Anti-floating prestress finish rolling rib anchor rod positioning system and construction method
Through the use of the precision-rolled bar anchor positioning system, the problems of eccentricity and slippage during the installation process of the anchor are solved, the stress balance and anti-floating performance of the anchoring system are improved, and the service life of the anchor is extended.
Patent Information
- Application Number
- CN202410901747.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2024-10-01
AI Technical Summary
In construction, precision-rolled high-strength steel anchors are prone to eccentricity and slippage during installation, leading to anchor failure and affecting anti-floating performance and design life.
Provide an anti-floating prestressed precision-rolled bar anchor positioning system, including a lifting unit, a positioning detection unit and a locking support unit. Through a load cell, a scanner, a range finder, a depth sounder and a locking mechanism, the anchor is ensured The rod is precisely positioned and suspended in the pile hole to prevent eccentricity and sinking.
It achieves balanced stress distribution in the resin layer within the anchoring system, extends the design life and anti-floating and tensile properties of the anchor, and improves construction efficiency and quality.
Smart Images

Figure CN118727733A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of anchor rod construction, and more specifically, relates to an anti-floating prestressed precision-rolled reinforcement anchor rod positioning system and a construction method. Background Art
[0002] The superior performance of high-strength fine-rolled steel bars has adapted to the requirements of the era of carbon reduction and green development. Technological innovation and iteration have developed rapidly, from the initial single fine-rolled high-strength steel bar replacing ordinary cages, to the single fine-rolled high-strength steel bar adding an expandable "boot foot", to the single fine-rolled high-strength steel bar being post-tensioned and consolidated with the base plate; the utilization efficiency is constantly improving, and at the same time, the construction quality requirements are also improving simultaneously.
[0003] At present, there are the following problems in the post-tensioned prestressed anti-floating pile technology: (1) After the pile hole is formed, when the fine-rolled high-strength steel anchor rod is installed, the anchor rod is prone to not being centered enough and touching the bottom of the pile hole; after anchoring, the anchor rod is seriously eccentric, and even the anchor rod directly contacts the rock layer without effective contact with the concrete. Over time, the bottom of the anchor rod corrodes and affects the use function of the anchor rod. Studies have shown that the eccentricity and bottom corrosion of the anchor rod will seriously weaken the anchoring performance of the anchor rod. The eccentricity of the anchor rod will cause uneven stress distribution and uncoordinated deformation of the resin layer in the anchor system, resulting in greater stress levels and deformation in areas with thinner resin layers. This will cause local preferential failure of the resin layer of the anchor system, reducing the bearing capacity of the anchor system and seriously affecting the design life of the anchor rod and its anti-floating and tensile resistance. (2) The currently commonly used steel bar binding and other temporary reinforcement measures have low work efficiency. (3) During the grouting process, the fine-rolled steel anchor rod is easy to slide to the bottom of the pile hole, which affects the construction quality when it is manually lifted, and is time-consuming and labor-intensive.
[0004] In view of this, according to actual needs, it is necessary to study a device and construction method that can both lift and position the prestressed precision-rolled reinforcement anchor rod and keep it suspended vertically, and it is convenient, simple, accurate, and easy to use flexibly on the construction site. Summary of the invention
[0005] In view of the problems in the prior art that anchor rods are prone to eccentricity and sliding down to the bottom during the casting process, resulting in anchor failure, the present invention provides an anti-floating prestressed precision-rolled reinforcement anchor rod positioning system and a construction method to solve such problems.
[0006] To achieve the above-mentioned purpose, the present invention provides an anti-floating prestressed precision-rolled reinforcement anchor rod positioning system, comprising a lifting unit, which includes a lifting device and a dynamometer, the lifting device is connected to the anchor rod through the dynamometer, the anchor rod is transported to the pile hole construction site and performs lifting operations, and the force condition of the anchor rod in the vertical direction is detected by the dynamometer; a positioning detection unit, which includes a scanner, a rangefinder and a depth sounder; the scanner detects and locates the pile hole position, the rangefinder detects the distance between the anchor rod and the top of the pile hole, and the depth sounder measures the depth of the pile hole; a locking support unit for locking and supporting the outer periphery of the anchor rod, including a locking mechanism and a supporting mechanism, the locking mechanism includes a locking sleeve, a locking assembly, a support connecting pipe and a water The support mechanism comprises a base and a telescopic support rod; and a control unit, which controls the lifting device to move to the pile hole, and according to the detection information of the scanner, the anchor rod is hoisted and rotated to align with the center point of the pile hole through the sling; the distance between the anchor rod and the top of the pile hole and the effective depth of the pile hole detected by the depth sounder are detected by the rangefinder to complete the detection of the effective length of the anchor rod descent; and the lifting unit is controlled to sink the anchor rod to the bottom to verify the detection distance data; after the verification is completed, the anchor rod is lifted to the set height and separated from the bottom of the pile hole; the outer periphery of the anchor rod is locked by the locking mechanism, and the extension length of the telescopic support rod is fine-tuned according to the detection information of the spirit level to keep the locking mechanism horizontal, so that the anchor rod is centered, and the anchor rod fixed support and positioning operations are completed.
[0007] Furthermore, the locking sleeve is a tubular structure, the inner diameter of which is smaller than the diameter of the anchor rod, and comprises a first half tube and a second half tube, wherein the first half tube and the second half tube are hingedly connected by a hinge.
[0008] Furthermore, the locking assembly includes a locking seat fixedly arranged at the other end of the first half pipe, and a locking screw rotatably arranged at the other end of the second half pipe. The locking screw is threadedly connected to the locking seat, so that the other end of the first half pipe and the other end of the second half pipe are pulled together, and pressure is applied to the anchor rod in the locking sleeve, thereby pressing the anchor rod.
[0009] Furthermore, the supporting connecting pipes are provided in three groups, which are circumferentially arranged on the locking sleeve body; the spirit level is fixedly arranged on the side of the locking sleeve.
[0010] Furthermore, the base is arranged on the ground around the pile hole, and is used to support the telescopic support rod. A through hole is opened on the base, and a ground anchor bolt is driven into the ground through the through hole, thereby increasing the connection force between the base and the ground.
[0011] Furthermore, the bottom of the telescopic support rod is arranged on the base, and it includes an outer positioning tube and an inner support rod. The bottom of the outer positioning tube is arranged on the base, and a plurality of positioning holes are opened on the tube body; the inner support rod is slidably arranged in the outer positioning tube, and its outer diameter is the same as that of the outer positioning tube. An upper reset lock pin is provided on the side of the upper end rod body, and a lower reset lock pin is provided on the side of the lower end rod body.
[0012] Furthermore, the upper reset lock pin passes through a locking hole provided in the support connecting tube to achieve locking between the inner support rod and the support connecting tube; the lower reset lock pin passes through a corresponding positioning hole to achieve locking between the inner support rod and the outer positioning tube.
[0013] Furthermore, the telescopic support rod adopts an electric push rod or a hydraulic rod, which is communicated with the control unit and fixedly connected to the support connecting pipe. According to the change of the inclination angle detected by the level meter, the control unit controls the corresponding telescopic support rod to adjust the extension length, so that the locking mechanism remains horizontal.
[0014] According to another aspect of the present invention, there is also provided a method for positioning and constructing an anti-floating prestressed finished rolled reinforcement anchor rod, characterized in that it comprises the following steps:
[0015] S100: The lifting unit enters the site and lifts the anchor rod through the sling;
[0016] S200: The scanner determines the position distance and center point of the pile hole, and the control unit controls the lifting unit to move to the pile hole, and the anchor rod is hoisted and rotated to align with the center point of the pile hole through the sling;
[0017] S300: The distance between the anchor rod and the top of the pile hole is detected by a distance meter and the effective depth of the pile hole is detected by a depth meter, so as to complete the detection of the effective length of the anchor rod descent;
[0018] S400: The lifting unit sinks the anchor rod to the bottom to verify whether the detection distance data is correct;
[0019] S500: After completing the verification of the detection distance data, the control unit controls the lifting unit to lift the anchor rod to the set height and separate it from the bottom of the pile hole;
[0020] S600: rotating the first half pipe and the second half pipe by hinges so that the two are closed to press the anchor rod, aligning the locking screw with the locking seat to threadably connect them, thereby pressing the anchor rod;
[0021] S700: Connect the three sets of telescopic support rods to the support connecting pipes respectively, and adjust the length so that the bottom base contacts the ground, and anchor the base to the ground;
[0022] S800: Fine-tune the extension length of the telescopic support rod until the level meter detects that the locking mechanism remains horizontal;
[0023] S900: After completing the anchor rod fixing support, the concrete pouring operation of the pile hole is carried out in the later stage.
[0024] In general, the above technical solutions conceived by the present invention can achieve the following beneficial effects compared with the prior art:
[0025] 1. The anchor rod positioning system of the present invention can accurately move the anchor rod into the pile hole and keep it suspended through the lifting unit and the positioning detection unit, and avoid serious eccentricity and sinking of the anchor rod during the pouring process through the locking support unit, thereby ensuring the balanced distribution of stress in the resin layer in the anchoring system after pouring, so that the design life of the anchor rod, anti-floating and anti-tensile properties, and bearing performance of the anchoring system meet the design requirements. The structure is simple and compact, easy to operate, and convenient to disassemble and install.
[0026] 2. The anchor positioning system of the present invention can detect the distance between the anchor and the bottom of the pile hole by providing a distance meter and a depth meter when performing anchor lifting and positioning, and verify the accuracy of the detected distance by observing the changes in the bottoming and force meter values. Through the above measures, the anchor can be accurately lifted to a setting height and separated from the bottom of the pile hole, thereby avoiding corrosion of the anchor by groundwater and enhancing the anti-floating effect and durability of the anchor.
[0027] 3. The anchor rod positioning system of the present invention determines the position distance and center point of the pile hole through a scanner, can rotate the anchor rod to align with the center point of the pile hole, and apply pressure through the anchor rod in the locking sleeve to press the anchor rod to prevent the anchor rod from moving in the vertical direction. The supporting mechanism supports the locking sleeve to adjust the horizontality, which can effectively prevent the anchor rod from deviating from the center, solves the problem of centering the anti-floating anchor rod, and makes the concrete protective layer uniform in thickness.
[0028] 4. The anchor positioning system of the present invention is provided with a locking mechanism, which includes a first half tube and a second half tube hinged by a hinge, a locking seat fixed at the other end of the first half tube, and a locking screw rotatably arranged at the other end of the second half tube. It can lock multiple types of anchors that are larger than its diameter, solves the installation of anchors of different diameters and specifications and ensures that the anchors are suspended in the air and do not fall to the bottom during the installation process. It is simple to make, simple and compact in structure, easy to operate, convenient to disassemble and install, and also easy to carry. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a structural schematic diagram of an anti-floating prestressed precision-rolled reinforcement anchor rod positioning system in an embodiment of the present invention;
[0030] Figure 2 A construction logic step diagram of an anchor positioning system in an embodiment of the present invention;
[0031] Figure 3 It is a structural schematic diagram of the locking mechanism in an embodiment of the present invention;
[0032] Figure 4 Schematic diagram of the structure of the support mechanism in the embodiment of the present invention
[0033] Figure 5The present invention is a flowchart of a method for positioning and constructing an anti-floating prestressed precision-rolled reinforcement anchor rod in an embodiment of the present invention.
[0034] In all the drawings, the same figure marks represent the same technical features, specifically: 1-locking mechanism, 11-locking sleeve, 111-first half tube, 112-second half tube, 113-hinge, 12-locking assembly, 13-support connecting tube, 131-locking hole, 14-level, 2-support mechanism, 21-base, 22-telescopic support rod, 221-external positioning cylinder, 222-inner support rod, 223-positioning hole, 224-upper reset lock pin, 225-lower reset lock pin. DETAILED DESCRIPTION
[0035] In order to make the purpose, technical solutions and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not intended to limit the present invention. In addition, the technical features involved in the various embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0036] like Figure 1-4 As shown, the present invention provides an anti-floating prestressed fine-rolled reinforcement anchor rod positioning system, which includes a lifting unit, a positioning detection unit, a locking support unit and a control unit. The lifting unit includes a lifting device and a dynamometer. The lifting device is connected to the anchor rod through the dynamometer, and can transport the anchor rod to the pile hole construction site and perform lifting operations. At the same time, the force condition of the anchor rod in the vertical direction is detected by the dynamometer. The positioning detection unit includes a scanner, a rangefinder and a depth sounder. The scanner detects and locates the pile hole position, the rangefinder detects the distance between the anchor rod origin and the top of the pile hole, and the depth sounder measures the depth of the pile hole. The locking support unit includes a locking mechanism 1 and a supporting mechanism 2. The locking mechanism 1 locks the outer periphery of the anchor rod, and the supporting mechanism 2 supports the locking mechanism 1 to avoid the displacement of the anchor rod and ensure the accuracy of the positioning when the anchor rod is cast. The anchor positioning system of the present invention can accurately move the anchor into the pile hole and keep it suspended through the lifting unit and the positioning detection unit, and avoid serious eccentricity and sinking of the anchor during the pouring process through the locking support unit, thereby ensuring the balanced distribution of stress in the resin layer in the anchoring system after pouring, so that the design life of the anchor, anti-floating and anti-tensile properties, and bearing performance of the anchor system meet the design requirements. The structure is simple and compact, easy to operate, and convenient to disassemble and install.
[0037] like Figure 1As shown, in the embodiment of the present invention, the lifting unit includes a lifting device and a dynamometer. The lifting device can be a crane or a small pressure lifting machine, which can be moved to the pile hole under the control of the control unit, and the anchor rod can be lifted by the sling to be lifted or lowered. The dynamometer is connected to the sling, which detects the vertical stress state of the anchor rod and sends the detection data to the control unit to determine whether the vertical stress of the anchor rod is abnormal.
[0038] The positioning detection unit includes a scanner, a rangefinder and a depth sounder. The scanner scans and images the construction site through a high-precision industrial camera, determines the location distance and center point of the pile hole and other corresponding detection information, and sends the detection information to the control unit to control the lifting unit to move to the pile hole, and hoist the anchor rod to align with the center point of the pile hole through the sling.
[0039] The distance meter is arranged on the lifting device, and detects the distance between the anchor rod and the top of the pile hole, and sends the detection data to the control unit, so as to control the lifting device to accurately lower the anchor rod into the pile hole.
[0040] The depth sounder is arranged at the top of the pile hole. It utilizes the characteristic of ultrasonic wave propagating at a uniform speed and in a straight line in a uniform medium. According to the round trip time of the sound wave and the speed of sound wave propagation in the measured water area, the pile hole depth can be accurately calculated, and the detection data can be sent to the control unit, so as to control the lifting device to accurately lower the anchor rod to the specified position in the pile hole to prevent it from touching the bottom or not sinking in place, so that the anchoring effect does not meet the design requirements; at the same time, by providing a depth sounder, the detected pile hole depth can be compared with the designed depth of the pile hole, so as to detect the state of the pile hole, and detect adverse conditions such as pile hole collapse after water injection and maintenance, so that maintenance personnel can perform maintenance on the pile hole in time.
[0041] like Figure 3-4 As shown, the locking support unit is used to fix the support anchor rod to prevent deviation during pouring, and includes a locking mechanism 1 and a support mechanism 2.
[0042] The locking mechanism 1 includes a locking sleeve 11, a locking assembly 12, a supporting connecting pipe 13 and a level 14. The locking sleeve 11 is an openable and closable pipe-mounted structure that can lock anchor rods of different diameters. It includes a first half pipe 111 and a second half pipe 112, and the first half pipe 111 and the second half pipe 112 are hinged by a hinge 113. The locking assembly 12 includes a locking seat fixedly arranged at the other end of the first half pipe 111, and a locking screw rotatably arranged at the other end of the second half pipe 112. The locking screw is threadedly connected to the locking seat, and the other end of the first half pipe 111 and the other end of the second half pipe 112 are pulled together to apply pressure to the anchor rod in the locking sleeve 11, thereby pressing the anchor rod to prevent the anchor rod from moving in the vertical direction. The locking sleeve 11 can lock multiple types of anchor rods that are larger than its diameter, and its installation and construction are simple and effective. The supporting connecting pipe 13 is provided with three groups, which are circumferentially arranged on the tube body of the locking sleeve 11, and are connected to the supporting mechanism 2 to support and limit the anchor rod. The level 14 is fixedly arranged on the side of the locking sleeve 11 to detect whether the locking sleeve 11 is horizontal, so as to prevent it from driving the anchor rod off the center point in the vertical direction, resulting in the anchoring effect failing to meet the design requirements.
[0043] The support mechanism 2 includes a base 21 and a telescopic support rod 22. The base 21 is arranged on the ground around the pile hole, and is used to support the telescopic support rod 22. In order to avoid force displacement when pouring the anchor rod, a through hole is also opened on the base 21, and the anchor bolt is driven into the ground through the through hole, thereby increasing the connection force between the base 21 and the ground, making the locking support unit more stable, and avoiding the displacement of the anchor rod. The bottom of the telescopic support rod 22 is arranged on the base 21, and it includes an outer positioning tube 221 and an inner support rod 222. The bottom of the outer positioning tube 221 is arranged on the base 21, and a plurality of positioning holes 223 are opened on the tube body. The inner support rod 222 is slidably arranged in the outer positioning tube 221, and its outer diameter is the same as that of the outer positioning tube 221. An upper reset lock pin 224 is provided on the side of the upper end rod body, and a lower reset lock pin 225 is provided on the side of the lower end rod body.
[0044] When supporting the locking mechanism 1, the upper end of the inner support rod 222 is inserted into the supporting connecting tube 13, and the upper reset locking pin 224 is passed through the locking hole 131 provided in the supporting connecting tube 13 to realize the locking between the inner support rod 222 and the supporting connecting tube 13; slide the outer positioning tube 221 until the base 21 contacts the ground, and anchor the base 21 to the ground, and fine-tune the distance between the three groups of inner support rods 222 and the outer positioning tube 221 until the spirit level 14 detects that the locking mechanism 1 remains horizontal, and the lower reset locking pin 225 passes through the corresponding positioning hole 223 to realize the locking of the inner support rod 222 and the outer positioning tube 221, thereby completing the support of the locking mechanism 1 by the supporting mechanism 2, which can effectively prevent the anchor rod from deviating from the center.
[0045] In another embodiment of the present invention, the telescopic support rod 22 adopts an electric push rod or a hydraulic rod, which is communicated with the control unit. After being connected to the support connecting pipe 13, the control unit controls the corresponding telescopic support rod 22 to adjust the extension length according to the inclination angle change detected by the spirit level 14, so that the locking mechanism 1 remains horizontal.
[0046] like Figure 2 As shown, when the positioning system of the present invention is in operation, the lifting unit enters the site, and under the path planning of the control unit, it moves to the pile hole, and lifts the anchor rod through the sling; the scanner scans and images the construction site through a high-precision industrial camera, determines the position distance and center point of the pile hole, and sends the detection information to the control unit, controls the lifting unit to move to the pile hole, and rotates the anchor rod to align with the center point of the pile hole through the sling; installs a depth meter on the top of the pile hole; uses the distance meter to detect the distance between the anchor rod and the top of the pile hole and the effective depth of the pile hole detected by the depth meter, and the control unit controls the lifting unit to lower the anchor rod; the lifting unit sinks the anchor rod to the bottom to verify whether the detection distance data is correct: when it is lowered to the detection distance, the anchor rod sinks to the bottom, contacts with the bottom of the pile hole to generate supporting force, the force meter count changes, and the detection distance data is correct; when it is lowered to the detection distance, the anchor rod does not sink to the bottom, the force meter count does not change, and the detection distance data is too small; when it is not lowered to the detection distance, the force meter count changes, the anchor rod sinks to the bottom in advance, and the detection distance data is too large; if the detection distance data is abnormal, the operator will check the distance meter and the depth meter. The depth meter performs detection and troubleshooting until the data is verified to be normal; after completing the verification of the detection distance data, the control unit controls the lifting unit to lift the anchor rod to the set height and separate it from the bottom of the pile hole to avoid corrosion of the anchor rod by groundwater and enhance the anti-floating effect and durability of the anchor rod; the locking sleeve 11 is opened and placed on the upper end of the anchor rod, and the first half pipe 111 and the second half pipe 112 are rotated by the hinge 113 to close the two to press the anchor rod, and the locking screw is aligned with the locking seat for threaded connection, and the other end of the first half pipe 111 and the locking seat are screwed together. The other end of the second half pipe 112 is pulled together to apply pressure to the anchor rod in the locking sleeve 11, thereby pressing the anchor rod to prevent the anchor rod from moving in the vertical direction; the three groups of telescopic support rods 22 are respectively connected to the support connecting pipes 13, and the lengths are adjusted so that the base 21 at the bottom is in contact with the ground, and the base 21 is anchored to the ground; the extension length of the telescopic support rod 22 is fine-tuned until the spirit level 14 detects that the locking mechanism 1 remains horizontal, thereby preventing the anchor rod from shifting; after completing the anchor rod fixed support, the concrete pouring operation of the pile hole is carried out in the later stage.
[0047] The anchor positioning system of the present invention can accurately move the anchor into the pile hole and keep it suspended through the lifting unit and the positioning detection unit, and avoid serious eccentricity and sinking of the anchor during the pouring process through the locking support unit, thereby ensuring the balanced distribution of stress in the resin layer in the anchoring system after pouring, so that the design life of the anchor, anti-floating and anti-tensile properties, and bearing performance of the anchor system meet the design requirements. The structure is simple and compact, easy to operate, and convenient to disassemble and install.
[0048] The anchor positioning system of the present invention can detect the distance between the anchor and the bottom of the pile hole by providing a rangefinder and a depth sounder when performing anchor lifting and positioning, and verify the accuracy of the detected distance by observing the changes in the bottoming and force meter values. Through the above measures, the anchor can be accurately lifted to a setting height and separated from the bottom of the pile hole, thereby avoiding corrosion of the anchor by groundwater and enhancing the anti-floating effect and durability of the anchor.
[0049] The anchor rod positioning system of the present invention determines the position distance and center point of the pile hole through a scanner, can rotate the anchor rod to align with the center point of the pile hole, and apply pressure through the anchor rod in the locking sleeve 11, so as to press the anchor rod to prevent the anchor rod from being displaced in the vertical direction. The support mechanism 2 supports the locking sleeve 11 to adjust the horizontality, which can effectively prevent the anchor rod from deviating from the center, solves the problem of centering the anti-floating anchor rod, and makes the concrete protective layer have uniform thickness.
[0050] The anchor positioning system of the present invention is provided with a locking mechanism 1, which includes a first half tube 111 and a second half tube 112 hingedly connected by a hinge 113, a locking seat fixedly arranged at the other end of the first half tube 111, and a locking screw rotatably arranged at the other end of the second half tube 112. It can lock various types of anchors larger than its diameter, solves the installation of anchors of different diameters and specifications, and ensures that the anchors are suspended in the air and do not fall to the bottom during the installation process. It is simple to manufacture, simple and compact in structure, easy to operate, convenient to disassemble and install, and also easy to carry.
[0051] like Figure 5 As shown, the present invention also provides a method for positioning and constructing an anti-floating prestressed fine-rolled reinforcement anchor rod, comprising the following steps:
[0052] S100: The lifting unit enters the site and lifts the anchor rod through the sling;
[0053] S200: The scanner determines the position distance and center point of the pile hole, and the control unit controls the lifting unit to move to the pile hole, and the anchor rod is hoisted and rotated to align with the center point of the pile hole through the sling;
[0054] S300: The distance between the anchor rod and the top of the pile hole is detected by a distance meter and the effective depth of the pile hole is detected by a depth meter, so as to complete the detection of the effective length of the anchor rod descent;
[0055] S400: The lifting unit sinks the anchor rod to the bottom to verify whether the detection distance data is correct;
[0056] S500: After completing the verification of the detection distance data, the control unit controls the lifting unit to lift the anchor rod to the set height and separate it from the bottom of the pile hole;
[0057] S600: Rotate the first half tube 111 and the second half tube 112 by the hinge 113 so that the two are closed to press the anchor rod, align the locking screw with the locking seat to threadably connect them, and thus press the anchor rod;
[0058] S700: Connect the three sets of telescopic support rods 22 to the support connecting pipes 13 respectively, and adjust the lengths so that the base 21 at the bottom contacts the ground, and anchor the base 21 to the ground;
[0059] S800: finely adjusting the extension length of the telescopic support rod 22 until the level meter 14 detects that the locking mechanism 1 remains horizontal;
[0060] S900: After completing the anchor rod fixing support, the concrete pouring operation of the pile hole is carried out in the later stage.
[0061] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An anti-floating prestressed finished rolled bar anchor rod positioning system, characterized in that: include: A lifting unit, which includes a lifting device and a dynamometer. The lifting device is connected to the anchor rod through the dynamometer, and the anchor rod is transported to the pile hole construction site and lifted and lowered. At the same time, the dynamometer is used to detect the stress condition of the anchor rod in the vertical direction; A positioning detection unit, comprising a scanner, a rangefinder and a depth sounder; the scanner detects and locates the position of the pile hole, the rangefinder detects the distance between the anchor rod and the top of the pile hole, and the depth sounder measures the depth of the pile hole; A locking support unit for locking and supporting the outer periphery of an anchor rod, comprising a locking mechanism (1) and a support mechanism (2), wherein the locking mechanism (1) comprises a locking sleeve (11), a locking assembly (12), a support connecting pipe (13) and a level (14), and the support mechanism (2) comprises a base (21) and a telescopic support rod (22); and a control unit, which controls the lifting device to move to the pile hole, and according to the detection information of the scanner, the anchor rod is hoisted and rotated to align with the center point of the pile hole through the sling; the distance between the anchor rod and the top of the pile hole and the effective depth of the pile hole detected by the depth meter are detected by the distance meter to complete the detection of the effective length of the anchor rod descent; and the lifting unit is controlled to sink the anchor rod to the bottom to verify the detection distance data; after the verification is completed, the anchor rod is lifted to the set height and separated from the bottom of the pile hole; the outer periphery of the anchor rod is locked by the locking mechanism (1), and the extension length of the telescopic support rod (22) is finely adjusted according to the detection information of the level meter (14), so that the locking mechanism (1) remains horizontal, thereby centering the anchor rod, and completing the anchor rod fixing support and positioning operation.
2. The anti-floating prestressed finished rolled bar anchor rod positioning system according to claim 1, characterized in that: The locking sleeve (11) is a tubular structure with an inner diameter smaller than the diameter of the anchor rod, comprising a first half-tube (111) and a second half-tube (112), wherein the first half-tube (111) and the second half-tube (112) are hingedly connected via a hinge (113).
3. The anti-floating prestressed finished rolled bar anchor rod positioning system according to claim 1, characterized in that: The locking assembly (12) comprises a locking seat fixedly arranged at the other end of the first half tube (111), and a locking screw rotatably arranged at the other end of the second half tube (112). The locking screw is threadedly connected to the locking seat, so that the other end of the first half tube (111) and the other end of the second half tube (112) are pulled together, and pressure is applied to the anchor rod in the locking sleeve (11), thereby pressing the anchor rod.
4. The anti-floating prestressed finished rolled bar anchor rod positioning system according to claim 1, characterized in that: The supporting connecting pipes (13) are provided in three groups and are circumferentially arranged on the tube body of the locking sleeve (11); the level (14) is fixedly arranged on the side of the locking sleeve (11).
5. An anti-floating prestressed finished rolled bar anchor rod positioning system according to any one of claims 1 to 4, characterized in that: The base (21) is arranged on the ground around the pile hole and is used to support the telescopic support rod (22). A through hole is formed on the base, and a ground anchor bolt is driven into the ground through the through hole, thereby increasing the connection force between the base (21) and the ground.
6. An anti-floating prestressed finished rolled bar anchor rod positioning system according to any one of claims 1 to 4, characterized in that: The bottom of the telescopic support rod (22) is arranged on the base (21), and it comprises an outer positioning tube (221) and an inner support rod (222). The bottom of the outer positioning tube (221) is arranged on the base (21), and a plurality of positioning holes (223) are opened on the tube body; the inner support rod (222) is slidably arranged in the outer positioning tube (221), and its outer diameter is the same as that of the outer positioning tube (221). An upper reset lock pin (224) is arranged on the side of the upper end of the rod body, and a lower reset lock pin (225) is arranged on the side of the lower end of the rod body.
7. The anti-floating prestressed finished rolled bar anchor rod positioning system according to claim 6, characterized in that: The upper reset lock pin (224) passes through a locking hole (131) provided in the support connecting tube (13) to achieve locking between the inner support rod (222) and the support connecting tube (13); the lower reset lock pin (225) passes through a corresponding positioning hole (223) to achieve locking between the inner support rod (222) and the outer positioning tube (221).
8. An anti-floating prestressed finished rolled bar anchor rod positioning system according to any one of claims 1 to 4, characterized in that: The telescopic support rod (22) is an electric push rod or a hydraulic rod, which is connected to the control unit for communication and is fixedly connected to the support connection pipe (13). According to the change of the inclination angle detected by the level meter (14), the control unit controls the corresponding telescopic support rod (22) to adjust the extension length, so that the locking mechanism (1) remains horizontal.
9. A method for positioning and constructing an anti-floating prestressed fine-rolled reinforcement anchor rod, characterized in that: The steps include: S100: The lifting unit enters the site and lifts the anchor rod through the sling; S200: The scanner determines the position distance and center point of the pile hole, and the control unit controls the lifting unit to move to the pile hole, and the anchor rod is hoisted and rotated to align with the center point of the pile hole through the sling; S300: The distance between the anchor rod and the top of the pile hole is detected by a distance meter and the effective depth of the pile hole is detected by a depth meter, so as to complete the detection of the effective length of the anchor rod descent; S400: The lifting unit sinks the anchor rod to the bottom to verify whether the detection distance data is correct; S5 00: After completing the verification of the detection distance data, the control unit controls the lifting unit to lift the anchor rod to the set height and separate it from the bottom of the pile hole; S600: rotating the first half tube (111) and the second half tube (112) by means of the hinge (113) so that the two are closed to press the anchor rod, aligning the locking screw with the locking seat to threadably connect them, thereby pressing the anchor rod; S700: Connect three sets of telescopic support rods (22) to the support connecting pipes (13) respectively, and adjust the lengths so that the base (21) at the bottom is in contact with the ground, and anchor the base (21) to the ground; S800: finely adjust the extension length of the telescopic support rod (22) until the level meter (14) detects that the locking mechanism (1) remains horizontal; S900: After completing the anchor rod fixing support, the concrete pouring operation of the pile hole is carried out in the later stage.