Method for installing passive containment cooling auxiliary water tank of nuclear power station

Through the modular construction method, the passive containment cooling auxiliary water tank of the nuclear power plant is assembled step by step. The flip-chip method and modular construction are used to solve the problems of large construction investment and high safety risks in the traditional installation method, and achieve efficient and safe installation. process.

CN118744293APending Publication Date: 2024-10-08CHINA NUCLEAR IND FIFTH CONSTR CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411091582.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-08
Publication Date
2024-10-08

AI Technical Summary

Technical Problem

The traditional installation method of the passive containment cooling auxiliary water tank of a nuclear power plant has the problems of large construction investment, high safety risks, and long construction period, and the traditional flip-chip method is not suitable for the installation of this equipment.

Method used

Adopting a modular construction method, it is divided into step 1: determine the construction center and assemble the tank bottom plate, step 2: assemble the tank roof module outside the construction center, step 3: construct annular reinforcement modules and tank wall modules at the tank bottom plate, step 4 : Construct the vertical stiffener module between the stiffener module and the tank wall module. Step 5: Hoist and assemble and weld the tank roof module. Use the inversion method and modular construction to improve efficiency and safety.

Benefits of technology

Modular construction improves construction efficiency, reduces safety risks, and solves the difficulty of installing tank roofs in traditional methods, achieving an efficient and safe installation process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118744293A_ABST
    Figure CN118744293A_ABST
Patent Text Reader

Abstract

The invention provides a nuclear power station passive containment cooling auxiliary water tank mounting method which comprises the following steps: determining a construction center, and assembling a tank bottom plate; a tank top module is assembled on the outer side of the construction center; an annular reinforcing rib module and a tank wall module are constructed on a tank bottom plate; wherein the annular reinforcing rib module is positioned in the tank wall module; after construction of the reinforcing rib modules and the tank wall modules is completed, vertical reinforcing rib modules are constructed between the annular reinforcing rib modules and the tank wall modules; and after construction of the vertical reinforcing rib modules is completed, the tank top modules are hoisted to the tops of the tank wall modules, assembly welding connection is conducted, and installation is completed. According to the mounting method, the tank top module, the annular reinforcing rib module and the tank wall module are separately constructed, so that the annular reinforcing rib module and the tank wall module can be constructed by adopting an inverted mounting method, and the tank top module, the annular reinforcing rib module and the tank wall module can be constructed in parallel, so that the construction efficiency is favorably improved, and the overall construction safety is higher.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of auxiliary water tank installation in nuclear power plants, and in particular to a method for installing an auxiliary water tank for passive containment cooling in a nuclear power plant. Background Art

[0002] The structure of the passive containment cooling auxiliary water tank of a nuclear power plant is different from that of a traditional single-capacity tank. It is a carbon steel storage tank with an inner and outer double-layer structure. The internal structure plays a reinforcing role and improves its seismic resistance.

[0003] There are two traditional methods for on-site assembly and installation of storage tanks: upright installation and inverted installation. The upright installation method is a bottom-up storage tank assembly method, which first assembles the tank bottom plate and the bottommost tank wall plate, and then assembles layer by layer until the tank top plate is assembled.

[0004] During the assembly process, the upright method requires the construction of scaffolding on the inside and outside of the tank layer by layer, and the tank is raised layer by layer in accordance with the progress of the tank installation. During the construction, the workers are always working at a height. In addition, when the passive containment cooling auxiliary water tank is installed by the upright method, the internal structure and the tank body are cross-constructed, the installation environment is complex, the construction investment is large, the safety risk is high, and the construction period is long.

[0005] The inverted assembly method is a top-down tank assembly method. After the tank bottom plate is assembled, the topmost tank wall plate is assembled first. An electric hoist or hydraulic jacking device is used to lift the assembled tank wall plate, and then the next layer of wall plate is assembled. The lifting and assembly are completed layer by layer until the entire tank wall is assembled.

[0006] The inverted installation method requires relatively little construction investment. Since the operation is always carried out at the height of the first layer of tank wall panels, the safety risk is relatively small and the construction efficiency is high.

[0007] However, the lifting height of the tank wall panel in the inverted installation method needs to be higher than the width of the next layer of wall panels, so the electric hoist column or hydraulic lifting device column used for lifting needs to be higher than the top circle wall panel, and the tank top plate needs to be opened or cannot be installed. At the same time, due to the reinforcement rib structure inside the passive containment cooling auxiliary water tank, after the tank top plate is installed by the inverted installation method, the reinforcement rib structure inside the tank will not be introduced from the top of the tank. Therefore, the traditional inverted installation method is not suitable for the installation of the passive containment cooling auxiliary water tank of a nuclear power plant.

[0008] Based on this, the inventor of the present application proposes a method for installing a passive containment cooling auxiliary water tank for a nuclear power plant, in order to solve the above-mentioned technical problems. Summary of the invention

[0009] The technical problem to be solved by the present invention is to overcome the defect of limited installation of passive containment cooling auxiliary water tanks for nuclear power plants in the prior art, and to provide a method for installing passive containment cooling auxiliary water tanks for nuclear power plants.

[0010] The present invention solves the above technical problems through the following technical solutions:

[0011] The present invention provides a method for installing a passive containment cooling auxiliary water tank for a nuclear power plant, which is characterized in that it includes:

[0012] Step 1: Determine the construction center and assemble the tank bottom plate;

[0013] Step 2, assembling the tank top module outside the construction center;

[0014] Step 3, constructing an annular reinforcement rib module and a tank wall module at the tank bottom plate; wherein the annular reinforcement rib module is located inside the tank wall module;

[0015] Step 4: after the reinforcement rib module and the tank wall module are constructed, a vertical reinforcement rib module is constructed between the annular reinforcement rib module and the tank wall module;

[0016] Step 5: After the construction of the vertical reinforcement rib module is completed, the tank top module is hoisted to the top of the tank wall module and welded to complete the installation.

[0017] According to one embodiment of the present invention, step 2 comprises:

[0018] Step 21, determining the assembly center of the tank top module, and setting at least three supporting columns at the assembly center;

[0019] Step 22: according to the number of top plates of the tank top module, a plurality of support columns are arranged around the assembly center and tank top wall plates are arranged around the support columns;

[0020] Step 23: Lay the top plate and weld it together to form the tank top module.

[0021] According to one embodiment of the present invention, in step 21,

[0022] Before constructing the top plate, a tank top center ring is constructed on the top of the support column, one end of the top plate is connected to the tank top center ring, and the other end is connected to the tank top wall plate.

[0023] According to one embodiment of the present invention, in step 23,

[0024] The top plates are laid in sequence in an interval and symmetrical manner; wherein,

[0025] The number of the support columns is at least half of the number of the top plates.

[0026] According to an embodiment of the present invention, in step 3, both the tank wall module and the annular reinforcement rib module include a plurality of assembly units, and both the tank wall module and the annular reinforcement rib module are constructed by an inverted assembly method.

[0027] According to one embodiment of the present invention, in step 3,

[0028] The tank wall module and the annular reinforcement rib module are constructed synchronously.

[0029] According to one embodiment of the present invention, step 3 comprises:

[0030] Step 31, setting a mounting pier on the tank bottom plate, and setting a positioning plate on the pier;

[0031] Step 32, arranging a lifting column on the tank bottom plate;

[0032] Step 33: Use the lifting column to sequentially hoist the assembly units of the tank wall module and / or the annular reinforcement rib module to complete the assembly.

[0033] According to one embodiment of the present invention, step 4 comprises:

[0034] Step 41, erecting a scaffold between the annular reinforcement rib module and the tank wall module, and using a scaffold work platform to mark the installation position line of the vertical reinforcement rib on the tank bottom plate, the annular reinforcement rib module and the tank wall module;

[0035] Step 42, perform pre-welding cleaning, and sequentially hoist the vertical reinforcement ribs, the annular reinforcement ribs and the tank wall module for assembly.

[0036] According to one embodiment of the present invention, in step 5,

[0037] A target crane and lifting conditions are selected according to the weight of the tank top module to complete the assembly of the tank top module and the tank wall module.

[0038] According to one embodiment of the present invention, a guiding and positioning mechanism is provided between the top of the tank wall module and the bottom of the tank roof module.

[0039] The positive and progressive effects of the present invention are:

[0040] According to the installation method of the passive containment cooling auxiliary water tank for a nuclear power plant of the present invention, the tank top module is constructed separately from the annular reinforcement rib module and the tank wall module, so that the annular reinforcement rib module and the tank wall module can be constructed by an inverted installation method, and the tank top module, the annular reinforcement rib module and the tank wall module can be constructed in parallel, which is beneficial to improving the construction efficiency and has higher overall safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0041] The above and other features, properties and advantages of the present invention will become more apparent through the following description in conjunction with the accompanying drawings and embodiments, in which:

[0042] Figure 1 It is a flow chart of the method for installing the passive containment cooling auxiliary water tank of a nuclear power plant according to the present invention;

[0043] Figure 2 The following is a construction flow chart of the tank bottom plate of the present invention;

[0044] Figure 3 This is a construction flow chart of the tank top module of the present invention;

[0045] Figure 4 It is a construction flow chart of the tank wall module, the annular reinforcement rib module and the vertical reinforcement rib module of the present invention;

[0046] Figure 5 It is a schematic diagram of the hoisting of the tank top module and the tank wall module of the present invention;

[0047] Figure 6 Schematic diagram of the water tank after lifting. DETAILED DESCRIPTION

[0048] The present invention is further described below in conjunction with specific embodiments and drawings. More details are elaborated in the following description to facilitate a full understanding of the present invention. However, the present invention can obviously be implemented in a variety of other ways different from the description herein. Those skilled in the art can make similar generalizations and deductions based on actual application situations without violating the connotation of the present invention. Therefore, the protection scope of the present invention should not be limited by the content of this specific embodiment.

[0049] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by technicians in the technical field to which this application belongs; the terms used herein are only for the purpose of describing specific embodiments and are not intended to limit this application; the terms "including" and "having" in the specification and claims of this application and the above-mentioned figure descriptions and any variations thereof are intended to cover non-exclusive inclusions.

[0050] Please refer to Figure 1 The present invention proposes a method for installing a passive containment cooling auxiliary water tank for a nuclear power plant, comprising:

[0051] S1. Determine the construction center and assemble the tank bottom plate.

[0052] Please refer to Figure 2 First, determine the construction center according to the orientation of the design plan, and make marking lines on the top and side surfaces of the foundation concrete. The marking lines are used to provide a construction benchmark for the later assembly of the annular reinforcement module and the vertical reinforcement module.

[0053] Then, according to the tank bottom layout, draw the center line position diagram of the middle plate pad on the foundation leveling layer. And lay the pad according to the center line of the pad. When laying the pad, the T-joint is not welded, and other joints are welded, and the welds are polished to be flush with the pad.

[0054] Use a crane to lift the tank bottom plate for assembly. First lay the outer ring plate, then lay the center middle plate. The cross line of the middle plate should coincide with the center line of the tank bottom foundation. Finally, lay other middle plates, adjust the assembly gap to make sure it is correct, and then spot weld to fix the position of each plate.

[0055] S2. Assemble the tank top module outside the construction center.

[0056] Please refer to Figure 3 , step 2 includes:

[0057] Step 21, determine the assembly center of the tank top module, and set at least three supporting columns at the assembly center; before constructing the top plate, construct the tank top center circle on the top of the supporting column, one end of the top plate is connected to the tank top center circle, and the other end is connected to the tank top wall plate.

[0058] Step 22: According to the number of roof panels of the tank roof module, multiple support columns are arranged around the assembly center and tank roof wall panels are arranged around the support columns. For example, two support columns are arranged for every three adjacent roof panels, and the two support columns support the roof panels on opposite sides, and the roof panel in the middle is overlapped on the roof panels on the adjacent sides. Alternatively, one or more support columns may be arranged under each roof panel, which is not limited here.

[0059] Step 23, laying the top plates and welding them together to form a tank top module. The top plates are laid in sequence in an interval and symmetrical manner; and the number of support columns is at least one-half of the number of top plates.

[0060] It should be noted that the assembly center of the roof assembly module is located near the construction center and does not coincide with the position of the tank bottom plate. Therefore, the annular reinforcement module and the tank wall module constructed on the tank roof module and the tank bottom plate do not affect each other and can be constructed synchronously.

[0061] That is, before assembling the top plate, at least three supporting columns are arranged at the center of the assembly. The present invention is described by taking four supporting columns as an example, but the number of supporting columns is not limited.

[0062] Then, a tank top center circle is arranged on the supporting columns. The supporting columns can be connected and reinforced by connecting pieces, and the height of the supporting columns corresponds to the height of the tank top module.

[0063] Furthermore, the top plates are hoisted in clockwise or counterclockwise directions, and after being assembled in place, the chain and tooling are adjusted to ensure that the misalignment and assembly gap between the top plates meet the requirements. After the weld gap, misalignment and radius are adjusted to meet the requirements, the groove is cleaned and spot welded. To control the deformation, the longitudinal seam is welded in sections from bottom to top.

[0064] After the top plate is welded, install the edge angle steel. The edge angle steel should be installed close to the tank wall. If the gap is large, it should be adjusted before welding.

[0065] After the installation of the edging angle steel is completed, the center top plate of the tank is installed. The center top plate of the tank is installed on the center ring of the tank top. After the center top plate of the tank is installed in place, the orientation and horizontality of the center ring of the tank top are adjusted to meet the requirements of the design drawings. After passing the requirements, the center ring of the tank top is welded and fixed to the supporting columns to prevent the center top plate of the tank from moving.

[0066] To facilitate later assembly, the tank top module includes a tank top and a tank top wall plate. Multiple top plates are assembled to form the tank top. The tank top wall plate is arranged under the tank top and connected to the tank top. The tank top wall plate also corresponds to the topmost plate of the tank wall module.

[0067] That is, after the construction of the center top plate of the tank is completed, the top plate is welded to the tank top wall plate. Among them, the tank top wall plate corresponds to the top plate of the tank wall module. Welding the top plate of the tank wall module to the top plate is to facilitate the alignment of the tank top module and the tank wall module during assembly, which is beneficial to improving the welding quality between the tank top module and the tank wall module.

[0068] For the top plate, the top plate adopts a symmetrical installation method, and the top plate is hoisted in turn in a clockwise direction from four equally divided azimuths. Before the tank top is installed, the position of each top plate should be marked on the edge angle steel to control the tank top orientation during installation.

[0069] S3. construct an annular reinforcement rib module and a tank wall module at the tank bottom plate; wherein the annular reinforcement rib module is located inside the tank wall module.

[0070] Specifically, the annular reinforcement module, the tank wall module and the tank top module can be constructed simultaneously, or the annular reinforcement module and the tank wall module can be constructed simultaneously according to the actual construction progress, and the tank wall module can be constructed afterwards or before, without specific limitation.

[0071] Please refer to Figure 4 The tank wall module and the annular reinforcement rib module both include multiple assembly units, and the tank wall module and the annular reinforcement rib module are both constructed using the inverted assembly method.

[0072] Specifically, the tank wall module includes a plurality of tank wall assembling units along its axial direction, and the annular reinforcement rib includes a plurality of annular reinforcement rib assembling units along its axial direction.

[0073] Among them, the tank wall module and the annular reinforcement rib module can be constructed simultaneously.

[0074] It should be noted that step 3 includes:

[0075] Step 31, setting a mounting pier on the tank bottom plate, and setting a positioning plate on the pier;

[0076] Step 32, setting a lifting column on the tank bottom plate;

[0077] Step 33: Use the lifting columns to sequentially hoist the assembly units of the tank wall module and / or the annular reinforcement rib module to complete the assembly.

[0078] For the tank wall module, the topmost tank wall assembly unit of the tank wall module is also assembled together with the topmost wall panel and the tank top, and the other assembly units are constructed by the inverted installation method.

[0079] For the annular reinforcement module, all assembly units are constructed using the inverted assembly method.

[0080] Specifically, temporary piers for assembling the tank wall modules are first installed and evenly distributed on the tank wall radius marking line. Positioning plates are installed on the piers, and the positioning plates are fixed to the piers by spot welding.

[0081] The radial positioning block is welded on the positioning plate according to the inner wall radius marking line of the tank wall module, and the adjustment block is welded 50mm away from the outer wall radius of the tank wall module. The inner and outer blocks should be on the same radius line and spot welded with the locking code plate at the corresponding position, so that the tank wall module can be positioned and locked after it is in place and the assembly gap can be adjusted.

[0082] Then, hoist the second top tank wall assembly units in clockwise direction, and adjust their positions with fall chains and tooling after assembly to ensure that the misalignment and gap between tank wall assembly units and the radius of tank wall assembly units meet the requirements. Spot weld the arc reinforcement plate, and fix the tank wall plate with inclined supports to prevent overturning.

[0083] Lifting columns are evenly arranged along the circumference near the tank wall assembly unit in the tank. The tank wall assembly units can be lifted from bottom to top in sequence by means of the lifting columns, and the assembly welding can be completed in sequence.

[0084] Specifically, the lifting column is used to lift the sub-top tank wall assembly unit to the target height, and then the crane is used to lift the next tank wall assembly unit to the lower end of the sub-top wall panel for assembly and welding. At this time, the workers are all in a relatively low position for welding, so it is safer.

[0085] Then, the above-mentioned inverted assembly method is used to assemble the remaining tank wall assembly units in sequence, and then the temporary piers are removed, and the fillet welding of the tank wall plate and the bottom plate is completed. When welding the fillet weld, the inside of the tank is welded first, and then the outside of the tank is welded. During welding, the welders are evenly distributed and the welding is reversed in sections along the same direction.

[0086] After the bottom seam welding is completed, according to the design drawings, a temporary entrance and exit with a diameter smaller than the manhole is opened at the manhole position of the tank wall as a passage for personnel to enter the tank.

[0087] For the annular stiffener module, the construction method is similar to that of the tank wall module.

[0088] Specifically, temporary piers for assembling the annular reinforcement module are installed first, and the piers are evenly distributed on the radius identification line of the annular reinforcement module.

[0089] The positioning plate is installed on the pier and fixed to the pier with spot welding. The radial positioning block is welded on the positioning plate according to the inner wall radius marking line of the annular reinforcement rib module, and the adjustment block is welded at a radius of 50mm from the outer side of the tank wall plate. The inner and outer blocks should be on the same radius line and the locking code plate should be spot welded at the corresponding position so that the annular reinforcement rib plate module can be positioned and locked after it is in place and the assembly gap can be adjusted.

[0090] Lift the top-level annular reinforcement assembly unit into place, adjust the assembly gap, ensure the flatness and misalignment of the upper edge of the rib plate, and then proceed with welding.

[0091] A circle of lifting columns is evenly arranged near the inner side of the annular reinforcement module to lift the assembled annular reinforcement assembly unit.

[0092] After the welding of the annular reinforcement assembly unit is completed, the temporary piers are removed, and the hole opening work on the annular reinforcement assembly unit is completed by referring to the drawing of the annular reinforcement module, and then the corner weld between the annular reinforcement and the bottom plate is completed by referring to the installation position of the annular reinforcement assembly unit marked on the tank bottom plate.

[0093] S4. After the construction of the reinforcement rib module and the tank wall module is completed, the vertical reinforcement rib module is constructed between the annular reinforcement rib module and the tank wall module.

[0094] Please continue to refer to Figure 4 , step 4 includes:

[0095] Step 41, set up a scaffold between the annular reinforcement rib module and the tank wall module, and use the scaffold work platform to mark the installation position lines of the vertical reinforcement ribs on the tank bottom plate, the annular reinforcement rib module and the tank wall module;

[0096] Step 42: perform pre-welding cleaning, and sequentially hoist the vertical reinforcement ribs, the annular reinforcement ribs and the tank wall module for assembly.

[0097] That is, before installing the vertical reinforcement, scaffolding needs to be set up on both sides of the installation position as an installation work platform. The scaffolding work platform is used to mark the installation position lines of the vertical reinforcement on the tank bottom plate, the outer wall of the annular reinforcement and the storage tank, and the parts that need to be welded are cleaned before welding.

[0098] Use a crane to lift the vertical stiffeners from above the tank wall module into the tank and install them one by one. After passing the acceptance, the welding of the vertical stiffener module and the tank bottom plate is completed.

[0099] S5. After the construction of the vertical reinforcement module is completed, the tank top module is hoisted to the top of the tank wall module and welded to complete the installation.

[0100] Please refer to Figure 5 and Figure 6 After the construction of the tank top module is completed, the lifting lugs are installed at the center position from the center to the edge of the tank top. The number can be but is not limited to 8 and they are evenly distributed.

[0101] In order to ensure the accuracy of the assembly sequence of the tank top module and the tank wall module, a guiding and positioning mechanism is provided between the top of the tank wall module and the bottom of the tank top module.

[0102] In one embodiment, the guide positioning mechanism is a matching method of a guide column and a guide groove, and may also be other methods such as a snap fit, which is not limited here.

[0103] Furthermore, during actual lifting, the target crane and lifting conditions will be selected according to the weight of the tank top module to complete the assembly of the tank top module and the tank wall module.

[0104] Specifically, the crane installation approaches the site along a predetermined route and is positioned at the designated location. The crew inspects the positioned crane and conducts a test run to ensure that the crane is in good condition during lifting.

[0105] That is, after the top component reaches the predetermined position, it slowly drops the hook. When the bottom of the tank top module is about 20 to 50 mm away from the top of the tank wall module, the hook is stopped. At the same time, the riveter uses hemp rope to slightly adjust the position of the top component so that the positioning plates can be matched with each other to ensure the position. After determining the position, continue to drop the hook until the component is in place.

[0106] After adjusting the position to meet the requirements, continue to drop the hook until the top component is in place, assemble and spot weld it, and after the fixation is completed, continue to drop the hook and remove the sling.

[0107] After the tank top module is hoisted into place, the assembly and welding are completed.

[0108] In summary, the installation method of the passive containment cooling auxiliary water tank for a nuclear power plant of the present invention adopts modular construction, and the tank top module is constructed separately from the annular reinforcement rib module and the tank wall module. Therefore, the annular reinforcement rib module and the tank wall module can be constructed by the inverted installation method, and the tank top module, the annular reinforcement rib module and the tank wall module can be constructed in parallel, which is beneficial to improving construction efficiency and has higher overall safety.

[0109] Combining the inverted method, open-top method and modularization, it not only has the advantages of high construction efficiency, low safety risk and low engineering investment of the inverted method, but the open-top method also solves the problem of difficulty in introducing reinforcing rib structure inside the pipe, and the modular block construction realizes the parallel construction of the three, shortens the construction period and improves the overall construction efficiency.

[0110] In the description of the embodiments of the present application, unless otherwise clearly specified and limited, technical terms such as "install", "connect", "connect", "fixed" and the like should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral connection; it can also be a mechanical connection. For ordinary technicians in this field, the specific meanings of the above terms in the embodiments of the present application can be understood according to the specific circumstances.

[0111] The present application uses specific words to describe the embodiments of the present application. For example, "one embodiment", "an embodiment", and / or "some embodiments" refer to a certain feature, structure or characteristic related to at least one embodiment of the present application. Therefore, it should be emphasized and noted that "one embodiment" or "an embodiment" or "an alternative embodiment" mentioned twice or multiple times in different positions in this specification does not necessarily refer to the same embodiment. In addition, some features, structures or characteristics in one or more embodiments of the present application can be appropriately combined.

[0112] Although the present invention is disclosed as above with preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art may make possible changes and modifications without departing from the spirit and scope of the present invention. Therefore, any modification, equivalent change and modification made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solution of the present invention shall fall within the protection scope defined by the claims of the present invention.

Claims

1. A method for installing a passive containment cooling auxiliary water tank for a nuclear power plant, characterized in that: include: Step 1: Determine the construction center and assemble the tank bottom plate; Step 2, assembling the tank top module outside the construction center; Step 3, constructing an annular reinforcement rib module and a tank wall module at the tank bottom plate; wherein the annular reinforcement rib module is located inside the tank wall module; Step 4: after the reinforcement rib module and the tank wall module are constructed, a vertical reinforcement rib module is constructed between the annular reinforcement rib module and the tank wall module; Step 5: After the construction of the vertical reinforcement rib module is completed, the tank top module is hoisted to the top of the tank wall module and welded to complete the installation.

2. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 1, characterized in that: The step 2 comprises: Step 21, determining the assembly center of the tank top module, and setting at least three supporting columns at the assembly center; Step 22: according to the number of top plates of the tank top module, a plurality of support columns are arranged around the assembly center and tank top wall plates are arranged around the support columns; Step 23: Lay the top plate and weld it together to form the tank top module.

3. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 2, characterized in that: In the step 21, Before constructing the top plate, a tank top center ring is constructed on the top of the support column, one end of the top plate is connected to the tank top center ring, and the other end is connected to the tank top wall plate.

4. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 2, characterized in that: In step 23, The top plates are laid in sequence in an interval and symmetrical manner; wherein, The number of the support columns is at least half of the number of the top plates.

5. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 1, characterized in that: In the step 3, the tank wall module and the annular reinforcement rib module both include a plurality of assembly units, and the tank wall module and the annular reinforcement rib module are both constructed by an inverted assembly method.

6. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 5, characterized in that: In the step 3, The tank wall module and the annular reinforcement rib module are constructed synchronously.

7. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 5, characterized in that: The step 3 comprises: Step 31, setting a mounting pier on the tank bottom plate, and setting a positioning plate on the pier; Step 32, arranging a lifting column on the tank bottom plate; Step 33: Use the lifting column to sequentially hoist the assembly units of the tank wall module and / or the annular reinforcement rib module to complete the assembly.

8. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 1, characterized in that: The step 4 comprises: Step 41, erecting a scaffold between the annular reinforcement rib module and the tank wall module, and using a scaffold work platform to mark the installation position line of the vertical reinforcement rib on the tank bottom plate, the annular reinforcement rib module and the tank wall module; Step 42, perform pre-welding cleaning, and sequentially hoist the vertical reinforcement ribs, the annular reinforcement ribs and the tank wall module for assembly.

9. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 1, characterized in that: In step 5, A target crane and lifting conditions are selected according to the weight of the tank top module to complete the assembly of the tank top module and the tank wall module.

10. The method for installing a passive containment cooling auxiliary water tank for a nuclear power plant according to claim 9, characterized in that: A guiding and positioning mechanism is provided between the top of the tank wall module and the bottom of the tank roof module.