Method, device and equipment for determining maintenance time window of wind generating set
By predicting wind speed and determining the time window for minimum loss of power generation, the problem of power generation loss during wind turbine maintenance is solved, achieving more efficient maintenance and reducing losses.
Patent Information
- Application Number
- CN202310302806.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-03-22
- Publication Date
- 2024-10-01
AI Technical Summary
Maintenance of wind turbines takes several hours, resulting in a loss of power generation, and it is difficult to effectively reduce this loss with existing technology.
By obtaining wind speed data, the prediction model is used to predict future wind speed, and based on the preset conversion relationship between unit function start-stop wind speed and wind speed power generation, the time window for minimum loss of power generation is determined for maintenance.
It effectively reduces the power generation loss caused by wind turbine maintenance and improves maintenance efficiency and accuracy.
Smart Images

Figure CN118735487A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of wind power generation, and in particular to a method, device and equipment for determining a maintenance time window of a wind power generator set. Background Art
[0002] A wind turbine is a large rotating machine that can convert wind energy into electrical energy. It consists of multiple parts. In order to ensure the reliability and safety of the wind turbine operation, the wind turbine needs to be maintained. The maintenance of a wind turbine often takes one to several hours. During the maintenance of the wind turbine, the wind turbine needs to be shut down and cannot generate electricity, resulting in a large loss of power generation. Summary of the invention
[0003] The embodiments of the present application provide a method, device and equipment for determining a maintenance time window of a wind turbine generator set, which can reduce power generation losses caused by maintenance of the wind turbine generator set.
[0004] In a first aspect, an embodiment of the present application provides a method for determining a maintenance time window of a wind turbine generator set, comprising: obtaining wind speed data of a machine site where a wind turbine generator set is located within a first time period; using the wind speed data and a wind speed prediction model obtained through previous training to obtain a predicted wind speed at the machine site where the wind turbine generator set is located within a second time period output by the wind speed prediction model based on the wind speed data, the second time period being located after the first time period; determining the predicted loss power generation within each predetermined time period according to the predicted wind speed within the predetermined time period obtained by dividing the second time period, the preset start and stop wind speed of the unit function, and the wind speed-to-power conversion relationship, the unit function start and stop wind speed representing the start wind speed and shutdown wind speed of the wind turbine generator set function, and the wind speed-to-power conversion relationship including a wind speed power trajectory; determining the maintenance time window based on one or more consecutive predetermined time periods with the smallest sum of the predicted loss power generation in the second time period.
[0005] In a second aspect, an embodiment of the present application provides a maintenance time window determination device for a wind turbine generator set, comprising: a wind speed acquisition module, used to acquire wind speed data of a machine position where a wind turbine generator set is located within a first time period; a wind speed prediction module, used to use the wind speed data and a wind speed prediction model obtained through previous training to obtain a predicted wind speed at the machine position where the wind turbine generator set is located within a second time period output based on the wind speed prediction model based on the wind speed data, wherein the second time period is located after the first time period; a power generation loss prediction module, used to determine the predicted loss power generation within each predetermined time period according to the predicted wind speed within the predetermined time period obtained by dividing the second time period, the preset start-stop wind speed of the unit function, and the wind speed-to-power conversion relationship, wherein the start-stop wind speed of the unit function represents the start-up wind speed and the shutdown wind speed of the wind turbine generator set function, and the wind speed-to-power conversion relationship includes a wind speed power trajectory; a maintenance time window determination module, used to determine the maintenance time window based on one or more consecutive predetermined time periods with the smallest sum of the predicted loss power generation in the second time period.
[0006] In a third aspect, an embodiment of the present application provides an electronic device, comprising: a processor and a memory storing computer program instructions; when the processor executes the computer program instructions, the method for determining the maintenance time window of a wind turbine generator set of the first aspect is implemented.
[0007] In a fourth aspect, an embodiment of the present application provides a computer-readable storage medium having computer program instructions stored thereon, and when the computer program instructions are executed by a processor, the method for determining a maintenance time window of a wind turbine generator set according to the first aspect is implemented.
[0008] The embodiment of the present application provides a method, device and equipment for determining the maintenance time window of a wind turbine generator set, which can use the wind speed prediction model obtained by previous training, based on the wind speed data of the position where the wind turbine generator set is located in the previous first time period, to predict the predicted wind speed of the position where the wind turbine generator set is located in the subsequent second time period. The second time period is divided into multiple predetermined time periods, and the predicted loss of power generation in each predetermined time period can be predicted based on the predicted wind speed in the predetermined time period, the preset start-stop wind speed of the unit function, and the wind speed-to-power conversion relationship including the wind speed-to-power trajectory. The maintenance time window in the subsequent second time period is determined based on one or more consecutive predetermined time periods with the smallest sum of the predicted loss of power generation in the second time period. The corresponding predicted loss of power generation in the determined maintenance time window is the smallest, and maintaining the wind turbine generator set in the determined maintenance time window can effectively reduce the power generation loss caused by the maintenance of the wind turbine generator set. BRIEF DESCRIPTION OF THE DRAWINGS
[0009] In order to more clearly illustrate the technical solution of the embodiments of the present application, the following is a brief introduction to the drawings required for use in the embodiments of the present application. For ordinary technicians in this field, other drawings can be obtained based on these drawings without any creative work.
[0010] Figure 1 A flow chart of a method for determining a maintenance time window for a wind turbine generator set provided in an embodiment of the present application;
[0011] Figure 2 A schematic diagram of a relationship curve of an example of predicting wind speed, electricity price and time in an embodiment of the present application;
[0012] Figure 3 A schematic diagram of an exemplary relationship curve between power, lost income and time of a wind turbine generator set in an embodiment of the present application;
[0013] Figure 4 A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in another embodiment of the present application;
[0014] Figure 5 A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in yet another embodiment of the present application;
[0015] Figure 6 A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in yet another embodiment of the present application;
[0016] Figure 7 A schematic diagram of the structure of a device for determining a maintenance time window for a wind turbine generator set provided in an embodiment of the present application;
[0017] Figure 8 A schematic diagram of the structure of an electronic device provided in one embodiment of the present application. DETAILED DESCRIPTION
[0018] The features and exemplary embodiments of various aspects of the present application will be described in detail below. In order to make the purpose, technical solutions and advantages of the present application clearer, the present application will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are only intended to explain the present application, rather than to limit the present application. For those skilled in the art, the present application can be implemented without the need for some of these specific details. The following description of the embodiments is only to provide a better understanding of the present application by illustrating the examples of the present application.
[0019] A wind turbine is a large rotating machine that can convert wind energy into electrical energy. It is composed of multiple components. For example, a wind turbine can be composed of a foundation ring, a tower, a nacelle, a hub, a generator, a mechanical transmission part, an impeller and other components. In order to ensure the reliability and safety of the operation of the wind turbine, the wind turbine needs to be maintained. The maintenance of the wind turbine often takes one to more hours. During the maintenance of the wind turbine, the wind turbine needs to be shut down and cannot generate electricity, resulting in a large loss of power generation. For example, taking a wind turbine with a rated power of 4000 kilowatts (kW) as an example, if one hour of maintenance is performed when the rated wind speed of the wind turbine is reached, the power generation will be lost by 4000 kilowatt-hours (kWh). The wind farm includes multiple wind turbines, and the accumulated loss of power generation of multiple wind turbines is a very huge loss.
[0020] The present application provides a method, device and equipment for determining a maintenance time window for a wind turbine generator set, which can predict the wind speed at the location of the wind turbine generator set in a future time period based on the wind speed data at the location of the wind turbine generator set in an existing time period, and predict the lost power generation in each predetermined time period in the future time period based on the predicted wind speed, the conversion relationship between wind speed and power generation, etc., so as to determine the time window that can minimize the lost power generation for maintenance of the wind turbine generator set, thereby minimizing the power generation loss caused by the maintenance of the wind turbine generator set.
[0021] A first aspect of the present application provides a method for determining a maintenance time window for a wind turbine generator set, which can be applied to a single wind turbine generator set or to multiple wind turbine generator sets in a wind farm. The method for determining a maintenance time window for a wind turbine generator set can be executed by a maintenance time window determination device, electronic equipment, etc. of the wind turbine generator set, and is not limited here. Figure 1 A flow chart of a method for determining a maintenance time window for a wind turbine generator set provided in an embodiment of the present application, such as Figure 1 As shown, the method for determining the maintenance time window of a wind turbine generator set may include steps S101 to S104.
[0022] In step S101, wind speed data of a wind turbine generator set at a location within a first time period is obtained.
[0023] The first time period is a historical time period. In some examples, the first time period may include a time period before the current moment, or the first time period may include a time period starting at a certain moment before the current moment and ending at the current moment. The duration of the first time period may be set according to the scenario, demand, experience, etc., and is not limited here. In order to improve the accuracy of the wind speed forecast in the subsequent steps, a shorter first time period may be set, and the first time period may be on the order of days. For example, the duration of the first time period may be 3 days.
[0024] The wind speed data obtained here can characterize the wind speed at the position where the wind turbine generator set is located. In some examples, the wind turbine generator set can be equipped with a wind speed collection device for collecting wind speed data. For example, the wind speed collection device may include a nacelle anemometer, and the wind speed data at the position where the wind turbine generator set is located can be obtained through the nacelle anemometer. For each wind turbine generator set, multiple wind speed data can be obtained in the first time period. Specifically, a wind speed data collection cycle can be set. The duration of the wind speed data collection cycle is less than the duration of the first time period. The duration of the wind speed data collection cycle can be determined according to the accuracy requirements for the wind speed data, the collection capacity of the wind speed collection device, other requirements, etc. In some examples, the wind speed data collection cycle can be in the order of milliseconds. For example, the wind speed data collection cycle can be 20 milliseconds. In some examples, in order to facilitate calculation, the collected wind speed data can be processed in subsequent steps. Please see the following description for details.
[0025] In some examples, status data of the wind turbine generator set may also be obtained, and the status data may represent the status of the wind turbine generator set. The status data of the wind turbine generator set may include one or more of the following: initialization status data, standby status data, fault shutdown status data, startup status data, maintenance shutdown status data, normal operation status data, etc.
[0026] In step S102, the wind speed data and the previously trained wind speed prediction model are used to obtain the predicted wind speed at the location of the wind turbine generator set within the second time period output by the wind speed prediction model based on the wind speed data.
[0027] The second time period is located after the first time period and may be a time period in the future. In some examples, the second time period may include a time period located after the current moment, for example, the second time period may include a time period starting at the current moment and ending at a moment after the current moment.
[0028] The wind speed prediction model can be trained in advance and used to predict the wind speed at the location of the wind turbine generator set in the future based on the wind speed data at the location of the wind turbine generator set in a historical period of time. The wind speed prediction model outputs the predicted wind speed at the location of the wind turbine generator set in the future as the predicted wind speed. The input data of the wind speed prediction model can be arranged in chronological order. For example, the input data of the wind speed prediction model can be expressed as a time series v = [v(t0), v(t1), v(t2), …, v(t n )], where v(t i ) is the i+1th input data. The granularity of the predicted wind speed output by the wind speed prediction model is consistent with the granularity of the input data of the wind speed prediction model. The granularity of the data is the coarseness of the data, which can be reflected as the time series interval period of the data. For example, the time series interval period of the input data of the wind speed prediction model is 60 seconds. Correspondingly, the time series interval period of the predicted wind speed output by the wind speed prediction model is also 60 seconds. The time series interval period is the interval length between two adjacent data arranged in chronological order. The amount of data of the predicted wind speed output by the wind speed prediction model is less than or equal to the amount of data of the input data of the wind speed prediction model. For example, if 100 input data are input into the wind speed prediction model, the wind speed prediction model can output less than or equal to 100 predicted wind speeds. The wind speed prediction model can use a wind speed prediction algorithm based on a time series to predict the wind speed. The type of wind speed prediction algorithm based on a time series is not limited herein. For example, the wind speed prediction algorithm based on a time series may include one or more of an exponential smoothing method (i.e., an exponential smoothing algorithm), a Holt-Winters algorithm, an autoregression algorithm (i.e., an auto-regression algorithm), a moving average algorithm (i.e., a moving average algorithm), an autoregressive moving average model (ARMA), etc.
[0029] In some examples, the acquired wind speed data within the first time period may be arranged in chronological order and directly input into the wind speed prediction model as input data, and the wind speed prediction model outputs the corresponding predicted wind speed based on the input data. In other examples, the acquired wind speed data within the first time period may be filtered, and the processed wind speed data may be arranged in chronological order and input into the wind speed prediction model as input data, and the wind speed prediction model outputs the corresponding predicted wind speed based on the input data.
[0030] In step S103, the predicted lost power generation in each predetermined time period is determined according to the predicted wind speed in the predetermined time period obtained by dividing the second time period, the preset wind speed for starting and stopping the unit function, and the wind speed power generation conversion relationship.
[0031] The second time period can be divided into a plurality of predetermined time periods, and correspondingly, the predicted wind speed in the second time period can be divided into predicted wind speeds in a plurality of predetermined time periods. The predetermined time period can be set according to the scene, demand, experience, etc., and is not limited here. For example, if the second time period is 3 days, i.e. 72 hours, the predetermined time period can be set to 4 hours, and the timing interval period is 60 seconds, then the second time period includes 18 predetermined time periods, and each predetermined time period corresponds to 240 predicted wind speeds.
[0032] The start-stop wind speed of the unit function can represent the start wind speed and the shut-down wind speed of the wind turbine generator set function. The start wind speed of the wind turbine generator set function is the basic wind speed for starting the normal operation function of the wind turbine generator set. The start wind speed of the wind turbine generator set function can be specifically set to the cut-in wind speed of the wind turbine generator set. When the wind speed is less than or equal to the start wind speed of the wind turbine generator set function, the wind turbine generator set does not operate to generate electricity; when the wind speed is greater than the start wind speed of the wind turbine generator set function, the wind turbine generator set operates and generates electricity. The shut-down wind speed of the wind turbine generator set function is the basic wind speed for shutting down the normal operation function of the wind turbine generator set. The shut-down wind speed of the wind turbine generator set function can be set to the maximum wind speed allowed for operation and maintenance of the wind turbine generator set. When the wind speed is greater than or equal to the shut-down wind speed of the wind turbine generator set function, the wind turbine generator set will not be maintained to ensure the safety of the maintenance personnel.
[0033] The wind speed-to-power conversion relationship may include the corresponding relationship between wind speed and power generation. By knowing the wind speed and wind speed-to-power conversion relationship, the power generation corresponding to the wind speed can be determined. The wind speed-to-power conversion relationship may include a wind speed-to-power trajectory. The wind speed-to-power trajectory may characterize the corresponding relationship between wind speed and the power of a wind turbine generator set. By knowing the wind speed and wind speed-to-power trajectory, the power of a wind turbine generator set corresponding to the wind speed can be determined. Based on the power of the wind turbine generator set, the power generation of the wind turbine generator set can be obtained. The wind speed-to-power trajectory may include a wind speed-to-power curve, a wind speed-to-power hash point, a wind speed-to-power fitting line, etc. The specific form of the wind speed-to-power trajectory is not limited here.
[0034] Based on the predicted wind speed in each scheduled time period and the start-stop wind speed of the unit function, the state of the wind turbine generator set in the scheduled time period can be predicted, that is, whether the wind turbine generator set can generate electricity in the scheduled time period and whether maintenance can be performed in the scheduled time period can be predicted. Combined with the wind speed power generation conversion relationship, the power generation of the wind turbine generator set in the scheduled time period can be predicted. The predicted power generation of the wind turbine generator set in the scheduled time period is the loss of power generation that will be generated by maintenance in the scheduled time period, that is, the predicted loss of power generation.
[0035] The predicted lost power generation can be realized as the predicted lost power generation energy, or as the income corresponding to the predicted lost power generation energy. If the predicted lost power generation can be realized as the income corresponding to the predicted lost power generation energy, the above-mentioned wind speed power generation conversion relationship can also include a power price cycle variable, which can ensure that the power price changes over time, and can include the corresponding relationship between the power price and time, so that the predicted lost power generation can be represented by the price corresponding to the predicted lost power generation energy.
[0036] For example, Figure 2 This is a diagram showing an example of a relationship curve between wind speed, electricity price and time predicted in an embodiment of the present application. Figure 3 The following is a graph showing the relationship between the power, lost income and time of a wind turbine generator set according to an embodiment of the present application. The lost income is the income corresponding to the lost power generated by the wind turbine generator set. Figure 2 and Figure 3 As shown, the horizontal axis is time, and the unit is minute (i.e. min). Figure 2 The vertical axis is the predicted wind speed and electricity price. The unit of the predicted wind speed is meter per second (m / s), and the unit of the electricity price is megawatt-hour (MWh). Figure 3 The vertical axis is the predicted power and lost income of the wind turbine generator set. The unit of power is kilowatt (kW) and the unit of lost income is yuan. Curve 1 shows the corresponding relationship between the predicted wind speed and time, curve 2 shows the corresponding relationship between the electricity price and time, curve 3 shows the corresponding relationship between the power corresponding to the predicted wind speed and time, and curve 4 shows the corresponding relationship between the predicted lost power generation and time. Figure 2 and Figure 3 On the basis of the fluctuations in the predicted wind speed and electricity price, the predicted power of the wind turbine and the predicted loss of power generation and time can be obtained according to the relationship between the predicted wind speed, electricity price and time, so as to obtain the predicted loss of power generation in each predetermined time period. The lost power generation can be calculated based on the electricity price.
[0037] In step S104, a maintenance time window is determined based on one or more than two consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest.
[0038] The maintenance time window is a time window for maintaining a wind turbine. The duration of the maintenance time window is greater than or equal to a predetermined time period. For example, the maintenance time window includes one or more consecutive predetermined time periods. The duration of the maintenance time window can be set according to scenarios, requirements, experience, etc., and is not limited here.
[0039] In some examples, the duration of the predetermined time period is consistent with the duration of the maintenance time window, and a predetermined time period in the second time period with the smallest predicted power generation loss can be determined as the maintenance time window. The wind turbine generator set is maintained within the maintenance time window, which can minimize the power generation loss caused by the maintenance of the wind turbine generator set. For example, the selection of the maintenance time window can be obtained according to the following formula (1):
[0040] J(ΔT i )=min([J(ΔT1),J(ΔT2),……,J(ΔT n )]) (1)
[0041] Among them, J(ΔT i ) is the maintenance time window; min is the calculation of the minimum value; J(ΔT1) is the first scheduled time period; J(ΔT2) is the second scheduled time period; J(ΔT n ) is the nth scheduled time period.
[0042] For example, assuming that the duration of the scheduled time period is 2 hours and the duration of the second time period is 1 day, Table 1 shows the predicted power loss corresponding to the twelve scheduled time periods within 1 day:
[0043] Table 1
[0044]
[0045]
[0046] The predicted power loss in Table 1 is calculated based on the electricity price, and the unit can be "yuan". It can be seen from Table 1 that the predicted power loss corresponding to the scheduled time period 12:00-14:00 is the smallest. Therefore, the scheduled time period 12:00-14:00 can be determined as the maintenance time window, and the wind turbine generator set can be maintained during the maintenance time window 12:00-14:00.
[0047] In some examples, the duration of the predetermined time period is less than the duration of the maintenance time window, and the predicted loss of power generation in the second time period and the minimum N consecutive predetermined time periods can be determined as the maintenance time window, where N is an integer greater than 1. In some examples, N can be determined based on the duration of the maintenance time window and the duration of the predetermined time period. Performing maintenance on the wind turbine generator set within the maintenance time window can minimize the power generation loss caused by the maintenance of the wind turbine generator set.
[0048] In an embodiment of the present application, the wind speed prediction model obtained by previous training can be used to predict the predicted wind speed at the position of the wind turbine generator set in the second time period in the future, based on the wind speed data at the position of the wind turbine generator set in the first time period in the past. The second time period is divided into a plurality of predetermined time periods, and the predicted loss of power generation in each predetermined time period can be predicted based on the predicted wind speed in the predetermined time period, the preset start-stop wind speed of the unit function, and the wind speed-to-power conversion relationship including the wind speed-to-power trajectory. Based on one or more consecutive predetermined time periods with the smallest sum of the predicted loss of power generation in the second time period, the maintenance time window in the second time period in the future is determined. The predicted loss of power generation corresponding to the determined maintenance time window is the smallest, and maintaining the wind turbine generator set in the determined maintenance time window can effectively reduce the power generation loss caused by the maintenance of the wind turbine generator set. The staff can also formulate reasonable operation and maintenance strategies based on the maintenance time window, so as to improve the maintenance efficiency of the wind turbine generator set.
[0049] Moreover, the predicted wind speed at the location of the wind turbine generator set is predicted in the embodiment of the present application, and its granularity is finer. The accuracy of the predicted lost power generation within a predetermined time period determined based on the predicted wind speed at the location of the wind turbine generator set is higher, and the effect of reducing the power generation loss of the selected maintenance time window is also better.
[0050] In some examples, the above step S104 can be specifically refined as follows: in the second time period, one or more consecutive predetermined time periods with the smallest sum of predicted lost power generation can be selected as the maintenance time window. That is, one or more consecutive predetermined time periods with the smallest sum of predicted lost power generation in the second time period are directly used as the maintenance time window.
[0051] In other examples, the above step S104 can be specifically refined as follows: in the second time period, one or more consecutive predetermined time periods with the smallest sum of predicted lost power generation can be selected as the time window to be verified, and when the sum of predicted lost power generation corresponding to the time window to be verified is less than or equal to the preset lost power generation threshold, the time window to be verified is determined as the maintenance time window. One or more consecutive predetermined time periods with the smallest sum of predicted lost power generation in the second time period can be selected as the time window to be verified, and the time window to be verified needs to be further verified to determine whether it can be used as a maintenance time window. The preset lost power generation threshold is the maximum acceptable value of lost power generation caused by maintenance of the wind turbine generator set, which can be set according to the scenario, demand, experience, etc., and is not limited here. The sum of the predicted loss of power generation corresponding to the time window to be verified is less than or equal to the preset loss of power generation threshold, indicating that the predicted loss of power generation is within an acceptable range, the wind turbine can be maintained, and the time window to be verified can be used as a maintenance time window; the sum of the predicted loss of power generation corresponding to the time window to be verified is greater than the preset loss of power generation threshold, indicating that the predicted loss of power generation is not within an acceptable range, maintenance of the wind turbine is not allowed, and the time window to be verified cannot be used as a maintenance time window, that is, there is no maintenance time window under the current circumstances.
[0052] In some embodiments, each predetermined time period may include multiple prediction time points, and the wind speed data can be filtered through a filtering processing window. The processed data is used as input data of the wind speed prediction model to calculate the predicted loss power generation component of each prediction time point, and then the predicted loss power generation amount in each predetermined time period is obtained through the predicted loss power generation component at the prediction time point. Figure 4 A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in another embodiment of the present application, Figure 4 and Figure 1 The difference is that Figure 1 Step S102 in the above example can be specifically broken down into the following steps: Figure 4 Steps S1021 to S1023 in Figure 1 Step S103 in the above example can be specifically broken down into Figure 4 Step S1031 and step S1032 in .
[0053] In step S1021, a filtering processing window is obtained.
[0054] The duration of the filtering processing window is the same as the time interval between two adjacent prediction time points. The time interval between two prediction time points is the time interval period in the above embodiment, which can be set according to the scene, demand, experience, etc., and is not limited here. The time interval between two prediction time points is greater than the duration of the wind speed data collection cycle and less than the duration of the predetermined time period. For example, the time interval between two prediction time points is 60 seconds, the wind speed data collection cycle is 20 milliseconds, and the predetermined time period is 4 hours.
[0055] In step S1022, the filtering processing window is gradually slid in the wind speed data in chronological order to obtain the average value of the wind speed data in each filtering processing window.
[0056] The sliding step size of the filter processing window can be set according to the scene, demand, experience, etc., and is not limited here. In some examples, the sliding step size may be less than or equal to the length of the filter processing window. The wind speed data can be arranged in chronological order according to the time of collection of the wind speed data, and the starting end of the sliding filter window is aligned with the first wind speed data, and the average value of all wind speed data in the sliding filter window at this time is calculated; the sliding filter window is slided according to the sliding step size, and the average value of all wind speed data in the sliding filter window after sliding is calculated; the sliding filter window is slided again according to the sliding step size, and the average value of all wind speed data in the sliding filter window after sliding is calculated, and so on, until the end of the sliding filter window is aligned with the last wind speed data.
[0057] In step S1023, the predicted wind speed output by the wind speed prediction model is obtained by using the average value of the wind speed data in each filtering processing window and the wind speed prediction model.
[0058] The average value of the wind speed data in each filtering processing window can be used as the input data of the wind speed prediction model, so as to obtain the predicted wind speed output by the wind speed prediction model. The average value of the wind speed data in each filtering processing window can also be used as an element to be arranged in chronological order, and divided according to a predetermined period, and the average value of the elements in each predetermined period is calculated, and the average value of the elements is used as the input data of the wind speed prediction model, so as to obtain the predicted wind speed output by the wind speed prediction model. The duration of the predetermined period can be equal to the duration of the filtering processing window. The input data of the wind speed prediction model can also be obtained by using an autoregressive sliding average algorithm based on the average value of the wind speed data in the filtering processing window.
[0059] The granularity of the input data and the granularity of the output data of the wind speed prediction model may be the length of the filter processing window, that is, the wind speed prediction model outputs the predicted wind speed corresponding to the prediction time point, and each prediction time point corresponds to a predicted wind speed.
[0060] In step S1031, the predicted loss power generation component at each prediction time point is obtained according to the predicted wind speed at each prediction time point, the relationship between the predicted wind speed and the start-stop wind speed of the unit function, and the wind speed power generation conversion relationship.
[0061] Based on the predicted wind speed at each predicted time point and the start-stop wind speed of the unit function, the state of the wind turbine at the predicted time point can be predicted, that is, it can be predicted whether the wind turbine can generate electricity at the predicted time point, and whether maintenance can be performed within the predetermined time period at the predicted time point. Combined with the wind speed power generation conversion relationship, the power generation of the wind turbine corresponding to the predicted time point can be predicted, that is, the predicted loss power generation component at the predicted time point.
[0062] In some examples, the wind speed for starting and stopping the unit function includes the wind speed for starting the unit function and the wind speed for shutting down the unit function. The wind speed for starting the unit function is the starting wind speed of the wind turbine generator set function in the above embodiment. For details, please refer to the relevant description of the starting wind speed of the wind turbine generator set function in the above embodiment. Correspondingly, the wind speed for shutting down the unit function is the shutting down wind speed of the wind turbine generator set function in the above embodiment. For details, please refer to the relevant description of the shutting down wind speed of the wind turbine generator set function in the above embodiment. No further details will be given here.
[0063] When the predicted wind speed at the prediction time point is less than or equal to the wind speed at which the unit function is started, the predicted loss power generation component at the prediction time point is zero. When the predicted wind speed at the prediction time point is less than or equal to the wind speed at which the unit function is started, the wind turbine generator set does not generate electricity, so the predicted loss power generation component at the prediction time point is zero.
[0064] In the case where the predicted wind speed at the prediction time point is greater than the unit function start wind speed and less than the unit function shutdown wind speed, the predicted loss power generation component at the prediction time point is obtained by converting the predicted wind speed at the prediction time point based on the wind speed power generation conversion relationship. The predicted wind speed at the prediction time point is greater than the unit function start wind speed and less than the unit function shutdown wind speed, and the wind turbine generator set can generate electricity normally. The predicted wind speed at the prediction time point can be converted into the predicted loss power generation component at the prediction time point through the wind speed power generation conversion relationship. In some examples, the wind speed power generation conversion relationship includes a wind speed power trajectory, and the power corresponding to the wind turbine generator set can be obtained according to the predicted wind speed and the wind speed power trajectory. The corresponding power is multiplied by the time interval between two adjacent prediction time points to obtain the predicted loss power generation component at the prediction time point. In some examples, the wind speed power generation conversion relationship includes a wind speed power trajectory and an electricity price periodic variable. The power corresponding to the wind turbine can be obtained based on the predicted wind speed and the wind speed power trajectory, and the electricity price corresponding to the predicted time point can be obtained based on the predicted time point and the electricity price periodic variable. The corresponding power, the time interval between two adjacent predicted time points, and the corresponding electricity price are multiplied together to obtain the predicted loss power generation component at the predicted time point.
[0065] In the case where the predicted wind speed at the predicted time point is greater than or equal to the wind speed at which the unit function is shut down, the predicted time point is marked with an invalid mark, and the scheduled time period including the predicted time point with the invalid mark is excluded from the maintenance time window. The predicted wind speed at the predicted time point is greater than or equal to the wind speed at which the unit function is shut down, and maintenance of the wind turbine generator set is not allowed, and the scheduled time period including the predicted time point cannot be used as a maintenance time window. In one or more embodiments, in order to facilitate participation in the calculation, the predicted loss power generation component at the predicted time point when the predicted wind speed is greater than or equal to the wind speed at which the unit function is shut down can be set to infinity, that is, +∞, and the predicted loss power generation of the scheduled time period including the predicted time point is also +∞, so that the scheduled time period including the predicted wind speed at the predicted time point when the predicted wind speed is greater than or equal to the wind speed at which the unit function is shut down can be excluded from the maintenance time window.
[0066] For example, the wind speed power generation conversion relationship includes the wind speed power trajectory. The predicted loss power generation component at the prediction time point in the above embodiment can be obtained according to the following formula (2):
[0067]
[0068] Among them, J(t i ) is the i-th prediction time point t i The predicted loss of power generation component; p(t i ) is the i-th prediction time point t i The corresponding power; v i is the i-th prediction time point t i The predicted wind speed v on The wind speed for the unit function startup; v off is the wind speed at which the unit function is shut down; Δt is the time interval between two adjacent prediction time points.
[0069] For another example, the wind speed power generation conversion relationship includes the wind speed power trajectory and the electricity price periodic variable. The predicted loss power generation component at the prediction time point in the above embodiment can be obtained according to the following formula (3):
[0070]
[0071] in, is the i-th prediction time point t i The corresponding electricity price; the definitions of other parameters are the same as those in formula (2) above and will not be repeated here.
[0072] In step S1032, the sum of the predicted power loss components at the predicted time points within the predetermined time period is calculated to obtain the predicted power loss amount within the predetermined time period.
[0073] The predetermined time period includes multiple prediction time points. The predicted power loss components of the prediction time points in the predetermined time period are added together to obtain the predicted power loss amount in the predetermined time period. For example, the predicted power loss amount in the predetermined time period can be obtained according to the following formula (4):
[0074]
[0075] Where J(ΔT) is the predicted power loss within the predetermined time period ΔT; J(t i ) is the i-th predicted time point t within the predetermined time period i The predicted loss power generation component, the specific calculation can be seen in the above formulas (2) and (3).
[0076] The predicted loss power generation within the predetermined time period is split into predicted loss power generation components, and the predicted loss power generation within the predetermined time period is obtained through the predicted loss power generation components at multiple prediction time points, thereby obtaining the most suitable maintenance time window.
[0077] In some embodiments, the wind speed prediction model can be trained using the wind speed data of the position of the wind turbine generator set in the third time period before the first time period. Specifically, the wind speed data of the position of the wind turbine generator set in the third time period is obtained; the initial wind speed prediction model is trained using the wind speed data in the first sub-time period to obtain the intermediate wind speed prediction model and the predicted wind speed to be verified in the second sub-time period output by the intermediate wind speed prediction model; the wind speed to be verified is compared with the wind speed data in the second sub-time period to obtain the model prediction error parameter; when the model prediction error parameter is less than or equal to the preset error threshold, the intermediate wind speed prediction model is determined as the wind speed prediction model.
[0078] The third time period is also a historical time period and may be located before the first time period. The third time period includes a first sub-time period and a second sub-time period that are successively distributed, the first sub-time period is adjacent to the second sub-time period, and the first sub-time period is before the second sub-time period. In some examples, the first sub-time period may account for 66% of the third time period, and the second sub-time period may account for 34% of the third time period. The initial wind speed prediction model is an untrained model. The initial wind speed prediction model is trained using the wind speed data in the first sub-time period to obtain an intermediate wind speed prediction model. Based on the wind speed data in the first sub-time period, input data is obtained, and the input data is input into the intermediate wind speed prediction model. The intermediate wind speed prediction model will output the predicted wind speed in the second sub-time period, that is, the predicted wind speed to be verified. The intermediate wind speed prediction model may be used as the final wind speed prediction model, or it may need to continue training. The accuracy of the wind speed predicted by the intermediate wind speed prediction model can be determined by comparing the predicted wind speed to be verified in the second sub-time period with the wind speed data in the second sub-time period. The model prediction error parameter can represent the error between the predicted wind speed to be verified in the second sub-time period and the wind speed data in the second sub-time period. The model prediction error parameter can be obtained by using a root mean square error algorithm. For example, the model prediction error parameter can be calculated according to the following formula (5):
[0079]
[0080] Among them, RMSE v is the model prediction error parameter; m is the number of prediction time points in the second sub-time period; v(t i ) is the i-th predicted time point t in the second sub-time period i Wind speed data; is the i-th predicted time point t in the second sub-time period i The predicted wind speed to be verified.
[0081] The preset error threshold is used to determine whether the model prediction error parameter meets the requirements. It can be set according to scenarios, requirements, experience, etc., and is not limited here. If the model prediction error parameter is less than or equal to the preset error parameter, it means that the model prediction error parameter meets the requirements, the prediction error of the intermediate wind speed prediction model is within an acceptable range, and the intermediate wind speed prediction model can be used as the wind speed prediction model. If the model prediction error parameter is greater than the preset error parameter, it means that the model prediction error parameter does not meet the requirements, the prediction error of the intermediate wind speed prediction model is not within an acceptable range, and the intermediate wind speed prediction model cannot be used as a wind speed prediction model. It is necessary to continue to use the wind speed data of the wind turbine generator unit to train the intermediate wind speed prediction model, and verify the model prediction error parameter again until the model prediction error parameter is less than or equal to the preset error parameter. The intermediate wind speed prediction model with a model prediction error parameter less than or equal to the preset error parameter is used as the wind speed prediction model.
[0082] It should be noted that the wind speed prediction model can be dynamically updated according to a certain time period. Specifically, the wind speed prediction model can be continuously trained and updated using the newly acquired wind speed data during the process of determining the maintenance time window of the wind turbine generator set, so as to obtain a wind speed prediction model that is more consistent with the actual situation and improve the accuracy of wind speed prediction. The maintenance time window can be dynamically updated according to the moving time period. Specifically, when the wind speed data of the position where the wind turbine generator set is located is newly acquired, the newly acquired wind speed data and the wind speed prediction model are used to predict the predicted wind speed in a new future period of time. According to the predicted wind speed in the predetermined time period in the new future period, the start-stop wind speed of the unit function, and the wind speed power generation conversion relationship, the predicted loss power generation in the predetermined time period in the new future period of time is determined. Based on the predicted loss power generation in the predetermined time period in the new future period of time, a new maintenance time window is determined, that is, the maintenance time window is updated, so as to obtain the most suitable maintenance time window with the smallest power generation loss, and optimize the maintenance time window.
[0083] In some examples, the wind speed power trajectory may be a wind speed power trajectory designed corresponding to the wind turbine generator set. When the predicted wind speed is obtained, a linear interpolation method may be used to obtain the power corresponding to the predicted wind speed from the wind speed power trajectory.
[0084] In other examples, the above-mentioned wind speed power trajectory can be implemented as a wind speed power trajectory model. The wind speed data of the position where the wind turbine generator set is located in the fourth time period and the output power data of the wind turbine generator set can be obtained; the initial wind speed power trajectory model is trained using the wind speed data and the output power data in the fourth time period to obtain the wind speed power trajectory model. The wind speed power trajectory model is used to characterize the wind speed power trajectory. The fourth time period is before the second time period, and the fourth time period can be the same as the first time period or the third time period, or it can be different, which is not limited here. The wind speed data and the output power data of the position where the wind turbine generator set is located in the fourth time period are both actual data collected. The initial wind speed power trajectory model is a model that has not been trained yet, and the initial wind speed power trajectory model can be trained using the actual data collected in the fourth time period to obtain the wind speed power trajectory model. The wind speed data is input into the wind speed power trajectory model, and the wind speed power trajectory model will output the power data corresponding to the wind speed data. Step S103 in the above embodiment can obtain the power of the wind turbine generator set through the wind speed power trajectory model, so as to obtain the predicted loss power generation according to the power of the wind turbine generator set.
[0085] In some embodiments, the operation of the wind turbine generator set may be controlled according to the maintenance time window to assist the staff in maintaining the wind turbine generator set. Figure 5A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in another embodiment of the present application, Figure 5 and Figure 1 The difference is that Figure 5 The shown method for determining a maintenance time window of a wind turbine generator set may further include steps S105 to S107.
[0086] In step S105, when the time reaches the start time of the maintenance time window, the wind turbine generator set is controlled to shut down.
[0087] The maintenance time window is a period of time in the future. When the time reaches the start time of the maintenance time window, the wind turbine generator set is controlled to shut down so that the staff can perform maintenance on the wind turbine generator set.
[0088] In step S106, maintenance progress information is obtained, and before the time reaches the end time of the maintenance time window and the maintenance progress information indicates that the maintenance is completed, the wind turbine generator set is controlled to resume operation.
[0089] In some examples, maintenance on the wind turbine may have been completed before the end time of the maintenance time window, and maintenance progress information that can represent the maintenance progress of the wind turbine can be obtained in real time. If the time has not reached the end time of the maintenance time window, but the maintenance progress information has indicated that the maintenance is completed, the wind turbine can be controlled to resume operation to avoid further loss of power generation from the wind turbine.
[0090] In step S107, when the time reaches the end time of the maintenance time window, the wind turbine generator set is controlled to resume operation.
[0091] In the absence of maintenance progress information, when the time reaches the end time of the maintenance time window, it can be indicated that the maintenance of the wind turbine generator set has been completed, and the wind turbine generator set can be controlled to resume operation to avoid further loss of power generation by the wind turbine generator set.
[0092] According to the maintenance time window and the control of the wind turbine generator set, it can be coordinated with the maintenance of the wind turbine generator set by the staff, and the maintenance efficiency of the wind turbine generator set can be further improved.
[0093] In some embodiments, the wind farm maintenance time window may be obtained according to the maintenance time windows of the wind turbine generator sets in the wind farm. Figure 6 A flowchart of a method for determining a maintenance time window for a wind turbine generator set provided in yet another embodiment of the present application, Figure 6 and Figure 1 The difference is that Figure 6 The shown method for determining a maintenance time window of a wind turbine generator set may further include step S108 and step S109.
[0094] In step S108, the maintenance time window of each wind turbine generator set in the wind farm is obtained.
[0095] The wind farm includes multiple wind turbines, and each wind turbine can determine the corresponding maintenance time window using the maintenance time window determination method for wind turbines provided in the embodiment of the present application. The wind turbines in the wind farm are relatively close to each other, and the wind conditions, meteorological data, etc. between the adjacent wind turbines are very similar. Correspondingly, the maintenance time windows of the adjacent wind turbines are also relatively close.
[0096] In step S109, the maintenance time windows of the wind turbines are merged to obtain the wind farm maintenance time window, or the time period in which the probability distribution density of the maintenance time windows of the wind turbines is the largest is determined as the wind farm maintenance time window.
[0097] In some examples, the maintenance time window of each wind turbine generator set can be taken as a time set, and the union of the maintenance time windows of each wind turbine generator set can be taken as the wind farm maintenance time window. The wind farm maintenance time window is a maintenance time window for the wind farm. For example, if the wind farm has n wind turbine generator sets, the wind farm maintenance time window can be obtained according to the following formula (6):
[0098] D total =D1∪D2∪……∪D n (6)
[0099] Among them, D total is the maintenance time window of the wind farm; D1 is the maintenance time window of the first wind turbine in the wind farm; D2 is the maintenance time window of the second wind turbine in the wind farm; D n is the maintenance time window of the nth wind turbine in the wind farm.
[0100] In other examples, the probability distribution density of the time period in which the maintenance time window of each wind turbine generator set in the wind farm is located can be counted first, and the more times the maintenance time window of the wind turbine generator set falls into a certain time period, the greater the probability distribution density of the time period. The time period in which the probability distribution density of the maintenance time window of each wind turbine generator set is the largest, that is, the time period in which the maintenance time windows of most wind turbine generator sets in the wind farm are located is selected as the wind farm maintenance time window.
[0101] Determining the wind farm maintenance time window through the maintenance time window of the wind turbine generator set can facilitate the formulation of the overall maintenance strategy for the wind farm and improve the maintenance efficiency of the wind farm.
[0102] A second aspect of the present application provides a device for determining a maintenance time window for a wind turbine generator set. Figure 7A schematic diagram of the structure of a device for determining a maintenance time window for a wind turbine generator set provided in an embodiment of the present application is shown in FIG. Figure 7 As shown, the maintenance time window determination device 200 for a wind turbine generator set may include a wind speed acquisition module 201 , a wind speed prediction module 202 , a power generation loss prediction module 203 and a maintenance time window determination module 204 .
[0103] The wind speed acquisition module 201 may be used to acquire wind speed data at a location where a wind turbine generator set is located within a first time period.
[0104] The wind speed prediction module 202 may be used to utilize wind speed data and a previously trained wind speed prediction model to obtain a predicted wind speed at the location of the wind turbine generator set within a second time period output by the wind speed prediction model based on the wind speed data.
[0105] The second time period is located after the first time period.
[0106] The power generation loss prediction module 203 can be used to determine the predicted power generation loss in each predetermined time period according to the predicted wind speed in the predetermined time period obtained by dividing the second time period, the preset unit function start-stop wind speed and the wind speed power generation conversion relationship.
[0107] The wind speed of the wind turbine function start-stop represents the start-up wind speed and the shut-down wind speed of the wind turbine function. The wind speed power generation conversion relationship includes the wind speed power trajectory.
[0108] In some examples, the wind speed power generation conversion relationship also includes an electricity price periodic variable.
[0109] The maintenance time window determination module 204 may be configured to determine the maintenance time window based on one or more than two consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest.
[0110] In an embodiment of the present application, the wind speed prediction model obtained by previous training can be used to predict the predicted wind speed at the position of the wind turbine generator set in the second time period in the future, based on the wind speed data at the position of the wind turbine generator set in the first time period in the past. The second time period is divided into a plurality of predetermined time periods, and the predicted loss of power generation in each predetermined time period can be predicted based on the predicted wind speed in the predetermined time period, the preset start-stop wind speed of the unit function, and the wind speed-to-power conversion relationship including the wind speed-to-power trajectory. Based on one or more consecutive predetermined time periods with the smallest sum of the predicted loss of power generation in the second time period, the maintenance time window in the second time period in the future is determined. The predicted loss of power generation corresponding to the determined maintenance time window is the smallest, and maintaining the wind turbine generator set in the determined maintenance time window can effectively reduce the power generation loss caused by the maintenance of the wind turbine generator set. The staff can also formulate reasonable operation and maintenance strategies based on the maintenance time window, so as to improve the maintenance efficiency of the wind turbine generator set.
[0111] Moreover, the predicted wind speed at the location of the wind turbine generator set is predicted in the embodiment of the present application, and its granularity is finer. The accuracy of the predicted lost power generation within a predetermined time period determined based on the predicted wind speed at the location of the wind turbine generator set is higher, and the effect of reducing the power generation loss of the selected maintenance time window is also better.
[0112] In some embodiments, each predetermined time period includes a plurality of predicted time points.
[0113] The power generation loss prediction module 203 can be used to: obtain the predicted loss power generation component at each prediction time point based on the predicted wind speed at each prediction time point, the relationship between the predicted wind speed and the start-stop wind speed of the unit function, and the wind speed power generation conversion relationship; calculate the sum of the predicted loss power generation components at the prediction time points within the predetermined time period to obtain the predicted loss power generation within the predetermined time period.
[0114] In some examples, the unit function start-stop wind speed includes the unit function start wind speed and the unit function shut-down wind speed.
[0115] When the predicted wind speed at the predicted time point is less than or equal to the unit function start-up wind speed, the predicted loss power generation component at the predicted time point is zero.
[0116] When the predicted wind speed at the prediction time point is greater than the unit function start-up wind speed and less than the unit function shutdown wind speed, the predicted loss power generation component at the prediction time point is obtained by converting the predicted wind speed at the prediction time point based on the wind speed power generation conversion relationship.
[0117] When the predicted wind speed at the predicted time point is greater than or equal to the unit function shutdown wind speed, the predicted time point is marked with an invalid mark, and the scheduled time period including the predicted time point with the invalid mark is excluded from the maintenance time window.
[0118] In some embodiments, each predetermined time period includes a plurality of predicted time points.
[0119] The wind speed prediction module 202 can be used to: obtain a filtering processing window, the duration of the filtering processing window is the same as the time interval between two adjacent prediction time points; gradually slide the filtering processing window in the wind speed data in chronological order to obtain the average value of the wind speed data in each filtering processing window; use the average value of the wind speed data in each filtering processing window and the wind speed prediction model to obtain the predicted wind speed output by the wind speed prediction model.
[0120] In some embodiments, the maintenance time window determination device 200 for a wind turbine generator set may further include a training module and a verification module.
[0121] The wind speed acquisition module 201 may also be used to acquire wind speed data at the location of the wind turbine generator set within a third time period.
[0122] The third time period is located before the first time period, and includes a first sub-time period and a second sub-time period that are successively distributed.
[0123] The training module can be used to: train the initial wind speed prediction model using the wind speed data in the first sub-time period to obtain the intermediate wind speed prediction model and the predicted wind speed to be verified in the second sub-time period output by the intermediate wind speed prediction model.
[0124] The verification module can be used to: compare the wind speed to be verified with the wind speed data in the second sub-time period to obtain the model prediction error parameter; when the model prediction error parameter is less than or equal to the preset error threshold, determine the intermediate wind speed prediction model as the wind speed prediction model.
[0125] In some embodiments, the maintenance time window determination module 204 can be used to: in the second time period, select one or more consecutive predetermined time periods with the smallest sum of predicted lost power generation as the maintenance time window; or, in the second time period, select one or more consecutive predetermined time periods with the smallest sum of predicted lost power generation as the time window to be verified, and when the sum of predicted lost power generation corresponding to the time window to be verified is less than or equal to a preset lost power generation threshold, the time window to be verified is determined as the maintenance time window.
[0126] In some embodiments, the maintenance time window determination device 200 of the wind turbine generator set may further include a wind farm maintenance module.
[0127] The wind farm maintenance module can be used to: obtain the maintenance time window of each wind turbine in the wind farm; merge the maintenance time windows of each wind turbine to obtain the wind farm maintenance time window, or determine the time period with the largest probability distribution density of the maintenance time windows of each wind turbine as the wind farm maintenance time window.
[0128] In some embodiments, the maintenance time window determination device 200 of the wind turbine generator set may further include a control module.
[0129] The control module can be used to: control the wind turbine to shut down when the time reaches the start time of the maintenance time window; obtain maintenance progress information, and control the wind turbine to resume operation before the time reaches the end time of the maintenance time window and the maintenance progress information indicates that the maintenance is completed; control the wind turbine to resume operation when the time reaches the end time of the maintenance time window.
[0130] In some embodiments, the maintenance time window determination device 200 for a wind turbine generator set may further include a wind power trajectory generation module.
[0131] The wind power trajectory generation module can be used to: obtain the wind speed data of the wind turbine generator set at the machine position and the output power data of the wind turbine generator set in a fourth time period, and the fourth time period is before the second time period; use the wind speed data and output power data in the fourth time period to train the initial wind speed power trajectory model to obtain the wind speed power trajectory model, and the wind speed power trajectory model is used to characterize the wind speed power trajectory.
[0132] A third aspect of the present application provides an electronic device. Figure 8 This is a schematic diagram of the structure of an electronic device provided by an embodiment of the present application. Figure 8 As shown, the electronic device 300 includes a memory 301 , a processor 302 , and a computer program stored in the memory 301 and executable on the processor 302 .
[0133] In some examples, the processor 302 may include a central processing unit (CPU), or an application specific integrated circuit (ASIC), or may be configured to implement one or more integrated circuits of the embodiments of the present application.
[0134] The memory 301 may include a read-only memory (ROM), a random access memory (RAM), a disk storage medium device, an optical storage medium device, a flash memory device, an electrical, optical or other physical / tangible memory storage device. Therefore, generally, the memory includes one or more tangible (non-transitory) computer-readable storage media (e.g., a memory device) encoded with software including computer executable instructions, and when the software is executed (e.g., by one or more processors), it is operable to perform the operations described with reference to the method for determining the maintenance time window of a wind turbine generator set in an embodiment of the present application.
[0135] The processor 302 runs a computer program corresponding to the executable program code by reading the executable program code stored in the memory 301 , so as to implement the method for determining the maintenance time window of the wind turbine generator set in the above embodiment.
[0136] In some examples, the electronic device 300 may further include a communication interface 303 and a bus 304. Figure 8 As shown, the memory 301, the processor 302, and the communication interface 303 are connected via a bus 304 and communicate with each other.
[0137] The communication interface 303 is mainly used to realize the communication between the modules, devices, units and / or equipment in the embodiment of the present application. The communication interface 303 can also be used to access input devices and / or output devices.
[0138] The bus 304 includes hardware, software, or both, coupling the components of the electronic device 300 to each other. By way of example and not limitation, the bus 304 may include an Accelerated Graphics Port (AGP) or other graphics bus, an Enhanced Industry Standard Architecture (EISA) bus, a Front Side Bus (FSB), a Hyper Transport (HT) interconnect, an Industry Standard Architecture (ISA) bus, an InfiniBand interconnect, a Low Pin Count (LPC) bus, a Memory bus, a Micro Channel Architecture (MCA) bus, a Peripheral Component Interconnect (PCI) bus, a PCI-Express (PCI-E) bus, a Serial Advanced Technology Attachment (SATA) bus, a Video Electronics Standards Association Local Bus (VLB) bus, or other suitable buses or a combination of two or more of these. Where appropriate, the bus 304 may include one or more buses. Although embodiments of the present application describe and illustrate a particular bus, the present application contemplates any suitable bus or interconnect.
[0139] In a fourth aspect, the present application provides a computer-readable storage medium, on which a computer program instruction is stored, and when the computer program instruction is executed by a processor, the maintenance time window determination method of the wind turbine generator set in the above-mentioned embodiment can be implemented, and the same technical effect can be achieved. To avoid repetition, it is not repeated here. Among them, the above-mentioned computer-readable storage medium may include a non-transitory computer-readable storage medium, such as a read-only memory (Read-Only Memory, referred to as ROM), a random access memory (Random Access Memory, referred to as RAM), a disk or an optical disk, etc., which is not limited here.
[0140] An embodiment of the present application provides a computer program product. When the instructions in the computer program product are executed by a processor of an electronic device, the electronic device executes the maintenance time window determination method for a wind turbine generator set in the above embodiment and can achieve the same technical effect. To avoid repetition, it will not be described here.
[0141] It should be clear that each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. For device embodiments, equipment embodiments, computer-readable storage medium embodiments, and computer program product embodiments, the relevant parts can refer to the description part of the method embodiment. The present application is not limited to the specific steps and structures described above and shown in the figures. Those skilled in the art can make various changes, modifications and additions, or change the order between the steps after understanding the spirit of the present application. In addition, for the sake of brevity, a detailed description of known method technologies is omitted here.
[0142] The above reference is according to the method of the embodiment of the present application, the flow chart of the device (system) and the computer program product and / or the block diagram described various aspects of the present application.It should be understood that each square box in the flow chart and / or the block diagram and the combination of each square box in the flow chart and / or the block diagram can be realized by computer program instructions.These computer program instructions can be provided to the processor of a general-purpose computer, a special-purpose computer or other programmable data processing device to produce a machine so that these instructions executed by the processor of the computer or other programmable data processing device enable the realization of the function / action specified in one or more square boxes of the flow chart and / or the block diagram.Such a processor can be but is not limited to a general-purpose processor, a special-purpose processor, a special application processor or a field programmable logic circuit.It can also be understood that each square box in the block diagram and / or the flow chart and the combination of the square boxes in the block diagram and / or the flow chart can also be realized by the dedicated hardware that performs the specified function or action, or can be realized by the combination of dedicated hardware and computer instructions.
[0143] Those skilled in the art should understand that the above embodiments are exemplary rather than restrictive. Different technical features appearing in different embodiments can be combined to achieve beneficial effects. Based on the study of the drawings, the specification and the claims, those skilled in the art should be able to understand and implement other variations of the disclosed embodiments. In the claims, the term "comprising" does not exclude other devices or steps; the quantifier "one" does not exclude multiple; the terms "first" and "second" are used to indicate names rather than to indicate any specific order. Any figure marks in the claims should not be understood as limiting the scope of protection. The functions of multiple parts appearing in the claims can be implemented by a single hardware or software module. The appearance of certain technical features in different dependent claims does not mean that these technical features cannot be combined to achieve beneficial effects.
Claims
1. A method for determining a maintenance time window of a wind turbine generator set, characterized in that: include: Obtain wind speed data at the location of the wind turbine generator set within a first time period; Using the wind speed data and a previously trained wind speed prediction model, a predicted wind speed at the position where the wind turbine generator set is located in a second time period output by the wind speed prediction model based on the wind speed data is obtained, wherein the second time period is after the first time period; Determine the predicted lost power generation in each of the predetermined time periods according to the predicted wind speed in the predetermined time period obtained by dividing the second time period, the preset unit function start-stop wind speed, and the wind speed power generation conversion relationship, wherein the unit function start-stop wind speed represents the start wind speed and the shut-down wind speed of the wind turbine generator function, and the wind speed power generation conversion relationship includes a wind speed power trajectory; A maintenance time window is determined based on one or more than two consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest.
2. The method according to claim 1, characterized in that: Each of the predetermined time periods includes a plurality of predicted time points, The predicted wind speed in the predetermined time period obtained by dividing the second time period, the preset wind speed for starting and stopping the unit function, and the wind speed power generation conversion relationship are used to determine the predicted power loss in each predetermined time period, including: According to the predicted wind speed at each predicted time point, the relationship between the predicted wind speed and the start-stop wind speed of the unit function, and the wind speed power generation conversion relationship, the predicted loss power generation component at each predicted time point is obtained; The predicted power loss components at the predicted time points within the predetermined time period are summed up to obtain the predicted power loss amount within the predetermined time period.
3. The method according to claim 2, characterized in that The unit function start-stop wind speed includes the unit function start wind speed and the unit function shut-down wind speed; Wherein, when the predicted wind speed at the predicted time point is less than or equal to the wind speed at which the unit function is started, the predicted loss power generation component at the predicted time point is zero; When the predicted wind speed at the predicted time point is greater than the wind speed for starting the unit function and less than the wind speed for shutting down the unit function, the predicted lost power generation component at the predicted time point is obtained by converting the predicted wind speed at the predicted time point based on the wind speed power generation conversion relationship; When the predicted wind speed at the predicted time point is greater than or equal to the unit function shutdown wind speed, the predicted time point is marked with an invalid mark, and the predetermined time period including the predicted time point with the invalid mark is excluded from the maintenance time window.
4. The method according to claim 1, characterized in that: Each of the predetermined time periods includes a plurality of predicted time points, The step of using the wind speed data and a previously trained wind speed prediction model to obtain a predicted wind speed at the location of the wind turbine generator set within a second time period output by the wind speed prediction model based on the wind speed data includes: Acquire a filtering processing window, wherein the duration of the filtering processing window is the same as the time interval between two adjacent prediction time points; Sliding the filtering processing window step by step in the wind speed data in chronological order to obtain an average value of the wind speed data in each filtering processing window; The predicted wind speed output by the wind speed prediction model is obtained by using the average value of the wind speed data in each filtering processing window and the wind speed prediction model.
5. The method according to claim 1, characterized in that Also includes: Acquire the wind speed data of the position where the wind turbine generator set is located in a third time period, wherein the third time period is located before the first time period and includes a first sub-time period and a second sub-time period that are successively distributed; Using the wind speed data in the first sub-time period to train an initial wind speed prediction model, to obtain an intermediate wind speed prediction model and a predicted wind speed to be verified in a second sub-time period output by the intermediate wind speed prediction model; Comparing the wind speed to be verified with the wind speed data in the second sub-time period to obtain a model prediction error parameter; When the model prediction error parameter is less than or equal to a preset error threshold, the intermediate wind speed prediction model is determined as the wind speed prediction model.
6. The method according to claim 1, characterized in that The determining of the maintenance time window based on one or more consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest comprises: In the second time period, one or more than two consecutive predetermined time periods with the smallest sum of the predicted lost power generation are selected as the maintenance time window; or, In the second time period, one or more consecutive predetermined time periods with the smallest sum of the predicted lost power generation are selected as time windows to be verified. When the sum of the predicted lost power generation corresponding to the time windows to be verified is less than or equal to a preset lost power generation threshold, the time windows to be verified are determined as the maintenance time windows.
7. The method according to claim 1, characterized in that Also includes: Acquire the maintenance time window of each wind turbine generator set in the wind farm; The maintenance time windows of the wind turbines are combined to obtain a wind farm maintenance time window, or the time period in which the probability distribution density of the maintenance time windows of the wind turbines is the largest is determined as the wind farm maintenance time window.
8. The method according to claim 1, characterized in that After determining the maintenance time window based on the one or more consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest, the method further includes: When the time reaches the start time of the maintenance time window, controlling the wind turbine generator set to shut down; Acquire maintenance progress information, and control the wind turbine generator set to resume operation before the end time of the maintenance time window and when the maintenance progress information indicates that the maintenance is completed; When the time reaches the end time of the maintenance time window, the wind turbine generator set is controlled to resume operation.
9. The method according to claim 1, characterized in that: Also includes: Acquire the wind speed data at the position where the wind turbine generator set is located and the output power data of the wind turbine generator set within a fourth time period, wherein the fourth time period is before the second time period; An initial wind speed power trajectory model is trained using the wind speed data and the output power data in the fourth time period to obtain a wind speed power trajectory model, wherein the wind speed power trajectory model is used to characterize the wind speed power trajectory.
10. The method according to any one of claims 1 to 9, characterized in that The wind speed power generation conversion relationship also includes a periodic variable of electricity price.
11. A device for determining a maintenance time window of a wind turbine generator set, characterized in that: include: A wind speed acquisition module, used to acquire wind speed data at the location of the wind turbine generator set within a first time period; A wind speed prediction module, used to use the wind speed data and a previously trained wind speed prediction model to obtain a predicted wind speed at the position of the wind turbine generator set within a second time period output by the wind speed prediction model based on the wind speed data, wherein the second time period is after the first time period; a power generation loss prediction module, configured to determine the predicted power generation loss in each of the predetermined time periods according to the predicted wind speed in the predetermined time period obtained by dividing the second time period, the preset unit function start-stop wind speed, and the wind speed power generation conversion relationship, wherein the unit function start-stop wind speed represents the start wind speed and the shut-down wind speed of the wind turbine generator function, and the wind speed power generation conversion relationship includes a wind speed power trajectory; The maintenance time window determination module is used to determine the maintenance time window based on one or more consecutive predetermined time periods in which the sum of the predicted lost power generation in the second time period is the smallest.
12. An electronic device, characterized in that: include: a processor and a memory storing computer program instructions; When the processor executes the computer program instructions, the method for determining the maintenance time window of a wind turbine generator set according to any one of claims 1 to 10 is implemented.
13. A computer-readable storage medium, characterized in that: The computer-readable storage medium stores computer program instructions, and when the computer program instructions are executed by a processor, the method for determining a maintenance time window of a wind turbine generator set according to any one of claims 1 to 10 is implemented.
Citation Information
Cited By
Method for determining predictive maintenance opportunity decision of front-end isolated switching power supply of aging table
CN119904223A