Post-consolidation installation method for special-shaped steel structure
By adopting the method of hinged first and then consolidated in the steel structure construction, combining the rod end hinged components and post-consolidated rod components, and gradually setting up temporary supports, the problem of vertical deformation difference between the steel truss and the core tube was solved, and the problem was improved. Improve installation accuracy and construction stability.
Patent Information
- Application Number
- CN202410900665.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-05
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-05
AI Technical Summary
In the construction of super high-rise and special-shaped steel structures, the difference in vertical deformation between the steel truss and the core tube leads to uneven internal forces in the structure, affecting installation accuracy and construction stability.
Adopt the method of hinge first and then consolidate, gradually set up temporary supports through rod end hinge components and post-consolidation rod components to reduce the influence of the steel structure's own weight on the internal force of the structure, and fix each part through chord connecting components to ensure installation accuracy .
It reduces the influence of vertical deformation difference on the internal force of the structure, improves the installation accuracy, reduces the influence of the steel structure's own weight on the initial internal force of the structure during the assembly process, and controls the construction load and engineering volume.
Smart Images

Figure CN118728095A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building engineering construction, in particular to a post-consolidation installation method for a special-shaped steel structure. Background Art
[0002] Super high-rise, special-shaped steel structures or steel-concrete composite structures are not only subjected to very complex forces during the use stage of the structure, but also to complex deformation and forces during the construction process. For steel frame-core tube structures with special shapes, there are many oblique truss structures, the top of which is strongly connected to the giant truss or core tube on the opposite side through horizontal members to form a "giant structure". Before and after the overall structure is closed, the force forms of the main components of the steel truss are very different.
[0003] In the installation of the oblique truss structure, the vertical components and the corresponding floor slabs are constructed layer by layer in the conventional order, while the oblique steel trusses need to be assembled in place first, and then the temporary supports are removed after the overall structure is formed, and the gravity load is applied. Due to the large difference in vertical stiffness between the core tube and the truss, the vertical deformation difference between the two causes a large internal force in the components connected to the core tube.
[0004] Therefore, a post-consolidation installation method for a special-shaped steel structure is provided, which adopts a method of first hinge and then consolidate to reduce the cantilever state of the newly assembled truss, thereby reducing structural deformation and ensuring installation accuracy. Summary of the invention
[0005] The object of the present invention is to provide a post-consolidation installation method for a special-shaped steel structure to solve the problems raised in the above-mentioned background technology.
[0006] In order to solve the above technical problems, the present invention provides the following technical solutions: a post-consolidation installation method for a special-shaped steel structure, comprising a core tube steel column, a steel truss temporary support, a rod end hinge assembly, a beam end fixing assembly, a post-consolidation rod assembly and a chord connecting assembly. The core tube steel column is fixed on a shear wall, the rod end hinge assembly is installed on the core tube steel column, the rod end hinge assembly is connected to the beam end fixing assembly, and the rod end hinge assembly hinges the device with the core tube steel column.
[0007] According to the above technical solution, the end hinge assembly includes a hinged end and a rigid short plate, a positioning bolt is installed on the surface of the hinged end, the middle of the hinged end is hinged with the rigid short plate, the rigid short plate is oblique, and a first pin is provided at the hinged portion between the rigid short plate and the hinged end.
[0008] According to the above technical solution, the beam end fixing assembly includes a temporary fixing plate, a second pin is provided between the temporary fixing plate and the rigid short plate, the upper part of the temporary fixing plate is connected to the left upper chord rod, and the lower part of the temporary fixing plate is connected to the left lower chord rod.
[0009] According to the above technical solution, the steel truss fixing assembly includes a connecting block 1, a connecting block 2, a connecting block 3, and a connecting block 4. The left side of the connecting block 1 is connected to the left upper chord, the right side of the connecting block 1 is connected to the right upper chord, the lower side of the connecting block 1 is connected to the right diagonal web member, the right diagonal web member is oblique, the other side of the right diagonal web member is fixed to the upper surface of the connecting block 2, the connecting block 2 is fixed to the right lower chord, the connecting block 3 fixes the left lower chord to the temporary fixing plate, and the connecting block 4 connects the left lower chord to the right lower chord.
[0010] According to the above technical solution, the chord connecting assembly includes a positioning hole and a connecting plate, the connecting plate is fixed at the connection between the left lower chord and the right lower chord, the connecting plate preliminarily fixes the chords on both sides by connecting bolts, the positioning hole is opened at the connection of the chord, and the positioning hole and the connecting block are fastened by high-strength bolts.
[0011] According to the above technical scheme, the rear-consolidation rod component includes a short beam and a connecting block three. The connecting block three is fixed to the left diagonal web member after the hinge device is removed. The upper end of the left diagonal web member is fixed to the lower end of the connecting block one to form a "K" shape fixation. The cross-section of the short beam is the same as the cross-section of the left lower chord member. The right end of the short beam is connected to the left end of the left lower chord member. The left end of the short beam is fixed to the core tube steel column. An angle steel is provided at the fixed position of the left end of the short beam. Reinforcing ribs are installed on the upper and lower parts of the short beam for reinforcement. A top plate embedded end is fixed below the core tube steel column. Temporary supports are gradually arranged between the core tube steel column and the integral truss.
[0012] Compared with the prior art, the beneficial effects achieved by the present invention are as follows: the present invention provides a rod end hinge assembly and a post-consolidation rod assembly, and the ends of the steel trusses are hinged first and then fixed, which can reduce the influence of the vertical deformation difference on the internal force of the structure and improve the installation accuracy;
[0013] By gradually setting up temporary supports, the influence of the steel structure's deadweight on the initial internal force of the structure can be reduced during the assembly process. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0015] Figure 1 It is a schematic diagram of the overall front structure of the present invention;
[0016] Figure 2 It is a schematic diagram of the installation completion of the present invention;
[0017] Figure 3is a schematic diagram of a truss connection of the present invention;
[0018] Figure 4 It is a schematic diagram of the installation process of the present invention;
[0019] In the figure: 1. Core tube steel column; 2. Left upper chord; 3. Right upper chord; 4. Left lower chord; 5. Right lower chord; 6. Right diagonal web; 7. Left diagonal web; 8. Hinge end; 9. Positioning bolt; 10. Second pin; 11. Rigid short plate; 12. First pin; 13. Temporary fixing plate; 14. Connection block one; 15. Connection block two; 16. Connection block three; 17. Connection block four; 18. High-strength bolt; 19. Short beam; 20. Angle steel; 21. Reinforcement rib; 22. Connection plate; 23. Connection bolt; 24. Positioning hole; 25. Top plate embedded end; 26. Temporary support. DETAILED DESCRIPTION
[0020] The following is a further non-limiting detailed description of the technical solution of the present invention in conjunction with the preferred embodiments and the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0021] See also Figure 1-3 The present invention provides a technical solution: a post-consolidation installation method for a special-shaped steel structure, comprising a core tube steel column 1, a rod end hinged assembly, a beam end fixing assembly, a steel truss fixing assembly, a chord connection assembly and a post-consolidation rod assembly, the core tube steel column 1 is fixed on the shear wall, the rod end hinged assembly is installed on the core tube steel column 1, the rod end hinged assembly and the beam end fixing assembly are connected, the rod end hinged assembly hinges the device to the core tube steel column 1, the beam end fixing assembly fixes the device to the steel truss as a whole, and the steel truss fixing assembly is fixed to various connection positions of the truss for reinforcement and connection.
[0022] The rod end hinge assembly includes a hinge end 8 and a rigid short plate 11. The hinge end 8 is fixed on the core tube steel column 1. A positioning bolt 9 is installed on the surface of the hinge end 8 to position it with the core tube steel column 1. The middle of the hinge end 8 is hinged to the rigid short plate 11. The rigid short plate 11 is oblique, and a first pin shaft 12 is provided at the hinge between the rigid short plate 11 and the hinge end 8.
[0023] The beam end fixing assembly includes a temporary fixing plate 13, which is fixedly connected to the end of the rigid short plate 11, and a second pin shaft 10 is installed at the connection. The upper part of the temporary fixing plate 13 is connected to the left upper chord 2, and the lower part of the temporary fixing plate 13 is connected to the left lower chord 4, which is used for temporary fixation of the upper and lower trusses.
[0024] The steel truss fixing assembly includes a connecting block 14, a connecting block 2 15, a connecting block 3 16, and a connecting block 4 17. The left side of the connecting block 14 is connected to the left upper chord 2, and the right side of the connecting block 14 is connected to the right upper chord 3. The bottom of the connecting block 14 is connected to the right diagonal web member 6. The right diagonal web member 6 is oblique, which makes the steel truss structure more stable. The other side of the right diagonal web member 6 is connected to the connecting block 2 15, and the connecting block 2 15 is fixed to the right lower chord 5. The connecting block 3 16 fixes the left lower chord 4 to the temporary fixing plate 13, and the connecting block 4 17 connects the left lower chord 4 to the right lower chord 5.
[0025] The chord connecting assembly includes a positioning hole 24 and a connecting plate 22. The connecting plate 22 is fixed at the connection between the left lower chord 4 and the right lower chord 5. The connecting plate 22 preliminarily fixes the chords on both sides through connecting bolts 23. The positioning hole 24 is opened at the connection of the chord, and is positioned and aligned with the connecting block four 17, and then fastened by high-strength bolts 18.
[0026] The connection block 1 14, the connection block 2 15, the connection block 3 16 and the connection block 4 17 all adopt the same connection method as the chord connection assembly. After the installation of the truss main structure is completed, the rod end hinge assembly is removed and the rear consolidation rod assembly is installed.
[0027] The rear-consolidation rod assembly includes a short beam 19 and a connecting block three 16. The connecting block three 16 is fixed to the left diagonal web member 7 after the hinge device is removed. The upper end of the left diagonal web member 7 is fixed to the lower end of the connecting block one 14 to form a "K" shape fixation. The cross-section of the short beam 19 is the same as the cross-section of the left lower chord member 4. The right end of the short beam 19 is connected to the left end of the left lower chord member 4. The left end of the short beam 19 is fixed to the core tube steel column 1 through an angle steel 20. Reinforcing ribs 21 are installed on the upper and lower parts of the short beam 19 for reinforcement.
[0028] See also Figure 4 A top plate embedded end 25 is fixed below the core tube steel column 1, and temporary supports 26 are gradually arranged between the core tube steel column 1 and the overall truss.
[0029] Working principle:
[0030] The post-consolidation installation of this special-shaped steel structure reduces the adverse effects of vertical deformation differences and ensures installation accuracy by first hinged and then consolidated the fasteners adjacent to the core tube.
[0031] Generally, after the construction of the vertical core tube structure is completed, temporary supports 26 are gradually set on the top plate embedded end 25, and the steel trusses are assembled layer by layer. The gradual setting of point supports can reduce the influence of the self-weight of the steel structure on the initial internal force of the structure during the layer-by-layer assembly process. The temporary support points are selected at the positions corresponding to the basement columns. In this way, the construction volume of temporary supports and the top plate construction load can be effectively controlled, and the various parts are connected by the chord rod connection assembly;
[0032] Specifically, after the left lower chord 4 is aligned with the right lower chord 5, it is first fixed by the connecting plate 22, and fastened with the connecting bolt 23. After the connecting block 17 is aligned with the positioning hole 24, it is reinforced with the high-strength bolt 18. After the assembly of the lower chord is completed, the left upper chord 2 is connected with the right upper chord 3 through the chord connecting assembly;
[0033] After the assembly of the upper and lower chords is completed, the right diagonal brace is assembled through the connecting block 14 and the connecting block 2 15, and at the same time, a temporary fixing plate 13 is installed on the left side to temporarily replace the left diagonal brace 7 for fixing in the vertical direction;
[0034] After the overall assembly of the rigid truss is completed, it is positioned on the core tube steel column 1 to confirm the installation position of the hinged end 8, and the hinged end 8 is fixed to the core tube steel column 1 by the positioning bolt 9. The rigid short plate 11 is installed between the hinged end 8 and the temporary fixing plate 13, and the hinged end 8 and the rigid short plate 11 are hinged by the first pin shaft 12. The temporary fixing plate 13 and the rigid short plate 11 are fixed by the second pin shaft 10. At this time, the main structural components of the steel frame are all installed.
[0035] Through the above steps, the main structure of the integral steel truss can be initially installed, avoiding the waste of high engineering measures fees caused by the use of full-floor scaffolding supports.
[0036] When all the main components of the main structure of the steel frame are installed, the temporary supports 26 are gradually removed to release some deformation of the main structure, and then the truss floor slabs of each layer are poured, and finally the remaining post-installation rods and post-consolidation rods are installed and fixed.
[0037] Specifically, the temporary hinged device, including the hinged end 8, the rigid short plate 11 and the temporary fixing plate 13, is removed, and the left diagonal web member 7 of the truss is installed and fixed to the connecting block three 16 and the connecting block one 14.
[0038] Take out the short beam 19 and select a suitable length. One end is in contact with the core tube steel column 1, and the other end is connected to the left lower chord 4 through the connecting block three 16. The same connection method as the connection of each chord is adopted. One side of the core tube of the short beam 19 is initially fixed by the connecting plate 20, and reinforcing ribs 21 are set on the upper and lower sides for reinforcement.
[0039] After the post-consolidation installation of the lower chord is completed, the upper chord is consolidated in the same way. The single-section truss presents a "K" shape, and then the installation of all trusses is completed.
[0040] It should be noted that this solution reduces the adverse effects of vertical deformation differences by the method of hinge-first and then fixation, reduces structural deformation, and improves installation accuracy. The temporary support frame needs to be located near the beam-column node to facilitate force transfer, and the temporary hinged fixed positioning and installation must be accurate.
[0041] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device.
[0042] Finally, it should be noted that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art can still modify the technical solutions described in the aforementioned embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A method for post-consolidation installation of a special-shaped steel structure, comprising a core tube steel column (1), a rod end hinge assembly, a beam end fixing assembly, a steel truss fixing assembly, a chord connecting assembly and a post-consolidation rod assembly, characterized in that: The core tube steel column (1) is fixed on the shear wall, the rod end hinge assembly is installed on the core tube steel column (1), the rod end hinge assembly is connected to the beam end fixing assembly, and the rod end hinge assembly hinges the device to the core tube steel column (1); The rod end hinge assembly comprises a hinge end (8) and a rigid short plate (11), a positioning bolt (9) is installed on the surface of the hinge end (8), the middle of the hinge end (8) is hinged to the rigid short plate (11), the rigid short plate (11) is oblique, and a first pin shaft (12) is provided at the hinge between the rigid short plate (11) and the hinge end (8).
2. A post-consolidation installation method for a special-shaped steel structure according to claim 1, characterized in that: The beam end fixing assembly comprises a temporary fixing plate (13), a second pin shaft (10) is arranged between the temporary fixing plate (13) and the rigid short plate (11), a left upper chord rod (2) is connected above the temporary fixing plate (13), and a left lower chord rod (4) is connected below the temporary fixing plate (13).
3. The post-consolidation installation method of a special-shaped steel structure according to claim 2, characterized in that: The steel truss fixing assembly comprises a connecting block 1 (14), a connecting block 2 (15), a connecting block 3 (16), and a connecting block 4 (17). The left side of the connecting block 1 (14) is connected to a left upper chord (2), the right side of the connecting block 1 (14) is connected to a right upper chord (3), the lower side of the connecting block 1 (14) is connected to a right diagonal web member (6), the right diagonal web member (6) is diagonal, the other side of the right diagonal web member (6) is fixed to the upper surface of the connecting block 2 (15), the connecting block 2 (15) is fixed to the right lower chord member (5), the connecting block 3 (16) fixes the left lower chord member (4) to the temporary fixing plate (13), and the connecting block 4 (17) connects the left lower chord member (4) to the right lower chord member (5).
4. The post-consolidation installation method of a special-shaped steel structure according to claim 3, characterized in that: The chord connecting assembly comprises a positioning hole (24) and a connecting plate (22). The connecting plate (22) is fixed at the connection between the left lower chord (4) and the right lower chord (5). The connecting plate (22) preliminarily fixes the chords on both sides through connecting bolts (23). The positioning hole (24) is opened at the connection of the chords. The positioning hole (24) and the connecting block four (17) are fastened by high-strength bolts (18).
5. The post-consolidation installation method of a special-shaped steel structure according to claim 4, characterized in that: The rear-consolidation rod component assembly comprises a short beam (19) and a connecting block three (16). The connecting block three (16) is fixed to the left diagonal web member (7) after the hinge device is removed. The upper end of the left diagonal web member (7) is fixed to the lower end of the connecting block one (14). The cross section of the short beam (19) is the same as the cross section of the left lower chord member (4). The right end of the short beam (19) is connected to the left end of the left lower chord member (4). The left end of the short beam (19) is fixed to the core tube steel column (1). An angle steel (20) is provided at the left end fixing position of the short beam (19). Reinforcing ribs (21) are installed on the upper and lower parts of the short beam (19) for reinforcement.
6. A post-consolidation installation method for a special-shaped steel structure according to claim 5, characterized in that: The overall truss is fixed in a "K" shape after post-consolidation.
7. The post-consolidation installation method of a special-shaped steel structure according to claim 6, characterized in that: A top plate embedded end (25) is fixed below the core tube steel column (1), and temporary supports (26) are gradually arranged between the core tube steel column (1) and the integral truss.
8. The post-consolidation installation method of a special-shaped steel structure according to claim 7, characterized in that: The temporary support (26) is removed after the installation of the truss main structure is completed.
Citation Information
Patent Citations
Delay connection installation method for outrigger of super high-rise building in steel frame-core tube structure
CN105672481A
Frame core tube rigid connection floor beam structure system and construction method
CN114134995A
Shock absorption and energy consumption type outrigger truss high-rise structure system
CN114197751A
Fabricated device for reinforcing traditional building wooden column
CN214659050U
Bidirectional high-rigidity large-span transfer truss system
CN214994652U