Prestress tensioning method applied to girder open-web box girder structure of rail bearing layer structure
By adopting the prestressed tensioning method of the hollow box girder structure in the rail-bearing layer structure, the problem of stress and deformation control of the large-span concrete beam structure is solved, the construction cost is reduced, the service life is extended, the seismic resistance is improved, and the Risk of prestressed tendon breakage.
Patent Information
- Application Number
- CN202411057307.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-02
- Publication Date
- 2024-10-11
AI Technical Summary
In the construction of the rail-bearing layer of a long-span concrete beam structure, it is difficult to effectively control structural stress, cracks and deformation with existing technology, leading to an increase in construction costs. Moreover, the hypertension method has high performance requirements for prestressed tendons, which can easily lead to damage to corrugated pipes. and the risk of prestressed tendon breakage.
The prestressed tensioning method of the open-web box girder structure is adopted. By setting the open-web box form between the transverse main beam formwork and the longitudinal main beam formwork, and grouting before the prestressed tendons are stretched, the relaxation and friction of the prestressed tendons are reduced, and excessive stress is avoided. Tensioning operation, using reinforced prestressed tendons to resist vibration.
It effectively reduces the self-weight of the rail-bearing layer structure, avoids bending deformation in the center of the main beam, extends the service life, reduces the relaxation stress loss of the prestressed tendons, reduces the ultimate tensile bearing capacity requirements of the prestressed tendon materials, and improves the earthquake resistance. The risk of prestressed tendon breakage is avoided.
Smart Images

Figure CN118756590A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of building structures, and in particular to a prestressing tensioning method applied to a hollow box girder structure of a main beam of a track-bearing layer structure. Background Art
[0002] Large-span concrete beam structures are widely used in buildings with large-span space requirements, such as stations and industrial plants. For concrete components, the increase in span will increase the cost of controlling structural stress, cracks and deformation. In the construction of the track-bearing layer, how to construct the large-span main beam structure, and how to ensure that the weight and vibration of the track-bearing layer during track laying and vehicle driving in the later stage, so that the track-bearing layer can have a longer service life, are the difficulties in current construction.
[0003] In the construction of beams, the existing technology usually adopts the post-tensioning method to embed prestressed tendons in the beams. However, when the span is larger or the deadweight is heavier, the super-tensioning method is used to reduce the prestress loss caused by the greater relaxation of the prestressed tendons. However, the super-tensioning method has higher requirements on the performance of the prestressed tendons and is costly. When the prestressed tendons are tensioned by the post-tensioning method, the friction between the prestressed tendons and the corrugated pipe is serious, which often causes the corrugated pipe to break. Super-tensioning will increase the friction between the prestressed tendons and the corrugated pipe. In addition, in the later use scenario with more vibrations, there is a risk of broken tendons in the super-tensioned prestressed tendons. Summary of the invention
[0004] In view of the above-mentioned deficiencies in the prior art, the present invention provides a prestressing tensioning method for a hollow box girder structure of a main beam of a track-bearing layer structure.
[0005] In order to achieve the above-mentioned object of the invention, the technical solution adopted by the present invention is:
[0006] A prestressing method for a hollow box girder structure of a main beam of a track-bearing layer structure is provided, comprising the following steps:
[0007] S1: Install the transverse main beam mold, which is parallel to the line between the two rail-bearing columns; install the longitudinal main beam mold perpendicular to the transverse main beam mold with the two rail-bearing columns as the center;
[0008] S2: Set up hollow box molds at both ends of the transverse main beam mold, both ends of the longitudinal main beam mold and the center of the transverse main beam mold; the top surface of the hollow box mold is provided with a reserved inspection port;
[0009] S3: Tie the skeleton steel bars between the transverse main beam formwork and the hollow box formwork, between the longitudinal main beam formwork and the hollow box formwork, and simultaneously lay the corrugated pipes symmetrically on both sides of the hollow box formwork according to the drawings;
[0010] S4: Anchor one end of the prestressed tendons after they are bundled, and install tensioning equipment at the other end;
[0011] S5: pouring concrete, and removing the horizontal supports in the hollow box form after the concrete solidifies;
[0012] S6: Use tensioning equipment to tension the prestressed tendons. After tensioning is completed, immediately remove the vertical brackets in the hollow box mold and inject grout into the corrugated pipe.
[0013] Furthermore, the hollow box formwork includes a first hollow box formwork at the center of the transverse main beam formwork, a second hollow box formwork at the end of the transverse main beam formwork, and a third hollow box formwork at the end of the longitudinal main beam formwork; the prestressed tendons include a first prestressed tendon running through the transverse main beam formwork and a second prestressed tendon running through the longitudinal main beam formwork; and reinforcing prestressed tendons are further arranged between the first hollow box formwork and the second hollow box formwork;
[0014] The first prestressed tendon is in the form of a first continuous parabola, the axis of symmetry of the continuous parabola is located at the center of the horizontal main beam mold; the first continuous parabola includes two crests and one trough, the vertices of the two crests are respectively located at the centers of the two rail-bearing columns; and the inflection point of the crest close to one end of the second hollow box mold and the side wall of the second hollow box mold close to the rail-bearing column are located in the same plane; the inflection point of the crest close to one end of the first hollow box mold and the side wall of the first hollow box mold close to the rail-bearing column are located in the same plane;
[0015] The reinforcing prestressed tendons and the second prestressed tendons present a second parabola, the second parabola includes a crest, the crest of the second parabola is located at the center of the rail support column, and the distance between the inflection point of the second parabola crest and the nearest surface of the rail support column is L is the length of the side wall of any hollow box mold close to the rail support column from the nearest surface of the rail support column.
[0016] Furthermore, the reinforced prestressed tendons include two reinforced prestressed tendon unit groups symmetrically arranged on both sides of the first prestressed tendon; working boxes are arranged at both ends of the reinforced prestressed tendon unit groups, and an anchoring device is arranged in the working box of the reinforced prestressed tendon unit group close to one end of the first hollow box mold, and a tensioning device is arranged at the other end.
[0017] Furthermore, a line connecting the center points of the two working boxes on the same side of the longitudinal main beam mold is in the same plane as a side of the first hollow box mold or the second hollow box mold close to the rail support column.
[0018] Furthermore, when the prestressed tendons are tensioned, the specific tensioning steps are as follows:
[0019] A1: Use tensioning equipment to tension the prestressed reinforcement bars and anchor both ends of the tensioned prestressed reinforcement bars;
[0020] A2: After the reinforcement prestressed tendons are anchored, wait for 24 hours, remove all horizontal supports in the hollow box mold after the reinforcement prestressed tendons are relaxed, and tension the first and second prestressed tendons at the same time;
[0021] A3: After anchoring the two ends of the first and second prestressed tendons, tension the reinforcing prestressed tendons again. When tensioning the reinforcing prestressed tendons again, remove the vertical brackets in the hollow box formwork, and grout the corrugated pipes of the first and second prestressed tendons at the same time; after the reinforcing prestressed tendons are tensioned again to the designed prestress, grout the corrugated pipes of the reinforcing prestressed tendons;
[0022] A4: After the grouting of the corrugated pipe for strengthening the prestressed tendons is completed, grouting is injected into the working box to close the working box.
[0023] Furthermore, after the horizontal supports in the empty box mold are removed in step S5, the horizontal supports are still retained in the empty box, and after the vertical supports in the empty box are removed, all the supports are transferred from the empty box together.
[0024] The beneficial effects of the present invention are:
[0025] 1. The present invention can effectively reduce the deadweight of the beam between two large-span rail-bearing columns by arranging a hollow box at the center of the transverse main beam mold between two large-span rail-bearing columns, thereby avoiding the downward bending and deformation of the center of the main beam during use after the construction is completed, thereby preventing safety hazards. At the same time, the hollow box arrangement on the transverse main beam mold and the longitudinal main beam mold reduces the deadweight, and when prestressed tendons are used for tensioning, the ultimate tensioning bearing capacity of the prestressed tendon material will not be exceeded. Therefore, in the construction of large-span rail-bearing layer structures, commonly used prestressed tendons can be used without the need to specially customize prestressed tendons with better performance.
[0026] 2. The present invention can more effectively resist the vibration generated by the vehicle running on the track by setting the strengthening prestressed tendons. The first prestressed tendons that mainly provide prestress for the transverse main beam, rather than the strengthening prestressed tendons, need to be carried out separately during the tensioning process of the entire prestressed tendons. After the strengthening prestressed tendons are tensioned, they need to be relaxed, and then the first prestressed tendons are tensioned to the designed tensioning amount, which replaces the over-tensioning operation and reduces the relaxation stress loss of the first prestressed tendons. BRIEF DESCRIPTION OF THE DRAWINGS
[0027] Figure 1 This is a schematic diagram of the track-bearing layer structure without concrete pouring;
[0028] Figure 2 is a schematic diagram of the installation structure of the first prestressed tendon;
[0029] Among them, 1. Track-bearing columns; 2. Horizontal main beam mold; 3. Longitudinal main beam mold; 4. Inspection port; 5. First hollow box mold; 6. Second hollow box mold; 7. Third hollow box mold; 8. First prestressed tendon; 9. Second prestressed tendon; 10. Strengthening prestressed tendon; 11. Working box. DETAILED DESCRIPTION
[0030] The specific implementation modes of the present invention are described below so that those skilled in the art can understand the present invention. However, it should be clear that the present invention is not limited to the scope of the specific implementation modes. For those of ordinary skill in the art, as long as various changes are within the spirit and scope of the present invention as defined and determined by the attached claims, these changes are obvious, and all inventions and creations utilizing the concept of the present invention are protected.
[0031] A prestressing method for a hollow box girder structure of a main beam of a track-bearing layer structure comprises the following steps:
[0032] S1: Install the transverse main beam mold 2, which is parallel to the line between the two rail support columns 1; install the longitudinal main beam mold 3 perpendicular to the transverse main beam mold 2 with the two rail support columns 1 as the center;
[0033] S2: A hollow box formwork is set up at both ends of the transverse main beam formwork 2, both ends of the longitudinal main beam formwork 3 and the center of the transverse main beam formwork 2; a reserved inspection opening 4 is set on the top surface of the hollow box formwork;
[0034] S3: Tie the skeleton steel bars between the horizontal main beam formwork 2 and the hollow box formwork, and between the longitudinal main beam formwork 3 and the hollow box formwork, and at the same time, lay the corrugated pipes symmetrically on both sides of the hollow box formwork according to the drawings;
[0035] S4: Anchor one end of the prestressed tendons after they are bundled, and install tensioning equipment at the other end;
[0036] S5: pouring concrete, and removing the horizontal supports in the hollow box form after the concrete solidifies;
[0037] S6: Use tensioning equipment to tension the prestressed tendons. After tensioning is completed, immediately remove the vertical brackets in the hollow box mold and inject grout into the corrugated pipe.
[0038] like Figure 1 As shown, the hollow box formwork includes a first hollow box formwork 5 at the center of the transverse main beam formwork 2, a second hollow box formwork 6 at the end of the transverse main beam formwork 2, and a third hollow box formwork 7 at the end of the longitudinal main beam formwork 3; the prestressed tendons include a first prestressed tendon 8 that runs through the transverse main beam formwork 2 and a second prestressed tendon 9 that runs through the longitudinal main beam formwork 3; and a reinforcing prestressed tendon 10 is further provided between the first hollow box formwork 5 and the second hollow box formwork 6;
[0039] like Figure 2As shown, the first prestressed tendon 8 is a first continuous parabola, and the symmetry axis of the continuous parabola is located at the center of the horizontal main beam mold 2; the first continuous parabola includes two crests and one trough, and the vertices of the two crests are respectively located at the centers of the two rail-bearing columns 1; and the inflection point of the crest close to one end of the second hollow box mold 6 and the side wall of the second hollow box mold 6 close to the rail-bearing column 1 are located in the same plane; the inflection point of the crest close to one end of the first hollow box mold 5 and the side wall of the first hollow box mold 5 close to the rail-bearing column 1 are located in the same plane;
[0040] The reinforcing prestressed tendons 10 and the second prestressed tendons 9 are in a second parabola, the second parabola includes a crest, the crest of the second parabola is located at the center of the rail support column 1, and the distance between the inflection point of the second parabola crest and the nearest surface of the rail support column 1 is L is the length of the side wall of any hollow box mold close to the rail support column 1 from the nearest surface of the rail support column 1. In specific implementation, the inflection points on both sides of the wave crest of the reinforcing prestressed tendon 10 are the length of the side wall of the first hollow box mold 5 close to the rail support column 1 from the nearest surface of the rail support column 1; the inflection points on both sides of the second prestressed tendon 9 are the length of the side wall of the third hollow box mold 7 close to the rail support column 1 from the nearest surface of the rail support column 1.
[0041] In specific implementation, 12 first prestressed tendons 8 and 12 second prestressed tendons 9 are provided, and the 12 prestressed tendons are evenly divided into two groups. The two groups of prestressed tendons are respectively located on both sides of the track support column 1, and each group of prestressed tendons is distributed in a matrix, and the number of rows of the matrix is 2 and the number of columns is 3. The number of reinforcing prestressed tendons 10 is 6, and every 3 reinforcing prestressed tendons 10 are in a group. The two groups of reinforcing prestressed tendons 10 are also respectively located on both sides of the track support column 1, and the reinforcing prestressed tendons 10 in each group are evenly spaced horizontally.
[0042] The reinforcing prestressed tendons 10 include two reinforcing prestressed tendon 10 unit groups symmetrically arranged on both sides of the first prestressed tendon 8; working boxes 11 are provided at both ends of the reinforcing prestressed tendon 10 unit group, and an anchoring device is provided in the working box 11 at one end of the reinforcing prestressed tendon 10 unit group close to the first hollow box mold 5, and a tensioning device is provided at the other end.
[0043] The center point connection line of the two working boxes 11 located on the same side of the longitudinal main beam mold 3 is in the same plane as the side of the first empty box mold 5 or the second empty box mold 6 close to the rail support column 1.
[0044] When prestressing tendons are tensioned, the specific tensioning steps are as follows:
[0045] A1: Use tensioning equipment to tension the reinforcing prestressed tendons 10, and anchor both ends of the tensioned reinforcing prestressed tendons 10;
[0046] A2: After the reinforced prestressed tendons 10 are anchored, wait for 24 hours, and after the reinforced prestressed tendons 10 are relaxed, remove all horizontal brackets in the hollow box mold, and tension the first prestressed tendons 8 and the second prestressed tendons 9 at the same time;
[0047] A3: After anchoring the two ends of the first prestressed tendon 8 and the second prestressed tendon 9, the reinforcing prestressed tendon 10 is tensioned again. When the reinforcing prestressed tendon 10 is tensioned again, the vertical bracket in the hollow box mold is removed, and the corrugated pipes of the first prestressed tendon 8 and the second prestressed tendon 9 are grouting at the same time; after the reinforcing prestressed tendon 10 is tensioned again to the designed prestress, the corrugated pipes of the reinforcing prestressed tendon 10 are grouting;
[0048] A4: After the grouting of the corrugated pipe for reinforcing the prestressed tendons 10 is completed, grouting is injected into the working box 11 to close the working box 11.
[0049] After the horizontal brackets in the hollow box mold are removed in step S5, the horizontal brackets are still left in the hollow box. After the vertical brackets in the hollow box are removed, all the brackets are moved out of the hollow box together. The horizontal brackets are not moved out of the hollow box. The weight of the brackets can accelerate the relaxation process of the reinforced prestressed tendons 10 and speed up the construction progress. At the same time, during the tensioning of the first prestressed tendons 8 and the second prestressed tendons 9, the weight of the brackets prompts the prestressed tendons to relax a part in advance. After the brackets are transferred, the missing weight can achieve an effect similar to super tensioning.
Claims
1. A prestressing method for a hollow box girder structure of a main beam of a track-bearing layer structure, characterized in that: The steps include: S1: Install a transverse main beam mold, wherein the transverse main beam mold is parallel to the connection line between the two rail support columns; and install a longitudinal main beam mold perpendicular to the transverse main beam mold with the two rail support columns as the center respectively; S2: A hollow box formwork is set up at both ends of the transverse main beam formwork, both ends of the longitudinal main beam formwork and the center of the transverse main beam formwork; a reserved inspection opening is set on the top surface of the hollow box formwork; S3: Tie the skeleton steel bars between the transverse main beam formwork and the hollow box formwork, between the longitudinal main beam formwork and the hollow box formwork, and simultaneously lay the corrugated pipes symmetrically on both sides of the hollow box formwork according to the drawings; S4: Anchor one end of the prestressed tendons after they are bundled, and install tensioning equipment at the other end; S5: pouring concrete, and removing the horizontal supports in the hollow box mold after the concrete solidifies; S6: Use tensioning equipment to tension the prestressed tendons. After tensioning is completed, the vertical brackets in the hollow box mold are immediately removed, and grouting is performed in the corrugated pipe to complete the prestressing of the track-bearing layer structure.
2. The prestressing method for the hollow box girder structure of the main beam of the track-bearing layer structure according to claim 1 is characterized in that: The hollow box formwork includes a first hollow box formwork at the center of the transverse main beam formwork, a second hollow box formwork at the end of the transverse main beam formwork, and a third hollow box formwork at the end of the longitudinal main beam formwork; the prestressed tendons include a first prestressed tendon running through the transverse main beam formwork and a second prestressed tendon running through the longitudinal main beam formwork; and a reinforcing prestressed tendon is further arranged between the first hollow box formwork and the second hollow box formwork; The first prestressed tendon is in the form of a first continuous parabola, the axis of symmetry of the continuous parabola is located at the center of the transverse main beam mold; the first continuous parabola includes two wave crests and one wave trough, the vertices of the two wave crests are respectively located at the centers of the two rail-bearing columns; and the inflection point of the wave crest close to one end of the second hollow box mold and the side wall of the second hollow box mold close to the rail-bearing column are located in the same plane; the inflection point of the wave crest close to one end of the first hollow box mold and the side wall of the first hollow box mold close to the rail-bearing column are located in the same plane; The reinforcing prestressed tendons and the second prestressed tendons are in a second parabola, the second parabola includes a crest, the crest of the second parabola is located at the center of the rail support column, and the distance between the inflection point of the second parabola crest and the nearest surface of the rail support column is L is the length of the side wall of any hollow box mold close to the rail support column from the nearest surface of the rail support column.
3. The prestressing method for the hollow box girder structure of the main beam of the track-bearing layer structure according to claim 2 is characterized in that: The reinforced prestressed tendons include two reinforced prestressed tendon unit groups symmetrically arranged on both sides of the first prestressed tendons; both ends of the reinforced prestressed tendon unit groups are provided with working boxes, and an anchoring device is provided in the working box of the reinforced prestressed tendon unit group close to one end of the first hollow box mold, and a tensioning device is provided at the other end.
4. The prestressing method for the hollow box girder structure of the main beam of the track-bearing layer structure according to claim 3 is characterized in that: The line connecting the center points of the two working boxes located on the same side of the longitudinal main beam mold is in the same plane as the side of the first hollow box mold or the second hollow box mold close to the rail support column.
5. The prestressing method for the hollow box girder structure of the main beam of the track-bearing layer structure according to claim 2 is characterized in that: When prestressing tendons are tensioned, the specific tensioning steps are as follows: A1: Use tensioning equipment to tension the prestressed reinforcement bars and anchor the two ends of the tensioned prestressed reinforcement bars; A2: After the reinforcement prestressed tendons are anchored, wait for 24 hours, remove all horizontal supports in the hollow box mold after the reinforcement prestressed tendons are relaxed, and tension the first and second prestressed tendons at the same time; A3: After anchoring the two ends of the first and second prestressed tendons, tension the reinforcing prestressed tendons again. When tensioning the reinforcing prestressed tendons again, remove the vertical brackets in the hollow box formwork, and grout the corrugated pipes of the first and second prestressed tendons at the same time; after the reinforcing prestressed tendons are tensioned again to the designed prestress, grout the corrugated pipes of the reinforcing prestressed tendons; A4: After the grouting of the corrugated pipe for strengthening the prestressed tendons is completed, grouting is injected into the working box to close the working box.
6. The prestressing method for the hollow box girder structure of the main beam of the track-bearing layer structure according to claim 1 is characterized in that: After the horizontal supports in the empty box mold are removed in step S5, the horizontal supports are still retained in the empty box. After the vertical supports in the empty box are removed, all the supports are transferred from the empty box together.