Ship lift lock head water retaining method suitable for ship lift channel water level rising greatly
Through the combined structure of the working door and the access door and the water drainage system between the doors, the problem of the ship lift lock head being unable to adapt to changes in water level in the channel is solved, the door position is flexibly adjusted and water is effectively blocked, and the workload and cost are reduced.
Patent Information
- Application Number
- CN202410960442.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-17
- Publication Date
- 2024-10-01
AI Technical Summary
The existing working door structure at the head of the ship lift lock cannot effectively adapt to large changes in water level in the channel, resulting in a heavy workload and inflexibility in adjusting the door position.
Adopting a combined structure of working door and inspection door, through the coordinated operation of the working door hoist and the inspection door hoist, the water level between the doors is adjusted by using the water drainage system between the doors, and the working laminated beam door and the inspection laminated beam door are increased or reduced to adapt to the channel. Changes in water level realize automatic adjustment of door position.
It realizes flexible door position adjustment when the channel water level changes significantly, reduces the door position adjustment workload, improves the compactness, efficiency and safety of the structure, and reduces costs and maintenance time.
Smart Images

Figure CN118727692A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of water retaining at a ship lift lock, and in particular to a water retaining method at a ship lift lock when the water level of a ship lift channel rises significantly. Background Art
[0002] As the ship lift usually runs vertically, when the ship compartment docks with the lock head, the docking sealing device extends to connect the ship compartment with the lock head working door to form a ship passage, so the docking sealing surface on the lock head working door must remain relatively fixed with the ship compartment. The miter door structure of the ship lock will move as a whole during operation and cannot provide a relatively fixed docking sealing surface, so it is not suitable for ship lifts.
[0003] At present, the working gate of the ship lift is a U-shaped flat door structure with a lying small door. The lying small door is opened by tilting and sinking, and is opened or closed by driving the oil cylinder to overcome the gravity of the lying small door. Therefore, the size of the lying small door cannot be designed to be too large. The water level fluctuation of the waterway that the gate can adapt to is determined by the size of the lying small door, so the water level fluctuation of the waterway that the gate can adapt to is also limited. When the hub power station is peaking or the water level in the basin is adjusted, the water level of the waterway will fluctuate greatly. A single gate cannot meet the needs of water retaining and navigation. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a method for blocking water at the head of a ship lift lock when the water level of a ship lift channel rises sharply, which does not occupy extra space and can also adapt to large changes in the water level of the channel, thereby reducing the workload of gate position adjustment.
[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: A method for retaining water at a ship lift lock head when the water level of a ship lift channel rises sharply comprises the following steps: Step 1): When the water level gauge of the ship lift channel detects that the water level rises beyond the adaptability range of the working gate, it is determined that a working stopgate door is added to block water at the gate head; Step 2): Run the maintenance door hoist and lower the maintenance door into the maintenance door slot to block water; after it is in place, disengage the hydraulic grab beam of the maintenance door hoist from the maintenance door; and run the maintenance door hoist to a position that does not affect the operation of the working door hoist and the working beam door; Step 3): Use the door drainage system to drain part of the water between the working door and the inspection door, so that the working door can be opened and closed without water; Step 4): Operate the working door hoist to lift the working door onto the working door support pier; after it is in place, disengage the hydraulic grab beam of the working door hoist from the working door; Step 5): Run the working door hoist to the appropriate working stop beam door support pier, located at the top of the working stop beam door with the correct number; lift a section of the working stop beam door through the working door hoist and drop it into the working door slot; after it is in place, disengage the hydraulic grab beam of the working door hoist from the working stop beam door; Step 6): Run the working door hoist to the working door support pier, located at the top of the working door; lift the working door through the working door hoist and drop it into the working door slot; after it is in place, disengage the hydraulic grab beam of the working door hoist from the working door, and lift the hydraulic grab beam of the working door hoist to the designed height without affecting the navigation clearance height of the waterway; Step 7): Run the maintenance door hoist and lift the maintenance door at a low speed and a small stroke. The water in the waterway will flow through the gap between the maintenance door and the maintenance stacked beam door to the space between the working door and the maintenance door. When the water level between the working door and the maintenance door is flush with the water level in the waterway, lift the maintenance door to the maintenance door support pier. After it is in place, disengage the hydraulic grab beam of the maintenance door hoist from the maintenance door. Step 8): Run the inspection door hoist to the inspection stacked beam door support pier and locate it on the top of the inspection stacked beam door with the correct number; lift a section of the inspection stacked beam door through the inspection door hoist and drop it into the inspection door slot; after it is in place, disengage the hydraulic grab beam of the inspection door hoist from the inspection stacked beam door; Step 9): Run the inspection door opening and closing machine to the top of the inspection door, connect and tighten the inspection door through the hydraulic grab beam of the inspection door opening and closing machine, and the water retaining height is increased.
[0006] The working door comprises a working gate with a lying door and a multi-section working stop beam door; a certain number of working stop beam doors are placed in the working door groove from bottom to top, and the working gate is placed on the top of the working stop beam door, and the adaptability range of the working door matches the water level elevation of the waterway; The inspection door comprises an inspection gate and a multi-section inspection stacked beam door; when adjusting the door position, a certain number of the inspection stacked beam doors are placed in the inspection door groove from bottom to top, and the inspection gate is placed on the top of the inspection stacked beam door; a certain number of working stacked beam doors and working gates block water from the ship lift gate head.
[0007] The lying door on the working gate is usually in a closed state; when the ship compartment is docked with the lock head, the lying door is opened to form a ship passing channel; when the water level fluctuation exceeds the adaptability of the lying door, a section of the working beam door is added or reduced to readjust the position of the working gate; the adjustment of the working gate and the working beam door is carried out under waterless conditions, and the lifting and lowering of the working gate and the working beam door are carried out by the working gate opening and closing machine.
[0008] When the ship lift is in normal navigation state, the water depth from the top of the inspection stopgate stacked in the inspection door slot to the water surface h0 ≥ the designed navigation depth h 设The maintenance gate and redundant maintenance stacked beam doors are stacked on the maintenance gate pier and the maintenance stacked beam door pier respectively, and the maintenance gate is fixed by the maintenance gate opening and closing machine.
[0009] The height of each section of the working beam door is h1, the height of each section of the maintenance beam door is h2, and the number of sections of the working beam door is n 工 , Number of sections of stacked beam doors for maintenance n 检 The maximum fluctuation of water level in the channel h 变 Sure: n 工 =h 变 / h1-1; n 检 =n 工 +1; And h2 工 <h2×n 检 .
[0010] When using the inter-door drainage system to drain part of the water between the working door and the inspection door, if it is necessary to add a section of working stopgate door, it is only necessary to drain the water between the working door and the inspection door until the bottom of the working door is completely exposed; if it is necessary to reduce a section of the working stopgate door, it is only necessary to drain the water between the working door and the inspection door until the bottom of the first section of the working stopgate door under the working door is completely exposed.
[0011] The present invention provides a method for retaining water at the lock head of a ship lift when the water level of a ship lift channel rises sharply, which has the following technical effects: 1) By adopting working gate slots, inspection gate slots and water retaining gate slots, and setting working gate piers, working stacked beam gate piers, inspection gate piers and inspection stacked beam gate piers to place working gates and inspection gates, using working gate hoists and inspection gate hoists to increase or decrease working gates and inspection gates, and using the inter-gate drainage system to adjust the water level, the function of raising or lowering the working gate position can be achieved when the water level in the waterway rises or falls sharply. It has the characteristics of compact structure, high efficiency and cost saving.
[0012] 2) The working door hoist and the inspection door hoist are one-way bridge cranes arranged on concrete frames. They are of the same model and share the same track. When working normally, the two bridge cranes run at the same time to improve efficiency. When one of them fails and stops running, the other can complete the adjustment of the gate position of the ship lift, which improves the safety and reliability of the operation of the water retaining device at the gate.
[0013] 3) The working stacked beam gate piers and the inspection stacked beam gate piers are composed of a series of pier groups with different heights. Each group of piers is stacked with corresponding numbered stacked beam gates. The elevation of each group of piers is calculated by adding the minimum navigation water level corresponding to the last section of the stacked beam gate to the minimum navigation clearance height. This can ensure that the stacked beam gates stacked on the stacked beam gate piers meet the minimum navigation clearance height requirement at any navigation water level, avoiding the construction of piers with the same height, reducing workload and cost, and saving working time when adjusting the number of stacked beam gates.
[0014] 4) When the working gate position is adjusted and the gate drainage system is used to drain part of the water between the working gate and the inspection gate, it is only necessary to drain the water between the two gates to the working stacked beam gate that does not need to be adjusted. There is no need to drain the water between the gates, which reduces the drainage time of the drainage system and the time for the gates to be filled with water after the working gate position is adjusted, thereby improving work efficiency.
[0015] 5) The maintenance platform is usually used for stacking working stacked beams and maintenance stacked beams. It can also be used for maintenance work such as water stopping, guiding device, and structural corrosion protection of working doors and maintenance doors, which facilitates the maintenance of the gate head water retaining device, shortens the shutdown time of the ship lift for maintenance, and improves the maintenance efficiency.
[0016] 6) A water retaining gate groove is set at the front end of the waterway. When the ship lift needs to stop for a long time to retain water, the inspection door opening and closing machine can be used to drop the inspection door into the water retaining gate groove. At the same time, the water between the inspection door and the working door can be drained by the door drainage system, which is convenient for dredging and inspection of the waterway and improves the inspection and maintenance efficiency of hydraulic structures.
[0017] 7) Set up multi-section working stacked beam doors, and adjust the door position of the working gate by increasing or decreasing the number of working stacked beam doors through the working door hoist, which can reduce the size of the working gate, thereby achieving the effect of reducing the maximum lifting weight of the working door hoist, and reducing the construction and installation costs of the working door hoist. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The present invention will be further described below in conjunction with the accompanying drawings and embodiments: Figure 1 It is a schematic diagram of the arrangement of the present invention.
[0019] Figure 2 It is a schematic diagram of water retaining of the working door in the present invention.
[0020] Figure 3 It is a schematic diagram of the working door in the present invention.
[0021] Figure 4 It is a schematic diagram of water retaining of the inspection door in the present invention.
[0022] Figure 5 It is a schematic diagram of the door drainage system in the present invention.
[0023] In the figure: working door 1, inspection door 2, working door slot 3, inspection door slot 4, water retaining door slot 5, working gate pier 6, working stop beam door pier 7, inspection gate pier 8, inspection stop beam door pier 9, working door opening and closing machine 10, inspection door opening and closing machine 11, door drainage system 12, inspection platform 13, working gate 1-1, working stop beam door 1-2, lying door 1-3, inspection gate 2-1, inspection stop beam door 2-2, drainage pipe 12-1, trash rack 12-2, energy dissipation valve 12-3, inspection valve 12-4, working valve 12-5, control system 12-6. DETAILED DESCRIPTION
[0024] like Figure 1 As shown, a lock head water retaining system suitable for large changes in water level in a ship lift channel includes a working door 1, an inspection door 2, a working door slot 3, an inspection door slot 4, a water retaining door slot 5, a working gate pier 6, a working stacked beam gate pier 7, an inspection gate pier 8, an inspection stacked beam gate pier 9, a working gate hoist 10, an inspection gate hoist 11, a gate inter-gate water discharge system 12, and an inspection platform 13.
[0025] The water retaining system of the ship lift lock extends outward from the ship lift cabin section and is respectively provided with a working gate slot 3, a gate drainage system 12, a maintenance gate slot 4, and a water retaining gate slot 5.
[0026] A working gate pier 6, a plurality of working stacked beam gate piers 7, a maintenance gate pier 8, a plurality of maintenance stacked beam gate piers 9 and a maintenance platform 13 are arranged on the top of the navigation channel at the head of the lock.
[0027] A working door hoist 10 and an inspection door hoist 11 are arranged on the track at the top of the gate head navigation channel.
[0028] like Figure 2-3 As shown, the working door 1 is composed of a working gate 1-1 with a lying door 1-3 and a multi-section working stop beam door 1-2, and the working gate 1-1 is placed on the top of the working stop beam door 1-2.
[0029] The main part of the working gate 1-1 with the lying door 1-3 is the prior art, as mentioned in the "A disassembly and assembly tool and method of the hydraulic cylinder of the lying door of the working gate of the ship lift lock" with application number "202111524437.1".
[0030] The working gate 1-1 is provided with a hydraulic opening and closing machine, a locking device, a hydraulic pump station and other equipment of the lying gate 1-3. The working gate 1-1 and the working stop beam door 1-2 are provided with lifting ears on both sides of the top, and the side water stop and bottom water stop are provided on both sides and the bottom. When placed in the gate groove 3, a sealed whole can be formed under the action of gravity and unilateral water pressure. Usually, the lying gate 1-3 on the working gate 1-1 is in a closed state. After the ship compartment is docked with the gate head, the lying gate 1-3 is opened to form a ship passage. The lying gate 1-3 can adapt to the water level fluctuation of a section of the working stop beam door 1-2 height h1. When the water level fluctuation exceeds the adaptability of the lying gate 1-3, the position of the working gate 1-1 is readjusted by adding or reducing a section of the working stop beam door 1-2. The adjustment of the working gate 1-1 and the working stop beam door 1-2 is carried out under waterless conditions. The lifting and lowering of the working gate 1 are carried out by the working gate opening and closing machine 10.
[0031] like Figure 4 As shown, the inspection door 2 includes an inspection gate 2-1 and a multi-section inspection stacked beam door 2-2. The main function of the inspection door 2 is to assist the working door 1 in adjusting the door position of the working door 1 under waterless conditions according to the water level changes in the ship lift waterway. The inspection door 2 selects a suitable number of inspection stacked beam doors 2-2 according to the door position adjustment requirements of the working door 1 and the water level of the waterway. The inspection stacked beam doors 2-2 and the inspection gate 2-1 are stacked in the inspection gate slot 4 to block water at the ship lift gate head when the number of working stacked beam doors 1-2 is adjusted. At this time, the inspection gate 2-1 is stacked on top of the inspection stacked beam door 2-2. The lifting and lowering of the inspection gate 2-1 and the inspection stacked beam door 2-2 are carried out by the inspection door opening and closing machine 11.
[0032] When the ship lift is in normal navigation state, the water depth from the top of the maintenance stopgate 2-2 stacked in the maintenance door slot 4 to the water surface h0 ≥ the designed navigation depth h 设 The maintenance gate 2-1 and the redundant maintenance stop beam gate 2-2 are stacked on the maintenance gate pier 8 and the maintenance stop beam gate pier 9 respectively, and the maintenance gate 2-1 is fixed by the maintenance gate hoist 11. The maintenance gate 2 can also serve as a flood control and water retaining gate for the ship lift channel. When serving as a flood control and water retaining gate, the maintenance gate 2 falls on the water retaining gate groove 5.
[0033] like Figure 1 As shown, the working door hoist 10 and the inspection door hoist 11 are bridge cranes arranged on a concrete bent frame, reciprocating along the water flow direction, and the working door hoist 10 and the inspection door hoist 11 are of the same model and share a common track, which is laid on two lines of steel structure track beams, and the steel structure track beams are erected on the top of the concrete column. The working door hoist 10 and the inspection door hoist 11 are standby for each other. If one of them fails and stops running, the other can complete the work of adjusting the gate position of the ship lift.
[0034] like Figure 5As shown, the inter-door drainage system 12 includes a drainage pipe 12-1, which is arranged in multiple sections and connected by flanges. A trash rack 12-2 is installed at the end of the drainage pipe 12-1, an energy dissipation valve 12-3, a check valve 12-4 and a working valve 12-5 are installed at appropriate positions on the drainage pipe 12-1, and a control system 12-6 is arranged on one side of the drainage pipe 12-1. The control system 12-6 electrically controls each valve, and the corresponding valve can be opened by starting the corresponding button on the control system 12-6.
[0035] When using the inter-door drainage system 12 to drain part of the water between the working door 1 and the inspection door 2, if it is necessary to add a section of the working stop beam door 1-2 at this time, it is only necessary to drain the water between the working door 1 and the inspection door 2 until the bottom of the working gate 1-1 is completely exposed; if it is necessary to reduce a section of the working stop beam door 1-2 at this time, it is only necessary to drain the water between the working door 1 and the inspection door 2 until the bottom of the first section of the working stop beam door 1-2 under the working gate 1-1 is completely exposed.
[0036] like Figure 1 As shown, the maintenance platform 13 is a concrete bridge structure, and piers for the working door 1 and the maintenance door 2 are arranged on the surface of the maintenance platform 13, which can be used for maintenance work such as water stopping, guiding device, and structural anti-corrosion of the working door 1 and the maintenance door 2. The working door 1 and the maintenance door 2 are rotated for maintenance according to the need for water blocking at the gate head.
[0037] Number of sections n of working stopgate 1-2 工 The maximum fluctuation of water level in the channel h 变 Determine, assuming that the height of each section of the working stop beam door 1-2 is h1, then n 工 =h 变 / h1-1.
[0038] The number of sections of the maintenance stopper door 2-2 is determined by the number of sections of the working stopper door 1-2. Assuming that the height of each section of the maintenance stopper door 2-2 is h2, then n 检 =n 工 +1.
[0039] The height h2 of the inspection stop beam door 2-2 is less than the height h1 of the working stop beam door 1-2, and satisfies h1×n 工 <h2×n 检 , it can be realized that when the same number of working stop beam doors 1-2 and maintenance stop beam doors 2-2 are added or removed synchronously in the working door slot 3 and the maintenance door slot 4, the water depth from the door top of the maintenance stop beam door 2-2 stacked in the maintenance door slot 4 to the water surface h0 ≥ the designed navigation depth h 设 Moreover, the water body of the channel can be blocked by simply lowering the inspection gate 2-1, thereby meeting the normal navigation requirements and performing rapid water blocking.
[0040] For example, the channel top elevation is 185m, and the channel water level changes from 145m to 175m. 变 =30, the water level fluctuation adapted by the lying gate 1-3 is 3.75m, so the height of each section of the working stop beam gate 1-2 is 3.75m, and the height of each section of the maintenance stop beam gate 2-2 is 3.5m. 工 =h 变 / h1-1=30 / 3.75-1=7; n 检 =n 工 +1=8.
[0041] That is, the working door 1 can be set as a working gate 1-1 and 7 sections of working stop beam doors 1-2. The 7 sections of working stop beam doors 1-2 are numbered 1-7, and the height of each section of the working stop beam door 1-2 is 3.75m.
[0042] The inspection door 2 can be set as an inspection gate 2-1 and 8 sections of inspection stacked beam doors 2-2. The 8 sections of inspection stacked beam doors 2-2 are numbered 1-8, and the height of each section of the inspection stacked beam door 2-2 is 3.5m.
[0043] Minimum navigation clearance height h 净 It is 18m, so the height of the maintenance gate pier 8 and the maintenance platform 13 stacking plane from the water surface at the highest navigable water level is h2≥193m.
[0044] The working stop beam gate pier 7 is composed of a series of pier groups with different heights, which can be set as three groups of piers, namely, pier ①, pier ②, and pier ③. Pier ① is stacked with working stop beam gates 1-2 numbered 1-3 from top to bottom, pier ② is stacked with working stop beam gates 1-2 numbered 4-5 from top to bottom, pier ③ is stacked with working stop beam gates 1-2 numbered 6, and maintenance platform 13 is stacked with working stop beam gates 1-2 numbered 7. The height h of each group of piers is 工支 The lowest navigable water level h within the water level range adapted by the last section of the working stoplog gate 1-2 stacked 低航 OK, that is h 工支 =h 低航 +h 净 The working stopgates 1-2 stacked on the working stopgate pier 7 can meet the minimum navigation clearance height requirement at any navigation water level.
[0045] For example, the last section of the working stoplog gate 1-2 stacked on pier ① is numbered 3, and the water level range it is adapted to is 156.25m-160m. The calculated elevation of pier ① = 156.25 + 18 = 174.25m, which is lower than the top elevation of the channel. Therefore, pier ① can be set at the top of the channel to the minimum elevation for easy construction and use, h 工支 It can be determined as 185.3m. The calculated elevation of pier ② is 163.75+18=181.75m, and h can also be determined工支 The calculated elevation of pier ③ is 167.5+18=185.5m, which can determine h 工支 It is 185.5m.
[0046] The working stopgate pier 7 is composed of a series of pier groups with different heights, which can reduce the amount of work required to build piers of uniform height while meeting the navigation clearance height, and save the time required for adjusting the working stopgate 1-2.
[0047] The maintenance stacked beam gate pier 9 is composed of a series of pier groups with different heights, which can be set as three groups of piers: pier A, pier B, and pier C. Pier A is stacked with maintenance stacked beam gates 2-2 numbered 1-3 from top to bottom, pier B is stacked with maintenance stacked beam gates 2-2 numbered 4-5 from top to bottom, pier C is stacked with maintenance stacked beam gates 2-2 numbered 6, and maintenance platform 13 is stacked with maintenance stacked beam gates 2-2 numbered 7-8. The height h of each group of piers 检支 The lowest navigable water level h corresponding to the last section of the stacked stoplog door 低航 OK, that is h 检支 =h 低航 +h 净 , which can satisfy the requirement that the maintenance stopgates 2-2 stacked on the maintenance stopgate pier 9 meet the minimum navigation clearance height requirement at any navigation water level. The number of maintenance stopgates 2-2 in the maintenance gate slot 4 and the number of working stopgates 1-2 in the working gate slot 3 increase and decrease synchronously, so the maintenance stopgate pier 9-1 is consistent with the working stopgate pier 7-1, the maintenance stopgate pier 9-2 is consistent with the working stopgate pier 7-2, and the maintenance stopgate pier 9-3 is consistent with the working stopgate pier 7-3.
[0048] Embodiment 1: When the water level in the channel rises from 145m to 148.75m, the water level detection system determines that the water level in the channel will continue to rise, and it is necessary to add a working stopgate door 1-2 to adjust the door position of the working gate 1-1. At this time, there is only the working gate 1-1 in the working gate slot 3, and there is no inspection door 2 in the inspection door slot 4.
[0049] Step 1: Run the inspection door hoist 11, and drop the inspection door 2-1 into the inspection door slot 4 to block water. After the inspection door 2-1 is dropped into place, the hydraulic grab beam of the inspection door hoist 11 is disengaged from the inspection door 2-1, and the inspection door hoist 11 is moved to the left to a position where it does not affect the operation of the working door hoist 10 to the working stop beam door 1-2.
[0050] Step 2: Use the door drainage system 12 to drain the water between the working door 1 and the inspection door 2, so that the working door 1-1 can be opened and closed under water-free conditions.
[0051] Step 3: Operate the working door opening and closing machine 10, lift the working door 1-1 and move it to the working door pier 6 (all door structures are directly placed on the pier, only the maintenance door needs to remain connected to the bridge crane grab beam), so that the hydraulic grab beam of the working door opening and closing machine 10 is disengaged from the working door 1-1.
[0052] Step 4: Operate the working door opening and closing machine 10 and move it to the top of the working beam door pier 7 with the appropriate number, located on the top of the No. 1 working beam door, lift the No. 1 working beam door through the working door opening and closing machine 10 and drop it into the working door groove 3. After it is in place, disengage the hydraulic grab beam of the working door opening and closing machine 10 from the No. 1 working beam door.
[0053] Step 5: Operate the working gate opening and closing machine 10 and move it to above the working gate pier 6, located on the top of the working gate 1-1; lift the working gate 1-1 through the working gate opening and closing machine 10 and drop it into the working gate slot 3. After it is in place, disengage the hydraulic grab beam of the working gate opening and closing machine 10 from the working gate 1-1, and lift the hydraulic grab beam of the working gate opening and closing machine 10 to the designed height without affecting the navigation clearance height of the waterway.
[0054] Step 6: Operate the inspection door opening and closing machine 11 to lift the inspection door 2-1 at a low speed and with a small stroke. The waterway water is filled between the working door 1 and the inspection door 2 through the gap between the inspection door 2-1 and the inspection beam door 2-2. When the water level between the working door 1 and the inspection door 2 is flush with the waterway water level, the inspection door 2-1 is lifted and moved to the inspection door pier 8. After it is in place, the hydraulic grab beam of the inspection door opening and closing machine 11 is disengaged from the inspection door 2-1.
[0055] Step 7: Operate the inspection door hoist 11 to the top of the No. 1 inspection stacked beam door, lift the No. 1 inspection stacked beam door through the inspection door hoist 11 and drop it into the inspection door slot 4; after it is in place, disengage the hydraulic grab beam of the inspection door hoist 11 from the No. 1 inspection stacked beam door.
[0056] Step 8: Run the maintenance door hoist 11 to the top of the maintenance door support 8 and the top of the maintenance door 2-1; connect and tighten the maintenance door 2-1 through the hydraulic grab beam of the maintenance door hoist 11 to prevent the maintenance door 2-1 from overturning in windy weather. The water retaining height is increased.
[0057] For every subsequent change of 3.75m in water level, one stacked beam will be added or reduced synchronously.
[0058] When the ship passes normally, the water retaining device at the gate does not need to be adjusted, only the small door needs to be laid down to open and close.
[0059] Embodiment 2: When the water level of the channel drops from 175m to 171.25m, the water level detection system determines that the water level of the channel will continue to drop, and it is necessary to reduce one section of the working stop beam door 1-2 to adjust the door position of the working gate 1-1. At this time, there are working gate 1-1 and 7 sections of working stop beam doors 1-2 in the working gate slot 3, and there are 7 sections of maintenance stop beam doors 2-2 in the maintenance gate slot.
[0060] Step 1: Operate the inspection door opening and closing machine 11 to lift the inspection door 2-1 to the inspection door slot 4 to block water; after it is in place, disengage the hydraulic grab beam of the inspection door opening and closing machine 11 from the inspection door 2-1, and move the inspection door opening and closing machine 11 to the left to a position where it does not affect the operation of the working door opening and closing machine 10 to move the working stacked beam door 1-2.
[0061] Step 2: Use the inter-door drainage system 12 to drain part of the water between the working door 1 and the inspection door 2 to completely expose the No. 7 working stop beam door adjacent to the working door 1, so that the working gate 1-1 and the No. 7 working stop beam door in the working door slot 3 can be opened and closed under waterless conditions.
[0062] Step 3: operate the working door opening and closing machine 10, lift the working door 1-1 and move it to the working door supporting pier 6; after it is in place, disengage the hydraulic grab beam of the working door opening and closing machine 10 from the working door 1-1.
[0063] Step 4: Run the working door opening and closing machine 10 to the working door slot 3, lift the No. 7 working beam door through the working door opening and closing machine 10 and drop it onto the working beam door pier 7 with the corresponding number; after it is in place, disengage the hydraulic grab beam of the working door opening and closing machine 10 from the No. 7 working beam door.
[0064] Step 5: Operate the working gate opening and closing machine 10 and move it to the working gate pier 6, located on the top of the working gate 1-1; lift the working gate 1-1 by the working gate opening and closing machine 10 and drop it into the working gate slot 3; after it is in place, disengage the hydraulic grab beam of the working gate opening and closing machine 10 from the working gate 1-2, and lift the hydraulic grab beam of the working gate opening and closing machine 10 to the designed height without affecting the navigation clearance height of the waterway.
[0065] Step 6: Operate the inspection door opening and closing machine 11 to lift the inspection door 2-1 at a low speed and with a small stroke. The waterway water is filled into the space between the working door 1 and the inspection door 2 through the gap between the inspection door 2-1 and the inspection beam door 2-2-7. When the water level between the working door 1 and the inspection door 2 is flush with the waterway water level, lift the inspection door 2-1 to the inspection door pier 8. After it is in place, disengage the hydraulic grab beam of the inspection door opening and closing machine 11 from the inspection door 2-1.
[0066] Step 7: Run the inspection door hoist 11 to the inspection door slot 4, lift the No. 7 inspection stacked beam door through the inspection door hoist 11 and drop it onto the inspection stacked beam door pier with the corresponding number; after it is in place, disengage the hydraulic grab beam of the inspection door hoist 11 from the No. 7 inspection stacked beam door.
[0067] Step 8: Run the inspection door hoist 11 to the top of the inspection door 2-1, so that the hydraulic grab beam of the inspection door hoist 11 is connected and tightened with the inspection door 2-1, and the water retaining height is reduced.
[0068] Embodiment 3: When the ship lift needs to be stopped for a long time for maintenance and water blocking, in order to meet safety requirements, the maintenance door 2 can be adjusted to the highest water blocking level. The specific operation process is as follows: Step 1: Run the inspection door hoist 11 to the inspection door slot 4, lift the inspection stacked beam door 2-2 through the inspection door hoist 11 and drop it onto the inspection stacked beam door pier 9 with the corresponding number; after it is in place, disengage the hydraulic grab beam of the inspection door hoist 11 from the inspection stacked beam door 2-2.
[0069] Step 2: Repeat step 1 until only maintenance stacked beam door No. 1 remains in the maintenance door slot 4.
[0070] Step 3: Run the inspection door hoist 11 to the inspection door slot 4, lift the No. 1 inspection stacked beam door through the inspection door hoist 11 and drop it into the water retaining gate slot 5; after it is in place, disengage the hydraulic grab beam of the inspection door hoist 11 from the No. 1 inspection stacked beam door.
[0071] Step 4: Operate the maintenance door hoist 11 to move to the maintenance stacked beam door pier 9 with the appropriate number, and locate it on the top of the next section of the maintenance stacked beam door 2-2, and use the maintenance door hoist 11 to lift the section of the maintenance stacked beam door 2-2 and drop it into the water retaining gate groove 5; after it is in place, disengage the hydraulic grab beam of the maintenance door hoist 11 from the section of the maintenance stacked beam door 2-2.
[0072] Step 5: Repeat step 4 until all eight sections of the inspection stacked beam doors 2-2 are dropped into the water retaining gate groove 5; after being in place, the hydraulic grab beam of the inspection door hoist 11 is disengaged from the last section of the inspection stacked beam door 2-2.
[0073] Step 6: Operate the inspection door opening and closing machine 11, and drop the inspection door 2-1 into the water retaining door groove 5. After it is in place, keep the hydraulic grab beam of the inspection door opening and closing machine 11 connected with the inspection door 2-1 and tighten it.
[0074] Step 7: Use the inter-door drainage system 12 to drain the water between the working door 1 and the inspection door 2, drain the navigation channel, and enable the working gate 1-1 and the working stopgate door 1-2 in the working door slot 3 to be opened and closed under water-free conditions.
Claims
1. A method for retaining water at a ship lift lock head when the water level of a ship lift channel rises sharply, comprising the following steps: Step 1): When the water level gauge of the ship lift channel detects that the water level rises beyond the adaptability range of the working gate (1), it is determined that a section of working stoplog gate (1-2) is added to block water at the gate head; Step 2): operate the inspection door opening and closing machine (11) to drop the inspection door (2-1) into the inspection door slot (4) to block water; after it is in place, disengage the hydraulic grab beam of the inspection door opening and closing machine (11) from the inspection door (2-1); and operate the inspection door opening and closing machine (11) to a position that does not affect the operation of the working door opening and closing machine (10) on the working stop beam door (1-2); Step 3): using the door drainage system (12) to drain part of the water between the working door (1) and the inspection door (2), so that the working door (1-1) can be opened and closed without water; Step 4): operate the working door opening and closing machine (10) to lift the working door (1-1) onto the working door supporting pier (6); after it is in place, disengage the hydraulic grab beam of the working door opening and closing machine (10) from the working door (1-1); Step 5): Run the working door hoist (10) to the appropriate working stop beam door support pier (7), located at the top of the working stop beam door (1-2) with the correct number; lift a section of the working stop beam door (1-2) by the working door hoist (10) and drop it into the working door groove (3); after it is in place, disengage the hydraulic grab beam of the working door hoist (10) from the working stop beam door (1-2); Step 6): Run the working door opening and closing machine (10) to the working door support pier (6), which is located at the top of the working door (1-1); lift the working door (1-1) by the working door opening and closing machine (10) and drop it into the working door slot (3); after it is in place, disengage the hydraulic gripping beam of the working door opening and closing machine (10) from the working door (1-1), and lift the hydraulic gripping beam of the working door opening and closing machine (10) to the designed height without affecting the navigation clearance height of the waterway; Step 7): operate the inspection door hoist (11) and make it lift the inspection door (2-1) at a low speed and a small stroke, so that the waterway water is filled between the working door (1) and the inspection door (2) through the gap between the inspection door (2-1) and the inspection stop beam door (2-2); when the water level between the working door (1) and the inspection door (2) is flush with the water level of the waterway, lift the inspection door (2-1) onto the inspection door support pier (8); after it is in place, disengage the hydraulic grab beam of the inspection door hoist (11) from the inspection door (2-1); Step 8): Run the inspection door hoist (11) to the inspection stop beam door support pier (9) and locate it on the top of the inspection stop beam door (2-2) with the correct number; lift a section of the inspection stop beam door (2-2) by the inspection door hoist (11) and drop it into the inspection door slot (4); after it is in place, disengage the hydraulic grab beam of the inspection door hoist (11) from the inspection stop beam door (2-2); Step 9): Run the inspection door opening and closing machine (11) to the top of the inspection door (2-1), connect and tighten the hydraulic grab beam of the inspection door opening and closing machine (11) to the inspection door (2-1), and the water retaining height is increased.
2. A method for blocking water at the ship lift lock head when the water level of the ship lift channel rises sharply according to claim 1, characterized in that: The working door (1) comprises a working gate (1-1) with a lying door (1-3) and a multi-section working stop beam door (1-2); a certain number of working stop beam doors (1-2) are placed in the working door groove (3) from bottom to top, the working gate (1-1) is placed on the top of the working stop beam door (1-2), and the adaptability range of the working door (1) matches the water level elevation of the waterway; The inspection door (2) comprises an inspection gate (2-1) and a plurality of inspection stacked beam doors (2-2); when adjusting the door position, a certain number of the inspection stacked beam doors (2-2) are placed in the inspection door slot (4) from bottom to top, and the inspection gate (2-1) is placed on the top of the inspection stacked beam doors (2-2); a certain number of working stacked beam doors (1-2) and the working gate (1-1) block water from the ship lift lock head.
3. A method for blocking water at the ship lift lock head when the water level of the ship lift channel rises sharply according to claim 2, characterized in that: The lying door (1-3) on the working gate (1-1) is usually in a closed state; when the ship compartment is docked with the lock head, the lying door (1-3) is opened to form a ship passing passage; when the water level fluctuation exceeds the adaptability of the lying door (1-3), a section of the working stop beam door (1-2) is added or reduced to readjust the position of the working gate (1-1); the adjustment of the working gate (1-1) and the working stop beam door (1-2) is performed under waterless conditions, and the lifting and lowering of the working gate (1-1) and the working stop beam door (1-2) are performed by the working gate opening and closing machine (10).
4. A method for blocking water at the ship lift lock head when the water level of the ship lift channel rises sharply according to claim 1, characterized in that: When the ship lift is in normal navigation state, the water depth from the top of the inspection stopgate (2-2) stacked in the inspection door slot (4) to the water surface h0 ≥ the designed navigation water depth h 设 The maintenance gate (2-1) and the redundant maintenance stacked beam gates (2-2) are respectively stacked on the maintenance gate support pier (8) and the maintenance stacked beam gate support pier (9), and the maintenance gate (2-1) is fixed by the maintenance gate opening and closing machine (11).
5. The method for blocking water at the ship lift lock head when the water level of the ship lift channel rises sharply according to claim 1, characterized in that: The height of each section of the working stop beam door (1-2) is h1, the height of each section of the inspection stop beam door (2-2) is h2, and the number of sections of the working stop beam door (1-2) is n. 工 、Maintenance stacked beam door (2-2) number of sections n 检 The maximum fluctuation of water level in the channel h 变 Sure: n 工 =h 变 / h1-1; n 检 =n 工 +1; And h2< h1; h1×n 工 <h2×n 检 .
6. The method for blocking water at the ship lift lock head when the water level of the ship lift channel rises sharply according to claim 1, characterized in that: When the inter-door water discharge system (12) is used to discharge part of the water between the working door (1) and the inspection door (2), if it is necessary to add a section of the working stop beam door (1-2), it is only necessary to discharge the water between the working door (1) and the inspection door (2) until the bottom of the working door (1-1) is completely exposed; if it is necessary to reduce a section of the working stop beam door (1-2), it is only necessary to discharge the water between the working door (1) and the inspection door (2) until the bottom of the first section of the working stop beam door (1-2) below the working door (1-1) is completely exposed.
Citation Information
Patent Citations
Channel ship elevator device and method for solving errors of water depth
CN102691285A
Anti-collision method of water blocking gate of navigation lock and ship lift
CN102995607A
Locking method and structure for tail water outlet overhaul gate
CN107964924A
Rapid maintenance method and maintenance platform for ship compartment door of ship lift
CN114232579A
Ship lift chamber gap water filling and draining method
CN115324018A