance rate of 37.6% before improvement; the smoothness index is 2.13, which is 6.89 compared with the smoothness index of the production line before improvement. The deviation degree of operation time of each unit and the dispersion of operation time are reduced by 69.08%; the actual parameters related to the production line are introduced into the mathematical model for simulation analysis, and the improvement of the production line is deeply analyzed in combination with the relevant theories of industrial engineering, so as to find measures to optimize the production line, improve production efficiency and production capacity, improve various standards of the production line, and realize the improvement of production line capacity and efficiency.

[0089] The above are only embodiments of the present invention, and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.

Claims

1. A method for optimizing the heat consumption of a food waste production line through simulation modeling, characterized in that: Optimize the heat consumption of the food waste treatment production line through the following steps: Step 1: Determine the production line equipment used in the food waste treatment production line and mark the type of production line equipment; the production line equipment type includes necessary production line equipment and adjustable production line equipment; Step 2: Conduct mathematical modeling for each production line equipment, and encapsulate it into a production line equipment module through a program, retaining the equipment input interface and equipment output interface to the outside; add the production line equipment module of each production line equipment to the equipment simulation module library; Step 3: Obtain the equipment connection relationship before the optimization of the food waste treatment production line and mark the equipment connection type; the equipment connection type includes necessary equipment connection and adjustable equipment connection; Step 4: Set up the simulation environment and place the production line equipment modules of each production line equipment in the simulation environment, connect the module interfaces according to the equipment connection relationship before optimization, and obtain the simulation model of the kitchen waste treatment production line before optimization; Step 5: Obtain the working timing of each production line equipment before optimization, obtain the working timing set of the production line equipment before optimization, and use it for the working control of the production line equipment module of the simulation model of the kitchen waste treatment production line before optimization; Step 6: Set the number of simulation iterations and boundary conditions, start the simulation and record the simulation process data to obtain the heat trend diagram of the production line before optimization, including the heat consumption curve of each production line equipment; Step 7: Generate several adjusted food waste treatment production line simulation models by changing the adjustable production line equipment and the adjustable equipment connection of the food waste treatment production line simulation model; Step 8: Set the working timing iteration controller in the simulation environment, start the simulation and perform working timing iteration and record the simulation process data, and obtain the adjusted production line equipment working timing set and the adjusted production line heat trend diagram; Step 9: By optimizing the heat trend diagram of the production line before and the heat trend diagram of the production line after adjustment, the net difference of heat consumption of the adjusted production line corresponding to each adjusted kitchen waste treatment production line simulation model is calculated; Step 10: Calculate the corresponding production line balance indexes respectively by optimizing the working timing set of the production line equipment before and after the adjustment; Step 11: Perform weighted sorting based on the production line balance index and the adjusted net difference in heat consumption of the production line, select the adjusted food waste treatment production line simulation model with the highest ranking, and output it as the optimized food waste treatment production line.

2. The method for optimizing the calorie consumption of a food waste production line by simulation modeling according to claim 1, characterized in that: The completion time of each production line equipment station is obtained through the production line equipment work sequence set. The production line balance index includes the production line balance rate and the production line smoothness index, which are calculated by the following formula: In the formula, LBR represents the production line balance rate, SI Line smoothing index; T i Indicates i Completion time of each workstation, It represents the sum of the time taken to complete all workstations. T max Indicates the bottleneck station time, N Indicates the number of processes, i Indicates the workstation number.

3. The method for optimizing the calorie consumption of a food waste production line by simulation modeling according to claim 1, characterized in that: The production line equipment modules include a dump silo module, a star screen module, a conveyor belt module, an auger module, an intelligent sorting machine module, a primary storage box module, a crusher module, an extruder module, a mixer module, an oil-water mixing box module, a heating tank module, a dryer module, a steam generator module, a condenser module, a dust removal tank module, a three-phase centrifuge module, an oil storage tank module, a sewage tank module, an oil press module, a granulator module, a storage hopper module and a deodorizing tower module.

4. The method for optimizing the calorie consumption of a kitchen waste production line by simulation modeling according to claim 1, characterized in that: The equipment connection relationship includes equipment hardware connection relationship, material flow connection relationship, liquid flow connection relationship and heat flow connection relationship.

5. The method for optimizing the calorie consumption of a food waste production line by simulation modeling according to claim 1, characterized in that: The corresponding equipment power consumption parameters are also set for each production line equipment module, and when executing the simulation, the corresponding equipment power consumption data is recorded and summarized to obtain the equipment power consumption curve; the total daily power consumption of the production line is obtained through each equipment power consumption curve and added to the weighted sorting of step 11.

6. The method for optimizing the calorie consumption of a food waste production line by simulation modeling according to claim 1, characterized in that: When executing the simulation, the maximum daily production capacity of the production line of each food waste treatment production line simulation model is also calculated and added to the weighted sorting in step 11.

7. The method for optimizing the calorie consumption of a food waste production line by simulation modeling according to claim 1, characterized in that: The working timing iteration controller performs working timing iteration through the following steps: Step A: Set the iteration timing step; Step B: Set the equipment working sequence of all production line equipment modules in the food waste treatment production line simulation model to normally open; Iterate the working sequence of production line equipment module X, and keep the working sequence of other equipment unchanged; X is the equipment number; Step C: The device working sequence is divided into two parts according to the iterative timing step length, and the divided parts are set to be normally closed, so as to obtain the first device working sequence and the second device working sequence; Step D: Through the working sequence of the first device and the working sequence of the second device, respectively, the simulation model of the kitchen waste treatment production line is simulated and the normal operation part of the simulation is retained to obtain the working sequence of the binary screening device; Step E: In the working sequence of the binary screening equipment, the middle parts of the shutdown are respectively set from the front to the back according to the iteration sequence step, and the simulation model of the kitchen waste treatment production line is simulated; Step F: If the simulation runs normally, the current shutdown middle part is retained and set to shutdown; if the simulation runs abnormally, the current shutdown middle part is removed and set to startup; Step G: Repeat step E and step F to complete the simulation iteration of the working sequence of the binary screening device and obtain the working sequence of the X device; Step H: Iteratively update the equipment number through X=X+1, and return to execute step B until all production line equipment modules complete the simulation iteration to obtain the production line equipment working timing set.