Avalanche protection system
By setting up blocking nets, energy dissipation pools and blocking dams in avalanche occurrence areas, combined with the design of blocking, absorbing and dispersing snow flow energy, the problems of poor effectiveness and high cost of the existing avalanche protection system are solved, and more effective avalanche protection is achieved .
Patent Information
- Application Number
- CN202411082748.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-08
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-08-08
AI Technical Summary
In the existing avalanche protection system, when avalanches occur at high altitudes, the huge kinetic energy and volume make conventional blocking measures ineffective and costly, making it difficult to effectively protect them.
Design an avalanche protection system that combines a primary blocking device (blocking net), an energy dissipating device (energy dissipating pool) and a secondary blocking device (barring dam), which are set up sequentially along the mountain slope, and are intercepted by the blocking net and the energy dissipating pool. Absorbing and blocking dams disperse snow flow energy, gradually reduce avalanche energy, and prevent avalanches from damaging humans and the natural environment.
It can effectively slow down the development and speed of avalanches, reduce the volume and kinetic energy of snow flow, reduce damage to forests, farmland, houses, etc., improve protection effects and reduce costs.
Smart Images

Figure CN118727636A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of disaster protection technology, and in particular to an avalanche protection system. Background Art
[0002] The avalanche protection system is mainly aimed at protecting avalanche occurrence and movement areas. When an avalanche occurs, it occurs at a high position and has high potential energy. It undergoes multiple accelerations from the top of the mountain to the accumulation area at the bottom. Its huge kinetic energy and volume make it difficult to achieve conventional barrier measures in avalanche occurrence and movement areas. The effect is poor and the cost is generally high. Summary of the invention
[0003] In view of this, the purpose of this application is to overcome the shortcomings of the prior art and to provide an avalanche protection system, which replaces blocking with dredging in avalanche prevention and control, and combines it with energy dissipation measures, so that the energy of the avalanche when it occurs is gradually reduced and the volume no longer increases, thereby enabling the protection system to play a more effective protective role.
[0004] This application provides the following technical solutions:
[0005] The embodiment of the present application provides an avalanche protection system, which includes a primary blocking device, an energy dissipation device and a secondary blocking device, wherein the primary blocking device, the energy dissipation device and the secondary blocking device are arranged in sequence along the slope of the mountain; wherein
[0006] The first-level blocking device includes a plurality of blocking nets, which are arranged at intervals along the slope direction, the blocking nets close to the top of the slope are covered with snow on the slope, and the plane where the blocking nets away from the top of the slope are located intersects with the slope;
[0007] The energy dissipation device includes at least one energy dissipation pool. When there are multiple energy dissipation pools, multiple barrier nets are sequentially arranged along the slope direction.
[0008] The secondary blocking device includes a plurality of retaining dams, which are arranged at intervals along the slope; the retaining dams have a plurality of openings, which are arranged at intervals along the extension direction of the retaining dams, and the openings of adjacent retaining dams are staggered.
[0009] In one of the embodiments, the mesh sizes of the plurality of barrier nets gradually decrease in the slope direction.
[0010] In one of the embodiments, a buffer layer is provided at the bottom of the energy dissipation pool.
[0011] In one embodiment, the bottom surface shape of the energy dissipation pool includes one of the following shapes:
[0012] Flat slopes, concave slopes and wavy slopes.
[0013] In one embodiment, the energy dissipation pool is formed by a recessed area of the slope, and a protective layer is provided on the surface of the energy dissipation pool.
[0014] In one embodiment, the energy dissipation device further comprises:
[0015] An energy dissipation dam is installed upstream of the energy dissipation pool and is close to the energy dissipation pool.
[0016] In one embodiment, the energy dissipation dam includes a dam body and fixed piles, the dam body and the fixed piles are connected, the dam body is arranged above the slope surface, and the fixed piles are arranged below the slope surface; wherein the width of the dam body gradually decreases in the direction away from the slope surface.
[0017] In one embodiment, the secondary blocking device also includes a sedimentation tank, a filter and a water reservoir, and the sedimentation tank, the filter and the water reservoir are arranged in sequence along the slope. The sedimentation tank is used to receive snow water flowing through the opening, and the sedimentation tank is connected to the water reservoir through the filter.
[0018] In one embodiment, the avalanche protection system further comprises:
[0019] A monitoring and early warning device, the monitoring and early warning device includes a collection module and an early warning control module, the collection module and the early warning control module are electrically connected, the collection module is installed at the monitoring point of the slope, the collection module is used to collect real-time environmental data of the monitoring point, the early warning control module is used to receive and process the real-time environmental data from the collection module, and determine whether to issue an early warning message based on the processing result.
[0020] In one embodiment, the acquisition module includes a horizontal deformation monitoring sensor, a vertical deformation monitoring sensor, a rotational deformation monitoring sensor and a data acquisition controller, the horizontal deformation monitoring sensor, the vertical deformation monitoring sensor, and the rotational deformation monitoring sensor are electrically connected to the data acquisition controller, respectively, and the data acquisition controller is electrically connected to the early warning control module; wherein, the horizontal deformation monitoring sensor is used to obtain the displacement deformation data of the monitoring point in the horizontal direction, the vertical deformation monitoring sensor is used to obtain the displacement deformation data of the monitoring point in the vertical direction, and the rotational deformation monitoring sensor is used to obtain the rotational deformation data of the ground at the monitoring point.
[0021] The embodiments of the present application have the following advantages:
[0022] The present application provides an avalanche protection system, wherein the barrier net is a protection net made of a steel wire rope net of a specific material, has good flexibility and high strength, can withstand large impact and tensile forces, and its high strength and durability can enhance the stability of the protection net and its ability to protect snow. The barrier net is fixed on the top of the slope to prevent the snow in the material source area on the top of the slope from sliding. Even if a small amount of snow slides, it will not cause a large amount of snow to slide, thereby reducing the volume of the avalanche; the energy dissipation device is arranged below the barrier net, and its main function is to dissipate the impact energy caused by the sliding of a large amount of snow; the barrier dam of the secondary barrier device is arranged at the bottom of the mountain slope, and its main function is to use the secondary barrier device to block excessive snow when a large-scale avalanche occurs on the mountain and the barrier net and energy dissipation device above are not sufficient to support a large area of snow. This prevents the snow from continuing to slide down and collapse, destroying large tracts of forests, farmland, houses, factories, roads, vehicles, etc., and affecting human production activities and the natural environment.
[0023] Therefore, this application replaces blocking with dredging in avalanche prevention and control, and combines it with energy dissipation measures, so that the energy of the avalanche when it occurs is gradually reduced, and the snow flow volume no longer increases, thereby enabling the protection system to play a more effective protective role.
[0024] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and understandable, preferred embodiments are given below and described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.
[0026] Figure 1 A schematic structural diagram of an avalanche protection system provided in an embodiment of the present application is shown;
[0027] Figure 2 A schematic diagram of the structure of a monitoring and early warning device provided in an embodiment of the present application is shown;
[0028] Figure 3 A schematic diagram of the structure of a barrier net provided in an embodiment of the present application is shown;
[0029] Figure 4 A schematic structural diagram of an energy dissipation device provided in an embodiment of the present application is shown;
[0030] Figure 5A schematic structural diagram of a secondary arresting device provided in an embodiment of the present application is shown.
[0031] Description of main component symbols:
[0032] 100-first-level blocking device; 110-blocking net; 200-monitoring and early warning device; 210-data receiving antenna; 220-indoor data analysis box; 230-standard pole; 240-wireless transmission antenna; 250-solar panel; 260-pole base; 270-collection module; 271-horizontal deformation monitoring sensor; 272-vertical deformation monitoring sensor; 273-rotational deformation monitoring sensor; 274-data acquisition controller; 280-deformation monitoring box; 300-energy dissipation device; 310-energy dissipation dam; 311-dam body; 312-fixed piles; 320-energy dissipation pool; 321-flat slope; 322-concave slope; 323-wavy slope; 400-second-level blocking device; 410-blocking dam; 411-opening; 420-sedimentation tank; 430-filter; 440-reservoir. DETAILED DESCRIPTION
[0033] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.
[0034] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. In contrast, when an element is referred to as being "directly on" another element, there is no intermediate element. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only.
[0035] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0036] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0037] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art to which this application belongs. The terms used herein in the specification of the template are only for the purpose of describing specific embodiments and are not intended to limit this application. The term "and / or" used herein includes any and all combinations of one or more of the related listed items.
[0038] In the related art, an avalanche refers to a phenomenon in which a large amount of snow suddenly collapses and slides down the slope rapidly due to the destruction of the stability of the snow layer on a snow-covered slope due to some inducement (such as earthquakes, additional loads, temperature changes, human activities, etc.). This natural phenomenon is extremely destructive and can carry a large amount of snow at a very high speed, causing serious damage to the terrain, vegetation, buildings and any organisms along the avalanche path, and even causing casualties. Avalanches usually occur in mountainous areas with a certain slope, especially after new snowfall, when the temperature rises and the snow layer melts, or when strong winds redistribute the snow surface.
[0039] The main methods of avalanche protection are geological monitoring for effective early warning, and the installation of an avalanche protection system on the slope of the mountain. The avalanche protection system is mainly used to protect the avalanche occurrence area and movement area. When an avalanche occurs, it has a high potential energy because it occurs at a high position. It has been accelerated many times from the top of the mountain to the accumulation area at the bottom. Its huge kinetic energy and volume make conventional barrier measures in the avalanche occurrence area and movement area have little effect, poor effect, and generally high cost.
[0040] like Figure 1 , Figure 4 and Figure 5As shown, in order to solve the above technical problems, an embodiment of the present application provides an avalanche protection system, which includes a primary blocking device 100, an energy dissipation device 300 and a secondary blocking device 400, wherein the primary blocking device 100, the energy dissipation device 300 and the secondary blocking device 400 are sequentially arranged along the slope direction of the mountain; wherein the primary blocking device 100 includes a plurality of blocking nets 110, wherein the plurality of blocking nets 110 are arranged at intervals along the slope direction, and the blocking nets 110 close to the top of the slope are covered with snow on the slope, The plane where the barrier net 110 away from the top of the slope is located intersects with the slope surface; the energy dissipation device 300 includes at least one energy dissipation pool 320. When there are multiple energy dissipation pools 320, multiple barrier nets 110 are arranged in sequence along the slope direction; the secondary barrier device 400 includes multiple retaining dams 410, and the multiple retaining dams 410 are arranged at intervals along the slope direction; the retaining dam 410 has multiple openings 411, and the multiple openings 411 are arranged at intervals along the extension direction of the retaining dam 410, and the openings 411 of adjacent retaining dams 410 are staggered.
[0041] In these embodiments, the primary blocking device 100 is mainly used to intercept part of the accumulated snow in the early stage of an avalanche to slow down the speed and development of the avalanche. Multiple blocking nets 110 are arranged at intervals along the slope, and the blocking nets 110 near the top of the slope cover the accumulated snow on the slope to slow down the start of the avalanche. The end of the blocking net 110 away from the top of the slope is tilted toward the upstream of the slope to block the snow flow and disperse the energy of the snow flow.
[0042] Exemplarily, the barrier net 110 away from the top of the slope is vertically arranged with the slope surface. In addition, in other embodiments, the angle between the barrier net 110 and the slope surface can also be set to 30°, 40°, 50°, 60°, 70°, 80°, etc., which is not specifically limited here.
[0043] The energy dissipation device 300 is used to further consume the energy of the avalanche and slow down its speed. The energy dissipation device 300 has at least one energy dissipation pool 320. When there are multiple energy dissipation pools 320, they are arranged in sequence along the slope. Obviously, the energy dissipation pool 320 is used to accommodate the snow flow to absorb part of the energy of the avalanche and reduce the speed of the snow flow.
[0044] For example, the energy dissipation pool 320 is mainly made of reinforced concrete, and the surface is sprayed in the complex terrain area. When the amount of snow sliding is too large, the snow goes over the efficiency base and enters the energy dissipation pool 320. The energy dissipation pool 320 has a large capacity and can store a large amount of snow. Multiple energy dissipation pools 320 can be set up continuously along the slope. When the first energy dissipation pool 320 is full, the snow will continue to move to the next energy dissipation pool 320, thereby achieving multi-level efficiency to reduce the impact of snow.
[0045] The secondary blocking device 400 is used as the last line of defense to finally intercept and control the snow flow. A plurality of blocking dams 410 are arranged at intervals along the slope. The blocking dams 410 have a plurality of openings 411, which are arranged at intervals along the extension direction of the blocking dams 410 to allow water to pass through while intercepting part of the snow flow. The openings 411 of adjacent blocking dams 410 are arranged in a staggered manner, which can more effectively disperse the energy of the snow flow and avoid blocking excessive snow flow and causing damage to the blocking dams 410.
[0046] That is to say, the setting of the retaining dam 410 can help reduce the direct impact and damage of the sliding snow on the foot of the slope when an avalanche occurs. By blocking the snow, a lot of time can be bought for the evacuation of mountain personnel and the harm caused by the avalanche can be reduced. The retaining dam 410 intercepts the mud and rocks in the avalanche, and effectively reduces the flow rate and bulk density of the sliding snow downstream of the dam body 311. The effect of reducing the flow rate and bulk density helps to reduce the destructiveness of the avalanche and reduce its impact on the downstream area.
[0047] Exemplarily, the retaining dam 410 is made of reinforced concrete. Alternatively, in other embodiments, the retaining dam 410 is made of steel plates.
[0048] Obviously, the blocking net 110 first intercepts the snow flow, slows down its speed and changes its direction. The snow flow enters the energy dissipation pool 320, and the resistance of the energy dissipation pool 320 consumes part of the kinetic energy. Finally, the snow flow reaches the barrier dam 410, and the structure of the barrier dam 410 further slows down the snow flow speed and finally intercepts it to avoid damage to the facilities.
[0049] In other words, the top of the mountain above the snow line is covered with snow all year round. After being disturbed by construction or other tectonic movements, the snow on the top of the mountain will quickly become unstable and form an avalanche; the barrier net 110 is a protective net made of a steel wire rope net of a specific material. It has good flexibility and high strength and can withstand large impact and tensile forces. Its high strength and durability can enhance the stability of the protective net and its ability to protect snow. The barrier net 110 is fixed on the top of the slope to prevent the snow in the material source area at the top of the slope from sliding. Even if a small amount of snow slides, it will not cause a large amount of snow to slide, reducing snow The energy dissipation device 300 is arranged below the barrier net 110, and its main function is to dissipate the impact energy caused by the sliding of a large amount of snow; the retaining dam 410 of the secondary retaining device 400 is arranged at the bottom of the mountain slope, and its main function is to use the secondary retaining device 400 to block the excessive snow when a large-scale avalanche occurs in the mountain and the barrier net 110 and the energy dissipation device 300 above are not sufficient to support a large area of snow accumulation, so as to prevent the snow from continuing to slide down and collapse, destroying large tracts of forests, farmland, houses, factories, roads, vehicles, etc., and affecting human production activities and the natural environment.
[0050] Therefore, this application replaces blocking with dredging in avalanche prevention and control, and combines it with energy dissipation measures, so that the energy of the avalanche when it occurs is gradually reduced, and the volume of the snow flow no longer increases, thereby enabling the protection system to play a more effective protective role.
[0051] In some embodiments, mesh sizes of the plurality of barrier nets 110 gradually decrease in the upward direction.
[0052] In these embodiments, the mesh sizes of the plurality of barrier nets 110 gradually decrease along the slope direction (i.e., the direction from the top of the mountain to the foot of the mountain), thereby being able to more effectively control and slow down the development of the avalanche. The barrier net 110 near the top of the slope has a larger mesh size, which helps to intercept larger snow blocks in the early stages of the avalanche while allowing smaller snow blocks to pass through. This can slow down the start of the avalanche and reduce the initial kinetic energy of the snow flow. As the snow flow moves downward, the mesh size of the barrier net 110 gradually decreases, which means that the closer the barrier net 110 is to the bottom, the smaller the snow blocks can be intercepted, so as to gradually increase the interception capacity of the snow flow, so that the snow blocks in the snow flow gradually become smaller, thereby reducing the overall kinetic energy of the snow flow.
[0053] Among them, by gradually reducing the mesh size, the snow blocks in the snow flow can be gradually intercepted and dispersed, thereby slowing down the snow flow and consuming its kinetic energy. This helps prevent the snow flow from forming a large-scale, high-speed snowball effect. Reducing the mesh size can improve the interception efficiency of snow blocks in the snow flow, reduce the possibility of snow flow passing through, and help to more effectively control the development of the snow flow along the entire avalanche path.
[0054] It should be noted that snow flows at different stages have different kinetic energy and snow block sizes. Gradually reducing the mesh size can better adapt to these changes and improve the overall effectiveness of the protection system. Of course, in addition to the mesh size, the shape of the mesh (such as rectangle, diamond, etc.) will also affect the interception efficiency. Similarly, the material of the mesh needs to be strong enough to withstand the impact of the snow flow, and also needs to have a certain degree of flexibility to adapt to different terrain conditions.
[0055] For example, Figure 3 As shown, the barrier net 110 is fixed and supported by ground nails, has a large bending and shear strength, and is about 70-100 cm long. It can reduce the impact force when impacted by snow and play a strong anchoring role.
[0056] The area where avalanches are formed is generally located in high-altitude and cold areas. The installation of the barrier net 110 in this area greatly reduces the difficulty of construction and is easy to operate. The barrier net 110 is installed on the top of the slope, and a large number of ground nails with a length of 70-100 cm are installed on the edge of the barrier net 110. After drilling to a predetermined depth with a tool, the ground nails are inserted, and then the drilled holes are backfilled with concrete mortar. The ground nails are used as extended anchoring measures to tighten the barrier net 110 with their own anchoring force. The barrier net 110 fixes the snow on the slope. Even if a small amount of snow slides, it will not cause a large amount of snow to slide, reducing the volume of the avalanche.
[0057] like Figure 4 As shown, in some embodiments, a buffer layer is provided at the bottom of the energy dissipation pool 320 .
[0058] In these embodiments, a buffer layer is provided at the bottom of the energy dissipation pool 320 to further improve the efficiency of the energy dissipation pool 320, especially in an avalanche protection system. The buffer layer can help absorb the energy generated when the snow flow hits the energy dissipation pool 320, reduce the impact force of the snow flow on the pool wall and the bottom, help reduce the speed of the snow flow, and reduce its kinetic energy.
[0059] The buffer layer can play a shock-absorbing role, reduce the vibration generated when the snow flow hits, protect the pool structure from damage, and help extend the service life of the energy dissipation pool 320. Obviously, the buffer layer helps to disperse the energy of the snow flow to a larger area, reduce local stress concentration, and prevent the pool bottom from being damaged due to excessive local stress.
[0060] For example, the buffer layer is generally made of materials with certain elasticity and energy absorption capacity, and these materials may include but are not limited to:
[0061] Foam materials, such as polystyrene foam (EPS), polyurethane foam, etc.
[0062] Rubber or elastic polymer, such as natural rubber, synthetic rubber, etc.
[0063] Sand or gravel. In some cases, a layer of sand or gravel can also be used as a buffer layer.
[0064] The thickness of the buffer layer needs to be determined according to the speed and volume of the snow flow and the specific size of the energy dissipation pool 320. A buffer layer that is too thin cannot effectively absorb energy, while a buffer layer that is too thick will increase the cost.
[0065] like Figure 4 As shown, in some embodiments, the bottom surface shape of the energy dissipation pool 320 includes one of the following shapes: a flat slope 321 , a concave slope 322 , and a wavy slope 323 .
[0066] In these embodiments, each shape has its specific design purpose and advantages. The characteristics of these shapes and their applications in the energy dissipation pool 320 are introduced below:
[0067] Smooth slope 321: The pool bottom is a smooth slope with a simple structure and easy construction.
[0068] Concave slope 322: The central part of the pool bottom is concave, which increases the contact area between the water flow and the pool bottom, improves the energy dissipation effect, and further consumes energy.
[0069] Wave-shaped slope 323: The surface of the pool bottom is wavy, which increases the complexity of the snow flow path and improves the friction between the snow flow and the pool bottom, thereby more effectively consuming the energy of the snow flow.
[0070] It should be noted that, in this embodiment, the bottom surface shape of the energy dissipation pool 320 is not specifically limited and is specifically set according to the actual shape of the slope.
[0071] For example, in this embodiment, the number of energy dissipation pools 320 is three, and the shapes of the bottom surfaces of the three energy dissipation pools 320 are, in sequence, a flat slope 321, a concave slope 322, and a wavy slope 323. Of course, in other embodiments, the shapes of the bottom surfaces of the three energy dissipation pools 320 are all flat slopes 321; or, the shapes of the bottom surfaces of the three energy dissipation pools 320 are all concave slopes 322; or, the shapes of the bottom surfaces of the three energy dissipation pools 320 are all wavy slopes 323; or, the shapes of the bottom surfaces of the three energy dissipation pools 320 are, in sequence, a wavy slope 323, a concave slope 322, and a flat slope 321.
[0072] In some embodiments, the energy dissipation pool 320 is formed by a concave area of a slope, and a protective layer is disposed on the surface of the energy dissipation pool 320 .
[0073] In these embodiments, the trench-type energy dissipation pool 320 is set up by utilizing the natural terrain of the valley (i.e., the sunken area), which facilitates construction and reduces damage to the environment.
[0074] The protective layer can improve the wear resistance of the pool bottom and pool wall, reduce the wear of the pool structure by snow flow, which helps to extend the service life of the energy dissipation pool 320. In addition, the protective layer can prevent moisture from penetrating into the soil.
[0075] Exemplarily, in this embodiment, the protective layer is set as a shotcrete layer, that is, the shotcrete layer is formed by spraying on the surface of the pool body. Of course, in other embodiments, the protective layer can also be set as a protective pad, etc.
[0076] like Figure 4 As shown, in some embodiments, the energy dissipation device 300 further includes an energy dissipation dam 310 , which is installed upstream of the energy dissipation pool 320 , and the energy dissipation dam 310 is close to the energy dissipation pool 320 .
[0077] The energy dissipation dam 310 is fixed on the slope. When the snow above slides downward, it first contacts the dam body 311 on the upper part of the energy dissipation dam 310 to dissipate energy and prevent the snow from sliding. The energy dissipation dam 310 is relatively strong and can block most of the impact energy of the sliding snow. The energy dissipation dam 310 effectively slows down the sliding speed of the snow, so that the impact force of the sliding snow is alleviated, and the impact force is dispersed and alleviated. The energy dissipation dam 310 is connected to the energy dissipation pool 320, and the energy dissipation dam 310 can prevent the lower energy dissipation pool 320 from directly bearing the impact of the snow.
[0078] For example, when the energy dissipation dam 310 and the energy dissipation pool 320 are constructed, the two are integrated. For example, the energy dissipation dam 310 and the energy dissipation pool 320 are integrated by using concrete and steel bars.
[0079] like Figure 4 As shown, in some embodiments, the energy dissipation dam 310 includes a dam body 311 and fixed piles 312, the dam body 311 and the fixed piles 312 are connected, the dam body 311 is arranged above the slope, and the fixed piles 312 are arranged below the slope; wherein the width of the dam body 311 gradually decreases in the direction away from the slope.
[0080] The energy dissipation dam 310 can initially slow down the speed of the snow flow and reduce the kinetic energy of the snow flow. This helps to reduce the impact of the snow flow on subsequent structures (such as the energy dissipation pool 320). The energy dissipation dam 310 can cause the snow flow to generate eddies and collisions when passing through, thereby consuming part of the energy and reducing the speed and energy of the snow flow when it reaches the energy dissipation pool 320.
[0081] Since the dam body 311 of the energy dissipation dam 310 is in a structure that is larger at the bottom and smaller at the top, the energy dissipation dam 310 can also disperse the impact force of the snow flow by changing the flow direction of the snow flow, thereby reducing the pressure on the energy dissipation pool 320. In other words, the dam body 311 is arranged on the slope and faces the direction of the snow flow. The width of the dam body 311 gradually decreases in the direction away from the slope, which can better disperse the impact force of the snow flow and reduce the lateral pressure of the snow flow on the dam body 311.
[0082] Of course, the material of the dam body 311 usually needs to have a certain strength and durability to resist the impact of snow flow, such as concrete, steel, wood, etc.
[0083] The fixed piles 312 are arranged under the slope surface to anchor the dam body 311 and increase the stability of the dam body 311. The length and diameter of the fixed piles 312 need to be determined according to the terrain and the characteristics of the snow flow to ensure that the dam body 311 can withstand the impact of the snow flow without displacement or damage.
[0084] For example, the material of the fixing piles 312 is usually concrete, steel or other high-strength materials.
[0085] like Figure 5 As shown, in some embodiments, the secondary blocking device 400 also includes a sedimentation tank 420, a filter 430 and a water reservoir 440. The sedimentation tank 420, the filter 430 and the water reservoir 440 are arranged in sequence along the slope. The sedimentation tank 420 is used to receive snow water flowing through the opening 411. The sedimentation tank 420 is connected to the water reservoir 440 through the filter 430.
[0086] In these embodiments, this design is intended to process snow water, reduce the impact of water flow after an avalanche on downstream areas, and potentially recycle water resources. Sedimentation tank 420 is used to receive snow water flowing through opening 411 of retaining dam 410, so that solid particles (such as mud, snow blocks, etc.) carried therein can be settled. Sedimentation tank 420 is generally designed to have a larger surface area and a shallower depth to facilitate the settling of solid particles. Sedimentation tank 420 is located behind retaining dam 410, immediately downstream of retaining dam 410.
[0087] The filter 430 is used to further remove the remaining suspended matter and impurities in the snow water. For example, the filter 430 can be in various forms, such as a sand filter, an activated carbon filter, etc., and a suitable filter material is selected as needed. The filter 430 is connected to the sedimentation tank 420, and the snow water flows from the sedimentation tank 420 into the filter 430 to further purify the water quality.
[0088] The water reservoir 440 is used to store the treated clean snow water, which can be used for irrigation, water supply, etc. The water reservoir 440 needs to have a sufficient volume to accommodate the expected amount of water and has good sealing to prevent water leakage. The water reservoir 440 is located after the filter 430 and is immediately downstream of the filter 430.
[0089] In short, by setting up the sedimentation tank 420, the filter 430 and the water reservoir 440, not only can the impact of the water flow after the avalanche on the downstream area be effectively reduced, but also the water resources can be recycled and the utilization rate of the water resources can be improved.
[0090] Of course, the water reservoir 440 is connected to a pumping pipeline, which can efficiently transport the melted snow water from one place to another to meet the needs of the irrigation system.
[0091] like Figure 2 As shown, in some embodiments, the avalanche protection system also includes a monitoring and early warning device 200, which includes a collection module 270 and an early warning control module. The collection module 270 and the early warning control module are electrically connected. The collection module 270 is installed at a monitoring point on the slope. The collection module 270 is used to collect real-time environmental data of the monitoring point. The early warning control module is used to receive and process the real-time environmental data from the collection module 270, and determine whether to issue an early warning message based on the processing results.
[0092] In these embodiments, the acquisition module 270 and the early warning control module communicate with each other through an electrical connection. By monitoring environmental data in real time, early warning of the occurrence of avalanches is provided, thereby improving the effectiveness of the protection system.
[0093] The acquisition module 270 is installed at key monitoring points on the slope to collect environmental data related to avalanches in real time. The acquisition module 270 can monitor a variety of environmental parameters, including but not limited to: surface displacement, temperature change, humidity, snow thickness, wind speed and direction, and other relevant meteorological parameters.
[0094] The early warning control module receives data from the acquisition module 270 and processes and analyzes it. The early warning control module analyzes the data according to the preset algorithm and threshold to determine whether the early warning condition is met. If the analysis result shows that there is a risk of avalanche, the early warning control module will trigger the early warning mechanism and send a warning message to relevant personnel.
[0095] For ease of understanding, the specific workflow is provided as follows: the acquisition module 270 continuously monitors and records key data. The collected data is sent to the early warning control module via wired or wireless means. The early warning control module analyzes the data and assesses the possibility of avalanche. When the data exceeds the set safety threshold, the system automatically issues an early warning signal. After receiving the early warning, the relevant personnel take action according to the emergency plan, such as evacuating personnel, closing roads, etc.
[0096] like Figure 2 As shown, in some embodiments, the acquisition module 270 includes a horizontal deformation monitoring sensor 271, a vertical deformation monitoring sensor 272, a rotational deformation monitoring sensor 273 and a data acquisition controller 274. The horizontal deformation monitoring sensor 271, the vertical deformation monitoring sensor 272, and the rotational deformation monitoring sensor 273 are electrically connected to the data acquisition controller 274, respectively, and the data acquisition controller 274 is electrically connected to the early warning control module; wherein, the horizontal deformation monitoring sensor 271 is used to obtain the displacement deformation data of the monitoring point in the horizontal direction, the vertical deformation monitoring sensor 272 is used to obtain the displacement deformation data of the monitoring point in the vertical direction, and the rotational deformation monitoring sensor 273 is used to obtain the rotational deformation data of the ground of the monitoring point.
[0097] In these embodiments, the early warning control module includes an indoor data analysis box 220 and an alarm, the indoor data analysis box 220 is electrically connected to the data acquisition controller 274 through a wireless communication module, and the alarm is electrically connected to the indoor data analysis box 220. Among them, the wireless module includes a data receiving antenna 210 and a wireless transmission antenna 240, the data receiving antenna 210 is electrically connected to the indoor data analysis box 220, and the wireless transmission antenna 240 is electrically connected to the data acquisition controller 274.
[0098] For example, the pole base 260 is connected to the standard pole 230, and its main function is to support the deformation monitoring box 280, transfer the weight and load of the deformation monitoring box 280 to the foundation, and play a bearing and supporting role; the deformation monitoring box 280 is provided with a rotation deformation monitoring sensor 273, a vertical deformation monitoring sensor 272, a horizontal deformation monitoring sensor 271, and a data acquisition controller 274. The main function is to provide protection for various precision instruments. The deformation monitoring box 280 is fixed at a certain height of the standard pole 230 by fixing bolts to prevent human damage and obtain the best data collection and transmission effect.
[0099] The rotational deformation monitoring sensor 273 monitors the rotational deformation through laser. Since the ground position is fixed, a reference point is set at the bottom of the ground. The rotational deformation monitoring sensor 273 can start working after being calibrated on site. If the ground rotates, the rotational deformation monitoring sensor 273 will accurately judge based on the position of the ground laser point obtained in the early stage, and then obtain the rotational deformation data of the ground.
[0100] The vertical deformation monitoring sensor 272 determines the vertical deformation according to the relative position to the ground and the vertical position of the standard rod 230. The main function of the vertical deformation monitoring sensor 272 is to measure and monitor the vertical deformation, monitor and judge the snow depth in real time, so as to timely detect any abnormal deformation or displacement. Once an abnormal situation is found, the early warning system can be used to remind relevant personnel and take timely measures to prevent accidents.
[0101] The horizontal deformation monitoring sensor 271 shines a laser on the standard rod 230 and the ground. If the pole base 260 produces horizontal displacement, the laser will analyze and judge based on the initial ground position, and calibrate the deformation in combination with the reference point of the standard rod 230. If the obtained horizontal displacement deformation keeps changing, the final horizontal deformation data will be transmitted to the data acquisition controller 274.
[0102] For example, the horizontal deformation monitoring sensor 271, the vertical deformation monitoring sensor 272, and the rotational deformation monitoring sensor 273 all work using a laser machine. Since the laser machine uses an intelligently adjustable controller, it can automatically change and adjust according to local lighting conditions, ensuring the stability and reliability of deformation monitoring.
[0103] The wireless transmission antenna 240 is connected to the deformation monitoring box 280 , and its main function is to transmit the deformation data obtained in the data acquisition controller 274 to the duty room, and the data receiving antenna 210 in the duty room receives the data and transmits it to the indoor data analysis box 220 .
[0104] The data acquisition controller 274 is connected to the duty room. Its main function is to use data lines to collect data from the rotational deformation monitoring sensor 273, the vertical deformation monitoring sensor 272, and the horizontal deformation monitoring sensor 271, and use the wireless transmission antenna 240 to transmit the data to the data receiving antenna 210 in the duty room and transmit it to the indoor data analysis box 220 for analysis.
[0105] Indoor data analysis box 220, which analyzes the received data and controls the sensors in deformation monitoring box 280 in real time according to the data;
[0106] The data receiving antenna 210 is mainly used to receive the real-time environmental data of the monitoring points detected by the horizontal deformation monitoring sensor 271 , the vertical deformation monitoring sensor 272 , and the rotational deformation monitoring sensor 273 .
[0107] For example, the entire monitoring and early warning device 200 will feed back the collected information to the indoor system in real time. A large number of indicator thresholds are set in the indoor system. When the threshold is exceeded, the system will alarm. The system will transmit the entire information to the road signs and warning systems in the area where avalanches may occur for looping, reminding passing vehicles and pedestrians to pay attention to safety.
[0108] In some embodiments, the standard pole 230 at the monitoring point is installed with a camera, and the camera and the data acquisition controller 274 can transmit the real-time picture of the monitoring point, further facilitating monitoring.
[0109] like Figure 2 As shown, in some embodiments, the monitoring and early warning device 200 also includes a solar power module, which is installed at one end of the standard pole 230 above the ground, and the solar power module is electrically connected to the collection module 270 and the early warning control module respectively.
[0110] In these embodiments, the solar power module can directly convert solar energy into electrical energy to power the entire monitoring and early warning device 200 without relying on external power grid power supply. It is particularly suitable for remote mountainous areas or high-altitude areas where traditional power supply may be difficult to cover or costly.
[0111] The solar power module enables the monitoring and early warning device 200 to continue to work in the event of extreme weather or power grid failure, thereby improving the independence and continuous operation capability of the system, which is crucial for the monitoring and early warning device 200 that requires continuous monitoring and immediate early warning.
[0112] In addition, if power is provided to the monitoring and early warning device 200 from the mains power line to an uninhabited area outdoors, very long wires need to be laid, which increases costs and limits the distributed installation of the monitoring and early warning device 200. Therefore, power supply by a solar power supply device can replace laying very long wires and has a more flexible layout.
[0113] Exemplarily, the solar power module includes a solar panel 250 , which is arranged on the upper part of the deformation monitoring box 280 . The solar panel 250 collects light energy and converts it into electrical energy to provide electrical energy for electronic components in the deformation monitoring box 280 .
[0114] In all examples shown and described herein, any specific values should be interpreted as merely exemplary and not as limiting, and thus other examples of the exemplary embodiments may have different values.
[0115] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.
[0116] The above-mentioned embodiments only express several implementation methods of the present application, and the descriptions thereof are relatively specific and detailed, but they cannot be understood as limiting the scope of the present application. It should be pointed out that, for ordinary technicians in this field, several variations and improvements can be made without departing from the concept of the present application, and these all belong to the protection scope of the present application.
Claims
1. An avalanche protection system, characterized in that: The avalanche protection system comprises a primary blocking device, an energy dissipation device and a secondary blocking device, wherein the primary blocking device, the energy dissipation device and the secondary blocking device are arranged in sequence along the slope of the mountain; wherein The first-level blocking device includes a plurality of blocking nets, which are arranged at intervals along the slope direction, the blocking nets close to the top of the slope are covered with snow on the slope, and the plane where the blocking nets away from the top of the slope are located intersects with the slope; The energy dissipation device includes at least one energy dissipation pool. When there are multiple energy dissipation pools, multiple barrier nets are sequentially arranged along the slope direction. The secondary blocking device includes a plurality of retaining dams, which are arranged at intervals along the slope; the retaining dams have a plurality of openings, which are arranged at intervals along the extension direction of the retaining dams, and the openings of adjacent retaining dams are staggered.
2. The avalanche protection system according to claim 1, characterized in that: On the slope, the mesh sizes of the plurality of barrier nets gradually become smaller.
3. The avalanche protection system according to claim 1, characterized in that: The bottom of the energy dissipation pool is provided with a buffer layer.
4. The avalanche protection system according to claim 3, characterized in that: The bottom surface shape of the energy dissipation pool includes one of the following shapes: Flat slopes, concave slopes and wavy slopes.
5. The avalanche protection system according to claim 1, characterized in that: The energy dissipation pool is formed by the sunken area of the slope, and a protective layer is arranged on the surface of the energy dissipation pool.
6. The avalanche protection system according to claim 1, characterized in that: The energy dissipation device also includes: An energy dissipation dam is installed upstream of the energy dissipation pool and is close to the energy dissipation pool.
7. The avalanche protection system according to claim 6, characterized in that: The energy dissipation dam includes a dam body and fixed piles, the dam body and the fixed piles are connected, the dam body is arranged above the slope surface, and the fixed piles are arranged below the slope surface; wherein the width of the dam body gradually decreases in a direction away from the slope surface.
8. The avalanche protection system according to claim 1, characterized in that: The secondary blocking device also includes a sedimentation tank, a filter and a water reservoir. The sedimentation tank, the filter and the water reservoir are arranged in sequence along the slope. The sedimentation tank is used to receive snow water flowing through the opening, and the sedimentation tank is connected to the water reservoir through the filter.
9. The avalanche protection system according to claim 1, characterized in that: The avalanche protection system further comprises: A monitoring and early warning device, the monitoring and early warning device includes a collection module and an early warning control module, the collection module and the early warning control module are electrically connected, the collection module is installed at the monitoring point of the slope, the collection module is used to collect real-time environmental data of the monitoring point, the early warning control module is used to receive and process the real-time environmental data from the collection module, and determine whether to issue an early warning message based on the processing result.
10. The avalanche protection system according to claim 9, characterized in that: The acquisition module includes a horizontal deformation monitoring sensor, a vertical deformation monitoring sensor, a rotational deformation monitoring sensor and a data acquisition controller. The horizontal deformation monitoring sensor, the vertical deformation monitoring sensor and the rotational deformation monitoring sensor are electrically connected to the data acquisition controller respectively, and the data acquisition controller is electrically connected to the early warning control module; wherein the horizontal deformation monitoring sensor is used to obtain the displacement deformation data of the monitoring point in the horizontal direction, the vertical deformation monitoring sensor is used to obtain the displacement deformation data of the monitoring point in the vertical direction, and the rotational deformation monitoring sensor is used to obtain the rotational deformation data of the ground at the monitoring point.
Citation Information
Patent Citations
Debris flow prevention and treatment system
CN111236161A
Comprehensive prevention and control method for avalanche disaster along road
CN113026587A
Classified filtering and blocking treatment method for debris flow
CN118308993A
SNS flexible active protective net for slope dangerous rock falling protection
CN218204490U
Avalanche prevention block and avalanche prevention structural body
JP2002302912A
Cited By
Avalanche potential release area determination method and device, electronic equipment and storage medium
CN121708501A
Avalanche protection system
WO2026031399A1