A steel cable winch assembly for bridge formwork hoisting construction

By designing the cable winch assembly and using the motor and tooth chain locking mechanism, the problems of offset and angle offset of the bridge formwork during climbing and moving are solved, lifting stability and safety are improved, and the quality differences of the template are automatically adapted to lifting adaptation.

CN118753965BActive Publication Date: 2024-11-19南通明林机械有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411237000.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-09-05
Publication Date
2024-11-19
Estimated Expiration
2044-09-05

AI Technical Summary

Technical Problem

The prefabricated bridge formwork is prone to offset and angular offset during climbing and moving, resulting in safety hazards and poor lifting adaptability, so it is impossible to automatically adapt to the quality differences of the template.

Method used

A steel cable winch assembly is designed, including a storage table, protective case, motor, noose drum, guidance mechanism and brake mechanism. The noose drum is driven to rotate through the motor, and the tooth sleeve is locked and locked with the motor and the tooth chain. Dead, use the signal transmission antenna and control panel to collect lifting information and risk control signal processing, and automatically adjust the cable wrapping and locking to ensure the stability and safety of the template.

Benefits of technology

It improves the stability and safety of bridge formwork lifting, reduces accident risks, ensures uniform winding of steel cables and lifting efficiency, and avoids template drops and angle offsets.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118753965B_ABST
    Figure CN118753965B_ABST
Patent Text Reader

Abstract

The present invention discloses a steel cable winch assembly for bridge formwork hoisting construction, relates to the technical field of bridge formwork hoisting construction, and is used to solve the problem that the precast bridge formwork is prone to deviation during its climbing and moving activities, and that the precast bridge formwork hoisting and adaptation work cannot be automatically performed. The present invention is to install four sets of protective shells around a storage platform, and the winch assembly located in the protective shells can perform multi-angle binding of the bridge formwork, thereby improving the overall bridge formwork hoisting stability. During the hoisting, the bridge formwork hoisting dynamic information is obtained through a pressure sensor installed in a fixed sleeve on a pad, and the hoisting risk is estimated. The control panel is synchronously operated and maintained to control the rotation of a motor in the shell and a motor on the protective shell, so as to control the bridge formwork hoisting distance and perform auxiliary locking of a gear sleeve on a winch drum wheel, thereby reducing the probability of accidental risks that may occur when subsequent hoists hoist and move the bridge formwork, and improving the safety of the entire bridge formwork hoisting construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of bridge formwork hoisting construction, and in particular to a steel cable winch assembly used for bridge formwork hoisting construction. Background Art

[0002] For the hoisting and use of bridge precast templates, check the size, quality, quantity, etc. of the components according to the construction drawings, check the number of the components entering the site, whether the reserved pipelines and reserved openings on the components have any deviations, and make detailed records. After binding the sling lock at the bottom of the crane or gantry with the bridge precast template, the displacement and transportation of the bridge precast template is carried out;

[0003] like Figure 1 As shown, the binding straps at the bottom of the support are fixed to both sides of the precast bridge formwork. The precast bridge formwork will shake during the movement. At the same time, due to the difference in quality on both sides during the preparation of the precast bridge formwork, the climbing activity of the hoist will easily cause the precast bridge formwork to have an angular deviation. In severe cases, the precast bridge formwork will easily fall off the hoist, posing a safety hazard. Summary of the invention

[0004] The purpose of the present invention is to provide a wire rope winch assembly for bridge formwork hoisting construction, so as to solve the problems raised in the above-mentioned background technology that the climbing and moving process of the bridge precast formwork is prone to deviation, and the bridge precast formwork hoisting adaptation work cannot be automatically performed.

[0005] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a wire rope winch assembly for bridge formwork hoisting construction, comprising a storage platform and a protective shell, the side wall of the storage platform is evenly and symmetrically installed with the protective shell by bolts, the top of the storage platform is fixed with a tower hoist by spot welding, the bottom of the storage platform is fixed with a central control column by spot welding, and the bottom of the central control column is fixedly connected with a pad;

[0006] A motor is fixed to the inner wall of the protective shell by bolts, a cable drum is fixedly connected to one side of the motor, a relay transmission is installed on the cable drum, a gear sleeve is fixedly mounted on the cable drum, a guide mechanism is fixedly connected to one side of the cable drum and located on the protective shell, and a braking mechanism is fixedly connected to one side of the protective shell and located on the gear sleeve.

[0007] Furthermore, the guiding mechanism includes a shell, a slide groove and a slider. The shell is fixed in the protective shell by bolts. A through groove is provided on the top of the shell. A slide groove is provided in the shell, and a slider is slidably connected in the slide groove. One end of the slider passes through the shell and is slidably connected to the through groove.

[0008] Furthermore, the guiding mechanism also includes a motor, transmission teeth and a lock. The motor is fixed to the inner wall of one side of the shell by bolts, and the inner wall of the shell is symmetrically and movably connected with transmission teeth on one side of the slide groove. A tooth chain is provided on two of the transmission teeth. The output end of the motor is fixed to one side of the transmission teeth, and a lock is fixedly connected to the tooth chain. A protrusion on one side of the lock is slidably connected to a hole on the slider, and the lock is located on one side of the slider, passes through the shell and is fixedly connected to a fixed disk.

[0009] Furthermore, the braking mechanism includes a sleeve, a block and a rotating rod. A sleeve is fixedly connected to the protective shell and located on one side of the gear sleeve. Blocks are symmetrically rotatably connected to the inner walls of both sides of the sleeve. A spring is fixedly connected to one side of the two blocks, and one side of the spring is connected to the inner wall of the sleeve. A rotating rod is movably connected to one side of the sleeve. One end of the rotating rod passes through the sleeve and is fixedly connected to an eccentric wheel. Both sides of the eccentric wheel are respectively abutted against one side of the two blocks.

[0010] Furthermore, the rotating rod is located on one side outside the ferrule and abuts against the fixed plate, and a guide rod is fixed to one side of the protective shell by bolts.

[0011] Furthermore, placement grooves are evenly opened on the pad, pillars are symmetrically connected to the inner walls of both sides of the placement grooves, fixing sleeves are symmetrically sleeved and connected in the placement grooves and on the pillars, and a signal transmission antenna is installed on the top of the pad.

[0012] Furthermore, the signal transmission antenna is used to send comprehensive information of bridge template hoisting and receive wind control signals. The signal transmission antenna sends the comprehensive information of bridge template hoisting to the control panel for processing, wherein the comprehensive information of bridge template hoisting consists of hoisting differential weight factor, hoisting swing amplitude factor and hoisting swing frequency factor;

[0013] The control panel includes a hoisting signal acquisition module and a hoisting signal processing module. The hoisting signal acquisition module is used to collect comprehensive information of bridge template hoisting. The hoisting signal processing module is used to supervise and correct the acquired comprehensive information of bridge template hoisting. The specific steps are as follows:

[0014] S1: calibrate the hoisting differential weight factor, hoisting swing amplitude factor and hoisting swing frequency factor in the comprehensive information of bridge template hoisting obtained by the hoisting signal acquisition module as Dz, Df and Dp;

[0015] S2: Obtain the lifting risk coefficient Y through formula processing, and compare the obtained lifting risk coefficient Y with the lifting risk coefficient threshold y stored in the control panel;

[0016] When Y≥y, a first-level hoisting wind control signal is generated, and the motor in the protective shell involved in the hoisting rotates, driving the cable drum to reel in the steel cable, shortening the distance between the bridge formwork and the pad, and cooperating with the hoisting device to move the bridge formwork;

[0017] At the same time, the control panel controls the motor in the housing to rotate, and the toothed chain on the transmission teeth rotates. The lock buckle at the bottom of the toothed chain is transformed into the top of the toothed chain. The rotation of the lock buckle drives the rotating rod in the ferrule to rotate, and the eccentric wheel squeezes the top block in the ferrule. The bottom block of the ferrule abuts against the toothed sleeve, completing the auxiliary locking of the entire toothed sleeve.

[0018] When Y<y, a secondary hoisting wind control signal is generated, and the hoisting device directly moves the bridge formwork. The top block in the clamping sleeve abuts against the gear sleeve to achieve the winding and locking of the noose drum.

[0019] Compared with the prior art, the present invention has the following beneficial effects:

[0020] In the present invention, the motor drives the cable drum to rotate, and the motor in the housing drives the transmission teeth to rotate, so as to realize the left and right movement of the lock buckle on the tooth chain, so that the steel cable passing through the slider is pulled and evenly wound on the surface of the cable drum, so that the steel cable is evenly distributed on the surface of the cable drum, and the problem of the steel cable being locked when directly winding and unwinding is avoided;

[0021] In the present invention, by installing four sets of protective shells around the storage platform, the winch assembly located in the protective shell can perform multi-angle binding of the bridge template, thereby improving the overall bridge template hoisting stability. During the hoisting, the bridge template hoisting dynamic information is obtained through the pressure sensor installed in the fixed sleeve on the pad, and sent to the control panel through the signal transmission antenna for hoisting risk estimation. The control panel is synchronously operated and maintained to control the rotation of the motor in the shell and the motor on the protective shell, to control the bridge template hoisting distance and the auxiliary locking of the gear sleeve on the noose drum, thereby reducing the probability of accidental risks when the subsequent hoisting equipment is used to hoist and move the bridge template, thereby improving the safety of the entire bridge template hoisting construction.

[0022] In the present invention, the movement of the lock buckle on the toothed chain drives the rotating rod in the sleeve to rotate, thereby completing the control of the rotation direction of the toothed sleeve on the entire cable drum wheel, and realizing the same frequency control of multiple groups of steel cable winches on the entire storage platform, thereby avoiding improper remote control by the operator, resulting in differences in the connection lengths of the same batch of steel cables, and affecting the subsequent lifting efficiency of the bridge formwork during leveling. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] Figure 1 This is a schematic diagram of the steel cable connection structure for the bridge formwork hoisting construction;

[0024] Figure 2 The overall structural diagram of the steel cable winch assembly invented for bridge formwork hoisting construction;

[0025] Figure 3 It is a schematic diagram of the connection structure between the winch assembly and the guide mechanism in the protective shell of the present invention;

[0026] Figure 4 It is a schematic diagram of the overall structure of the guiding mechanism of the present invention;

[0027] Figure 5 It is a schematic diagram of the connection structure between the brake mechanism of the present invention and the gear sleeve on the winch;

[0028] Figure 6 It is a schematic diagram of the abutment structure between the fixed disk and the inner rotating rod of the ferrule of the present invention;

[0029] Figure 7 It is a schematic diagram of the overall structure of the pad of the present invention.

[0030] In the figure: 1. storage table; 2. tower crane; 3. protective shell; 4. motor; 5. rope drum; 6. guiding mechanism; 601. shell; 602. slide groove; 603. through groove; 604. slider; 605. transmission gear; 606. tooth chain; 607. lock; 608. motor; 609. fixed plate; 7. gear sleeve; 8. braking mechanism; 801. clamping sleeve; 802. rotating rod; 803. eccentric wheel; 804. clamping block; 805. spring; 9. relay transmission; 10. guide rod; 11. pad; 12. placement groove; 13. fixing sleeve; 14. central control column; 15. pillar; 16. signal transmission antenna. DETAILED DESCRIPTION

[0031] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0032] See also Figure 1-7 , the present invention provides a technical solution:

[0033] Example 1: For the hoisting of the existing bridge template, considering the distance between the two sides of the bridge template, in order to ensure the overall stability during hoisting and avoid the problem of unhooking, a bracket is installed between the original hoists, such as Figure 1As shown, a strap is provided on the bracket, one end of which acts on the bridge template, and the crane or gantry is used for lifting and moving. Since the strap distance is fixed, the adaptability is low when lifting bridge templates of multiple sizes. During the lifting process, the bridge template shakes greatly, and there is a risk of the bridge template falling. For this reason, improvements are made to the original bracket, and two sets of steel cable winch assemblies are added to assist in the lifting of the bridge template, thereby improving the overall stability and safety of the bridge template lifting.

[0034] like Figure 2 As shown, a tower crane 2 is arranged on the top of the storage platform 1, which is responsible for connecting the crane with the storage platform 1. Two sets of protective shells 3 are fixed on the storage platform 1, and a wire rope winch assembly is installed in the protective shell 3, wherein the main body of the wire rope winch assembly is a motor 4 for providing power, a cable drum wheel 5 for winding the main body, an electrically controlled relay transmission 9 and a guide mechanism 6 for moving the wire rope. Different from the original cable guide, the entire shell 601 is moved by a slider 604 that moves left and right during the winding process, so that the winding of the wire rope on the cable drum wheel 5 is more regular;

[0035] like Figure 4 As shown, a through slot 603 is provided on the top of the housing 601, and a slide slot 602 is provided inside the housing 601 for limiting the movement of the slider 604. Meanwhile, a motor 608 is installed inside the housing 601, and the output end of the motor 608 is connected to the transmission gear 605. A tooth chain 606 is sleeved on the two transmission gears 605, and a lock buckle 607 is fixed on the tooth chain 606. The movement of the tooth chain 606 drives the lock buckle 607 to move synchronously, but the lock buckle 607 at the transmission gear 605 will rotate 180°. Therefore, when the lock buckle 607 rotates, the slider 604 in the slide slot 602 is in a stationary state.

[0036] The protrusion on one side of the lock buckle 607 abuts against the hole on the slider 604, and the movement of the lock buckle 607 also drives the slider 604 to move left and right. Under normal circumstances, when the motor 608 drives the lock buckle 607 on the toothed chain 606 to move, it will only drive the lock buckle 607 to move horizontally, and then rotate in the opposite direction after reaching the rotation point of the toothed chain 606, so that the left and right movement frequency of the lock buckle 607 remains consistent;

[0037] A fixing plate 609 is also provided on one side of the lock buckle 607 and penetrates the housing 601 and is fixedly connected thereto. Figure 6 As shown, the steel cable wound on the cable drum 5 passes through the slider 604 and follows the guide rod 10 on one side of the protective shell 3 to the top of the pad 11.

[0038] Embodiment 2: A placement groove 12 is provided on the entire pad 11, and pillars 15 are symmetrically fixed in the placement groove 12, and a fixing sleeve 13 is installed on the pillar 15. Since the steel cable needs to pass through the pillar 15 and be fixed to the bridge template, when the bridge template is pulled, part of the horizontal pressure of the steel cable will act on the pillar 15. A pressure sensor is installed in the fixing sleeve 13 on the pillar 15, and the initial signal of the bridge template lifting is collected according to the force given by the steel cable, including the lifting differential weight factor, the lifting amplitude factor and the lifting frequency factor;

[0039] The lifting differential weight factor is the difference in the lateral squeezing force of the steel cables on the two pillars 15 at the initial stage of lifting. The lifting sway amplitude factor is the maximum pressure difference value of the steel cables acting on the pillars 15 on both sides when the lifting is vertically lifted to a height of 2m. The lifting sway frequency factor is the number of pressure changes of the steel cables acting on the pillars 15 on both sides when the lifting is vertically lifted to a height of 2m.

[0040] After obtaining the relevant values, the pressure sensor in the fixed sleeve 13 sends the comprehensive information of the bridge template hoisting to the signal transmission antenna 16 on the pad 11, and then sends it to the control panel in the hands of the operator through the signal transmission antenna 16. The control panel includes a hoisting signal acquisition module and a hoisting signal processing module. The hoisting signal acquisition module obtains the pressure data signal sent by the pressure sensor on the fixed sleeve 13 in real time through the signal transmission antenna 16, and then completes the processing and analysis of the pressure data signal through the hoisting signal processing module;

[0041] After receiving the comprehensive information of bridge formwork hoisting, the control panel performs supervision and correction operations. The specific steps are as follows:

[0042] S1: The hoisting differential weight factor, hoisting swing amplitude factor and hoisting swing frequency factor in the acquired bridge formwork hoisting comprehensive information are calibrated as Dz, Df and Dp;

[0043] S2: Through the formula Y= , where a1, a2 and a3 are correction factors, and a1>a3>a2>0, a1+a2+a3=6.234, the hoisting risk coefficient Y is obtained by processing, and the obtained hoisting risk coefficient Y is compared with the hoisting risk coefficient threshold y stored in the control panel;

[0044] When Y≥y, a first-level hoisting wind control signal is generated, that is, during the hoisting process, when the original steel cable length remains unchanged, the difference in the forces on both sides of the bridge template during the hoisting process is large, or the bridge template at the bottom of the pad 11 shakes with a large amplitude and a high shaking frequency. In the subsequent movement process, the risk of the bridge template falling is also greater. At this time, the motor 4 in the protective shell 3 involved in the hoisting rotates, driving the cable drum 5 to reel in the steel cable, shortening the distance between the bridge template and the pad 11, and cooperating with the sling to move the bridge template. At this time, the winch assembly will automatically work to reel in the steel cable fixed on the entire bridge template, shortening the distance between the pad 11 and the bridge template, and the horizontal force on the pad 11 is increased, acting on the central control column 14, but the overall hoisting stability of the bridge template is improved;

[0045] At the same time, the control panel controls the motor 608 in the housing 601 to rotate, and the toothed chain 606 on the transmission tooth 605 rotates. The lock buckle 607 moves at the bottom of the toothed chain 606 and changes to move at the top of the toothed chain 606. The rotation of the lock buckle 607 drives the rotating rod 802 in the ferrule 801 to rotate, and the eccentric wheel 803 squeezes the top block 804 in the ferrule 801. The bottom block 804 of the ferrule 801 abuts against the toothed sleeve 7, completing the auxiliary locking of the entire toothed sleeve 7.

[0046] The motor 608 drives the lock 607 to move before the motor 4 drives the rope drum 5. Figure 4 , Figure 5 and Figure 6 From the above, it can be seen that the toothed chain 606 in the initial state drives the lock sleeve to move horizontally left and right, and does not rotate. When the first-level hoisting wind control signal is generated, the motor 608 at this time first drives the lock buckle 607 on the toothed chain 606 to rotate. A fixed disk 609 is connected to one side of the lock buckle 607. The fixed disk 609 abuts against the end of the rotating rod 802 on the ferrule 801, that is, the fixed disk 609 rotates while keeping the center different. At the same time, the entire rotating rod 802 is driven to rotate by the texture on the fixed disk 609. At this time, the rotation of the rotating rod 802 causes the bottom block 804 in the ferrule 801 to abut against the toothed sleeve 7.

[0047] At this time, when the motor 4 drives the rope drum 5 to rotate, the counterclockwise rotating gear sleeve 7 constantly contacts the block 804, and the block 804 acts on the spring 805 and will not affect the rotation of the gear sleeve 7. Then, after the steel cable is wound up, when the motor 4 stops rotating, the gear sleeve 7 wants to rotate clockwise at this time, but will be abutted by the bottom block 804, and the steel cable cannot be placed, thereby realizing auxiliary clamping of the steel cable during the lifting process to prevent damage to the motor 4 and cause the bridge formwork to fall off.

[0048] When Y<y, a secondary hoisting wind control signal is generated, and the hoist directly moves the bridge template, and the top block 804 in the clamping sleeve 801 abuts against the gear sleeve 7, so that the rope drum 5 is rolled up and locked;

[0049] At this time, the top block 804 of the clamping sleeve 801 abuts against the gear sleeve 7, and the motor 4 cannot rotate the cable drum 5 to reel in the cable, thereby ensuring that the hoisting height of the same batch of bridge templates remains consistent, and the length difference between the connecting cables will not occur due to the reeling work of the motor 4 on one side;

[0050] By installing four groups of protective shells 3 around the storage table 1, the winch assembly located in the protective shell 3 can perform multi-angle binding of the bridge template, thereby improving the overall stability of the bridge template hoisting. During the hoisting, the dynamic information of the bridge template hoisting is obtained through the pressure sensor installed in the fixed sleeve 13 on the pad 11, and the hoisting risk is estimated in the control panel. The control panel is operated and maintained synchronously, and the braking mechanism 8 works synchronously to control the rotation of the motor 608 in the shell 601 and the motor 4 on the protective shell 3, so as to control the hoisting distance of the bridge template and the auxiliary locking of the gear sleeve 7 on the noose drum wheel 5, thereby reducing the probability of unexpected risks when the subsequent hoisting equipment is used to hoist and move the bridge template, thereby improving the safety of the entire bridge template hoisting construction.

[0051] The working process and principle of the present invention are as follows:

[0052] The bridge template is bound with steel cables on both sides and hoisted. First, the hoist lifts the storage platform 1 and the bridge template connected by the steel cables. At this time, the pressure sensor in the fixed sleeve 13 on the support 15 collects the initial pressure signal of the bridge template hoisting according to the force given by the steel cables, and generates a corresponding control signal after processing by the control panel;

[0053] For the generated first-level hoisting wind control signal, the motor 608 at this time first drives the lock buckle 607 on the toothed chain 606 to rotate, and a fixed disk 609 is connected to one side of the lock buckle 607, and the fixed disk 609 abuts against the end of the rotating rod 802 on the sleeve 801, that is, the fixed disk 609 rotates with the center different, and at the same time relies on the texture on the fixed disk 609 to drive the entire rotating rod 802 to rotate. At this time, the rotation of the rotating rod 802 causes the bottom block 804 in the sleeve 801 to abut against the gear sleeve 7. At this time, when the motor 4 drives the cable drum 5 to rotate, the counterclockwise rotating gear sleeve 7 continuously contacts the block 804, and the block 804 acts on the spring 805, which will not affect the rotation of the gear sleeve 7. Then the steel cable is wound up to shorten the distance between the bridge template and the pad 11, and the bridge template is moved in cooperation with the sling;

[0054] The secondary lifting wind control signal is generated. At this time, the top block 804 of the sleeve 801 is in contact with the gear sleeve 7. At this time, the motor 4 cannot rotate the cable drum 5 to reel in the steel cable, ensuring that the lifting height of the same batch of bridge formwork remains consistent, and the hoisting equipment directly moves the bridge formwork.

[0055] The above contents are merely examples and explanations of the structure of the present invention. The technicians in this technical field may make various modifications or additions to the specific embodiments described or replace them in a similar manner. As long as they do not deviate from the structure of the invention or exceed the scope defined by the claims, they should all fall within the protection scope of the present invention.

[0056] In the description of this specification, the description with reference to the terms "one embodiment", "example", "specific example", etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present invention. In this specification, the schematic representation of the above terms does not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described can be combined in any one or more embodiments or examples in a suitable manner.

[0057] The preferred embodiments of the present invention disclosed above are only used to help explain the present invention. The preferred embodiments do not describe all the details in detail, nor do they limit the invention to only specific implementation methods. Obviously, many modifications and changes can be made according to the content of this specification. This specification selects and specifically describes these embodiments in order to better explain the principles and practical applications of the present invention, so that those skilled in the art can understand and use the present invention well. The present invention is limited only by the claims and their full scope and equivalents.

Claims

1. A wire rope winch assembly for bridge formwork hoisting construction, comprising a storage platform (1) and a protective shell (3), wherein the protective shell (3) is evenly and symmetrically mounted on the side wall of the storage platform (1) by bolts, It is characterized in that The top of the storage platform (1) is fixed with a tower crane (2) by spot welding, the bottom of the storage platform (1) is fixed with a central control column (14) by spot welding, and the bottom of the central control column (14) is fixedly connected with a pad (11); A motor (4) is fixed to the inner wall of the protective shell (3) by means of bolts, a cable drum (5) is fixedly connected to one side of the motor (4), a relay transmission (9) is mounted on the cable drum (5), a gear sleeve (7) is sleeved and fixed on the cable drum (5), a guide mechanism (6) is fixedly connected to one side of the cable drum (5) and located on the protective shell (3), and a brake mechanism (8) is fixedly connected to one side of the gear sleeve (7) on the protective shell (3); The guiding mechanism (6) comprises a shell (601), a slide groove (602) and a slider (604); the shell (601) is fixed in the protective shell (3) by bolts; a through groove (603) is provided on the top of the shell (601); a slide groove (602) is provided in the shell (601); a slider (604) is slidably connected in the slide groove (602); one end of the slider (604) passes through the shell (601) and is slidably connected to the through groove (603); The guide mechanism (6) further comprises a motor (608), a transmission tooth (605) and a lock (607); the motor (608) is fixed to an inner wall of one side of the housing (601) by means of bolts; the transmission tooth (605) is symmetrically and movably connected to the inner wall of the housing (601) and located on one side of the slide groove (602); a tooth chain (606) is sleeved on two of the transmission teeth (605); the output end of the motor (608) is fixed to one side of one of the transmission teeth (605); the lock (607) is fixedly connected to the tooth chain (606); a protrusion on one side of the lock (607) is slidably connected to a hole on the slider (604); the lock (607) is located on one side of the slider (604), penetrates the housing (601) and is fixedly connected to a fixing plate (609); The braking mechanism (8) comprises a clamping sleeve (801), a clamping block (804) and a rotating rod (802); the clamping sleeve (801) is fixedly connected to one side of the protective shell (3) and located on the gear sleeve (7); the inner walls of both sides of the clamping sleeve (801) are symmetrically rotatably connected to the clamping blocks (804); one side of the two clamping blocks (804) is fixedly connected to a spring (805), and one side of the spring (805) is connected to the inner wall of the clamping sleeve (801); one side of the clamping sleeve (801) is movably connected to the rotating rod (802); one end of the rotating rod (802) passes through the clamping sleeve (801) and is fixedly connected to an eccentric wheel (803); and the two sides of the eccentric wheel (803) are respectively in contact with one side of the two clamping blocks (804); A signal transmission antenna (16) is installed on the top of the pad (11), and the signal transmission antenna (16) is used to send comprehensive information on the hoisting of the bridge template and receive wind control signals. The signal transmission antenna (16) sends the comprehensive information on the hoisting of the bridge template to the control panel for processing, wherein the comprehensive information on the hoisting of the bridge template consists of a hoisting differential weight factor, a hoisting swing amplitude factor, and a hoisting swing frequency factor; The control panel includes a hoisting signal acquisition module and a hoisting signal processing module. The hoisting signal acquisition module is used to collect comprehensive information of bridge template hoisting. The hoisting signal processing module is used to supervise and correct the acquired comprehensive information of bridge template hoisting. The specific steps are as follows: S1: calibrate the hoisting differential weight factor, hoisting swing amplitude factor and hoisting swing frequency factor in the comprehensive information of bridge template hoisting obtained by the hoisting signal acquisition module as Dz, Df and Dp; S2: Through the formula Y= ,in, 1. 2 and 3 is the correction factor, and 1> 3> 2>0, 1+ 2+ 3=6.234, the hoisting risk factor Y is obtained by processing, and the obtained hoisting risk factor Y is compared with the hoisting risk factor threshold y stored in the control panel; When Y≥y, a first-level lifting wind control signal is generated, and the motor (4) in the protective shell (3) involved in the lifting rotates, driving the cable drum (5) to reel in the steel cable, shortening the distance between the bridge template and the pad (11), and cooperating with the lifting device to move the bridge template; At the same time, the control panel controls the motor (608) located in the housing (601) to rotate, and the toothed chain (606) located on the transmission tooth (605) rotates. At the same time, the lock buckle (607) is transformed from the movement at the bottom of the toothed chain (606) to the movement at the top of the toothed chain (606). The rotation of the lock buckle (607) drives the internal rotating rod (802) of the clamping sleeve (801) to rotate, and the eccentric wheel (803) squeezes the top block (804) in the clamping sleeve (801). The bottom block (804) of the clamping sleeve (801) abuts against the toothed sleeve (7), completing the auxiliary locking of the entire toothed sleeve (7); When Y<y, a secondary hoisting wind control signal is generated, the hoisting device directly moves the bridge template, and the top clamping block (804) located in the clamping sleeve (801) abuts against the gear sleeve (7), thereby achieving the winding and locking of the noose drum wheel (5).

2. A wire rope winch assembly for bridge formwork hoisting construction according to claim 1, It is characterized in that The rotating rod (802) is located on one side outside the clamping sleeve (801) and abuts against the fixed plate (609), and a guide rod (10) is fixed to one side of the protective shell (3) by means of bolts.

3. A wire rope winch assembly for bridge formwork hoisting construction according to claim 2, It is characterized in that The pad (11) is evenly provided with placement grooves (12), the inner walls on both sides of the placement groove (12) are symmetrically connected to pillars (15), and a fixing sleeve (13) is symmetrically sleeved and connected in the placement groove (12) and located on the pillar (15).