Full-secondary air cooling type industrial steam condensing device

Through the new tube design and the layout of the full secondary condensation device, the problems of low steam condensation efficiency and high material cost in the existing technology are solved, efficient heat exchange and material saving are achieved, and it is suitable for large industrial steam condensation devices.

CN118758079APending Publication Date: 2024-10-11EVAPCO INC
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202410860312.3
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Priority Date
2016-12-05
Filing Date
2017-06-21
Publication Date
2024-10-11

AI Technical Summary

Technical Problem

Existing large-scale on-site air-cooled industrial steam condensation devices have deficiencies in heat exchange efficiency and material usage, especially in summer conditions due to large steam pressure drops and high material costs.

Method used

Adopting new tube design and full secondary condensation device layout, the cross-sectional size of the tube is 100-200mm wide, the height is less than 10mm, the fin height is 17-20mm, and there are 9-12 fins per inch. All tube bundles form a secondary tube bundle , receiving steam from the bottom and collecting condensate, and discharging non-condensable gas from the top, forming a V-shaped or A-shaped frame structure to reduce the use of primary tube bundles.

Benefits of technology

The heat exchange efficiency is significantly improved by more than 30%, while material usage is reduced, the capacity is increased by 25-30%, and the system size is smaller, making it suitable for power plants and other places.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118758079A_ABST
    Figure CN118758079A_ABST
Patent Text Reader

Abstract

A novel design of a large industrial steam condensing device for on-site erection, in which all tube bundles are configured as secondary tube bundles, presenting an A-shaped frame or V-shaped structure; an angle of 25-35 degrees is formed between the pipe and the vertical direction; collecting steam from the bottom and collecting condensate from the bottom of the tube bundle using a combination / mixing manifold, each delivering steam to the conduit and collecting condensate from the conduit, and configured to prevent condensate from redirecting to the steam delivery riser; and wherein the cross-sectional dimension of the tube is 125 mm in width and less than 10 mm in cross-sectional height, has a fin height of 9.25 mm, and has 9 to 12 fins arranged per inch.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] This application is a divisional application, the corresponding parent application number is 201780039592.X, the application date is June 21, 2017, and the name of the invention is "Fully secondary air-cooled industrial steam condensing device". Technical Field

[0002] The invention relates to a large-scale on-site erected air-cooled industrial steam condensing device. Background Art

[0003] The finned tubes currently used in most large field erected air cooled industrial steam condensing units ("ACC") are flat tubes with a length of about 11m, a width (also called "air travel length") of 200mm, semi-circular leading and trailing edges, and an internal height (perpendicular to the air travel length) of 18.8mm. The tube wall thickness is 1.35mm. The fins are brazed to the two flat sides of each tube. The fin height is typically 18.5mm, with 11 fins per inch. The fin surface is in a wavy pattern to enhance heat transfer and contribute to the stiffness of the fins. The standard spacing between tubes is 57.2mm center to center. The tube itself constitutes approximately one-third of the cross-sectional area (perpendicular to the direction of air flow); while the fins constitute nearly two-thirds of the cross-sectional area. There is a small gap of 1.5mm between adjacent fin tips. For summer ambient conditions, the maximum steam velocity through the tube can typically be as high as 28mps, with 23 to 25mps being more typical. The single A-frame formed by these tube and fin combination designs has been optimized based on tube length, fin spacing, fin height and shape, and air travel length. The finned tubes are assembled to form heat exchanger bundles, typically with 39 tubes per heat exchanger bundle, and 10-14 bundles are arranged into two heat exchangers, with each fan having a single A-frame made up of the two heat exchangers. The fan is typically located below the A-frame to force air through the tube bundle. The overall design of the tubes and fins and the air pressure drop of the combination of tubes and fins are also optimized to match the ability of large (36 foot diameter) fans running at 200 to 250 horsepower to move air. Since the concept of single row oval tubes was introduced more than 20 years ago, this optimized arrangement has remained relatively unchanged among many different manufacturers.

[0004] The typical A-frame ACC described above includes a first or "primary" condenser bundle and a second or "secondary" bundle. Approximately 80% to 90% of the heat exchanger bundles belong to the first or primary condenser bundle. Steam enters the top of the primary condenser bundle, while condensate and some steam leave the bottom. The first-stage configuration is thermally efficient; however, it does not provide a method for removing non-condensable gases. In order to purge non-condensable gases through the first-stage bundle, 10% to 20% of the heat exchanger bundles are configured as secondary or secondary bundles, which are usually interspersed in the primary bundle to draw steam from the lower condensate manifold. In this arrangement, steam and non-condensable gases pass through the first-stage bundle as they are drawn into the bottom of the secondary bundle. As the gas mixture travels upward through the secondary bundle, the remaining steam condenses, condensing into non-condensable gases. The top of the secondary bundle is connected to a vacuum manifold that is used to remove non-condensable gases from the system.

[0005] Variations on the standard prior art ACC arrangement have been disclosed, for example, in U.S. Patents US2015 / 0204611 and US2015 / 0330709. These applications show identical but substantially shortened finned tubes which are then arranged in a series of small A-frames, typically with 5 A-frames for each fan. Part of the logic is to reduce the steam pressure drop, which has a small effect on total capacity in summer conditions, but a greater effect on total capacity in winter conditions. Another part of the logic is that expensive field welding work can be saved by welding the top steam manifold pipe to each tube bundle at the factory and shipping them together. The net effect of this arrangement of connecting the steam manifold at the factory and shipping it with the tube bundle is to reduce the length of the tubes so that the manifold can be accommodated in a standard height cubic shipping container. As the tubes are shortened, the total amount of surface area is reduced, reducing the relative capacity of a standard single A-frame design of similar overall dimensions by about 3% in summer conditions. Summary of the invention

[0006] The inventions presented herein are: 1) a novel tube design for heat exchanger systems, including but not limited to large field erected industrial steam condensing units; and 2) a novel design for large field erected industrial steam condensing units for power plants and the like; both of which are capable of significantly increasing the thermal capacity of ACCs while reducing the material used in certain configurations. Various aspects and / or embodiments of the invention are described below:

[0007] According to various embodiments of the tube design invention, the tube length is 2.044m, the cross-sectional dimensions of the tube are 100-200mm wide, preferably 125mm wide (air travel length), while the cross-sectional height (perpendicular to the air travel length) is less than 10mm, and the cross-sectional height (also referred to as "outer tube width") is preferably 4-10mm, more preferably 5.0-9mm, even more preferably 5.2-7mm, most preferably 6.0mm, and there are 9 to 12 fins per inch, preferably 9.8 fins. According to another preferred embodiment, the actual fin height can be 17-20mm, preferably 18.5mm, and the fins span the spacing between two adjacent tubes, effectively making each tube on each side have a 9.25mm fin respectively.

[0008] It is directly contrary to the prevailing wisdom in the art that tubes should be made of as large a cross section as possible in order to accommodate the large quantities of steam output by large power plants, and that it is precisely because larger tubes provide a reduction in cost that it is desirable to make tubes of smaller cross section (same air travel length but significantly less height). Although the cost of such an arrangement is significantly higher than the prior art tube arrangements, the inventors have surprisingly discovered that the increased efficiency of the lower height tubes compared to the prior art tubes (in the most preferred embodiment, the efficiency increase is in excess of 30% compared to the prior art tubes) more than offsets the increased cost. This new tube design can be used in a prior art large field erected industrial steam condensing plant (e.g., as described in the Background section), or it can be used in conjunction with the new ACC design described below.

[0009] The main feature of the invention for a new design of a large, field erected industrial steam condensing plant is that all the tube bundles of the ACC according to the invention are constructed as secondary tube bundles, wherein steam is fed from the bottom into the tubes facing upwards (aligned parallel to the transverse axis of the tube bundle, each tube is typically angled 25°-35° to the vertical, preferably 30°), and condensate is collected from the bottom of the tube bundle; preferably a combining / mixing manifold is used, which is able to both transmit steam to the tubes and collect condensate from the tubes. According to one embodiment, the combining / mixing manifold can be constructed so that the condensate cannot return along the steam transport riser, but is conveyed to a condensate recovery pipe connected to the combining / mixing manifold. According to an alternative embodiment, the combining / mixing manifold can be constructed so that the condensate can travel down the steam transport riser and be removed from the steam transport pipe closer to the ground. The top of the tubes is connected to a separate manifold for collecting non-condensable gases. This new “all-secondary” ACC arrangement can be configured in an A-frame with two secondary tube bundles connected at the top and a single manifold collecting non-condensable gases from these tubes, or with two non-condensable manifolds, one at the top of each tube bundle.

[0010] The terms "all secondary" and "no primaries" are used herein to refer to a large field-erected, air-cooled, industrial steam condensing unit in which all tube bundles receive steam from the bottom and collect condensate at the bottom, and discharge non-condensable gases out the top. In contrast, the primary tube bundles in a large field-erected, air-cooled, industrial steam condensing unit receive steam at the top and deliver condensate at the bottom, and deliver non-condensable gases at the bottom to a separate secondary condensing unit.

[0011] Preferably, however, the ACC of the present invention may be arranged in a V-shaped configuration wherein two secondary-only condensing device tube bundles are joined at a single combined steam distribution manifold / condensate collection manifold at the bottom, with a separate non-condensable collection manifold provided at the top of each tube bundle.

[0012] According to the preferred embodiment of the V-shaped structure, since the steam manifold is located at the bottom of the tube bundle, there is more than one location to enter the manifold, thus reducing the size of the manifold and allowing the fin tubes to be slightly longer. When combined with the smaller cross-section tubes described herein (200mm by less than 10mm high, where the height is preferably 4-10mm, more preferably 5.0-9mm, even more preferably 5.2-7mm, and most preferably 6.0mm), the system demonstrates at least a 25% to 30% improvement in performance relative to the standard ACC arrangement and structure described above, and the device can be made smaller by a similar amount in plan area.

[0013] According to another alternative embodiment, the new ACC design of the present invention with offset fins can be used with tubes having dimensions of 100 mm by preferably 4-10 mm height, with the height more preferably being 5.0-9 mm, even more preferably 5.2-7 mm, and most preferably 6.0 mm.

[0014] According to another embodiment, the new ACC design of the present invention can be used with 120 mm or up to 200 mm by 5 mm to 7 mm tubes having "arrow" shaped fins with 9.8 fins per inch arranged.

[0015] According to yet another embodiment, the new ACC design of the present invention can be used with tubes having "louvered" fins, which have approximately the same performance as offset fins, but are easier to obtain and manufacture.

[0016] According to the preferred and most preferred embodiments of the present invention, combined with the most preferred ACC structure and the most preferred tube size, the ACC of the present invention has the following features and dimensions:

[0017] All tube bundles are secondary tube bundles (all tubes receive steam from the bottom, distribute condensate through the bottom and distribute non-condensable gases out the top);

[0018] No primary tube bundle;

[0019] Four, five (most preferred) or six V-tube pairs per unit / fan;

[0020] The cross-section of the outer dimension of the tube is 4-10 mm (preferably 5-7 mm, most preferably 6.0 mm) by 100-200 mm (most preferably 125 mm);

[0021] The tube spacing cc is 20-29 mm (most preferably 24.5 mm);

[0022] The tube wall thickness is 0.7-0.9 mm (most preferably 0.8 mm);

[0023] Each tube bundle has 40-60 (most preferably 50) tubes;

[0024] Tube length is 1700-2400mm (most preferably 2044mm);

[0025] Arrow-shaped fins (preferred, but not required) span between adjacent tubes and thermally connect both tubes;

[0026] Fin height is 17-19 mm (most preferably 18.5 mm (effective height per tube side is 9.25 mm));

[0027] The air stroke length is 95mm-195mm, and the most preferred is 120mm.

[0028] Relatively speaking, the total tube bundle surface area according to the most preferred embodiment is 79% of the area of ​​the prior art ACC with the same total fan power, steam volume and thermal conditions; similarly, the total planned area of ​​the most preferred embodiment is 79% of the area of ​​the prior art ACC with the same total fan power, steam volume and thermal conditions.

[0029] Additionally, the ACC design of the present invention can be more easily positioned, thereby requiring less overall space within a power plant. BRIEF DESCRIPTION OF THE DRAWINGS

[0030] Figure 1A is a perspective view of the heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing plant of the prior art;

[0031] Figure 1Bis a partially exploded close-up view of the heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing plant of the prior art, showing the orientation of the tubes relative to the steam distribution manifold;

[0032] Figure 2 is a perspective view of a heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing unit ("ACC") in accordance with a first embodiment of the present invention;

[0033] Figure 3 is a perspective view of a heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing unit ("ACC") according to a second embodiment of the present invention;

[0034] Figure 4A is a perspective view of a heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing unit ("ACC") according to a third embodiment of the present invention;

[0035] Figure 4B is a perspective view of a heat exchange portion of a large-scale field-erected air-cooled industrial steam condensing unit ("ACC") according to a fourth embodiment of the present invention;

[0036] Figure 5 is a cross-sectional perspective view of a prior art ACC tube and fin;

[0037] Figure 6 is a perspective view of a microtube and a fin according to an embodiment of the present invention;

[0038] Figure 7 is a perspective view of a microtube and a fin according to another embodiment of the present invention;

[0039] Figure 8 FIG. 1 is a side view of a large-scale on-site air-cooled industrial steam condensing device according to an embodiment of the present invention, which includes: Figure 4A The arrangement shown is V-shaped and has only secondary heat exchange tube bundle pairs;

[0040] Fig. 9 yes Figure 8 An end view of a large field erected air-cooled industrial steam condensing plant as shown in;

[0041] Fig.10 yes Figure 8 A top view of a large field erected air-cooled industrial steam condensing plant shown in , showing a turbine exhaust pipe divided into 6 (6 rows) longitudinal steam headers, each steam header including 6 units;

[0042] Fig.11 is a perspective view of a finned tube bundle of a secondary condensing device according to an embodiment of the present invention;

[0043] Fig.12 is Fig.11 A perspective photograph of the secondary condensing unit finned tube bundle is shown in FIG. DETAILED DESCRIPTION

[0044] A-frame ACC with full secondary tube bundle

[0045] refer to Figure 2 , the tubes 2 are arranged in the secondary tube bundles 4. The longitudinal axis of the tubes 2 is aligned parallel to the transverse axis of the tube bundle, and each tube is generally at an angle of 25°-35° to the vertical direction, preferably at an angle of 30°. A combined steam distribution / condensate collection manifold 6 is attached at the bottom of each of the two secondary tube bundles 4, and the two secondary tube bundles 4 are joined at their tops to form an A-frame structure. Steam is distributed to the tubes 2 through the combined steam distribution / condensate collection manifold 6, and condensate is formed in the tubes 2 when the steam condenses and travels down the tubes 2 into the combined steam distribution / condensate collection manifold 6. A single non-condensable collection manifold 8 is attached to the top of the two tube bundles 6 to collect non-condensable gases traveling to the top of the tubes 2. Steam is supplied to the combined steam distribution / condensate collection manifold 6 from the steam pipe 10 through the riser 12. The condensed water collected in the combined steam distribution / condensate collection manifold 6 is taken away from the ACC into the condensate recovery pipe 14.

[0046] Figure 3 Shown with Figure 2 The embodiment is very similar to the embodiment of , except that each tube bundle 4 is connected at its top to a dedicated non-condensable collection manifold.

[0047] V-shaped ACC with full secondary tube bundle

[0048] refer to Figure 4A and Figure 4B , the tubes 2 are arranged in the secondary tube bundles 4. The longitudinal axis of the tubes 2 is aligned parallel to the transverse axis of the tube bundle, and each tube is generally at an angle of 25°-35° to the vertical direction, preferably at an angle of 30°. A combined steam distribution / condensate collection manifold 6 is attached to the bottom of the two secondary tube bundles 4, and the two secondary tube bundles 4 are connected to form a V-shaped structure at an angle of 55°-65°, wherein the angle is preferably 60°. Steam is distributed to the tubes 2 through the combined steam distribution / condensate collection manifold 6, and condensate is formed in the tubes 2 when the steam condenses and travels down the tubes 2 into the combined steam distribution / condensate collection manifold 6. The non-condensable collection manifold 8 is attached to the top of the two tube bundles 6 to collect the non-condensable gas traveling to the top of the tubes 2. Steam is supplied to the combined steam distribution / condensate collection manifold 6 from the steam pipe 10 through a riser 12. The condensed water collected in the combined steam distribution / condensate collection manifold 6 is taken away from the ACC into the condensate recovery pipe 14.

[0049] The new ACC design described above can be used with any prior art tube, including Figure 5 The tube shown in FIG. 1 has a length of about 11 m, a width (or "air travel length") of 200 mm, a semicircular leading and trailing edge, an internal height (perpendicular to the air travel length) of 18.8 mm, and a tube wall thickness of 1.35 mm; fins are brazed to the two flat sides of each tube, the fin height is typically 18.5 mm, and there are 11 fins per inch of spacing. However, according to a more preferred embodiment, the novel ACC design of the present invention has the following features and dimensions:

[0050] All tube bundles are secondary tube bundles (all tubes receive steam from the bottom, distribute condensate through the bottom and distribute non-condensable gases out the top);

[0051] No primary tube bundle;

[0052] Four, five (most preferred) or six V-tube pairs per unit / fan;

[0053] The cross-section of the outer dimension of the tube is 4-10 mm (preferably 5-7 mm, most preferably 6.0 mm) by 100-200 mm (most preferably 125 mm);

[0054] The tube spacing cc is 20-29 mm (most preferably 24.5 mm);

[0055] The tube wall thickness is 0.7-0.9 mm (most preferably 0.8 mm);

[0056] Each tube bundle has 40-60 (most preferably 50) tubes;

[0057] Tube length is 1700-2400mm (most preferably 2044mm);

[0058] Arrow-shaped fins (preferred, but not required) span between adjacent tubes and thermally connect both tubes;

[0059] Fin height is 18.5mm (effective height on each tube side is 9.25mm);

[0060] The air stroke length is 95mm-195mm, and the most preferred is 120mm.

[0061] For a single unit with constant fan power, this preferred embodiment increases capacity by 25-30% compared to prior art A-frame designs with standard tubes.

[0062] Figure 8-Figure 10A representative large-scale on-site air-cooled industrial steam condensing device according to an embodiment of the present invention is shown. Figure 4A Only the secondary heat exchange tube bundle pairs are shown in a V-shape. Figure 8-Figure 10 The device shown in is an ACC including 36 units (6 columns x 6 units), and the most preferred embodiment is that each unit includes 5 tube bundle pairs, but the present invention can also be used with ACCs of any size, and each unit can have any number of tube bundle pairs.

Claims

1. A large-scale, field-erected, air-cooled industrial steam condensing unit with a full secondary tube bundle connected to an industrial steam production facility, comprising: Two tube bundles, each of which comprises a plurality of finned flat tubes mounted adjacent to each other, each of the tube bundles being oriented such that the longitudinal axes of the finned flat tubes are at an angle of 55° to 65° to the horizontal plane; a combined steam distribution-condensate collection manifold connected to the bottom of each of the tube bundles and extending along the length of the tube bundles, the tube bundles being configured to deliver steam to the bottom of the tubes and to collect condensate formed in the tubes from the steam as the steam cools; A non-condensable collecting manifold is connected to the top of each of the tube bundles and extends along the tube bundles in parallel to the length direction of the steam distribution manifold and is configured to collect non-condensable gases from the steam.

2. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: All condensate collected from the tubes is collected in the combined steam distribution-condensate collection manifold.

3. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: All steam delivered to the tubes is delivered from the combined steam distribution-condensate collection manifold.

4. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The longitudinal axis of the finned flat tube is at an angle of 60° to the horizontal.

5. A large scale field erected air cooled industrial steam condensing plant with full secondary tube bundles as claimed in claim 1, which does not include primary condensing plant tubes.

6. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The two tube bundles are arranged in an A-frame configuration with a single non-condensable collection manifold connected to the top of both of the two tube bundles and separate combined steam distribution-condensate collection manifolds attached to the bottom of both of the two tube bundles.

7. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The two tube bundles are arranged in an A-frame structure, having two non-condensable collecting manifolds, each of which is connected to the top of one of the two tube bundles, and having two combined steam distribution-condensate collecting manifolds, each of which is attached to the bottom of one of the two tube bundles.

8. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The two tube bundles are arranged in a V-shaped configuration with a single combined steam distribution-condensate collection manifold connected to the bottom of the two tube bundles and having two separate non-condensable collection manifolds, one attached to the top of each of the two tube bundles.

9. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube is 100 mm-200 mm and the cross-sectional height is 4-10 mm.

10. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube was 125 mm and the cross-sectional height was 5.2-7 mm.

11. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube was 125 mm and the cross-sectional height was 6.0 mm.

12. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The tubes have fins attached to the flat sides of the tubes, the fins are 10 mm in height and are spaced 9 to 12 fins per inch.

13. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube was 200 mm and the cross-sectional height was 17-20 mm.

14. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube was 200 mm and the cross-sectional height was 18.8 mm.

15. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The cross-sectional width of the tube was 125 mm and the cross-sectional height was 4-10 mm.

16. The large-scale, field-erected, air-cooled industrial steam condensing plant with full secondary tube bundles according to claim 1, wherein: The length of the tube is about 1700 mm to about 2400 m.

17. A large scale field erected air cooled industrial steam condensing plant with full secondary tube bundles as in claim 1 comprising from about 40 to about 60 of said tubes.

Citation Information

Patent Citations

  • Modular air cooled condenser apparatus and method

    US20150204611A1

  • Modular air cooled condenser apparatus and method

    US20150330709A1