Honeycomb aluminum plate curtain wall construction method
By introducing positioning mechanisms and support units into the honeycomb aluminum panel curtain wall structure, the precise installation of the purlins and the stable positioning of the upper ear plates are achieved, which solves the problem of structural loosening and deformation in bad weather and improves the overall stability and wind resistance.
Patent Information
- Application Number
- CN202411212598.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-30
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-08-30
AI Technical Summary
The existing honeycomb aluminum panel curtain wall structure has problems such as loosening of the connecting bolts between the upper and lower ear plates, deformation of the upper ear plates, and uncertainty in the installation position of the purlins in bad weather, which affects the structural stability.
The positioning mechanism and support unit are used to ensure the installation position and height of the purlins through the precise positioning of the support unit and the installation unit, improve the stability of the upper ear plate, and disperse the pressure of wind and rain impact through the positioning mechanism to prevent the deformation of the upper ear plate. .
It improves the overall stability and wind resistance of the honeycomb aluminum panel curtain wall, prevents the upper ear plate from loosening or deforming due to external forces, and ensures the stability of the structure in bad weather.
Smart Images

Figure CN118728100A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of curtain wall construction, and in particular to a honeycomb aluminum plate curtain wall construction method. Background Art
[0002] With the continuous development of economy and society, the number of buildings with large curtain wall structures continues to rise. Nowadays, the exterior decoration and decoration of curtain walls, especially their decorative shapes, are increasingly attracting people's attention.
[0003] Existing honeycomb aluminum panel curtain wall structures such as Figure 1 As shown, it includes purlin 2, upper ear plate 7 and lower ear plate 8, purlin 2 is fixedly connected to the steel frame, lower ear plate 8 is fixedly connected to the top of purlin 2, upper ear plate 7 is connected to lower ear plate 8 by No. 1 connecting bolt 9 and No. 2 connecting bolt 10, angle steel 30 is fixedly connected to upper ear plate 7, and honeycomb aluminum plate 4 is fixedly connected to the top of angle steel 30. This technical solution can adjust the angle of honeycomb aluminum plate 4. Specifically, when adjusting the angle, first pass No. 1 connecting bolt 9 through upper ear plate 7 and lower ear plate 8, but do not fix and lock No. 1 connecting bolt 9, adjust the angle of honeycomb aluminum plate 4, after the angle is adjusted, lock No. 1 connecting bolt 9, and fix upper ear plate 7 and lower ear plate 8 again by No. 2 connecting bolt 10.
[0004] However, although this technical solution can adjust the angle of the honeycomb aluminum plate, it has many problems when encountering bad weather (such as stormy weather). The strong wind brought by the storm may cause the connecting bolts between the upper ear plate and the lower ear plate to be continuously subjected to vibration and shear force. After a long time, the connecting bolts may become loose, resulting in the connection between the upper ear plate and the lower ear plate no longer being tight. If the bolts are seriously loose, the upper ear plate may shake to a certain extent, thereby affecting the stability of the honeycomb aluminum plate; at the same time, extreme wind and rain impact may exert huge pressure on the upper ear plate, causing it to deform. If the material of the upper ear plate is not strong enough or the design strength is insufficient, it may bend, twist, and other deformations under the action of strong wind. The deformed upper ear plate may not be able to fix the honeycomb aluminum plate normally, and may even damage the aluminum plate. In addition, this technical solution cannot accurately locate the installation position and height of the purlin. Summary of the invention
[0005] The present invention aims to provide a construction method of a honeycomb aluminum panel curtain wall, so as to improve the stability of an upper ear panel and prevent the upper ear panel from being deformed, and at the same time, the installation position and height of a purlin can be accurately positioned.
[0006] To achieve the above object, the present invention adopts the following technical scheme: A honeycomb aluminum panel curtain wall construction method comprises the following steps: S1: Installation and construction preparation of steel frame; S2: Positioning and installation of purlins: A support unit is provided between the steel frame and the purlins, through which the purlins can be fixed on the steel frame, and the height of the support unit can be adjusted; a positioning mechanism is provided on the steel frame, which can position the support unit; S3: Installation and angle correction of honeycomb aluminum panels: Several installation units are arranged on the purlins, and the positioning mechanism can also position the installation units. Each installation unit is composed of two installation parts, and each installation part includes an upper ear plate, a lower ear plate and a No. 1 connecting bolt. The lower ear plate is fixedly connected to the top of the purlin, and the upper ear plate is connected to the lower ear plate by a No. 1 connecting bolt. The honeycomb aluminum panel is fixedly connected to the top of the upper ear plate. The angle of the honeycomb aluminum panel is adjusted. After the angle adjustment is completed, the upper ear plate is positioned by the positioning mechanism.
[0007] The beneficial effects of this solution are as follows: In this technical solution, due to the setting of the positioning mechanism, when installing the support unit, the installation position and height of the support unit can be accurately positioned, thereby ensuring the installation accuracy of the purlin. At the same time, after the angle adjustment of the honeycomb aluminum plate is completed, the positioning mechanism can effectively position the upper ear plate, greatly improving the stability of the upper ear plate and preventing the upper ear plate from deforming. In the event of severe weather (such as stormy weather), the positioning mechanism can ensure that the upper ear plate remains firmly in a fixed position to avoid movement due to external forces (such as wind, slight vibration, etc.). In this way, the honeycomb aluminum plate can be stably fixed at the desired angle, thereby enhancing the stability of the entire structure. When extreme wind and rain impact the honeycomb aluminum plate, huge pressure will be exerted on the upper ear plate. However, due to the setting of the positioning mechanism, the upper ear plate can transfer the pressure it bears to the positioning mechanism, and the positioning mechanism then transfers the pressure to the purlin. In this way, the pressure borne by the upper ear plate is dispersed to a larger range, thereby effectively preventing the deformation of the upper ear plate due to stress concentration.
[0008] The positioning mechanism of this technical solution can not only position the support unit, but also the upper ear plate. By positioning the support unit, the installation position and height of the purlin can be accurately determined, ensuring the stability of the connection between the steel frame and the purlin. The positioning of the upper ear plate further enhances the installation stability of the honeycomb aluminum panel, especially in severe weather conditions, and can effectively prevent the upper ear plate from being deformed or loosened due to external forces. In short, the positioning mechanism has important application value and broad development prospects in buildings with large curtain wall structures.
[0009] Preferably, the support unit comprises a support adapter tube, which is fixedly connected to the top of the steel frame, the upper end of which is threadedly connected to a support tube, and the purlin is fixedly connected to the top of the support tube.
[0010] The beneficial effect of this solution is that: since the support adapter tube is threadedly connected to the support tube in this technical solution, the height of the support tube can be adjusted, and the adjustment of the installation height of the purlin is further realized.
[0011] Preferably, the positioning mechanism comprises a first positioning unit and a second positioning unit, the first positioning unit is used to position the supporting unit, and the second positioning unit is used to position the mounting unit.
[0012] Preferably, the first positioning unit includes a No. 1 positioning rod, which is fixed on the steel frame and has a height equal to the installation height of the support unit. A positioning screw is rotatably connected to the support adapter tube. The positioning screw includes a smooth section, a threaded section, a limit section and a positioning section that are connected in sequence. The limit section rotates and is clamped on the support adapter tube. The positioning section is located inside the support adapter tube, and the positioning section is used to position the support adapter tube.
[0013] The beneficial effects of this solution are as follows: due to the setting of the first positioning unit, this technical solution can enable the support adapter tube to maintain a coaxial setting with the No. 1 positioning rod, thereby improving the positioning accuracy. When positioning the support adapter tube, first put the support adapter tube on the No. 1 positioning rod, and adjust the position of the support adapter tube so that the spherical surface of the positioning section contacts the spherical groove on the No. 1 positioning rod. This can achieve the positioning of the support adapter tube, and then fix the support adapter tube on the steel frame.
[0014] The No. 1 positioning rod is welded on the steel frame. Its height is equal to the installation height of the support unit. It can be used to preliminarily locate the installation position of the support unit and provide an accurate reference for the installation height. This makes the installation of the support unit more accurate and ensures the stability and accuracy of the entire structure.
[0015] Preferably, the second positioning unit includes a slider, which is threadedly connected to the threaded segment to form a screw pair, a guide rod is fixedly connected to the support adapter tube, the slider is slidably set on the guide rod, the top of the slider is detachably connected to a push rod, a positioning block is slidably set on the purlin, a No. 2 positioning rod is fixedly connected to the inclined surface of the positioning block close to the upper ear plate, a No. 1 positioning hole is provided on the inclined surface of the upper ear plate close to the positioning block, the No. 2 positioning rod can be inserted into the No. 1 positioning hole, and the push rod can push the positioning block to move to position the upper ear plate.
[0016] The beneficial effect of this solution is: due to the setting of the positioning block, this technical solution can detect the installation angle of the honeycomb aluminum panel. When the honeycomb aluminum panel deviates, there will be a gap at the contact position between the positioning block and the honeycomb aluminum panel, thereby intuitively judging whether the installation angle of the honeycomb aluminum panel meets the requirements.
[0017] In bad weather (such as stormy weather), the connection between the upper ear plate and the lower ear plate can be prevented from loosening, thereby improving the stability of the honeycomb aluminum plate. After the angle of the honeycomb aluminum plate is adjusted, rotate the positioning screw. At this time, the positioning screw will drive the slider to move horizontally toward the side close to the upper ear plate, and then drive the push rod to push the positioning block toward the direction close to the upper ear plate, so that the No. 2 positioning rod can be inserted into the No. 1 positioning hole, and the inclined surface of the positioning block close to the upper ear plate can contact the upper ear plate, thereby accurately positioning the upper ear plate.
[0018] Preferably, one end of the positioning section close to the No. 1 positioning rod is a spherical surface, and a corresponding spherical groove is opened on the No. 1 positioning rod, and the spherical surface can rotate in the spherical groove.
[0019] The beneficial effects of this solution are as follows: due to the setting of the spherical surface and the spherical groove, the positioning screw can rotate smoothly, which is convenient for positioning the upper ear plate. At the same time, it can reduce the wear of the No. 1 positioning rod and the positioning screw.
[0020] Preferably, S1.1: using 3DMAX software to model, determining the spatial coordinates of the steel frame according to the modeling parameters, and installing the steel frame; S1.2: Erect steel pipe scaffolding; S1.3: Use BIM technology to model the steel frame and pre-assemble it, and number the upper ear plate, lower ear plate and honeycomb aluminum plate at each connection point to ensure that factory prefabrication and on-site construction are carried out simultaneously.
[0021] The beneficial effect of this solution is that this technical solution can accurately determine the spatial coordinates of the steel frame through 3DMAX software modeling, thereby improving the installation accuracy of the steel frame.
[0022] This technical solution uses BIM technology to model the steel frame and pre-assemble it, which can extract the parameters of components such as upper ear plates, lower ear plates and honeycomb aluminum plates, facilitate factory prefabrication and on-site installation, and improve construction efficiency.
[0023] Preferably, the positioning and installation of the purlins in S2 comprises the following steps: S2.1: Positioning and installation of support units; S2.1.1: The support transfer pipe is positioned by using a total station to locate the spatial position and upper top elevation of the support unit, and the No. 1 positioning rod is used as a positioning pile to be fixed on the steel frame, and then the support transfer pipe is positioned by the first positioning unit and the No. 1 positioning rod; S2.1.2: Fix the support adapter to the steel frame; S2.1.3: Adjust the height of the support tube to the top elevation of the No. 1 positioning rod; S2.1.4: Setting of stiffeners on support units; S2.2: Purlin hoisting; S2.3: Purlin positioning; S2.4: Purlin installation.
[0024] The beneficial effects of this solution are as follows: this technical solution can locate the spatial position and upper top elevation of the support unit through a total station, and pre-fix a No. 1 positioning rod on the steel frame to determine the installation position of the support unit, and then cooperate with the first positioning unit through the No. 1 positioning rod to ensure that the support adapter tube is coaxial with the No. 1 positioning rod, thereby improving the installation accuracy of the purlin.
[0025] Preferably, an angle steel is fixedly connected to the upper ear plate, and the honeycomb aluminum plate is fixedly connected to the angle steel.
[0026] Preferably, the inclined surface of the positioning block close to the upper ear plate is a stepped surface, and the inclined surface of the upper ear plate close to the positioning block is also a stepped surface, and the stepped surface on the positioning block is adapted to the stepped surface on the upper ear plate, and a No. 3 positioning rod is fixedly connected to the stepped surface of the positioning block, and a No. 2 positioning hole is provided on the stepped surface of the upper ear plate, and the No. 3 positioning rod can be inserted into the No. 2 positioning hole.
[0027] The beneficial effects of this solution are: by setting a stepped surface on the positioning block and the upper ear plate, on the one hand, the design of the stepped surface makes the contact between the positioning block and the upper ear plate closer and more stable. In severe weather conditions, such as stormy weather, the honeycomb aluminum plate will be subjected to strong wind force. The mutual fit of the stepped surfaces can increase the friction and resistance between the upper ear plate and the positioning block, and effectively resist the pushing and twisting effect of the wind on the upper ear plate. This design makes the entire structure more solid in a strong wind environment, reduces the shaking and displacement caused by wind, and improves the wind resistance of the honeycomb aluminum plate. At the same time, the stepped surface can better withstand forces from different directions, reducing the risk of deformation and damage caused by stress concentration. On the other hand, when the installation angle of the honeycomb aluminum plate does not meet the requirements, there will be a situation where the stepped surface on the positioning block does not match the stepped surface on the upper ear plate. Therefore, it can be used to detect whether the installation angle of the honeycomb aluminum plate meets the requirements.
[0028] Due to the provision of the No. 3 positioning rod and the No. 2 positioning hole, the technical solution can connect the upper ear plate and the positioning block into a whole, thereby further improving the stability of the upper ear plate. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is a structural schematic diagram of the existing honeycomb aluminum panel curtain wall; Figure 2 A partial three-dimensional diagram of the honeycomb aluminum panel curtain wall in Example 1 of the present invention; Figure 3 A three-dimensional diagram of a support unit and a mounting unit in Embodiment 1 of the present invention; Figure 4 A three-dimensional diagram of the lower ear plate in Example 1 of the present invention; Figure 5 A three-dimensional diagram of the upper ear plate in Example 1 of the present invention; Figure 6 A three-dimensional diagram of the cooperation between the positioning mechanism, the mounting unit and the supporting unit in Embodiment 1 of the present invention; Figure 7 This is a schematic diagram of the structure of the positioning bolt in Example 1 of the present invention; Figure 8 This is a schematic diagram of the cooperation between the upper ear plate and the positioning block in Example 2 of the present invention. DETAILED DESCRIPTION
[0030] The following is further described in detail through specific implementation methods: The figure marks in the drawings of the specification include: steel frame 1, purlin 2, connecting pipe 3, honeycomb aluminum plate 4, support adapter tube 5, support tube 6, upper ear plate 7, lower ear plate 8, No. 1 connecting bolt 9, No. 2 connecting bolt 10, No. 1 round hole 11, No. 1 arc hole 12, No. 2 round hole 13, No. 2 arc hole 14, No. 1 positioning rod 15, clamping claw 16, connecting rod 17, connecting seat 18, positioning screw 19, smooth section 20, threaded section 21, limiting section 22, positioning section 23, slider 24, positioning block 25, guide rod 26, push rod 27, strip hole 28, connecting block 29, angle steel 30, reinforcement rib 31.
[0031] Example 1 The structure of the honeycomb aluminum curtain wall is basically as follows Figure 1-7 shown.
[0032] like Figure 2 The honeycomb aluminum panel curtain wall shown in the figure includes a steel frame 1, purlins 2 and a positioning mechanism. There are a number of purlins 2, and three supporting units are arranged between each purlin 2 and the steel frame 1. The purlin 2 is fixed to the steel frame 1 through the supporting units. Connecting pipes 3 are welded between adjacent purlins 2. Three mounting units are arranged on the top of each purlin 2, and honeycomb aluminum panels 4 are mounted on the mounting units. The mounting units can adjust the mounting angle of the honeycomb aluminum panels 4, and the positioning mechanism can position the supporting units and the mounting units. It should be noted that Figure 1 What is shown is only a part of the honeycomb aluminum panel 4 curtain wall, which is intended for the convenience of illustration, rather than a complete display of the entire honeycomb aluminum panel 4 curtain wall. This partial view is only used to assist in understanding the structure, design features or construction details of the honeycomb aluminum panel 4 curtain wall, and cannot represent the overall shape and scale of the entire honeycomb aluminum panel 4 curtain wall.
[0033] like Figure 3As shown, each support unit includes a support adapter tube 5, which is welded to the top of the steel frame 1. The upper end of the support adapter tube 5 is threadedly connected to a support tube 6. Since the support tube 6 and the support adapter tube 5 are threadedly connected, the purlin 2 is welded to the top of the support tube 6 after the support tube 6 is rotated to adjust its height.
[0034] like Figure 3-5 As shown, each mounting unit is composed of two mounting parts, and the two mounting parts are arranged in parallel at the top of the purlin 2. Each mounting part includes an upper ear plate 7, a lower ear plate 8, a No. 1 connecting bolt 9 and a No. 2 connecting bolt 10. The lower ear plate 8 is welded to the top of the purlin 2. The upper side of the lower ear plate 8 is provided with a No. 1 circular hole 11 and a No. 1 arc hole 12, and the No. 1 circular hole 11 and the No. 1 arc hole 12 are arranged concentrically. The lower side of the upper ear plate 7 is provided with a No. 2 circular hole 13 and a No. 2 arc hole 14, and the No. 2 circular hole 13 and the No. 2 arc hole 14 are arranged concentrically. The upper ear plate 7 can Rotating around the No. 1 circular hole 11, the No. 1 connecting bolt 9 passes through the No. 1 circular hole 11 and the No. 2 circular hole 13 to fix the upper ear plate 7 on the lower ear plate 8, and the No. 2 connecting bolt 10 passes through the No. 1 arc hole 12 and the No. 2 arc hole 14 to further fix the upper ear plate 7 and improve the stability of the upper ear plate 7. The honeycomb aluminum plate 4 can be directly installed on the upper ear plate 7, and can also be installed on the upper ear plate 7 through the angle steel 30. In this embodiment, the upper ear plate 7 is connected with the angle steel 30 by bolts, and the honeycomb aluminum plate 4 is installed on the top of the angle steel 30 by bolts.
[0035] like Figure 6 As shown, the positioning mechanism includes a first positioning unit and a second positioning unit, the first positioning unit is used to position the supporting unit, and the second positioning unit is used to position the mounting unit.
[0036] like Figure 6-7As shown, the first positioning unit includes a No. 1 positioning rod 15, which is welded on the steel frame 1. Its height is equal to the installation height of the support unit. Due to the setting of the No. 1 positioning rod 15, the installation position of the support unit can be preliminarily positioned, and at the same time, a reference for the installation height of the support unit is provided. A positioning screw 19 is rotatably connected to the support adapter tube 5. Specifically, the positioning screw 19 includes a smooth section 20, a threaded section 21, a limit section 22 and a positioning section 23 from left to right. These four parts are integrally formed. A connecting seat 18 is rotatably provided on the smooth section 20. The connecting seat 18 can be threadedly connected to the threaded section 21. A slider 24 is threadedly connected to the threaded section 21. The slider 24 and the threaded section 21 form a screw pair. A guide rod 26 is welded to the support adapter tube 5. The slider 24 slides It is arranged on the guide rod 26, and the guide rod 26 does not contact the connecting seat 18. The limiting section 22 rotates and is clamped on the support transfer tube 5. The positioning section 23 is located inside the support transfer tube 5. The right end of the positioning section 23 is a spherical surface. A corresponding spherical groove is opened on the No. 1 positioning rod 15. The spherical surface can contact with the spherical groove and can rotate in the spherical groove. The support transfer tube 5, the positioning screw 19, the guide rod 26, the connecting seat 18 and the slider 24 are integrated No. 1 prefabricated parts prefabricated in advance in the factory. When positioning the support transfer tube 5, first put the support transfer tube 5 on the No. 1 positioning rod 15, adjust the position of the support transfer tube 5 so that the spherical surface of the positioning section 23 contacts with the spherical groove on the No. 1 positioning rod 15, and then the support transfer tube 5 can be positioned. Then, the support transfer tube 5 is welded to the steel frame 1.
[0037] like Figure 6As shown, the second positioning unit includes two positioning blocks 25, which are respectively slidably arranged on the purlins 2 at the front and rear sides of the installation unit, a connecting block 29 is welded between the two positioning blocks 25, a push rod 27 is welded at the bottom of the connecting block 29, and a strip hole 28 for the push rod 27 to move is opened on the purlin 2, the inclined surface of the positioning block 25 close to the upper ear plate 7 can contact the upper ear plate 7, and a No. 2 positioning rod is welded on the inclined surface of the positioning block 25 close to the upper ear plate 7, and a No. 1 positioning hole is opened on the inclined surface of the upper ear plate 7 close to the positioning block 25, and the No. 2 positioning rod can be inserted into the No. 1 positioning hole. The positioning block 25, the connecting block 29, and the push rod 27 are integrated No. 2 prefabricated parts prefabricated in advance in the factory, and the positioning block 25 matches the prefabricated upper ear plate 7. The top of the slider 24 is opened with a No. 2 positioning hole, and the push rod 27 can be inserted into the No. 2 positioning hole to achieve the plug-in connection between the slider 24 and the push rod 27. In bad weather (such as stormy weather), the connection position between the upper ear plate 7 and the lower ear plate 8 can be prevented from loosening, thereby improving the stability of the honeycomb aluminum plate 4. When the angle of the honeycomb aluminum plate 4 is adjusted, the positioning screw 19 is rotated. At this time, the positioning screw 19 will drive the slider 24 to move horizontally toward the side close to the upper ear plate 7, and then drive the push rod 27 to push the positioning block 25 toward the direction close to the upper ear plate 7, so that the second positioning rod can be inserted into the first positioning hole, and the inclined surface of the positioning block 25 close to the upper ear plate 7 can contact the upper ear plate 7, so as to accurately position the upper ear plate 7. Since the purlin 2 is set at an angle, if the positioning block 25 is directly blocked between the upper ear plate 7 and the purlin 2 to limit the upper ear plate 7, there will be a problem that the positioning block 25 slides down along the purlin 2, and the positioning of the upper ear plate 7 cannot be achieved. However, the technical solution can quickly achieve the positioning of the upper ear plate 7 by connecting the second prefabricated part with the first prefabricated part.
[0038] like Figure 6 As shown, a No. 3 prefabricated part is also provided on the steel skeleton 1. The No. 3 prefabricated part includes a clamping jaw 16 and a connecting rod 17. The clamping jaw 16 includes a clamping part and a hand-held part. The clamping part can be clamped on the steel skeleton 1 by a torsion spring. The connecting rod 17 is welded to the rear side of the hand-held part. A connecting hole is opened on the connecting seat 18, and the connecting rod 17 can be inserted into the connecting hole. Since the limiting section 22 rotates and is clamped on the support transfer tube 5, the limiting section 22 and the support transfer tube 5 are fixed by friction. After the positioning block 25 is positioned on the upper ear plate 7, in order to prevent the positioning screw 19 from rotating, after the positioning block 25 is positioned, the connecting seat 18 is rotated so that the connecting seat 18 is threadedly connected with the threaded section 21, and the connecting rod 17 is inserted into the connecting hole to improve the stability of the positioning block 25.
[0039] The construction method of the honeycomb aluminum panel curtain wall comprises the following steps: S1: Installation and construction preparation of steel frame; S1.1: Use 3DMAX software to model, determine the spatial coordinates of the steel frame 1 according to the modeling parameters, and install the steel frame 1; S1.2: Erect steel pipe scaffolding, using Q235 ordinary steel pipe; S1.3: Use BIM technology to model and pre-assemble the steel frame 1, number the upper ear plate 7, lower ear plate 8 and honeycomb aluminum plate 4 at each connection point, and ensure that factory prefabrication and on-site construction are carried out simultaneously; S2: Positioning and installation of purlins; S2.1: Positioning and installation of support units; S2.1.1: Positioning of the support transfer tube: use a total station to locate the spatial position and upper top elevation of the support unit, use the No. 1 positioning rod 15 as a positioning pile welded on the steel frame 1, and then use the first positioning unit and the No. 1 positioning rod 15 to position the support transfer tube 5, ensure that the support transfer tube 5 is coaxial with the No. 1 positioning rod 15, and ensure the accuracy of the installation position of the purlin 2; S2.1.2: Weld the support transfer tube 5 to the steel frame 1. The weld quality level is grade 3. After welding, remove the welding slag and apply two coats of anti-rust paint; S2.1.3: Adjust the height of the support tube 6 to the top elevation of the No. 1 positioning rod 15; S2.1.4: The reinforcement ribs 31 are set on the support unit. The reinforcement ribs 31 are customized parts. S2.1.4.1: The distance between the purlin 2 and the steel frame 1 is within 300 mm, and the reinforcing ribs 31 are only provided at the lower end of the supporting unit; S2.1.4.2: The distance between the purlin 2 and the steel frame 1 is more than 300 mm, and reinforcing ribs 31 are provided at both the upper and lower ends of the support unit; S2.2: Purlin hoisting: Purlin 2 is raw material, which is cut and processed on site according to the actual size of the corresponding parts. Purlin 2 is hoisted to each working surface by hoisting equipment. During hoisting, each working surface is equipped with a directing worker, and only one purlin 2 is hoisted at a time; S2.3: Positioning of purlins: First, hang the purlins 2 on the support tubes 6 without fixing them, so that they are in a free state where they can be adjusted on all sides. Then, use a total station to measure and locate the lower lugs 8 on the same side of the upper and lower ends of the purlins 2. Adjust the spatial position of the purlins 2 according to the measured positions of the lower lugs 8. S2.4: Purlin installation: After measuring and positioning, weld the purlin 2 to the support tube 6. The welds at all welding points should be uniform to ensure quality. The weld quality grade is level three. After welding, remove the welding slag and apply two coats of anti-rust paint. S3: Installation and angle correction of honeycomb aluminum panels; S3.1: Positioning and installation of lower ear plates: After the positioning welding of purlin 2 is completed, use the total station to input the modeling coordinate points, measure the position of the lower ear plate 8 on purlin 2 through a small prism, and spot weld the lower ear plate 8 on purlin 2 after the measurement is completed; use the same method to measure and position the remaining lower ear plates 8 and weld them. After the ear plates in this area are spot welded, they are all fully welded. The welds at all welding points should be uniform to ensure quality. The weld quality level is level three. After welding, remove the welding slag and apply two coats of anti-rust paint; S3.2: Fluorocarbon paint spraying: The lower ear plate 8 is made of Q345 steel plate and deburred, and after welding with the purlin 2, it is fluorocarbon sprayed together with the purlin 2; the angle steel 30 is made of Q345 steel plate, and is fluorocarbon sprayed after hot-dip galvanizing; the upper ear plate 7 is made of Q345 steel plate and deburred, and is fluorocarbon sprayed after hot-dip galvanizing.
[0040] S3.3: Angle steel model drawing and processing: Because the size and adjustment angle of each honeycomb aluminum plate 4 are different, the matching angle steel 30 also needs to be adjusted with the width and slope of the honeycomb aluminum plate 4, so the angle steel 30 needs to be further designed and laid out; the thickness of the angle steel 30 is 4mm, and the cutting shape depends on the honeycomb aluminum plate 4. The AutoCAD software is used to draw the angle steel 30 model of each honeycomb aluminum plate 4, and then the factory processes it according to the model, laser engraves the number and sprays anti-rust paint; S3.4: Installation of honeycomb aluminum panel: pass No. 1 connecting bolt 9 through No. 1 circular hole 11 and No. 2 circular hole 13, but do not tighten No. 1 connecting bolt 9 to ensure that the upper ear plate 7 can rotate, so as to facilitate the angle adjustment after installing the honeycomb aluminum panel 4. Install the angle steel 30 on the upper ear plate 7 with bolts, and hoist the honeycomb aluminum panel 4 to the corresponding working surface through the lifting equipment. The honeycomb aluminum panel 4 is connected to the angle steel 30 with T-bolts, and the plane angle of the honeycomb aluminum panel 4 is adjusted to be on the same plane as the aluminum panel on the same plane. After the position is adjusted, tighten the T-bolt. When the angle steel 30 is connected to the honeycomb aluminum panel 4, insert an asbestos gasket to avoid bimetallic contact corrosion.
[0041] S3.5: Angle correction of honeycomb aluminum plate: The angle between the honeycomb aluminum plate 4 and the purlin 2 is determined according to the modeling parameters. The angle of the honeycomb aluminum plate 4 can be freely adjusted up and down by the No. 1 connecting bolt 9. After the angle is adjusted, the No. 1 connecting bolt 9 is locked. At the same time, the upper ear plate 7 and the lower ear plate 8 are fixed again by the No. 2 connecting bolt 10.
[0042] S3.6: Positioning of the installation unit: After the angle of the honeycomb aluminum plate 4 is adjusted, the upper ear plate 7 is positioned by the second positioning unit. After the positioning is completed, the clamping claw 16 is welded to the steel frame 1.
[0043] S4: Cleaning and finished product protection: After each honeycomb aluminum panel 4 is installed, clean the surroundings to remove dust, glass glue, etc. After the inspection and acceptance, send a special person to protect the finished product to prevent dust and other pollution and human damage until it is completed and put into use.
[0044] Example 2 On the basis of Example 1, Figure 8 As shown, the inclined surface of the positioning block 25 close to the upper ear plate 7 is a stepped surface, and the inclined surface of the upper ear plate 7 close to the positioning block 25 is also a stepped surface, and the stepped surface on the positioning block 25 is adapted to the stepped surface on the upper ear plate 7, and a No. 3 positioning rod is integrally formed on the stepped surface of the positioning block 25, and a No. 2 positioning hole is opened on the stepped surface of the upper ear plate 7, and the No. 3 positioning rod can be inserted into the No. 2 positioning hole. By setting the stepped surface on the positioning block 25 and the upper ear plate 7, on the one hand, the design of the stepped surface makes the contact between the positioning block 25 and the upper ear plate 7 more compact and stable, and under severe weather conditions, such as stormy weather, the honeycomb aluminum plate 4 will be subjected to strong wind force. The mutual fit of the stepped surfaces can increase the friction and resistance between the upper ear plate 7 and the positioning block 25, effectively resisting the pushing and twisting effect of the wind on the upper ear plate 7. This design makes the entire structure more solid in a strong wind environment, reduces the shaking and displacement caused by the wind, and improves the wind resistance of the honeycomb aluminum plate 4. At the same time, the stepped surface can better withstand forces from different directions, reducing the risk of deformation and damage caused by stress concentration. On the other hand, when the installation angle of the honeycomb aluminum plate 4 does not meet the requirements, there will be a situation where the stepped surface on the positioning block 25 does not match the stepped surface on the upper ear plate 7. Therefore, it can be used to detect whether the installation angle of the honeycomb aluminum plate 4 meets the requirements.
[0045] The above is only an embodiment of the present invention, and the common knowledge such as the known specific technical solutions and / or characteristics in the solution is not described in detail here. It should be pointed out that for those skilled in the art, without departing from the technical solution of the present invention, several modifications and improvements can be made, which should also be regarded as the protection scope of the present invention, and these will not affect the effect of the implementation of the present invention and the practicality of the patent. The scope of protection required by this application shall be based on the content of its claims, and the specific implementation methods and other records in the specification can be used to interpret the content of the claims.
Claims
1. The construction method of honeycomb aluminum panel curtain wall is characterized by: The following steps are involved: S1: Installation of steel frame and construction preparation; S2: Positioning and installation of purlins: A support unit is provided between the steel frame and the purlins, through which the purlins can be fixed on the steel frame, and the height of the support unit can be adjusted; a positioning mechanism is provided on the steel frame, which can position the support unit; S3: Installation and angle correction of honeycomb aluminum panels: Several installation units are arranged on the purlins, and the positioning mechanism can also position the installation units. Each installation unit is composed of two installation parts, and each installation part includes an upper ear plate, a lower ear plate and a No. 1 connecting bolt. The lower ear plate is fixedly connected to the top of the purlin, and the upper ear plate is connected to the lower ear plate by a No. 1 connecting bolt. The honeycomb aluminum panel is fixedly connected to the top of the upper ear plate. The angle of the honeycomb aluminum panel is adjusted. After the angle adjustment is completed, the upper ear plate is positioned by the positioning mechanism.
2. The method for constructing a honeycomb aluminum panel curtain wall according to claim 1, characterized in that: The support unit comprises a support adapter tube, which is fixedly connected to the top of the steel frame, the upper end of which is threadedly connected to a support tube, and the purlin is fixedly connected to the top of the support tube.
3. The method for constructing a honeycomb aluminum panel curtain wall according to claim 2, characterized in that: The positioning mechanism comprises a first positioning unit and a second positioning unit, the first positioning unit is used to position the supporting unit, and the second positioning unit is used to position the mounting unit.
4. The method for constructing a honeycomb aluminum panel curtain wall according to claim 3, characterized in that: The first positioning unit includes a No. 1 positioning rod, which is fixed on the steel frame and has a height equal to the installation height of the support unit. A positioning screw is rotatably connected to the support adapter tube. The positioning screw includes a smooth section, a threaded section, a limit section and a positioning section that are connected in sequence. The limit section rotates and is clamped on the support adapter tube. The positioning section is located inside the support adapter tube. The positioning section is used to position the support adapter tube.
5. The method for constructing a honeycomb aluminum panel curtain wall according to claim 4, characterized in that: The second positioning unit includes a slider, which is threadedly connected to the threaded segment to form a screw pair, a guide rod is fixedly connected to the support adapter tube, the slider is slidably set on the guide rod, the top of the slider is detachably connected to a push rod, a positioning block is slidably set on the purlin, a No. 2 positioning rod is fixedly connected to the inclined surface of the positioning block close to the upper ear plate, a No. 1 positioning hole is provided on the inclined surface of the upper ear plate close to the positioning block, the No. 2 positioning rod can be inserted into the No. 1 positioning hole, and the push rod can push the positioning block to move to position the upper ear plate.
6. The method for constructing a honeycomb aluminum panel curtain wall according to claim 5, characterized in that: One end of the positioning section close to the No. 1 positioning rod is a spherical surface, and the No. 1 positioning rod is provided with a corresponding spherical groove, and the spherical surface can rotate in the spherical groove.
7. The method for constructing a honeycomb aluminum panel curtain wall according to claim 6, characterized in that: The installation and construction preparation of the steel frame in S1 includes the following steps: S1.1: Use 3DMAX software to model, determine the spatial coordinates of the steel frame according to the modeling parameters, and install the steel frame; S1.2: Erect steel pipe scaffolding; S1.3: Use BIM technology to model the steel frame and pre-assemble it, and number the upper ear plate, lower ear plate and honeycomb aluminum plate at each connection point to ensure that factory prefabrication and on-site construction are carried out simultaneously.
8. The method for constructing a honeycomb aluminum panel curtain wall according to claim 7, characterized in that: The positioning and installation of the purlins in S2 includes the following steps: S2.1: Positioning and installation of support units; S2.1.1: The support transfer pipe is positioned by using a total station to locate the spatial position and upper top elevation of the support unit, and the No. 1 positioning rod is used as a positioning pile to be fixed on the steel frame, and then the support transfer pipe is positioned by the first positioning unit and the No. 1 positioning rod; S2.1.2: Fix the support adapter to the steel frame; S2.1.3: Adjust the height of the support tube to the top elevation of the No. 1 positioning rod; S2.1.4: Setting of stiffeners on support units; S2.2: Purlin hoisting; S2.3: Purlin positioning; S2.4: Purlin installation.
9. The method for constructing a honeycomb aluminum panel curtain wall according to claim 8, characterized in that: An angle steel is fixedly connected to the upper ear plate, and the honeycomb aluminum plate is fixedly connected to the angle steel.
10. The method for constructing a honeycomb aluminum panel curtain wall according to claim 9, characterized in that: The inclined surface of the positioning block close to the upper ear plate is a stepped surface, and the inclined surface of the upper ear plate close to the positioning block is also a stepped surface, and the stepped surface on the positioning block is adapted to the stepped surface on the upper ear plate. A No. 3 positioning rod is fixedly connected to the stepped surface of the positioning block, and a No. 2 positioning hole is provided on the stepped surface of the upper ear plate, and the No. 3 positioning rod can be inserted into the No. 2 positioning hole.
Citation Information
Patent Citations
Curtain wall keel welding positioning device
CN117984034A
Processing device for stone curtain wall plate installation groove
CN204019760U
Rapid positioning device for steel structure daylighting roof purline
CN219411907U
Multi-directional adjustable purlin hanger device for metal roof
CN219671652U
Curtain wall with adjustable installation angle of curtain wall plate
CN220266938U