A controllable power generation device for base station
By using the control module to monitor and adjust the output voltage of the rectifier module in the base station controllable power generator device, the generator is ensured that the power supply only to the base station load, and the fuel consumption and cost increase caused by the generator charging the battery is solved, and the generator is improved Efficiency and service life.
Patent Information
- Application Number
- CN202411234255.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-04
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-09-04
AI Technical Summary
Existing generators will charge the backup battery after power supply, resulting in increased fuel consumption, increased costs, excessive generator load power, reduced efficiency and accelerated aging.
Design a base station controllable power generator, including generator, rectifier module and control module, monitor the status of backup battery by detecting equipment, control the output voltage of rectifier module consistent with the output voltage of backup battery, avoid the generator charging the battery, and ensure the generator Power is only provided to the base station load.
It effectively reduces the fuel consumption and cost of the generator, improves the operating efficiency of the generator, extends its service life and reduces maintenance costs.
Smart Images

Figure CN118739516B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of power control and relates to a controllable power generation device for a base station. Background Art
[0002] In modern industry, communications, data centers and other fields, the continuity and stability of electricity are the basis for ensuring normal operation. In order to cope with power outages caused by natural disasters, power grid failures and other reasons, key equipment and facilities such as communication base stations and data centers are equipped with backup power supply systems, such as backup batteries and generators. These backup power supply systems can start quickly when the city power is interrupted to provide power to the load and ensure the normal operation of the load.
[0003] However, in actual research, it was found that when the generator starts working for a certain period of time, in addition to supplying power to the load normally, the generator will also charge the battery. This method will cause the generator to consume more fuel, increase unnecessary consumption and costs, and also cause the generator load power to be excessive, reducing the operating efficiency of the generator, and accelerating the aging and wear of the generator, thereby increasing maintenance costs. Summary of the invention
[0004] In order to solve the above-mentioned problems in the prior art, the present invention provides a controllable power generation device for a base station.
[0005] In order to achieve the above object, the technical solution adopted by the present invention is:
[0006] In the first aspect, the present application provides a controllable power generation device for a base station, comprising: a generator, a rectifier module, a control module and a detection device; the generator is connected to the rectifier module; the control module is respectively connected to the rectifier module and the detection device; the output end of the rectifier module is connected to the DC bus of the base station, and the DC bus is also connected to the load equipment of the base station and the backup battery of the base station; the detection device is used to monitor the status parameters of the backup battery; the control module is configured to: in response to determining that the mains power supply is disconnected, continuously obtain the status parameters of the backup battery collected by the detection device, and when it is determined that the output voltage of the rectifier module is consistent with the output voltage of the backup battery, control the rectifier module to provide stable power supply with the output voltage.
[0007] Optionally, the detection device is a current transformer; the current transformer is connected to the control module; when in use, the current transformer is used to be installed on the connection line between the backup battery and the DC bus; the control module is also configured to: control the rectifier module to output pulses with a step-up, and receive the current value sensed by the current transformer; determine the output voltage of the rectifier module aligned with the critical point time based on the current value sensed by the current transformer; wherein the output voltage of the rectifier module aligned with the critical point time is consistent with the output voltage of the backup battery; the critical point is the endpoint where the current value sensed by the current transformer goes from large to small and then from small to large, and the critical point represents that the backup battery changes from a discharge state to a charging state.
[0008] Optionally, the control module is further configured to: control the rectifier module to output pulses, and the voltage of the pulses is pulled up once in each control stage to form a step-up trend; wherein the number of cycles in each control stage is T; and the range of T is 3 to 5.
[0009] Optionally, the voltage fluctuation amplitude set in each control stage is A; wherein the range of A is 0.5V~1.5V; the frequency of the voltage waveform set in each control stage is f; wherein the range of f is 5Hz~20Hz; the number of times the voltage standard waveform appears in each control stage is Q, and Q is greater than or equal to 2; wherein the voltage standard waveform is the voltage fluctuation amplitude A and the frequency f.
[0010] Optionally, the detection device is a voltage detection circuit; one end of the voltage detection circuit is connected to the output end of the backup battery, and the other end of the voltage detection circuit is connected to the control module; the voltage detection circuit is used to detect the output voltage of the backup battery; the control module is specifically configured to: compare the output voltage of the rectifier module with the output voltage of the backup battery, and when the output voltage of the rectifier module is consistent with the output voltage of the backup battery, control the rectifier module to provide stable power supply with the output voltage; wherein the output voltage of the backup battery is a state parameter of the backup battery.
[0011] Optionally, the detection device is a current detection circuit; one end of the current detection circuit is connected to one end of the backup battery, and the other end of the current detection circuit is connected to the control module; the current detection circuit is used to detect the output current of the backup battery; the control module is specifically configured to: determine the output voltage of the rectifier module aligned with the critical point time based on the output current of the backup battery; wherein the output voltage of the rectifier module aligned with the critical point time represents consistency with the output voltage of the backup battery; the critical point is the endpoint where the output current of the backup battery changes from large to small and then from small to large, and the critical point represents that the backup battery changes from a discharge state to a charging state; wherein the output current of the backup battery is a state parameter of the backup battery.
[0012] Optionally, the control module is further configured to determine that the mains power supply is disconnected if the output current detected by the current detection circuit is received after the output current of the current detection circuit is not received within a preset time period.
[0013] Optionally, the control module includes a controller and a voltage regulating module; the controller is connected to the voltage regulating module; the controller is configured to: adjust the output voltage of the rectifier module to be consistent with the output voltage of the backup battery, and control the rectifier module to provide stable power supply with this output voltage.
[0014] Optionally, the power ratio of the generator is K times the load power of the load equipment of the base station; wherein the range of K is 1.2~1.4.
[0015] Optionally, the generator includes: an internal combustion engine and a permanent magnet generator; the internal combustion engine is used to burn fuel to provide source power for the permanent magnet generator; the permanent magnet generator is used to rotate to generate electricity and provide it to the rectifier module, so that the rectifier module outputs a DC voltage.
[0016] The beneficial effects of the embodiments of the present application include: in the scenario with generator power supply and backup battery power supply, the rectifier module of the generator is connected to the control module, and the control module is configured to continuously obtain the state parameters of the backup battery collected by the detection device in response to the disconnection of the mains power supply, and when it is determined that the output voltage of the rectifier module is consistent with the output voltage of the backup battery, the rectifier module is controlled to provide stable power supply with the output voltage. In this way, the generator will not charge the backup battery, and the generator will only supply power to the load equipment of the base station, thereby effectively reducing the fuel consumption of the generator, that is, reducing the unnecessary consumption and cost of the generator, and at the same time, the load power of the generator will not be too large, ensuring the operating efficiency of the generator. In addition, the use and maintenance costs of the generator are also reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A module block diagram of a base station controllable power generation device provided by an embodiment of the present invention;
[0018] Figure 2 A module block diagram of a base station provided in an embodiment of the present invention;
[0019] Figure 3 A schematic diagram of a pulse provided by an embodiment of the present invention;
[0020] Figure 4 A circuit diagram of a voltage detection circuit provided by an embodiment of the present invention;
[0021] Figure 5 A circuit diagram of a current detection circuit provided by an embodiment of the present invention.
[0022] Reference numerals:
[0023] 100-base station controllable power generation device; 10-generator; 20-rectifier module; 30-control module; 40-detection equipment. DETAILED DESCRIPTION
[0024] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0025] In actual research, it was found that when the generator starts working for a certain period of time, in addition to supplying power to the load normally, the generator will also charge the battery. This method will cause the generator to consume more fuel, increase unnecessary consumption and costs, and also cause the generator load power to be too large, reducing the operating efficiency of the generator, and accelerating the aging and wear of the generator, thereby increasing maintenance costs.
[0026] In view of the above problems, the present application provides the following embodiments to solve them:
[0027] See also Figure 1-Figure 2 An embodiment of the present application provides a base station controllable power generation device 100, including: a generator 10, a rectifier module 20, a control module 30 and a detection device 40.
[0028] The generator 10 is connected to the rectifier module 20. The control module 30 is connected to the rectifier module 20 and the detection device 40 respectively.
[0029] It should be noted that the output end of the rectifier module 20 is connected to the DC bus of the base station, and the DC bus is also connected to the load equipment of the base station and the backup battery of the base station; the AC power is connected through the DC bus to power the load equipment of the base station; of course, the DC bus is also used to fully charge the backup battery to cope with sudden emergency situations.
[0030] The detection device 40 is used to monitor the status parameters of the backup battery.
[0031] Here, the construction of the base station may at least include: a DC bus, a load device and a backup battery. In addition, the base station may also include a switching power supply; the switching power supply and the load device are connected via a DC bus, and the switching power supply is connected to the mains.
[0032] The DC bus is connected to the mains to supply power to the load equipment. Since the backup battery is also connected to the DC bus, when the mains power is interrupted, the backup battery configured in the base station itself (usually, the backup battery is fully charged) can be used to maintain the normal operation of the load equipment.
[0033] The base station here may refer to a communication base station, a data center, etc., and the load device is the electrical equipment in the base station.
[0034] The control module 30 is configured to: in response to determining that the AC power supply is disconnected, continuously obtain the status parameters of the backup battery collected by the detection device 40, and when it is determined that the output voltage of the rectifier module 20 is consistent with the output voltage of the backup battery, control the rectifier module 20 to provide stable power supply with the output voltage.
[0035] In other words, after the mains power supply is disconnected, the control module 30 controls the output voltage of the stable power supply of the rectifier module 20 by continuously acquiring the state parameters of the backup battery of the base station.
[0036] Here, when the mains power supply is disconnected, the fully charged battery works first, and then the generator 10 also intervenes to supply power.
[0037] It should be noted that after the generator 10 is started, the output voltage gradually rises after rectification by the rectifier module 20. When the output voltage of the rectifier module 20 is consistent with the output voltage of the backup battery, the output voltage is used for stable power supply, that is, the output voltage of the rectifier module 20 is finally consistent with the output voltage of the backup battery. By keeping the output voltage of the rectifier module 20 consistent with the output voltage of the backup battery, the rectifier module 20 and the backup battery can simultaneously supply power to the base station load, thereby making the generator 10 and the backup battery equivalent to two parallel power modules. Then, at this time, the generator 10 will not charge the backup battery.
[0038] In summary, the base station controllable power generation device 100 provided in the embodiment of the present application has the following beneficial effects, including: in the scenario with power supply by the generator 10 and the backup battery, the rectifier module 20 of the generator 10 is connected to the control module 30, and the control module 30 is configured to continuously obtain the state parameters of the backup battery collected by the detection device 40 in response to the disconnection of the mains power supply, and when it is determined that the output voltage of the rectifier module 20 is consistent with the output voltage of the backup battery, the rectifier module 20 is controlled to supply power stably with the output voltage. In this way, the generator 10 will not charge the backup battery, and the generator 10 only supplies power to the load equipment of the base station, thereby effectively reducing the fuel consumption of the generator 10, that is, reducing the unnecessary consumption and cost of the generator 10, and at the same time, the load power of the generator 10 will not be too large, ensuring the operating efficiency of the generator 10, and in addition, the use and maintenance cost of the generator 10 is also reduced.
[0039] As for the deployment of the generator 10, the embodiment of the present application provides two deployment methods. The first deployment method is that the base station itself has pre-deployed the generator 10, the rectifier module 20, the control module 30, the detection device 40 and the backup battery. That is, in the line of the base station, in addition to the backup battery, the generator 10, the rectifier module 20, the control module 30, and the detection device 40 are also pre-connected. Then the detection device 40 here can continuously obtain the state parameters of the backup battery through an access-type monitoring method. For example, the detection device 40 can be implemented by pre-designed current detection circuits, voltage detection circuits, sensors and other equipment, and the equipment and facilities need to be pre-connected to the base station. Then after the mains power supply is disconnected, the control module 30 can directly monitor the state parameters of the backup battery in real time according to the equipment connected to the line, thereby effectively regulating the output voltage of the generator 10.
[0040] Another deployment method is that the current base station only has a backup battery pre-deployed. At this time, the base station controllable power generation device 100 provided in the embodiment of the present application is connected to the base station after the mains power supply is disconnected. It should be noted that since the base station has not pre-deployed the detection device 40, the line can no longer be changed in the line to access the current detection circuit, voltage detection circuit, sensor and other equipment for implementation (but the generator 10 can be easily directly connected), but at this time it is necessary to continuously obtain the state parameters of the backup battery to regulate the output voltage of the rectifier module 20. It is not realistic to deploy the above-mentioned current detection circuit, voltage detection circuit, sensor and other equipment in real time. In view of this difficulty, the embodiment of the present application also provides a non-access detection method to deal with the above situation.
[0041] Specifically, the detection device 40 is a current transformer.
[0042] The current transformer is connected to the control module 30. The current transformer may be an AC transformer.
[0043] In one embodiment, the current transformer may also be a Rogowski coil.
[0044] Here, when the current transformer is in use, it is used to be installed on the connection line between the backup battery and the DC bus.
[0045] The control module 30 is further configured to: control the rectifier module 20 to output pulses with step-up, and receive the current value sensed by the current transformer; and determine the output voltage of the rectifier module aligned with the critical point time based on the current value sensed by the current transformer.
[0046] Among them, the output voltage representation of the rectifier module aligned with the critical point time is consistent with the output voltage of the backup battery; the critical point is the endpoint where the current value sensed by the current transformer changes from large to small and then from small to large, and the critical point represents the transition of the backup battery from a discharge state to a charge state.
[0047] In other words, the control module 30 can provide a fluctuating pulse, and accordingly, the current transformer can sense the current value. During the startup process of the generator 10, the output voltage of the control module 30 will continue to increase, and finally after it exceeds the output voltage of the backup battery, the generator 10 will charge the backup battery. Therefore, the current change of the backup battery is that after the generator 10 is connected, the output current continues to decrease, and then when the generator 10 charges the backup battery, the output current continues to increase. Therefore, the endpoints of the current value detected by the current transformer from large to small and then from small to large can be used as critical points to determine the turning point of charging and discharging of the backup battery. Therefore, the output voltage of the rectifier module aligned with the critical point time can be determined to be consistent with the output voltage of the backup battery, and then the output voltage is used as the continuous output voltage of the rectifier module 20.
[0048] It can be seen that a non-access voltage regulation method is provided in the embodiment of the present application. It is not necessary to readjust the lines inside the base station. Instead, the output voltage is regulated by controlling the rectifier module 20 to output pulses with a step-up, and receiving the current value sensed by the current transformer. This method can be applied to the scenario where the above-mentioned base station is only pre-deployed with a backup battery. In other words, any base station (including a backup battery) can be installed and configured using the base station controllable power generation device 100 provided in the embodiment of the present application after the mains power is disconnected, and the effect of the generator 10 not supplying the backup battery can be achieved.
[0049] Optionally, the control module 30 is further configured to: control the rectifier module 20 to output pulses, and the voltage of the pulse is pulled up once in each control stage to form a step-up trend.
[0050] The number of cycles in each control stage is T, and the range of T is 3~5.
[0051] Optionally, the voltage fluctuation amplitude set in each control stage is A; wherein the range of A is 0.5V~1.5V; the frequency of the voltage waveform set in each control stage is f; wherein the range of f is 5Hz~20Hz; the number of times the voltage standard waveform appears in each control stage is Q, Q is greater than or equal to 2; wherein, the voltage standard waveform is the voltage fluctuation amplitude A and the frequency f.
[0052] The pulse diagram can be found in Figure 3 .
[0053] It should be noted that, considering that in the actual application process, the load equipment in the base station also fluctuates dynamically, there will be a situation where the voltage fluctuation and the load fluctuation offset each other, which will affect the accuracy of the subsequent monitoring of the state parameters of the backup battery. Therefore, in the embodiment of the present application, the fluctuating pulse output by the rectifier module 20 is configured to ensure that the number of cycles in each control stage is 3 to 5, and after the number of times the voltage standard waveform appears in each control stage is Q (greater than or equal to any set value in 2), it is pulled up again. In this way, occasional overlaps are avoided, interference is reduced, and the accuracy of the subsequent monitoring of the state parameters of the backup battery is improved.
[0054] The first access deployment method is described in detail below.
[0055] Optionally, the detection device 40 can be a voltage detection circuit; one end of the voltage detection circuit is connected to the output end of the backup battery, and the other end of the voltage detection circuit is connected to the control module 30; the voltage detection circuit is used to detect the output voltage of the backup battery; the control module 30 is specifically configured to: compare the output voltage of the rectifier module 20 with the output voltage of the backup battery, and when the output voltage of the rectifier module 20 is consistent with the output voltage of the backup battery, control the rectifier module 20 to provide stable power supply with the output voltage; wherein the output voltage of the backup battery is the acquired state parameter of the backup battery.
[0056] That is, in access-type deployment, a voltage detection deployment method can be directly adopted to directly obtain the output voltage of the backup battery for comparison, so as to achieve more accurate regulation of the output voltage of the generator.
[0057] In one embodiment, the circuit diagram of the voltage detection circuit can refer to Figure 4 .
[0058] like Figure 4As shown, the voltage detection circuit includes: a first operational amplifier, a capacitor C1, a capacitor C2, a capacitor C3, a resistor R4, a resistor R5, a resistor R6, a resistor R7, and a resistor R8.
[0059] The first input terminal (-pin) of the first operational amplifier is connected to the resistor R4, and the first input terminal (-pin) of the first operational amplifier is also connected to the first end of the resistor R5. The second end of the resistor R4 is grounded, and the second end of the resistor R5 is connected to the output terminal of the first operational amplifier.
[0060] The second input terminal (+ pin) of the first operational amplifier is connected to the first end of the resistor R6 and the first end of the resistor R7. The second end of the resistor R6 is used to connect to the DC bus (corresponding to the output end of the backup battery, usually +48V). The second end of the seventh resistor R7 is grounded.
[0061] The output end of the first operational amplifier is also connected to the first end of the resistor R8, the second end of the resistor R8 is connected to the first end of the capacitor C1, the first end of the capacitor C2 and the first end of the capacitor C3; the second end of the capacitor C1, the second end of the capacitor C2 and the second end of the capacitor C3 are all grounded; the first end of the capacitor C2 (PA2-ADC1-2) is also connected to the control module 30.
[0062] Optionally, the detection device 40 can also be a current detection circuit; one end of the current detection circuit is connected to one end of the backup battery, and the other end of the current detection circuit is connected to the control module 30; the current detection circuit is used to detect the output current of the backup battery; the control module 30 is specifically configured as: based on the output current of the backup battery, determine the output voltage of the rectifier module 20 aligned with the critical point time; wherein the output voltage of the rectifier module 20 aligned with the critical point time is consistent with the output voltage of the backup battery; the critical point is the endpoint where the output current of the backup battery changes from large to small and then from small to large, and the critical point represents that the backup battery changes from a discharge state to a charging state; wherein the output current of the battery is the acquired state parameter of the battery.
[0063] It should be noted that the logic of controlling by current detection has been described in the aforementioned non-accessible monitoring method, and the same parts can be referred to each other and will not be described in detail here.
[0064] In one embodiment, the circuit diagram of the current detection circuit can refer to Figure 5 .
[0065] See also Figure 5 Optionally, the current detection circuit includes: a second operational amplifier, a resistor R9, a resistor R10, a capacitor C4, a capacitor C5, a capacitor C6 and a capacitor C7.
[0066] The first input terminal (pin -) of the second operational amplifier is connected to the output terminal of the second operational amplifier.
[0067] The second input terminal (pin +) of the second operational amplifier is connected to the first terminal of the resistor R9, and the second terminal of the resistor R9 is used to be connected to the backup battery.
[0068] The output end of the second operational amplifier is connected to the first end of the resistor R10, the second end of the resistor R10 is connected to the first end of the capacitor C4, the first end of the capacitor C5 and the first end of the capacitor C6, the second end of the capacitor C4, the second end of the capacitor C5 and the second end of the capacitor C6 are grounded; the first end of the capacitor C5 (PA0-ADC1-0) is also connected to the control module 30.
[0069] A power supply terminal of the second operational amplifier is connected to a power supply (VDD5) and a first terminal of a capacitor C7, and a second terminal of the capacitor C7 is grounded.
[0070] Optionally, the control module 30 is further configured to determine that the mains power supply is disconnected if the output current detected by the current detection circuit is received after the output current of the current detection circuit is not received within a preset time period.
[0071] The above-mentioned preset time period can be 1 hour, 5 hours, 10 hours, etc., and this application is not limited thereto.
[0072] That is, the embodiment of the present application provides a method for determining whether the AC power supply is disconnected. Under normal circumstances, the backup battery will remain fully charged during the AC power supply. At this time, the backup battery will not provide current output. If the output current of the current detection circuit is not received within a preset time period, and the output current detected by the current detection circuit is suddenly received, it indicates that the backup battery has started and is working, which further indicates that the AC power supply is disconnected. It can be seen that through this method, the start-up of the generator 10 after the AC power supply can be quickly responded.
[0073] Optionally, the control module 30 includes a controller and a voltage regulating module; the controller is connected to the voltage regulating module; the controller is configured to: adjust the output voltage of the rectifier module 20 to be consistent with the output voltage of the backup battery, and control the rectifier module 20 to provide stable power supply with the output voltage.
[0074] Optionally, the power ratio of the generator 10 is K times the load power of the load equipment of the base station; wherein the range of K is 1.2-1.4.
[0075] It should be noted that, due to the characteristics of the base station load, the generator 10 is generally configured to be about 1.5 times the equipment load of the base station, which causes waste of resources, waste of fuel consumption, and low economic benefits. Therefore, in the embodiment of the present application, the ratio of the power of the generator 10 to the load equipment of the base station is reduced to 1.2~1.4 times, thereby reducing the investment and construction costs of the base station.
[0076] Optionally, the generator 10 includes: an internal combustion engine and a permanent magnet generator; the internal combustion engine is used to burn fuel to provide source power for the permanent magnet generator; the permanent magnet generator is used to rotate to generate electricity and provide it to the rectifier module 20, so that the rectifier module 20 outputs a DC voltage.
[0077] It should be noted that, in the description of the present application specification and the appended claims, the terms "first", "second", "third", etc. are only used to distinguish the descriptions and cannot be understood as indicating or implying relative importance.
[0078] References to "one embodiment" or "some embodiments" etc. described in the specification of this application mean that one or more embodiments of the present application include specific features, structures or characteristics described in conjunction with the embodiment. Therefore, the statements "in one embodiment", "in some embodiments", "in some other embodiments", "in some other embodiments", etc. that appear in different places in this specification do not necessarily refer to the same embodiment, but mean "one or more but not all embodiments", unless otherwise specifically emphasized in other ways. The terms "including", "comprising", "having" and their variations all mean "including but not limited to", unless otherwise specifically emphasized in other ways.
[0079] In the description of the embodiments of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "install", "connect", "connect", and "assemble" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0080] In the description of the embodiments of the present invention, specific features, structures, materials or characteristics may be combined in a suitable manner in any one or more embodiments or examples.
[0081] In the description of the embodiments of the present invention, it should be understood that "-" and "~" represent a range between two values, and the range includes the endpoints. For example, "AB" represents a range greater than or equal to A and less than or equal to B. "A~B" represents a range greater than or equal to A and less than or equal to B.
[0082] In the description of the embodiments of the present invention, the term "and / or" herein is merely a description of the association relationship of associated objects, indicating that three relationships may exist. For example, A and / or B may represent: A exists alone, A and B exist at the same time, and B exists alone. In addition, the character " / " herein generally indicates that the associated objects before and after are in an "or" relationship.
[0083] Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A controllable power generation device for a base station, It is characterized in that include: Generator, rectifier module, control module and testing equipment; The generator is connected to the rectifier module; the control module is connected to the rectifier module and the detection device respectively; The output end of the rectifier module is connected to the DC bus of the base station, and the DC bus is also connected to the load device of the base station and the backup battery of the base station; the detection device is used to monitor the state parameters of the backup battery; The control module is configured to: in response to determining that the mains power supply is disconnected, continuously obtain the state parameters of the backup battery collected by the detection device, and when it is determined that the output voltage of the rectifier module is consistent with the output voltage of the backup battery, control the rectifier module to stably supply power with the output voltage; Wherein, the detection device is a current transformer or a current detection circuit; When the detection device is the current transformer, the current transformer is connected to the control module; when in use, the current transformer is used to be mounted on the connection line between the backup battery and the DC bus; the control module is further configured to: control the rectifier module to output a pulse with a step-up, and receive the current value sensed by the current transformer; determine the output voltage of the rectifier module aligned with the critical point time based on the current value sensed by the current transformer; wherein the output voltage of the rectifier module aligned with the critical point time represents the same as the output voltage of the backup battery; the critical point is the end point where the current value sensed by the current transformer changes from large to small and then from small to large, and the critical point represents that the backup battery changes from a discharge state to a charge state; When the detection device is the current detection circuit, one end of the current detection circuit is connected to one end of the backup battery, and the other end of the current detection circuit is connected to the control module; the current detection circuit is used to detect the output current of the backup battery; the control module is specifically configured to: determine the output voltage of the rectifier module aligned with the critical point time based on the output current of the backup battery; wherein the output voltage of the rectifier module aligned with the critical point time represents consistency with the output voltage of the backup battery; the critical point is the endpoint where the output current of the backup battery changes from large to small and then from small to large, and the critical point represents that the backup battery changes from a discharge state to a charge state; wherein the output current of the backup battery is a state parameter of the backup battery.
2. The base station controllable power generation device according to claim 1, It is characterized in that The control module is further configured to: control the rectifier module to output pulses, and the voltage of the pulses is pulled up once in each control stage to form a step-up trend; The number of cycles in each control stage is T, and the range of T is 3~5.
3. The base station controllable power generation device according to claim 2, It is characterized in that The voltage fluctuation amplitude set in each control stage is A; Among them, the range of A is 0.5V~1.5V; The frequency of the voltage waveform set in each control stage is f; Among them, the range of f is 5Hz~20Hz; The number of times the voltage standard waveform appears in each control stage is Q, and Q is greater than or equal to 2; wherein the voltage standard waveform is a voltage fluctuation amplitude of A and a frequency of f.
4. The base station controllable power generation device according to claim 1, It is characterized in that The control module is further configured to determine that the mains power supply is disconnected if the output current detected by the current detection circuit is received after the output current of the current detection circuit is not received within a preset time period.
5. The base station controllable power generation device according to claim 1, It is characterized in that The control module includes a controller and a voltage regulating module; The controller is connected to the voltage regulating module; the controller is configured to: adjust the output voltage of the rectifier module to be consistent with the output voltage of the backup battery, and control the rectifier module to provide stable power supply with the output voltage.
6. The base station controllable power generation device according to claim 1, It is characterized in that The power ratio of the generator is K times the load power of the load equipment of the base station; Among them, the range of K is 1.2~1.
4.
7. The base station controllable power generation device according to claim 1, It is characterized in that The generator comprises: an internal combustion engine and a permanent magnet generator; The internal combustion engine is used to burn fuel to provide source power for the permanent magnet generator; The permanent magnet generator is used for rotating to generate electric power and providing it to the rectifier module, so that the rectifier module outputs a direct current voltage.